CN109258322A CN201810946176.4A CN201810946176A CN109258322A CN 109258322 A CN109258322 A CN 109258322A CN 201810946176 A CN201810946176 A CN 201810946176A CN 109258322 A CN109258322 A CN 109258322A
Authority
CN
China
Prior art keywords
plant
slope
construction method
side slope
grass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810946176.4A
Other languages
Chinese (zh)
Inventor
周跃飞
庞林军
耶律根迪
陈翕和
马克乾
余淦
龚超
何金
付凯强
李光川
贺治鹏
乔思凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201810946176.4A priority Critical patent/CN109258322A/en
Publication of CN109258322A publication Critical patent/CN109258322A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G20/00Cultivation of turf, lawn or the like; Apparatus or methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The present invention relates to a kind of slope plant grass temporarily to answer green construction method, belong to slope construction technical field, the present invention is by covering one layer of plant plait on side slope surface, and it is fixed with nailing, so that side slope surface color becomes green, the problems moment on jetting cement surface has obtained " screening ", " decoration ", fast implement side slope " temporarily multiple green " effect, so that side slope and surrounding enviroment coordination of landscape, it is unified, not only increase civilized construction standard, and plant plait surface plastic cement grass layer is intensive, conducive to draining, it avoids rainwater and directly washes away side slope surface, it is more advantageous to the stabilization of side slope.The interim multiple green construction is simple, quickly of plant plait, the human and material resources of investment are less, and plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.

Description

A kind of interim multiple green construction method of slope plant grass
Technical field
The invention belongs to slope construction technical fields, specifically, are related to a kind of slope plant grass temporarily multiple green construction party Method.
Background technique
Current city track traffic engineering development scale more and more rapidly, grow, bring is the convenience, fast of people's trip It is prompt.And the raising by a relatively large margin that nowadays people's nontimber forest and living standard also obtain, life Happiness Index Also it is improving, the requirement to environment is also gradually improving.
The particularity of city track traffic engineering itself, engineering in general is in city, edge, even in city prosperity The sensitive areas such as area, residential block require civilized construction in construction site especially high.For there are road slope or bases in building site Interim slope project is cheated, in construction period, usually in the injection 10cm thickness C25 concrete gib of side slope surface until engineering terminates again It backfills, is multiple green.Because jetting cement main component is cement, sand, surface color is canescence, is not assisted with the trees on periphery, careless landscape It adjusts, civilized construction standard is relatively low.Moreover, jetting cement sprays anchor during jet-anchor execution, by side slope brush slope flatness, spray gun hand The influence of the human factors such as technical level, jetting cement surface smoothness is poor, and generally there are anchor pole, drain hole in jetting cement surface in addition Etc. exposed component, sprays anchor flatness problem and become apparent.In addition, jetting cement is because construction needs, segmentation, piecemeal are applied under normal conditions Inevitably there is color difference in work.At the same time, over time, surface inevitably will appear to be split side slope jetting cement It stitches, fall off, the scenes such as scale, jetting cement surface treatment trace, color difference become apparent after repairing, so that jetting cement surface is not beautiful Sight, harmony are worse, and civilized construction standard is lower, and deal with work consuming time-consuming again, uneconomical.
Summary of the invention
In order to solve the problems, such as background technique, the present invention provides a kind of slope plant grass temporarily to answer green construction party Method and is fixed with nailing by covering one layer of plant plait on surface, and side slope surface color becomes green, jetting cement surface it is all More problem moments have obtained " screening ", " decoration ", side slope " temporarily multiple green " effect are fast implemented, so that side slope and surrounding enviroment scape It sees and coordinates, uniformly, not only increase civilized construction standard, and plant plait surface plastic cement grass layer is intensive, be conducive to draining, avoid Rainwater directly washes away side slope surface, is more advantageous to the stabilization of side slope.Plant plait temporarily answers green construction is simple, quick, the people of investment Power, material resources are less, and plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.
To achieve the above object, the present invention is achieved through the following technical solutions:
The interim multiple green construction method of the slope plant grass, specifically includes the following steps: slope excavating in place after, It hangs steel mesh and sprays C25 concrete, jetting cement flatness is controlled in course of injection, after injection concrete strength reaches design strength, Surface is laid with plant plait.
Further, steel mesh is having a size of 200*200mm.
Further, spray C25 concrete with a thickness of 10cm.
Further, be laid with plant plait with a thickness of 5cm.
Further, it when plant plait is laid with from the bottom to top, from left to right successively paves.
Further, the lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is tightened in paving process, is smeared It is flat, it is ensured that surface is smooth.
Further, plant plait pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
Beneficial effects of the present invention:
1, the plant plait temporarily application of green method again makes side slope color become green, and realization is temporarily multiple green, assists with surrounding enviroment Adjust unified, civilized construction standard height.
2, after plant plait covering, the problems on jetting cement surface have obtained " screening " well and " decoration ", surface are flat It is whole smooth, exquisite appearance.
3, after plant plait covering, jetting cement surface forms one layer " greenism umbrella ", and rainwater is avoided directly to wash away jetting cement Surface, and draining is smooth, conducive to the stabilization of side slope.
4, temporarily multiple green method is easy to operate, quick for plant plait, and the human and material resources of investment are less, can be recycled after engineering, Turnover utilizes, remarkable in economical benefits.
Detailed description of the invention
Fig. 1 is plant plait of the present invention temporarily multiple green front view;
Fig. 2 is plant plait of the present invention temporarily multiple green sectional view;
Fig. 3 is site operation Fig. 1 of embodiment;
Fig. 4 is site operation Fig. 2 of embodiment;
Fig. 5 is site operation Fig. 3 of embodiment.
In figure, 1- excavation face, 2- jetting cement, 3- plant plait, 4- nailing.
Specific embodiment
It, below will be to preferred reality of the invention in order to keep the purpose of the present invention, technical scheme and beneficial effects clearer It applies example to be described in detail, to facilitate the technical staff to understand.
Embodiment
The present embodiment carries out plant plait temporarily multiple green construction by taking certain section side slope as an example.
(1) process flow: slope excavating → linked network → jetting cement → plant plait paves → and nailing fixes.
(2) construction method: as shown in Figure 1, 2.
1) slope excavating: side slope is layered according to design drawing, piecemeal excavates, and every layer of excavation height is no more than 3m.
2) linked network: slope excavating in place after, hang 200*200mm steel mesh.
3) jetting cement: injection C25 concrete, thick 10cm control jetting cement flatness in course of injection.
4) plant plait paves: injection concrete strength reaches the plant plait of Manual 5cm thickness after design strength.When laying under It is supreme, from left to right successively pave.The lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is taut in paving process Tightly, it smoothes out, it is ensured that surface is smooth.
5) nailing is fixed: plant plait pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
As in Figure 3-5, it by covering one layer of plant plait on side slope surface, and is fixed with nailing, side slope surface color becomes For green, the problems moment on jetting cement surface obtained " screening ", " decoration ", fast implements side slope " temporarily multiple green " effect Fruit, so that side slope and surrounding enviroment coordination of landscape, uniformly, not only increase civilized construction standard, and plant plait surface plastic cement Grass layer is intensive, is conducive to draining, avoids rainwater and directly wash away side slope surface, be more advantageous to the stabilization of side slope.
1 Slope greening contrast of the economic effect table of table
Serial number Engineering project Connection is mixed to spray multiple green method Plant plait answers green method
1 Construction efficiency Slowly Fastly
2 Personnel's investment It is more It is few
3 Equipment investment It is more It is few
4 Comprehensive unit price (m2/ member) 150.3 25
5 Multiple green speed Slowly Fastly
6 Maintenance Artificial watering maintenance Nothing
Compared with the technology (mixed spraying multiple green method as being connected to) of existing Slope greening, plant plait temporarily multiple green construction is simple, Quickly, cost is relatively low, and the human and material resources of investment are less, and construction and multiple green speed are fast, maintenance of the later period without complexity, and And plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.
Finally, it is stated that preferred embodiment above is only used to illustrate the technical scheme of the present invention rather than limits, although logical It crosses above preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be Various changes are made to it in form and in details, without departing from claims of the present invention limited range.

