CN116014893A - Remote visual intelligent inspection system for transformer substation - Google Patents
Remote visual intelligent inspection system for transformer substation Download PDFInfo
- Publication number
- CN116014893A CN116014893A CN202211702340.XA CN202211702340A CN116014893A CN 116014893 A CN116014893 A CN 116014893A CN 202211702340 A CN202211702340 A CN 202211702340A CN 116014893 A CN116014893 A CN 116014893A
- Authority
- CN
- China
- Prior art keywords
- management
- recording
- layer
- data
- fault
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The invention discloses a remote visual intelligent patrol system of a transformer substation, which comprises: the station control layer is used for completing the functions of centralized storage and access of data, protection information management, running state monitoring, operation control and configuration management of a monitoring system and locking incorrect operation; the spacer layer is used for carrying out on-site protection, measurement and control and fault recording on the equipment in the station; and the process layer is used for realizing all relevant functions of the interface with the primary equipment and converting the acquired analog quantity into digital quantity to be provided for an upper layer. The operation and maintenance personnel can make a good inspection plan in the intelligent inspection system, the intelligent inspection system comprises corresponding detection areas, detection equipment, detection projects and other contents, the intelligent inspection system automatically stores analysis results, pictures and alarm information into the system according to the configured plan, and the inspection results are automatically imported into the visualization platform, so that substation inspection tasks can be intelligently, efficiently, safely, low in cost and high in accuracy.
Description
Technical Field
The invention relates to the technical field of intelligent patrol of transformer substations, in particular to a remote visual intelligent patrol system of a transformer substation.
Background
Substation intellectualization is an important component of smart power grids, and future substations will be towards the trend of intelligent substations. The transformer equipment is the foundation of the transformer substation, the reliable and safe operation of the transformer substation is related to the production safety and the corresponding social benefit of the transformer substation, and the safety and the stability of the intelligent power grid are greatly influenced. An important link in the transformer substation management work is transformer substation inspection, and the link can inspect the running condition of equipment to master the running rule of the equipment in real time, so that the stable and safe work of the transformer substation is ensured. The substation equipment inspection work and the importance thereof can avoid unnecessary loss if the hidden problem of the equipment can be found in time, and plays an important role in enhancing the safety and economic operation index of the power supply system.
Therefore, the equipment of the substation needs to be checked regularly. However, most of the current transformer substations do not have a unified inspection management method by adopting a paper recording mode, and many disadvantages and shortcomings exist.
(1) Inspection personnel leak inspection. The transformer substation equipment is numerous, and a conventional 220kV transformer substation is generally provided with 2 primary equipment such as a 200kV main transformer, outlet intervals of various voltage levels, a 10kV capacitor, a reactor, PT and the like, and also has secondary equipment such as various protection screens and the like, so that the layout is complex, and inspection workers are easy to miss inspection. The inspection is not detailed enough, and the operators pay more attention to the primary equipment such as transformers, CT, PT and the like, and usually neglect the secondary equipment which is remote in places. Moreover, the transformer substation reserves enough margin from the new production, and many intervals are not put into operation, and the transformer substation needs to be extended according to the economic development in the later operation process, so that inspection personnel can easily miss inspection of new equipment according to subjective experience.
(2) The inspection tool is not uniform. The defects of most equipment such as the heating of a knife switch interface cannot be identified by naked eyes, and the assistance of equipment of an infrared thermometer is needed. The unattended transformer substation is a transformer substation with a plurality of patrol center pipes, each transformer substation cannot be provided with expensive instruments, the transformer substation is uniformly placed in the patrol center, and the transformer substation is carried by patrol personnel when the transformer substation needs to be patrol. However, in daily practice, the inspection personnel easily forget to carry or forget to carry, or forget to perform routine inspection on auxiliary instruments, and often find that the instruments with the past are dead or damaged, cannot be used, and influence the inspection quality.
(3) The inspection time is too short. The inspection content of the power transformation equipment is many, the standard is strict, the inspection is required to be performed strictly, and enough inspection time is required to be ensured. Therefore, the quality of inspection is greatly dependent on the time for the operator to inspect the equipment. The common working intensity before of the operators in the someone duty mode is lower, the workload is greatly increased after the inspection center is established, the number of substations to be inspected is increased, and a part of operators are led to be led to practice during the inspection. The inspection is not in place, responsibility of running inspection personnel is not strong, the inspection work is performed on tigers, work output is not performed, equipment defects are easily seen, and big errors are generated. Therefore, it is necessary to make a scientific inspection route to improve the inspection rate.
Because no person on duty handles on site for the first time when no person on duty substation equipment has an accident, the equipment is inspected, and the fact that the equipment with defects or abnormality is found in time is the important thing in running work. Because a strict inspection standard is not formulated, the inspection standard and the operation method of specific equipment in the transformer substation are not standardized, task information of tasks of each transformer substation equipment is lacking, whether workers carefully and carefully fulfill working obligations is difficult to ensure for daily inspection, special inspection and night inspection, visual management of inspection conditions and corresponding equipment is not facilitated for management staff, the inquiry function is difficult to realize by the traditional paper information recording method, the operation is extremely complicated, and the intelligent operation is completely insufficient. Therefore, it is necessary to design a remote visual intelligent patrol system for the transformer substation.
Disclosure of Invention
Aiming at the situation, in order to overcome the defects of the prior art, the invention provides the remote visual intelligent inspection system for the transformer substation, wherein operation and maintenance personnel make an inspection plan in the intelligent inspection system, the intelligent inspection system comprises corresponding detection areas, detection equipment, detection items and other contents, the intelligent inspection system automatically stores analysis results, pictures and alarm information into the system according to the configured plan, and the inspection results are automatically imported into a visual platform, so that the inspection task of the transformer substation can be intelligently, efficiently, safely, low-cost and high-accuracy.
In order to achieve the above purpose, the present invention provides the following technical solutions: a substation remote visualization intelligent patrol system, the patrol system comprising:
the station control layer comprises a monitoring host, a data communication network shutdown, a data server, a comprehensive application server, an operator station, an engineer workstation and a synchronous phasor measurement management terminal, and is used for completing the functions of centralized storage and access of data, protection information management, running state monitoring, operation control and configuration management of a monitoring system and incorrect operation locking;
the spacer layer consists of a relay protection device, a measurement and control device, a metering device, a fault wave recording device, a network message analyzer and a stability control device and is used for carrying out on-site protection, measurement and control and fault recording on equipment in a station;
the process layer comprises a camera, a circuit breaker, a disconnecting switch, a current/voltage transformer, an intelligent component to which the current/voltage transformer belongs and an independent intelligent electronic device, and is used for realizing all relevant functions of interfaces with primary equipment, converting acquired analog quantity into digital quantity, providing the digital quantity to an upper layer, and receiving and executing control commands issued by the upper layer.
Preferably, the management terminal comprises a device management module, used for recording the position, the device name, the number, the delivery date, the specification model and the manufacturer information of the device;
the system management module is used for carrying out background management and maintenance on the system, and has the highest authority, and the management on the system comprises system setup, approval authority, user management and equipment operation and maintenance.
Preferably, the spacer layer includes:
the acquisition unit is used for acquiring MMS, GOOSE, SV and other messages corresponding to the acquisition module of the fault wave recording device and the message receiving module of the network message analyzer, marking an accurate entry time mark, and uploading the data to the recording unit after the data are summarized;
the recording unit is used for corresponding to a wave recording module of the fault wave recording device and a message recording module of the network message analyzer, and realizing the functions of wave recording starting, fault on-line analysis, wave recording file storage, analysis, MMS communication and the like;
the management unit is used for corresponding to the recording management module of the fault recording device and the message analysis module of the network message analyzer, and realizing the functions of man-machine interface, parameter configuration, system state monitoring, secondary equipment state monitoring and message retrieval analysis of the system.
Preferably, the workflow of the network message analyzer is as follows:
1) When the power grid fails, automatically starting wave recording, wherein wave recording data comprise state data before disturbance and failure information after disturbance;
2) Waveform analysis is carried out through wave recording software, meanwhile, analysis and calculation can be carried out on power, differential current, harmonic wave, fault ranging and the like, and SV, GOOSE, MMS messages are analyzed and screened in an online analysis and offline analysis mode;
3) And uploading the recording data and the message record analysis data to the station control layer through the Ethernet.
Preferably, the fault wave recording device is used for collecting fault transient state data, and the network message analyzer is used for recording all steady state data.
Preferably, the monitoring host comprises a visualization platform for realizing the functions of data access and storage, graphic display and management, human-computer interface operation control, misoperation prevention and locking, alarm direct transmission and remote browsing.
Preferably, the flow of the patrol system executing the patrol scheme is as follows:
1) The station control layer firstly transmits an operation target to the spacer layer, the spacer layer obtains a corresponding operation ticket according to the current state and the target state of the equipment, uploads a schedule, and issues an execution command after the schedule is simulated and verified;
2) The spacer layer is executed according to the execution instruction according to the steps, and the execution result is checked, if the field condition is met, the video system of the linkage process layer can judge the operation result so as to ensure that the field reality is consistent with the operation ticket:
3) And returning the scheduling execution command after all the steps are executed.
Preferably, the station control layer and the process layer are respectively assembled into a single star network, IEC61850-8-1 protocol communication is adopted between the station control layer and the spacer layer, the spacer layer and the process layer are in unit communication, and GOOSE protocol is adopted between the spacer layer and the process layer intelligent terminal.
The beneficial effects of the invention are as follows:
1. the operation and maintenance personnel make a patrol plan in the intelligent patrol system, wherein the intelligent patrol system comprises corresponding detection areas, detection equipment, detection projects and other contents, automatically stores analysis results, pictures and alarm information into the system according to the configured plan, automatically guides the patrol results into a visualization platform, and can intelligently, efficiently, safely, low-cost and high-accuracy finish substation patrol tasks;
2. the management terminal comprises a device management module and a system management module and is used for realizing the operation and maintenance management and the authority management of the device management and intelligent patrol system;
3. the fault wave recording device is used for collecting fault transient state data, the network message analyzer is used for recording all steady state data, and the analysis of combining the two device function information together is more accurate, and the fault positioning is quicker.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention. In the drawings:
fig. 1 is a schematic diagram of the overall planar structure of a remote visual intelligent inspection system of a transformer substation.
Detailed Description
Hereinafter, only certain exemplary embodiments are briefly described. As will be recognized by those of skill in the pertinent art, the described embodiments may be modified in various different ways without departing from the spirit or scope of the present invention. Accordingly, the drawings and description are to be regarded as illustrative in nature and not as restrictive.
In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include one or more such feature.
The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings.
Example 1
Given by fig. 1, the present invention provides the following technical solutions: remote visual intelligent inspection system of transformer substation, inspection system includes:
the station control layer comprises a monitoring host, a data communication network shutdown, a data server, a comprehensive application server, an operator station, an engineer workstation and a synchronous phasor measurement management terminal, and is used for completing the functions of centralized storage and access of data, protection information management, running state monitoring, operation control and configuration management of a monitoring system and incorrect operation locking;
the spacer layer consists of a relay protection device, a measurement and control device, a metering device, a fault wave recording device, a network message analyzer and a stability control device and is used for carrying out on-site protection, measurement and control and fault recording on equipment in a station;
the process layer comprises a camera, a circuit breaker, a disconnecting switch, a current/voltage transformer, an intelligent component to which the current/voltage transformer belongs and an independent intelligent electronic device, and is used for realizing all relevant functions of interfaces with primary equipment, converting acquired analog quantity into digital quantity, providing the digital quantity to an upper layer, and receiving and executing control commands issued by the upper layer.
Preferably, the monitoring host comprises a visual platform for realizing the functions of data access and storage, graphic display and management, human-computer interface operation control, misoperation prevention and locking, alarm direct transmission and remote browsing.
Preferably, the flow of the patrol system executing the patrol scheme is as follows:
1) The station control layer firstly transmits an operation target to the spacer layer, the spacer layer obtains a corresponding operation ticket according to the current state and the target state of the equipment, uploads a schedule, and issues an execution command after the schedule is simulated and verified;
2) The spacer layer is executed according to the execution instruction according to the steps, and the execution result is checked, if the field condition is met, the video system of the linkage process layer can judge the operation result so as to ensure that the field reality is consistent with the operation ticket:
3) And returning the scheduling execution command after all the steps are executed.
Preferably, the station control layer and the process layer are respectively assembled into a single star network, IEC61850-8-1 protocol communication is adopted between the station control layer and the spacer layer, the spacer layer is communicated with the process layer merging unit, and GOOSE protocol is adopted between the spacer layer and the process layer intelligent terminal
The operation and maintenance personnel make a patrol plan in the intelligent patrol system, the intelligent patrol system comprises corresponding detection areas, detection equipment, detection projects and other contents, the intelligent patrol system automatically stores analysis results, pictures and alarm information into the system according to the configured plan, and the patrol results are automatically imported into the visualization platform, so that substation patrol tasks can be intelligently, efficiently, safely, low in cost and high in accuracy.
Example two
Referring to fig. 1, as another preferred embodiment, there is a difference from the first embodiment in that the management terminal includes a device management module for recording the location, device name, number, delivery date, specification model, and manufacturer information of the device;
the system management module is used for carrying out background management and maintenance on the system, has the highest authority, and can carry out system setting, approval authority, user management and equipment operation and maintenance on the system
The management terminal comprises a device management module and a system management module, and is used for realizing the operation and maintenance management and the authority management of the device management and the intelligent patrol system.
Example III
Referring to fig. 1, as another preferred embodiment, a difference from the first embodiment is that the spacer layer includes:
the acquisition unit is used for acquiring MMS, GOOSE, SV and other messages corresponding to the acquisition module of the fault wave recording device and the message receiving module of the network message analyzer, marking an accurate entry time mark, and uploading the data to the recording unit after the data are summarized;
the recording unit is used for corresponding to a wave recording module of the fault wave recording device and a message recording module of the network message analyzer, and realizing the functions of wave recording starting, fault on-line analysis, wave recording file storage, analysis, MMS communication and the like;
the management unit is used for corresponding to the recording management module of the fault recording device and the message analysis module of the network message analyzer, and realizing the functions of man-machine interface, parameter configuration, system state monitoring, secondary equipment state monitoring and message retrieval analysis of the system.
Preferably, the workflow of the network message analyzer is as follows:
1) When the power grid fails, automatically starting wave recording, wherein wave recording data comprise state data before disturbance and failure information after disturbance;
2) Waveform analysis is carried out through wave recording software, meanwhile, analysis and calculation can be carried out on power, differential current, harmonic wave, fault ranging and the like, and SV, GOOSE, MMS messages are analyzed and screened in an online analysis and offline analysis mode;
3) And uploading the recording data and the message record analysis data to the station control layer through the Ethernet.
Preferably, the fault wave recording device is used for collecting fault transient state data, and the network message analyzer is used for recording all steady state data.
The fault wave recording device is used for collecting fault transient state data, the network message analyzer is used for recording all steady state data, and the analysis of combining the two device function information together is more accurate, and the fault positioning is quicker.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present invention, and the present invention is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present invention has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (8)
1. Remote visual intelligent inspection system of transformer substation, characterized in that, the inspection system includes:
the station control layer comprises a monitoring host, a data communication network shutdown, a data server, a comprehensive application server, an operator station, an engineer workstation and a synchronous phasor measurement management terminal, and is used for completing the functions of centralized storage and access of data, protection information management, running state monitoring, operation control and configuration management of a monitoring system and incorrect operation locking;
the spacer layer consists of a relay protection device, a measurement and control device, a metering device, a fault wave recording device, a network message analyzer and a stability control device and is used for carrying out on-site protection, measurement and control and fault recording on equipment in a station;
the process layer comprises a camera, a circuit breaker, a disconnecting switch, a current/voltage transformer, an intelligent component to which the current/voltage transformer belongs and an independent intelligent electronic device, and is used for realizing all relevant functions of interfaces with primary equipment, converting acquired analog quantity into digital quantity, providing the digital quantity to an upper layer, and receiving and executing control commands issued by the upper layer.
2. The substation remote visual intelligent patrol system according to claim 1, wherein the management terminal comprises a device management module for recording the location, device name, number, date of delivery, specification and manufacturer information of the device;
the system management module is used for carrying out background management and maintenance on the system, and has the highest authority, and the management on the system comprises system setup, approval authority, user management and equipment operation and maintenance.
3. A substation remote visualization intelligent patrol system according to claim 1, wherein said spacer layer comprises:
the acquisition unit is used for acquiring MMS, GOOSE, SV and other messages corresponding to the acquisition module of the fault wave recording device and the message receiving module of the network message analyzer, marking an accurate entry time mark, and uploading the data to the recording unit after the data are summarized;
the recording unit is used for corresponding to a wave recording module of the fault wave recording device and a message recording module of the network message analyzer, and realizing the functions of wave recording starting, fault on-line analysis, wave recording file storage, analysis, MMS communication and the like;
the management unit is used for corresponding to the recording management module of the fault recording device and the message analysis module of the network message analyzer, and realizing the functions of man-machine interface, parameter configuration, system state monitoring, secondary equipment state monitoring and message retrieval analysis of the system.
4. A substation remote visual intelligent patrol system according to claim 3, wherein the workflow of the network message analyzer is:
1) When the power grid fails, automatically starting wave recording, wherein wave recording data comprise state data before disturbance and failure information after disturbance;
2) Waveform analysis is carried out through wave recording software, meanwhile, analysis and calculation can be carried out on power, differential current, harmonic wave, fault ranging and the like, and SV, GOOSE, MMS messages are analyzed and screened in an online analysis and offline analysis mode;
3) And uploading the recording data and the message record analysis data to the station control layer through the Ethernet.
5. A substation remote visual intelligent patrol system according to claim 3, wherein the fault logging device is configured to collect fault transient data, and the network message analyzer is configured to record all steady state data.
6. The substation remote visual intelligent patrol system according to claim 1, wherein the monitoring host comprises a visual platform for realizing data access and storage, graphic display and management, man-machine interface operation control, misoperation prevention and locking, alarm direct transmission and remote browsing functions.
7. The substation remote visual intelligent patrol system according to claim 1, wherein the process of executing the patrol scheme by the patrol system is as follows:
1) The station control layer firstly transmits an operation target to the spacer layer, the spacer layer obtains a corresponding operation ticket according to the current state and the target state of the equipment, uploads a schedule, and issues an execution command after the schedule is simulated and verified;
2) The spacer layer is executed according to the execution instruction according to the steps, and the execution result is checked, if the field condition is met, the video system of the linkage process layer can judge the operation result so as to ensure that the field reality is consistent with the operation ticket:
3) And returning the scheduling execution command after all the steps are executed.
8. The substation remote visual intelligent patrol system according to claim 1, wherein the station control layer and the process layer are respectively assembled into a single star network, IEC61850-8-1 protocol communication is adopted between the station control layer and the spacer layer, the spacer layer and the process layer are communicated with each other through a merging unit, and GOOSE protocol is adopted between the spacer layer and the process layer intelligent terminal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211702340.XA CN116014893A (en) | 2022-12-29 | 2022-12-29 | Remote visual intelligent inspection system for transformer substation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211702340.XA CN116014893A (en) | 2022-12-29 | 2022-12-29 | Remote visual intelligent inspection system for transformer substation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN116014893A true CN116014893A (en) | 2023-04-25 |
Family
ID=86026274
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211702340.XA Pending CN116014893A (en) | 2022-12-29 | 2022-12-29 | Remote visual intelligent inspection system for transformer substation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN116014893A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116418121A (en) * | 2023-06-09 | 2023-07-11 | 广东电网有限责任公司广州供电局 | Substation secondary security system, method, device and computer equipment |
-
2022
- 2022-12-29 CN CN202211702340.XA patent/CN116014893A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116418121A (en) * | 2023-06-09 | 2023-07-11 | 广东电网有限责任公司广州供电局 | Substation secondary security system, method, device and computer equipment |
CN116418121B (en) * | 2023-06-09 | 2023-10-20 | 广东电网有限责任公司广州供电局 | Substation secondary security system, method, device and computer equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106709580B (en) | Transformer substation secondary system operation and maintenance cloud platform | |
CN112765258B (en) | Power distribution network graph model checking management system and method thereof | |
CN107167704B (en) | Power distribution network fault diagnosis system and method based on CIM model | |
CN107346917A (en) | Secondary device based on virtual machine integrates joint debugging method | |
CN101714780A (en) | Relay protection running management information system | |
CN110658760A (en) | Electric power operation and maintenance terminal with remote positioning and communication functions | |
CN110647054A (en) | Substation primary equipment state simulation rehearsal system and error-proof checking method | |
CN111948489B (en) | Intelligent substation secondary equipment board card level abnormal defect diagnosis positioning method and system | |
CN104539047A (en) | Intelligent substation fault diagnosing and positioning method based on multi-factor comparison visualization | |
CN109507968B (en) | Visual monitoring and backtracking simulation system suitable for assembly line | |
CN104063761A (en) | SCADA data development system based on smart grid | |
CN113722311A (en) | Power distribution network power failure range positioning method, system, equipment and medium | |
CN103544561A (en) | Method for realizing dynamic display of power transmission circuits, method for realizing operational maintenance of power transmission circuits and system for realizing management of power transmission circuits | |
CN116014893A (en) | Remote visual intelligent inspection system for transformer substation | |
CN113872332A (en) | Intelligent operation and maintenance and anti-error management and control system and method for secondary pressing plate of transformer substation | |
CN109038820A (en) | A kind of anti-misoperation system and a kind of method for preventing misoperation based on image inspection based on image inspection | |
CN103616616A (en) | Fault detection method for large-scale grounding grid | |
CN204906004U (en) | Distributed intelligent regional power grid of network layering | |
CN103279520A (en) | Power substation secondary system failure reconnaissance method | |
CN111626542B (en) | Big data-based detection method for generator excitation system | |
CN201846134U (en) | Automatic inspecting system for transformer substation | |
CN116664763A (en) | Automatic generation method of indication map of forbidden limit area of power construction site of three-dimensional point cloud | |
CN116522746A (en) | Power distribution hosting method for high-energy-consumption enterprises | |
CN115224802A (en) | Information communication system based on cloud server | |
CN114357762A (en) | Wisdom power equipment high in clouds control automatic system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |