CN1858353A - Cement asphalt mortar injection bag type pouring method - Google Patents
Cement asphalt mortar injection bag type pouring method Download PDFInfo
- Publication number
- CN1858353A CN1858353A CN 200610020623 CN200610020623A CN1858353A CN 1858353 A CN1858353 A CN 1858353A CN 200610020623 CN200610020623 CN 200610020623 CN 200610020623 A CN200610020623 A CN 200610020623A CN 1858353 A CN1858353 A CN 1858353A
- Authority
- CN
- China
- Prior art keywords
- mortar
- pouring method
- bag type
- type pouring
- injection bag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The present invention discloses cement asphalt (CA) mortar injection bag type pouring method, and belongs to the field of building construction technology. The pouring method includes the following steps: spreading injected bags, spreading and regulating positioning track boards, pouring CA mortar, and removing support screws after 24 hr and reaching strength of 0.1 MPa. The present invention is used for jointing between the track board and the pedestal, and can reach the close jointing and long service life of the track, and produce certain regulating and buffering effect.
Description
Technical field
The present invention relates to a kind of constructional materials, be specifically related to a kind of method for filling of mortar.
Background technology
Along with the development of society, the common target of pursuing in high-speed railway transportation having become countries in the world.For the requirement of the high stationarity that adapts to high-speed railway, high-durability, comfortableness, need to adopt and the ballastless track of the few maintenance of development.The rail that ballastless track adopts is directly installed on the track plate, and track slab pavement is on footing foundation.Because footing foundation and track plate all are steel concrete builds and form, both can not direct closely connected joint, therefore, need add between footing foundation and track plate and adjust layer, makes both tightly engage.
Summary of the invention
The objective of the invention is to: provide a kind of cement asphalt mortar that will have adjustment, shock-absorbing capacity to be poured into method between footing foundation and the track plate.
Technical scheme of the present invention is: a kind of cement asphalt mortar injection bag type pouring method is characterized in that:
Mainly contain following steps:
A, cement asphalt mortar is injected bag be tiled on the rail bed basis, and it is folding fixing; On the track plate carrying bolt is installed, carrying bolt props up and stands on the footing foundation; The laid rail guidance tape also is adjusted to desired location with it; Open cement asphalt mortar and inject bag, and wrinkle must not be arranged;
B, the perfusing hole of mixer and cement asphalt mortar are injected a bag inlet firmly be connected, open the perfusing hole by-pass valve control, cement asphalt mortar injects cement asphalt mortar and injects in the bag, the cement asphalt mortar height reaches more than the 70mm in the perfusing hole of cement asphalt mortar injection bag opposite side, and after closely connected at the bottom of the plate, perfusion finishes;
The perfusion of c, cement asphalt mortar finish reach 0.1MPa through 24 hours and intensity after, in time remove carrying bolt.In order to reach better technique effect, the present invention can also have following feature:
Every block of track plate is poured into by the fill orifice of a side.
The cement injection asphalt mortar, bituminous mortar should carry out under 5~25 ℃ environment temperature.
Cement asphalt mortar if be placed in the surge tank, must keep 10~30 rev/mins mixing speed after mixing and stirring.
In longitudinal gradient and curve area, should be from low side inlet cement injection asphalt mortar, bituminous mortar, and cement asphalt mortar injects bag and be fixed on the footing foundation with the footing foundation contact surface, prevent that cement asphalt mortar from injecting that bag slides or displacement.
Cement asphalt mortar should once pour into and finish under every block of track plate.
After described carrying bolt is removed,, make it be beneficial to draining by designing requirement finishing cement asphalt mortar layer edge.
Paste the section of rubber spacer in track plate bottom, the thickness range of cement asphalt mortar layer is 30~100mm; The thickness range of other section cement asphalt mortar layers at the bottom of the track plate is 40~100mm.
Described track plate or slab track plate, or frame rail plate.
Described carrying bolt is installed on the lifting nut of track plate.
Need to prove: cement asphalt mortar is commonly called the CA mortar on engineering.
The invention has the beneficial effects as follows: can be so that track plate and footing foundation tightly engage, and have and adjust and the buffering effect, make track have certain elasticity simultaneously, thereby can strengthen the application life of track.
Description of drawings
Fig. 1 is that the present invention pours into the front view when finishing;
Fig. 2 is the lateral view of Fig. 1;
Fig. 3 is the vertical view of embodiment 1;
Wherein, Reference numeral is, 1 is footing foundation, and 2 is the slab track plate, and 3 is the cement asphalt mortar layer, and 4 is carrying bolt, and 5 is connecting bolt, and 6 is that cement asphalt mortar injects a bag inlet, and 7 be the frame rail plate, and 8 is that the track plate lifts by crane nut.
The specific embodiment
As Fig. 1, Fig. 2 and shown in Figure 3, a kind of cement asphalt mortar injection bag type pouring method mainly contains following steps:
A, cement asphalt mortar is injected bag be tiled on the rail bed basis 1, and it is folding fixing; The connecting bolt 5 of level is housed on track plate lifting nut 8, and the steel plate on the connecting bolt 5 is provided with screwed hole, and carrying bolt 4 passes this screwed hole and props up and stands on the footing foundation 1; Laid rail guidance tape 2 also is adjusted to desired location with it; It is folding to open cement asphalt mortar injection bag, and wrinkle must not be arranged;
B, the perfusing hole of mixer and cement asphalt mortar are injected a bag inlet 6 firmly be connected, open the perfusing hole by-pass valve control, cement asphalt mortar injects cement asphalt mortar and injects in the bag, the cement asphalt mortar height reaches more than the 70mm in the perfusing hole of cement asphalt mortar injection bag opposite side, and after closely connected at the bottom of the plate, perfusion finishes; Cement asphalt mortar under every block of track plate should once pour into to be finished;
The perfusion of c, cement asphalt mortar finish reach 0.1MPa through 24 hours and intensity after, in time remove carrying bolt;
D, by the edge of designing requirement finishing screed 3, make it be beneficial to draining.
As Fig. 1, Fig. 2 and shown in Figure 4, a kind of cement asphalt mortar injection bag type pouring method mainly contains following steps:
A, cement asphalt mortar is injected bag be tiled on the rail bed basis 1, and it is folding fixing; The connecting bolt 5 of level is housed on track plate lifting nut 8, and the steel plate on the connecting bolt 5 is provided with screwed hole, and carrying bolt 4 passes this screwed hole and props up and stands on the footing foundation 1; Lay frame rail plate 7 and it is adjusted to desired location; It is folding to open cement asphalt mortar injection bag, and wrinkle must not be arranged; Paste the section of rubber spacer in frame rail plate 7 bottoms, the thickness of cement asphalt mortar layer 3 is 30~100mm; The thickness of other section cement asphalt mortar layers at 7 ends of frame rail plate is 40~100mm.
B, in longitudinal gradient and curve area, should be from low side inlet cement injection asphalt mortar, bituminous mortar, and cement asphalt mortar injects bag and be fixed on the footing foundation with the footing foundation contact surface, prevent that cement asphalt mortar from injecting that bag slides or displacement;
C, cement injection asphalt mortar, bituminous mortar carry out under 5~25 ℃ environment temperature;
D, the perfusing hole of mixer and cement asphalt mortar are injected a bag inlet 6 firmly be connected, open the perfusing hole by-pass valve control, cement asphalt mortar injects cement asphalt mortar and injects in the bag, the cement asphalt mortar height reaches more than the 70mm in the perfusing hole of cement asphalt mortar injection bag opposite side, and after closely connected at the bottom of the plate, perfusion finishes;
The perfusion of e, cement asphalt mortar finish reach 0.1MPa through 24 hours and intensity after, in time remove carrying bolt 4;
F, by the edge of designing requirement finishing screed 3.
In filling process, note following item:
1. cement asphalt mortar is placed in the surge tank after mixing and stirring, and must keep 10~30 rev/mins mixing speed.
2. every block of track plate is poured into by the fill orifice of a side.
3. the cement asphalt mortar under every block of track plate should once pour into and finish.
4. mixing cement asphalt mortar after the system should pour at the appointed time and finish.
Claims (10)
1, a kind of CA mortar injection bag type pouring method is characterized in that: mainly contain following steps:
A, the CA mortar is injected bag be tiled on the rail bed basis (1), and it is folding fixing; Carrying bolt (4) is installed on the track plate, and carrying bolt (4) props up and stands on the footing foundation (1); Laid rail guidance tape (2) also is adjusted to desired location with it; Open the CA mortar and inject bag, and wrinkle must not be arranged;
B, the perfusing hole of mixer and CA mortar are injected a bag inlet (6) firmly be connected, open the perfusing hole by-pass valve control, the CA mortar injects the CA mortar and injects in the bag, and CA mortar height reaches more than the 70mm in the perfusing hole of CA mortar injection bag opposite side, and after closely connected at the bottom of the plate, perfusion finishes;
C, CA mortar injection finish reach 0.1MPa through 24 hours and intensity after, in time remove carrying bolt.
2, CA mortar injection bag type pouring method according to claim 1 is characterized in that: every block of track plate is poured into by the fill orifice that injects bag one side.
3, CA mortar injection bag type pouring method according to claim 1 is characterized in that: perfusion CA mortar should carry out under 5~25 ℃ environment temperature.
4, according to claim 1 or 3 described CA mortar injection bag type pouring methods, it is characterized in that: the CA mortar if be placed in the buffering perfusion jar, must keep 10~30 rev/mins mixing speed after mixing and stirring.
5, CA mortar injection bag type pouring method according to claim 1 is characterized in that: in longitudinal gradient and curve area, should pour into the CA mortar from low side inlet, and CA mortar injection bag is fixed on the footing foundation (1) with footing foundation (1) contact surface.
6, CA mortar injection bag type pouring method according to claim 1 is characterized in that: the CA mortar should once pour into and finish under every block of track plate.
7, CA mortar injection bag type pouring method according to claim 1 is characterized in that: after described carrying bolt (4) is removed, by designing requirement finishing CA screed (3) edge.
8, CA mortar injection bag type pouring method according to claim 1 is characterized in that: paste the section of rubber spacer in track plate bottom, the thickness range of CA screed (3) is 30~100mm; The thickness range of other sections CA screed (3) at the bottom of the track plate is 40~100mm.
9, CA mortar injection bag type pouring method according to claim 1 is characterized in that: described track plate or slab track plate (2), or frame rail plate (7).
10, CA mortar injection bag type pouring method according to claim 1 is characterized in that: described carrying bolt (4) is installed on the lifting nut (8) of track plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200610020623 CN1858353A (en) | 2006-03-30 | 2006-03-30 | Cement asphalt mortar injection bag type pouring method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200610020623 CN1858353A (en) | 2006-03-30 | 2006-03-30 | Cement asphalt mortar injection bag type pouring method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN1858353A true CN1858353A (en) | 2006-11-08 |
Family
ID=37297304
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200610020623 Pending CN1858353A (en) | 2006-03-30 | 2006-03-30 | Cement asphalt mortar injection bag type pouring method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1858353A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101851884A (en) * | 2010-03-23 | 2010-10-06 | 中国建筑股份有限公司 | Construction method for paving CRTS I-type plate-type ballastless track plate in severe cold area |