Claims (7)

1. a kind of slope plant grass temporarily answers green construction method, it is characterised in that: the slope plant grass temporarily multiple green construction Method, specifically includes the following steps: slope excavating in place after, hang steel mesh and spray C25 concrete, in course of injection control spray Concrete flatness is penetrated, after injection concrete strength reaches design strength, is laid with plant plait on surface.
2. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: steel mesh size For 200*200mm.
3. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: injection C25 concrete With a thickness of 10cm.
4. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: be laid with plant Grass with a thickness of 5cm.
5. according to claim 1 or a kind of interim multiple green construction method of 4 described in any item slope plant grass, it is characterised in that: When plant plait is laid with from the bottom to top, it from left to right successively paves.
6. according to a kind of interim multiple green construction method of the described in any item slope plant grass of claim 4 or 5, it is characterised in that: The lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is tightened in paving process, is smoothed out, it is ensured that surface is smooth.
7. a kind of slope plant grass according to claim 1-6 temporarily answers green construction method, it is characterised in that: plant Object grass pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
CN201810946176.4A 2018-08-20 2018-08-20 A kind of interim multiple green construction method of slope plant grass Pending CN109258322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810946176.4A CN109258322A (en) 2018-08-20 2018-08-20 A kind of interim multiple green construction method of slope plant grass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810946176.4A CN109258322A (en) 2018-08-20 2018-08-20 A kind of interim multiple green construction method of slope plant grass

Publications (1)

Publication Number Publication Date
CN109258322A true CN109258322A (en) 2019-01-25

Family

ID=65154174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810946176.4A Pending CN109258322A (en) 2018-08-20 2018-08-20 A kind of interim multiple green construction method of slope plant grass

Country Status (1)

Country Link
CN (1) CN109258322A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85108364A (en) * 1984-10-19 1986-08-27 迈克尔·查尔斯·塔克 Stablizing of earth surfaces
JPH07197471A (en) * 1993-12-28 1995-08-01 Diatex Co Ltd Slope-covering method and slope-covering material
JPH08284172A (en) * 1995-04-14 1996-10-29 Nittoc Constr Co Ltd Green bed rock structure of concrete sprayed surface
CN1570292A (en) * 2003-07-15 2005-01-26 中国科学院地质与地球物理研究所 Surface afforestation method for anchor spraying construction slopes
JP2007023635A (en) * 2005-07-19 2007-02-01 Sekisui Jushi Co Ltd Seeding and planting method of concrete surface
CN1920185A (en) * 2005-08-24 2007-02-28 沈敏鑫 Construction method of green concrete
JP3194627U (en) * 2014-09-09 2014-12-04 大 佐久間 Artificial planting mat
CN105625440A (en) * 2014-11-05 2016-06-01 黄弘 Vegetation restoration method for rock slope and hard protection slope
CN107447765A (en) * 2017-05-24 2017-12-08 四川君羊建设集团有限公司 Side slope construction supported with framed anchor construction
CN207260168U (en) * 2017-09-22 2018-04-20 中交第一公路工程局有限公司 A kind of tufa stone side slope protection layer

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85108364A (en) * 1984-10-19 1986-08-27 迈克尔·查尔斯·塔克 Stablizing of earth surfaces
JPH07197471A (en) * 1993-12-28 1995-08-01 Diatex Co Ltd Slope-covering method and slope-covering material
JP3007250B2 (en) * 1993-12-28 2000-02-07 ダイヤテックス株式会社 Slope coating method and slope coating material
JPH08284172A (en) * 1995-04-14 1996-10-29 Nittoc Constr Co Ltd Green bed rock structure of concrete sprayed surface
CN1570292A (en) * 2003-07-15 2005-01-26 中国科学院地质与地球物理研究所 Surface afforestation method for anchor spraying construction slopes
JP2007023635A (en) * 2005-07-19 2007-02-01 Sekisui Jushi Co Ltd Seeding and planting method of concrete surface
CN1920185A (en) * 2005-08-24 2007-02-28 沈敏鑫 Construction method of green concrete
JP3194627U (en) * 2014-09-09 2014-12-04 大 佐久間 Artificial planting mat
CN105625440A (en) * 2014-11-05 2016-06-01 黄弘 Vegetation restoration method for rock slope and hard protection slope
CN107447765A (en) * 2017-05-24 2017-12-08 四川君羊建设集团有限公司 Side slope construction supported with framed anchor construction
CN207260168U (en) * 2017-09-22 2018-04-20 中交第一公路工程局有限公司 A kind of tufa stone side slope protection layer

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
蒙莉莉: "德兴铜矿生态恢复工程研究 ", 《科技情报开发与经济》 *
郭松等: "基于红色文化特色的南百高速公路绿化改造研究 ", 《中外公路》 *
鲁通: "公路与环保 ", 《中国公路》 *

Similar Documents

Publication Publication Date Title
CN103866669B (en) The preparation method that a kind of surface different colours or material aggregate realize the cement permeable concrete ground structure of fade effect
CN206667272U (en) A kind of slope vegetation protection structure
CN106988323B (en) A kind of construction method of silty clay degree of being backfilling and compacted control
CN109258322A (en) A kind of interim multiple green construction method of slope plant grass
US20220210985A1 (en) Greenhouse and indoor cultivation method for stropharia stropharia
CN110073768A (en) A kind of high altitude localities side slope Spray turfing construction method
CN2816109Y (en) Film applicating machine for nourishing nd wet-retaining protective film in road construction
CN202482736U (en) Honeycomb geotechnical lattice room
CN105155388A (en) Road surface laying method for exposed aggregate finish
CN204238225U (en) High steep rock slope active defense facility
CN109056750A (en) A kind of vegetation ecological concrete protection blended stock and its construction method
CN205848131U (en) A kind of ecological afforestation enclosure wall
CN205912566U (en) Be applied to slope surface structure's landscape plant growing device
CN109989523A (en) A kind of clear water moulding green concrete column Nest architecture and way
CN104372877A (en) Construction method for tall vertical stone water curtain wall
CN206536921U (en) A kind of environmentally friendly lawn plate
CN1680664A (en) Slope planting engineering structure with nonwoven fabrics for protection of culture media
CN207376776U (en) slit type drainage ditch
CN208469434U (en) Band cavern and stream ramp piling and layout of stones artificial hillock
CN207314086U (en) A kind of stone material permeable pavement Rotating fields
CN204000903U (en) Slope protection greening net
CN206736930U (en) Ecological revetment brick and ecological revetment
CN110629768A (en) Method for constructing green assembled permanent side slope protective surface layer
CN206467536U (en) Suitable for the modular ecological pavement brick of garden landscape
CN207176424U (en) A kind of landscape walkway intersection beautifying apparatus

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190125

RJ01 Rejection of invention patent application after publication