CN109258322A - A kind of interim multiple green construction method of slope plant grass - Google Patents
A kind of interim multiple green construction method of slope plant grass Download PDFInfo
- Publication number
- CN109258322A CN109258322A CN201810946176.4A CN201810946176A CN109258322A CN 109258322 A CN109258322 A CN 109258322A CN 201810946176 A CN201810946176 A CN 201810946176A CN 109258322 A CN109258322 A CN 109258322A
- Authority
- CN
- China
- Prior art keywords
- plant
- slope
- construction method
- side slope
- grass
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G20/00—Cultivation of turf, lawn or the like; Apparatus or methods therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Environmental Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Cultivation Of Plants (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The present invention relates to a kind of slope plant grass temporarily to answer green construction method, belong to slope construction technical field, the present invention is by covering one layer of plant plait on side slope surface, and it is fixed with nailing, so that side slope surface color becomes green, the problems moment on jetting cement surface has obtained " screening ", " decoration ", fast implement side slope " temporarily multiple green " effect, so that side slope and surrounding enviroment coordination of landscape, it is unified, not only increase civilized construction standard, and plant plait surface plastic cement grass layer is intensive, conducive to draining, it avoids rainwater and directly washes away side slope surface, it is more advantageous to the stabilization of side slope.The interim multiple green construction is simple, quickly of plant plait, the human and material resources of investment are less, and plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.
Description
Technical field
The invention belongs to slope construction technical fields, specifically, are related to a kind of slope plant grass temporarily multiple green construction party
Method.
Background technique
Current city track traffic engineering development scale more and more rapidly, grow, bring is the convenience, fast of people's trip
It is prompt.And the raising by a relatively large margin that nowadays people's nontimber forest and living standard also obtain, life Happiness Index
Also it is improving, the requirement to environment is also gradually improving.
The particularity of city track traffic engineering itself, engineering in general is in city, edge, even in city prosperity
The sensitive areas such as area, residential block require civilized construction in construction site especially high.For there are road slope or bases in building site
Interim slope project is cheated, in construction period, usually in the injection 10cm thickness C25 concrete gib of side slope surface until engineering terminates again
It backfills, is multiple green.Because jetting cement main component is cement, sand, surface color is canescence, is not assisted with the trees on periphery, careless landscape
It adjusts, civilized construction standard is relatively low.Moreover, jetting cement sprays anchor during jet-anchor execution, by side slope brush slope flatness, spray gun hand
The influence of the human factors such as technical level, jetting cement surface smoothness is poor, and generally there are anchor pole, drain hole in jetting cement surface in addition
Etc. exposed component, sprays anchor flatness problem and become apparent.In addition, jetting cement is because construction needs, segmentation, piecemeal are applied under normal conditions
Inevitably there is color difference in work.At the same time, over time, surface inevitably will appear to be split side slope jetting cement
It stitches, fall off, the scenes such as scale, jetting cement surface treatment trace, color difference become apparent after repairing, so that jetting cement surface is not beautiful
Sight, harmony are worse, and civilized construction standard is lower, and deal with work consuming time-consuming again, uneconomical.
Summary of the invention
In order to solve the problems, such as background technique, the present invention provides a kind of slope plant grass temporarily to answer green construction party
Method and is fixed with nailing by covering one layer of plant plait on surface, and side slope surface color becomes green, jetting cement surface it is all
More problem moments have obtained " screening ", " decoration ", side slope " temporarily multiple green " effect are fast implemented, so that side slope and surrounding enviroment scape
It sees and coordinates, uniformly, not only increase civilized construction standard, and plant plait surface plastic cement grass layer is intensive, be conducive to draining, avoid
Rainwater directly washes away side slope surface, is more advantageous to the stabilization of side slope.Plant plait temporarily answers green construction is simple, quick, the people of investment
Power, material resources are less, and plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.
To achieve the above object, the present invention is achieved through the following technical solutions:
The interim multiple green construction method of the slope plant grass, specifically includes the following steps: slope excavating in place after,
It hangs steel mesh and sprays C25 concrete, jetting cement flatness is controlled in course of injection, after injection concrete strength reaches design strength,
Surface is laid with plant plait.
Further, steel mesh is having a size of 200*200mm.
Further, spray C25 concrete with a thickness of 10cm.
Further, be laid with plant plait with a thickness of 5cm.
Further, it when plant plait is laid with from the bottom to top, from left to right successively paves.
Further, the lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is tightened in paving process, is smeared
It is flat, it is ensured that surface is smooth.
Further, plant plait pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
Beneficial effects of the present invention:
1, the plant plait temporarily application of green method again makes side slope color become green, and realization is temporarily multiple green, assists with surrounding enviroment
Adjust unified, civilized construction standard height.
2, after plant plait covering, the problems on jetting cement surface have obtained " screening " well and " decoration ", surface are flat
It is whole smooth, exquisite appearance.
3, after plant plait covering, jetting cement surface forms one layer " greenism umbrella ", and rainwater is avoided directly to wash away jetting cement
Surface, and draining is smooth, conducive to the stabilization of side slope.
4, temporarily multiple green method is easy to operate, quick for plant plait, and the human and material resources of investment are less, can be recycled after engineering,
Turnover utilizes, remarkable in economical benefits.
Detailed description of the invention
Fig. 1 is plant plait of the present invention temporarily multiple green front view;
Fig. 2 is plant plait of the present invention temporarily multiple green sectional view;
Fig. 3 is site operation Fig. 1 of embodiment;
Fig. 4 is site operation Fig. 2 of embodiment;
Fig. 5 is site operation Fig. 3 of embodiment.
In figure, 1- excavation face, 2- jetting cement, 3- plant plait, 4- nailing.
Specific embodiment
It, below will be to preferred reality of the invention in order to keep the purpose of the present invention, technical scheme and beneficial effects clearer
It applies example to be described in detail, to facilitate the technical staff to understand.
Embodiment
The present embodiment carries out plant plait temporarily multiple green construction by taking certain section side slope as an example.
(1) process flow: slope excavating → linked network → jetting cement → plant plait paves → and nailing fixes.
(2) construction method: as shown in Figure 1, 2.
1) slope excavating: side slope is layered according to design drawing, piecemeal excavates, and every layer of excavation height is no more than 3m.
2) linked network: slope excavating in place after, hang 200*200mm steel mesh.
3) jetting cement: injection C25 concrete, thick 10cm control jetting cement flatness in course of injection.
4) plant plait paves: injection concrete strength reaches the plant plait of Manual 5cm thickness after design strength.When laying under
It is supreme, from left to right successively pave.The lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is taut in paving process
Tightly, it smoothes out, it is ensured that surface is smooth.
5) nailing is fixed: plant plait pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
As in Figure 3-5, it by covering one layer of plant plait on side slope surface, and is fixed with nailing, side slope surface color becomes
For green, the problems moment on jetting cement surface obtained " screening ", " decoration ", fast implements side slope " temporarily multiple green " effect
Fruit, so that side slope and surrounding enviroment coordination of landscape, uniformly, not only increase civilized construction standard, and plant plait surface plastic cement
Grass layer is intensive, is conducive to draining, avoids rainwater and directly wash away side slope surface, be more advantageous to the stabilization of side slope.
1 Slope greening contrast of the economic effect table of table
Serial number | Engineering project | Connection is mixed to spray multiple green method | Plant plait answers green method |
1 | Construction efficiency | Slowly | Fastly |
2 | Personnel's investment | It is more | It is few |
3 | Equipment investment | It is more | It is few |
4 | Comprehensive unit price (m2/ member) | 150.3 | 25 |
5 | Multiple green speed | Slowly | Fastly |
6 | Maintenance | Artificial watering maintenance | Nothing |
Compared with the technology (mixed spraying multiple green method as being connected to) of existing Slope greening, plant plait temporarily multiple green construction is simple,
Quickly, cost is relatively low, and the human and material resources of investment are less, and construction and multiple green speed are fast, maintenance of the later period without complexity, and
And plant plait can turnaround cycle utilize, economic benefit and social benefit are obvious.
Finally, it is stated that preferred embodiment above is only used to illustrate the technical scheme of the present invention rather than limits, although logical
It crosses above preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be
Various changes are made to it in form and in details, without departing from claims of the present invention limited range.
Claims (7)
1. a kind of slope plant grass temporarily answers green construction method, it is characterised in that: the slope plant grass temporarily multiple green construction
Method, specifically includes the following steps: slope excavating in place after, hang steel mesh and spray C25 concrete, in course of injection control spray
Concrete flatness is penetrated, after injection concrete strength reaches design strength, is laid with plant plait on surface.
2. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: steel mesh size
For 200*200mm.
3. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: injection C25 concrete
With a thickness of 10cm.
4. a kind of slope plant grass according to claim 1 temporarily answers green construction method, it is characterised in that: be laid with plant
Grass with a thickness of 5cm.
5. according to claim 1 or a kind of interim multiple green construction method of 4 described in any item slope plant grass, it is characterised in that:
When plant plait is laid with from the bottom to top, it from left to right successively paves.
6. according to a kind of interim multiple green construction method of the described in any item slope plant grass of claim 4 or 5, it is characterised in that:
The lap of splice is 10cm between every piece of plant plait, and each angle of plant plait is tightened in paving process, is smoothed out, it is ensured that surface is smooth.
7. a kind of slope plant grass according to claim 1-6 temporarily answers green construction method, it is characterised in that: plant
Object grass pave it is smooth after fixed with nailing, nailing arrange spacing be 1.0*1.0m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810946176.4A CN109258322A (en) | 2018-08-20 | 2018-08-20 | A kind of interim multiple green construction method of slope plant grass |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810946176.4A CN109258322A (en) | 2018-08-20 | 2018-08-20 | A kind of interim multiple green construction method of slope plant grass |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109258322A true CN109258322A (en) | 2019-01-25 |
Family
ID=65154174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810946176.4A Pending CN109258322A (en) | 2018-08-20 | 2018-08-20 | A kind of interim multiple green construction method of slope plant grass |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109258322A (en) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85108364A (en) * | 1984-10-19 | 1986-08-27 | 迈克尔·查尔斯·塔克 | Stablizing of earth surfaces |
JPH07197471A (en) * | 1993-12-28 | 1995-08-01 | Diatex Co Ltd | Slope-covering method and slope-covering material |
JPH08284172A (en) * | 1995-04-14 | 1996-10-29 | Nittoc Constr Co Ltd | Green bed rock structure of concrete sprayed surface |
CN1570292A (en) * | 2003-07-15 | 2005-01-26 | 中国科学院地质与地球物理研究所 | Surface afforestation method for anchor spraying construction slopes |
JP2007023635A (en) * | 2005-07-19 | 2007-02-01 | Sekisui Jushi Co Ltd | Seeding and planting method of concrete surface |
CN1920185A (en) * | 2005-08-24 | 2007-02-28 | 沈敏鑫 | Construction method of green concrete |
JP3194627U (en) * | 2014-09-09 | 2014-12-04 | 大 佐久間 | Artificial planting mat |
CN105625440A (en) * | 2014-11-05 | 2016-06-01 | 黄弘 | Vegetation restoration method for rock slope and hard protection slope |
CN107447765A (en) * | 2017-05-24 | 2017-12-08 | 四川君羊建设集团有限公司 | Side slope construction supported with framed anchor construction |
CN207260168U (en) * | 2017-09-22 | 2018-04-20 | 中交第一公路工程局有限公司 | A kind of tufa stone side slope protection layer |
-
2018
- 2018-08-20 CN CN201810946176.4A patent/CN109258322A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85108364A (en) * | 1984-10-19 | 1986-08-27 | 迈克尔·查尔斯·塔克 | Stablizing of earth surfaces |
JPH07197471A (en) * | 1993-12-28 | 1995-08-01 | Diatex Co Ltd | Slope-covering method and slope-covering material |
JP3007250B2 (en) * | 1993-12-28 | 2000-02-07 | ダイヤテックス株式会社 | Slope coating method and slope coating material |
JPH08284172A (en) * | 1995-04-14 | 1996-10-29 | Nittoc Constr Co Ltd | Green bed rock structure of concrete sprayed surface |
CN1570292A (en) * | 2003-07-15 | 2005-01-26 | 中国科学院地质与地球物理研究所 | Surface afforestation method for anchor spraying construction slopes |
JP2007023635A (en) * | 2005-07-19 | 2007-02-01 | Sekisui Jushi Co Ltd | Seeding and planting method of concrete surface |
CN1920185A (en) * | 2005-08-24 | 2007-02-28 | 沈敏鑫 | Construction method of green concrete |
JP3194627U (en) * | 2014-09-09 | 2014-12-04 | 大 佐久間 | Artificial planting mat |
CN105625440A (en) * | 2014-11-05 | 2016-06-01 | 黄弘 | Vegetation restoration method for rock slope and hard protection slope |
CN107447765A (en) * | 2017-05-24 | 2017-12-08 | 四川君羊建设集团有限公司 | Side slope construction supported with framed anchor construction |
CN207260168U (en) * | 2017-09-22 | 2018-04-20 | 中交第一公路工程局有限公司 | A kind of tufa stone side slope protection layer |
Non-Patent Citations (3)
Title |
---|
蒙莉莉: "德兴铜矿生态恢复工程研究 ", 《科技情报开发与经济》 * |
郭松等: "基于红色文化特色的南百高速公路绿化改造研究 ", 《中外公路》 * |
鲁通: "公路与环保 ", 《中国公路》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103866669B (en) | The preparation method that a kind of surface different colours or material aggregate realize the cement permeable concrete ground structure of fade effect | |
CN206667272U (en) | A kind of slope vegetation protection structure | |
CN106988323B (en) | A kind of construction method of silty clay degree of being backfilling and compacted control | |
CN109258322A (en) | A kind of interim multiple green construction method of slope plant grass | |
US20220210985A1 (en) | Greenhouse and indoor cultivation method for stropharia stropharia | |
CN110073768A (en) | A kind of high altitude localities side slope Spray turfing construction method | |
CN2816109Y (en) | Film applicating machine for nourishing nd wet-retaining protective film in road construction | |
CN202482736U (en) | Honeycomb geotechnical lattice room | |
CN105155388A (en) | Road surface laying method for exposed aggregate finish | |
CN204238225U (en) | High steep rock slope active defense facility | |
CN109056750A (en) | A kind of vegetation ecological concrete protection blended stock and its construction method | |
CN205848131U (en) | A kind of ecological afforestation enclosure wall | |
CN205912566U (en) | Be applied to slope surface structure's landscape plant growing device | |
CN109989523A (en) | A kind of clear water moulding green concrete column Nest architecture and way | |
CN104372877A (en) | Construction method for tall vertical stone water curtain wall | |
CN206536921U (en) | A kind of environmentally friendly lawn plate | |
CN1680664A (en) | Slope planting engineering structure with nonwoven fabrics for protection of culture media | |
CN207376776U (en) | slit type drainage ditch | |
CN208469434U (en) | Band cavern and stream ramp piling and layout of stones artificial hillock | |
CN207314086U (en) | A kind of stone material permeable pavement Rotating fields | |
CN204000903U (en) | Slope protection greening net | |
CN206736930U (en) | Ecological revetment brick and ecological revetment | |
CN110629768A (en) | Method for constructing green assembled permanent side slope protective surface layer | |
CN206467536U (en) | Suitable for the modular ecological pavement brick of garden landscape | |
CN207176424U (en) | A kind of landscape walkway intersection beautifying apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190125 |
|