CN101245580B (en) * | 2007-12-28 | 2011-03-16 | 中铁二局股份有限公司 | Asphalt mortar bottling method for rail plate |
CN101748665B (en) * | 2009-12-22 | 2011-07-27 | 中铁二局股份有限公司 | Fragment-free track slab pavement method |
CN102433809A (en) * | 2011-10-08 | 2012-05-02 | 中铁十二局集团有限公司 | Hopper for pouring cement emulsified asphalt mortar and pouring method thereof |
CN102535274A (en) * | 2012-02-19 | 2012-07-04 | 中交第四公路工程局有限公司 | Closure and edge-banding device and edge-banding method for CA (cement asphalt) mortar injection for high-speed rail ballastless track |
CN103757993A (en) * | 2013-12-27 | 2014-04-30 | 北京中铁瑞威基础工程有限公司 | System and method for high-speed railway subgrade settlement restoration |
-
2006
- 2006-03-30 CN CN 200610020623 patent/CN1858353A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101245580B (en) * | 2007-12-28 | 2011-03-16 | 中铁二局股份有限公司 | Asphalt mortar bottling method for rail plate |
CN101748665B (en) * | 2009-12-22 | 2011-07-27 | 中铁二局股份有限公司 | Fragment-free track slab pavement method |
CN101851884A (en) * | 2010-03-23 | 2010-10-06 | 中国建筑股份有限公司 | Construction method for paving CRTS I-type plate-type ballastless track plate in severe cold area |
CN102433809A (en) * | 2011-10-08 | 2012-05-02 | 中铁十二局集团有限公司 | Hopper for pouring cement emulsified asphalt mortar and pouring method thereof |
CN102433809B (en) * | 2011-10-08 | 2013-07-17 | 中铁十二局集团有限公司 | Hopper for pouring cement emulsified asphalt mortar and pouring method thereof |
CN102535274A (en) * | 2012-02-19 | 2012-07-04 | 中交第四公路工程局有限公司 | Closure and edge-banding device and edge-banding method for CA (cement asphalt) mortar injection for high-speed rail ballastless track |
CN103757993A (en) * | 2013-12-27 | 2014-04-30 | 北京中铁瑞威基础工程有限公司 | System and method for high-speed railway subgrade settlement restoration |
CN103757993B (en) * | 2013-12-27 | 2016-02-17 | 北京中铁瑞威基础工程有限公司 | High-speed railway subgrade sedimentation repair system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1858353A (en) | Cement asphalt mortar injection bag type pouring method | |
CN100346033C (en) | Pre-assembled plate consisting of armoured concrete | |
CN1948622A (en) | Polymer modified cement hole concrete road surface structure and construction method | |
CN102839601A (en) | Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure | |
CN202787055U (en) | Pier fixed connection structure of steel structure overhead bridge | |
CN103321111A (en) | Tramcar track continuous-laying construction method | |
CN1587531A (en) | Method for anti-cracking in hogging moment area of steel-concrete combined beam | |
CN102102315B (en) | Method for constructing sleeper bolted elastic crossing | |
CN1858354A (en) | Cement asphalt mortar vertical mould type pouring method | |
CN105239502A (en) | Uniform force transmission device used for bridge support and installation method of uniform force transmission device | |
CN215947749U (en) | Prefabricated assembled ballast bed | |
CN112176813B (en) | Asphalt concrete pavement maintenance structure and method thereof | |
CN105239484A (en) | Road surface structure suitable for heavy-duty traffic | |
CN105297620A (en) | Steel plate spherical crown polymer mortar structure support and construction method thereof | |
CN112030630A (en) | Grouting bag for ballastless track adjusting layer and using method thereof | |
JP2010053511A (en) | Method for constructing road with smooth face material | |
CN204000522U (en) | A kind of novel roadbed retaining structure | |
CN1818212A (en) | Plated rail without ballast | |
RU2318947C2 (en) | Road paving construction method | |
CN207176527U (en) | Bridge Crack bracing means | |
CN205188803U (en) | Steel sheet spherical crown polymer mortar structure support | |
CN211522841U (en) | Road bridge transition lap joint plate device | |
CN1222617A (en) | Composite concrete floor board with stone facing and its fabrication and paving process | |
CN108894098B (en) | Bridge slab base for solving problem of vehicle bump at bridge head and method for solving problem of vehicle bump at bridge head | |
CN102296969A (en) | Tunnel compartment wall lining construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |