CN114197847A - Construction method of assembled roof cornice modeling curtain wall - Google Patents

Construction method of assembled roof cornice modeling curtain wall Download PDF

Info

Publication number
CN114197847A
CN114197847A CN202111409938.5A CN202111409938A CN114197847A CN 114197847 A CN114197847 A CN 114197847A CN 202111409938 A CN202111409938 A CN 202111409938A CN 114197847 A CN114197847 A CN 114197847A
Authority
CN
China
Prior art keywords
track
curtain wall
assembly
walking
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111409938.5A
Other languages
Chinese (zh)
Other versions
CN114197847B (en
Inventor
邢连杰
赵越
温连虎
孙志伟
李章睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202111409938.5A priority Critical patent/CN114197847B/en
Publication of CN114197847A publication Critical patent/CN114197847A/en
Application granted granted Critical
Publication of CN114197847B publication Critical patent/CN114197847B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/34Mobile scaffolds; Scaffolds with mobile platforms characterised by supporting structures provided on the roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/283Mobile scaffolds; Scaffolds with mobile platforms mobile horizontally

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Curtains And Furnishings For Windows Or Doors (AREA)

Abstract

The invention discloses an assembled roof cornice modeling curtain wall construction device which comprises a first support component, a second support component, a third support component, a walking component, a crane group and a positioning piece, wherein the walking component and a track are positioned through the positioning piece; assembling the curtain wall construction device; a unit steel truss machining and manufacturing process; assembling the unit steel truss; hoisting the aluminum plate unit; assembling the aluminum plate unit; the curtain wall construction device formed by combining the first support assembly, the second support assembly, the third support assembly, the walking assembly, the crane group and the positioning piece is arranged to hoist and mount building materials, and the walking assembly and the positioning piece are used for conveniently adjusting the position of the whole structure, so that the flexibility of the whole device in actual use is improved.

Description

Construction method of assembled roof cornice modeling curtain wall
Technical Field
The invention relates to the technical field of building construction, in particular to a construction method of an assembled roof cornice modeling curtain wall.
Background
With the progress and development of the times, the construction of buildings is changing day by day. The construction of building curtain walls is an important component of buildings, and people have higher and higher requirements on the building curtain walls. The roof is used as a high point of a building, the forms of curtain walls are various, and the cornice modeling curtain wall is the most common one in the roof modeling. The traditional cornice modeling curtain wall construction needs to arrange and install the keels one by one, so that not only is the safety risk large, but also the construction precision and the construction speed are not satisfactory.
Disclosure of Invention
The invention aims to provide a construction method of an assembled roof cornice modeling curtain wall, which aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides an assembled roofing modeling curtain construction method that cornices, assembled roofing cornices modeling curtain construction equipment includes:
the supporting legs are fixedly welded on the cross beams on the two sides of the first bracket component;
the second bracket component is connected to the front side end of the first bracket component;
the third bracket component is connected to the rear side end of the first bracket component;
the walking assemblies are arranged at the lower side ends of the supporting legs and are arranged on rails in a sliding manner, the rails are symmetrically arranged in one group, and the rails are fixedly arranged on the top layer of the building;
the crane group is arranged on the linear guide rail on the second bracket component in a sliding manner and is driven by a driving structure;
the invention also discloses a construction method of the assembled roof cornice modeling curtain wall, which comprises the following steps; the invention achieves the purpose.
Preferably, the first bracket component is arranged at a height higher than the height of the parapet on the top layer of the building, and the traveling crane group is arranged outside the wall of the parapet.
Preferably, a counterweight assembly is fixedly mounted on the third bracket assembly at a position close to the rear side through a fixing structure.
Preferably, the walking assembly is formed by combining a connecting plate and walking rollers, the walking rollers are arranged on the track in a rolling mode, and one side of the connecting plate is provided with an upper positioning hole.
Preferably, the tracks are symmetrically provided with a group, the tracks are of a track structure with an I-shaped section, one side of each track is provided with a lower positioning hole, the upper positioning holes and the lower positioning holes are correspondingly arranged, the upper positioning holes and the lower positioning holes are arranged at equal intervals, and the upper positioning holes and the lower positioning holes are positioned through positioning pieces.
Preferably, the positioning piece is formed by combining a positioning rod and a supporting piece, and the diameter value of the positioning rod is matched with the diameter values of the upper positioning hole and the lower positioning hole.
Preferably, an upper guide groove is formed in the side wall of the upper positioning hole, a lower guide groove and a limiting groove are formed in the side wall of the lower positioning hole, the upper guide groove, the lower guide groove and the limiting groove are arranged in groups, the cross-sectional sizes of the upper guide groove, the lower guide groove and the limiting groove are identical, the upper guide groove completely penetrates through the connecting plate, the lower guide groove completely penetrates through the upper transverse plate of the track, and the length value of the limiting groove is smaller than that of the lower guide groove.
Preferably, the side wall of the lower end of the positioning rod is integrally formed with a limiting protrusion, the limiting protrusion is symmetrically provided with a group, the size of the limiting protrusion is matched with that of a notch of the limiting groove, the limiting protrusion is embedded into the limiting groove when the positioning piece is actually installed, and the supporting piece is in a compressed state at the moment.
Preferably, a threaded hole is formed in the connecting plate, a limiting part is installed on the connecting plate, the limiting part is of a channel steel structure, a mounting hole is formed in the upper side face of the limiting part, the mounting hole and the threaded hole are correspondingly arranged, the limiting part and the connecting plate are positioned through a bolt, a lower lateral plate of the limiting part is embedded into a groove opening in the side edge of the track, the limiting part and the track are not in contact, a roller groove is formed in the upper surface of the track, and a wheel body of the walking roller is arranged in the roller groove.
The construction method of the assembled roof cornice modeling curtain wall comprises the following steps:
the method comprises the following steps: assembling the curtain wall construction device;
step two: a unit steel truss machining and manufacturing process;
step three: assembling the unit steel truss;
step four: hoisting the aluminum plate unit;
step five: and (5) assembling the aluminum plate unit.
Compared with the prior art, the invention has the beneficial effects that:
1. the curtain wall construction device formed by combining the first support assembly, the second support assembly, the third support assembly, the walking assembly, the crane group and the positioning piece is arranged to hoist and mount the building materials, and the walking assembly and the positioning piece are used for conveniently adjusting the position of the whole structure, so that the flexibility of the whole device in actual use is improved;
2. an upper guide groove is formed in the side wall of the upper positioning hole, a lower guide groove and a limiting groove are formed in the side wall of the lower positioning hole, the positioning piece is formed by combining the positioning rod and the supporting piece, and a limiting bulge is formed in the side wall of the lower end of the positioning rod, so that the convenience in assembling and disassembling the positioning piece is improved;
3. through the limiting effect of the limiting part, the reliability of the whole device in actual operation is improved, and the phenomenon that the whole device turns on one's side due to the fact that a hoisted object is too heavy is avoided.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of the structure at A in FIG. 1;
FIG. 3 is a schematic view of the installation position of the walking assembly;
FIG. 4 is an enlarged view of the structure at B in FIG. 3;
FIG. 5 is a half sectional view of the track;
FIG. 6 is an enlarged view of the structure at C in FIG. 5;
FIG. 7 is a schematic view of a positioning member;
FIG. 8 is an enlarged view of the structure at D in FIG. 7;
fig. 9 is a schematic view of a position limiting member.
In the figure: the device comprises a first bracket component 1, a second bracket component 2, a third bracket component 3, supporting legs 4, a walking component 5, a track 6, a positioning component 7, a building top layer 8, a parapet 9, a linear guide rail 10, a traveling crane component 11, a counterweight component 12, a connecting plate 13, a walking roller 14, an upper positioning hole 15, a lower positioning hole 16, an upper guiding groove 17, a lower guiding groove 18, a limiting groove 19, a positioning rod 20, a supporting component 21, a limiting protrusion 22, a threaded hole 23, a limiting component 24, a mounting hole 25, a bolt 26 and a roller groove 27.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-9, the present invention provides a technical solution: the utility model provides an assembled roofing modeling curtain construction method of cornicing, assembled roofing cornicing modeling curtain construction equipment includes:
the support frame comprises a first support frame component 1, wherein support legs 4 are fixedly welded on cross beams on two sides of the first support frame component 1;
the second bracket assembly 2, the second bracket assembly 2 is connected to the front side end of the first bracket assembly 1;
the third bracket component 3, the third bracket component 3 is connected to the back side end of the first bracket component 1;
the building material lifting device comprises a walking component 5, wherein the walking component 5 is arranged at the lower side end of a supporting leg 4, the walking component 5 is slidably arranged on a track 6, the track 6 is symmetrically provided with one group, the track 6 is fixedly arranged on a building top layer 8, a curtain wall construction device formed by combining a first bracket component 1, a second bracket component 2, a third bracket component 3, the walking component 5, a traveling crane group 11 and a positioning piece 7 is arranged to lift and install the building material, and the walking component 5 and the positioning piece 7 are used for conveniently adjusting the position of the whole structure, so that the flexibility of the whole device in actual use is improved;
the traveling crane group 11 is arranged on the linear guide rail 10 on the second bracket component 2 in a sliding way, and the traveling crane group 11 is driven by a driving structure;
the invention also discloses a construction method of the assembled roof cornice modeling curtain wall, which comprises the following steps; the invention achieves the purpose.
The first frame assembly 1 is arranged at a height higher than the height of the parapet 9 on the building roof 8, and the traveling crane group 11 is arranged outside the wall of the parapet 9.
A counterweight assembly 12 is fixedly mounted on the third bracket assembly 3 at a position close to the rear side by a fixing structure.
The walking assembly 5 is composed of a connecting plate 13 and a walking roller 14, the walking roller 14 is arranged on the track 6 in a rolling mode, and an upper positioning hole 15 is formed in one side of the connecting plate 13.
The rails 6 are symmetrically provided with a group, the rails 6 are of a rail structure with an i-shaped section, one side of each rail 6 is provided with a lower positioning hole 16, the upper positioning holes 15 and the lower positioning holes 16 are correspondingly arranged, the upper positioning holes 15 and the lower positioning holes 16 are arranged at equal intervals, and the upper positioning holes 15 and the lower positioning holes 16 are positioned through the positioning pieces 7.
The positioning member 7 is composed of a positioning rod 20 and a supporting member 21, and the diameter value of the positioning rod 20 matches with the diameter values of the upper positioning hole 15 and the lower positioning hole 16.
The side wall of the upper positioning hole 15 is provided with an upper guide groove 17, the side wall of the lower positioning hole 16 is provided with a lower guide groove 18 and a limiting groove 19, the upper guide groove 17, the lower guide groove 18 and the limiting groove 19 are all arranged in groups, the cross section sizes of the upper guide groove 17, the lower guide groove 18 and the limiting groove 19 are identical, the upper guide groove 17 completely penetrates through the connecting plate 13, the lower guide groove 18 completely penetrates through the upper transverse plate of the track 6, and the length value of the limiting groove 19 is smaller than the length value of the lower guide groove 18.
The side wall of the lower end of the positioning rod 20 is integrally formed with a limiting protrusion 22, the limiting protrusion 22 is symmetrically provided with a group, the size of the limiting protrusion 22 is matched with the size of the notch of the limiting groove 19, and the positioning member 7 is actually installed, the limiting protrusion 22 is embedded in the limiting groove 19, and the supporting member 21 is in a compressed state at the moment, the upper guide groove 17 is formed in the side wall of the upper positioning hole 15, the lower guide groove 18 and the limiting groove 19 are formed in the side wall of the lower positioning hole 16, the positioning member 7 is formed by combining the positioning rod 20 and the supporting member 21, and the limiting protrusion 22 is arranged on the side wall of the lower end of the positioning rod 20, so that the assembling and disassembling convenience of the positioning member 7 is improved.
A threaded hole 23 is formed in the connecting plate 13, a limiting part 24 is arranged on the connecting plate 13, the limiting part 24 is of a channel steel structure, a mounting hole 25 is formed in the upper side face of the limiting part, the mounting hole 25 is arranged corresponding to the threaded hole 23, the limiting part 24 and the connecting plate 13 are positioned through a bolt 26, a transverse plate at the lower side of the limiting part 24 is embedded into a notch at the side edge of the track 6, the limiting part 24 is not in contact with the track 6, a roller groove 27 is formed in the upper surface of the track 6, a wheel body of the walking roller 14 is arranged in the roller groove 27, and the reliability of the whole device in actual operation is improved through the limiting effect of the limiting part 24, so that the phenomenon that the whole device is turned on one side due to too heavy hoisting of objects is avoided;
the construction method of the assembled roof cornice modeling curtain wall comprises the following steps:
the method comprises the following steps: assembling the curtain wall construction device;
step two: a unit steel truss machining and manufacturing process;
step three: assembling the unit steel truss;
step four: hoisting the aluminum plate unit;
step five: and (5) assembling the aluminum plate unit.
The working principle is as follows: the curtain wall construction device formed by combining the first bracket component 1, the second bracket component 2, the third bracket component 3, the walking component 5, the traveling crane group 11 and the positioning component 7 is arranged to hoist and mount building materials, the walking component 5 and the positioning component 7 are used for conveniently adjusting the position of the whole structure, so that the flexibility of the whole device in actual use is improved, an upper guide groove 17 is formed on the side wall of an upper positioning hole 15, a lower guide groove 18 and a limiting groove 19 are formed on the side wall of a lower positioning hole 16, the positioning component 7 is formed by combining a positioning rod 20 and a supporting component 21, a limiting bulge 22 is arranged on the side wall of the lower end of the positioning rod 20, so that the convenience in assembling and disassembling of the positioning component 7 is improved, in actual use, when the position of the curtain wall construction device needs to be adjusted, a worker presses the positioning component 7 downwards, then rotate the setting element 7 ninety degrees, then take it out again, then adjust curtain construction equipment's position, after the adjustment is accomplished, the staff inserts through limiting protrusion 22 on the setting element 7 along upper guide way 17, lower guide way 18, then exerts pressure to setting element 7 again to rotate the setting element 7 ninety degrees again, then loosen setting element 7 again, thereby let limiting protrusion 22 imbed to can accomplish positioning work among limiting groove 19.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides an assembled roofing modeling curtain construction equipment that cornices which characterized in that: assembled roofing modeling curtain construction equipment that cornices includes:
the support frame comprises a first support frame assembly (1), wherein support legs (4) are fixedly welded on cross beams on two sides of the first support frame assembly (1);
the second bracket component (2), the second bracket component (2) is connected to the front side end of the first bracket component (1);
the third bracket component (3), the third bracket component (3) is connected to the rear side end of the first bracket component (1);
the walking assembly (5) is arranged at the lower side end of the supporting leg (4), the walking assembly (5) is slidably arranged on the track (6), the tracks (6) are symmetrically arranged in a group, and the track (6) is fixedly arranged on a building top layer (8);
the crane group (11) is arranged on the linear guide rail (10) on the second bracket component (2) in a sliding manner, and the crane group (11) is driven by a driving structure;
the positioning piece (7) is used for positioning between the walking component (5) and the track (6) through the positioning piece (7).
2. The assembly type roof cornice modeling curtain wall construction device of claim 1, characterized in that: the height of the first support assembly (1) is higher than that of a parapet wall (9) on a building top layer (8), and the traveling crane assembly (11) is arranged on the outer side of the wall of the parapet wall (9).
3. The assembly type roof cornice modeling curtain wall construction device of claim 1, characterized in that: and a counterweight component (12) is fixedly arranged at the position close to the rear side of the third bracket component (3) through a fixing structure.
4. The assembly type roof cornice modeling curtain wall construction device of claim 1, characterized in that: the walking assembly (5) is formed by combining a connecting plate (13) and a walking roller (14), the walking roller (14) is arranged on the track (6) in a rolling mode, and an upper positioning hole (15) is formed in one side of the connecting plate (13).
5. The assembly type roof cornice modeling curtain wall construction device of claim 4, characterized in that: the utility model discloses a rail structure, including track (6), lower locating hole (16), upper locating hole (15) and lower locating hole (16), the equal interval of upper locating hole (15) and lower locating hole (16) is provided with a plurality ofly, and is fixed a position through setting element (7) between upper locating hole (15) and lower locating hole (16), and the common symmetry of track (6) is provided with a set ofly, and track (6) is the track structure that the cross-section is the I shape, lower locating hole (16) has been seted up to one side of track (6), for corresponding the setting between upper locating hole (15) and lower locating hole (16).
6. The assembly type roof cornice modeling curtain wall construction device of claim 5, characterized in that: the positioning piece (7) is formed by combining a positioning rod (20) and a supporting piece (21), and the diameter value of the positioning rod (20) is matched with the diameter values of the upper positioning hole (15) and the lower positioning hole (16).
7. The assembly type roof cornice modeling curtain wall construction device of claim 6, characterized in that: seted up last guide way (17) on the lateral wall of upper locating hole (15), seted up down guide way (18) and spacing groove (19) on the lateral wall of lower locating hole (16), upper guide way (17), lower guide way (18), spacing groove (19) are the setting in groups, and the cross sectional dimension of three is identical, and upper guide way (17) is for running through connecting plate (13) completely, lower guide way (18) are for running through the upside diaphragm of track (6) completely, spacing groove (19) length value is less than the length value of lower guide way (18).
8. The assembly type roof cornice modeling curtain wall construction device of claim 7, characterized in that: spacing arch (22) are integrated into one piece on the lower extreme lateral wall of locating lever (20), spacing arch (22) are the symmetry altogether and are provided with a set ofly, and the size of spacing arch (22) is identical with the notch size of spacing groove (19), and when setting element (7) was actually installed, its spacing arch (22) were for imbedding among spacing groove (19), and support piece (21) was in the compressed state this moment.
9. The assembly type roof cornice modeling curtain wall construction device of claim 8, characterized in that: threaded hole (23) is seted up on connecting plate (13), and installs locating part (24) on connecting plate (13), locating part (24) are the channel-section steel structure, and seted up mounting hole (25) on its upper flank, mounting hole (25) set up with threaded hole (23) is corresponding, and fixes a position through bolt (26) between locating part (24) and connecting plate (13), and the downside diaphragm of locating part (24) is for imbedding in the notch of track (6) side, and does not contact between locating part (24) and track (6), and the upper surface of track (6) has seted up roller groove (27), the wheel body of walking gyro wheel (14) sets up for being located among roller groove (27).
10. A construction method of an assembled roof cornice modeling curtain wall as claimed in any one of claims 1 to 9, characterized in that: the construction method of the assembled roof cornice modeling curtain wall comprises the following steps:
the method comprises the following steps: assembling the curtain wall construction device;
step two: a unit steel truss machining and manufacturing process;
step three: assembling the unit steel truss;
step four: hoisting the aluminum plate unit;
step five: and (5) assembling the aluminum plate unit.
CN202111409938.5A 2021-11-25 2021-11-25 Construction method of assembled roof cornice modeling curtain wall Active CN114197847B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111409938.5A CN114197847B (en) 2021-11-25 2021-11-25 Construction method of assembled roof cornice modeling curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111409938.5A CN114197847B (en) 2021-11-25 2021-11-25 Construction method of assembled roof cornice modeling curtain wall

Publications (2)

Publication Number Publication Date
CN114197847A true CN114197847A (en) 2022-03-18
CN114197847B CN114197847B (en) 2023-03-21

Family

ID=80648840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111409938.5A Active CN114197847B (en) 2021-11-25 2021-11-25 Construction method of assembled roof cornice modeling curtain wall

Country Status (1)

Country Link
CN (1) CN114197847B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116335381A (en) * 2023-04-14 2023-06-27 新昌县城乡市政园林建设有限公司 Movable steel structure construction platform on steel truss

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4828073A (en) * 1986-03-20 1989-05-09 Friday Ronald W Mobile suspended scaffold
JPH0640190U (en) * 1992-10-30 1994-05-27 日本ビソー株式会社 Roof rail laying structure
CN202324576U (en) * 2011-11-23 2012-07-11 武汉凌云建筑装饰工程有限公司 Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall
CN107795112A (en) * 2017-10-21 2018-03-13 成都中机盈科科技有限公司 A kind of high maneuverability external wall aerial work platform structure
CN108277971A (en) * 2018-04-09 2018-07-13 上海市机械施工集团有限公司 A kind of translatable formula operating platform for the curtain wall construction that is suitable for cornicing
CN111335615A (en) * 2020-04-18 2020-06-26 中建七局建筑装饰工程有限公司 Large-span net rack eaves mouth suspension type automatic movement construction platform
CN211949524U (en) * 2020-04-10 2020-11-17 无锡市傲世机械制造有限公司 3D curtain wall construction system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4828073A (en) * 1986-03-20 1989-05-09 Friday Ronald W Mobile suspended scaffold
JPH0640190U (en) * 1992-10-30 1994-05-27 日本ビソー株式会社 Roof rail laying structure
CN202324576U (en) * 2011-11-23 2012-07-11 武汉凌云建筑装饰工程有限公司 Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall
CN107795112A (en) * 2017-10-21 2018-03-13 成都中机盈科科技有限公司 A kind of high maneuverability external wall aerial work platform structure
CN108277971A (en) * 2018-04-09 2018-07-13 上海市机械施工集团有限公司 A kind of translatable formula operating platform for the curtain wall construction that is suitable for cornicing
CN211949524U (en) * 2020-04-10 2020-11-17 无锡市傲世机械制造有限公司 3D curtain wall construction system
CN111335615A (en) * 2020-04-18 2020-06-26 中建七局建筑装饰工程有限公司 Large-span net rack eaves mouth suspension type automatic movement construction platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116335381A (en) * 2023-04-14 2023-06-27 新昌县城乡市政园林建设有限公司 Movable steel structure construction platform on steel truss

Also Published As

Publication number Publication date
CN114197847B (en) 2023-03-21

Similar Documents

Publication Publication Date Title
CN106958346B (en) Intelligent attached lifting scaffold equipment for curved surface super high-rise building and construction method
CN103422663B (en) Attached lift scaffold
AU2017235906A1 (en) House having aluminum alloy structure
CN114197847B (en) Construction method of assembled roof cornice modeling curtain wall
CN212773549U (en) Sliding device for hoisting truss
CN204310646U (en) A kind of novel elevator hoistway
CN2858855Y (en) Dual-purpose wall plastering machine
CN215407312U (en) Overhanging climbing device
CN214195487U (en) Elevator shaft operating platform capable of climbing
CN201202236Y (en) Mounting mechanism for portal type overhead pressure plate
CN209582787U (en) A kind of mobile toter of staircase assembly
CN219316128U (en) Prefabricated wallboard and precast beam installation connection structure
CN220599121U (en) Wall-attached double-guide-wheel structure
CN206376564U (en) A kind of counterforce device for adjusting Tall Frameworks post installation accuracy
CN221370245U (en) Crane girder structure capable of adjusting span of crane
CN220226298U (en) Point type glass curtain wall construction equipment
CN211313424U (en) A auxiliary device for hoist and mount of large-span steel truss
CN221167447U (en) High-altitude repair operation trolley for bridge guardrail
CN112942851A (en) Large-span steel structure roof truss high altitude roller bearing displacement device
CN214402557U (en) A easy installing support for stores pylon
CN217106089U (en) Consolidate hanging flower basket practicality instrument
CN216076257U (en) Retractable inserted lift scaffold attaches wall support
CN210342489U (en) Assembled stair
CN215563425U (en) Steel construction building wall body plate structure
CN218970379U (en) Curtain wall suspension type stand column and steel-concrete connecting mechanism

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 250014 17th floor, unit 1, phase II office building, Zhongjian cultural city, 16 Wenhua East Road, Lixia District, Jinan City, Shandong Province

Applicant after: THE SECOND CONSTRUCTION LIMITED COMPANY OF CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION

Address before: 250014 18th floor, Zhongjian building, No.16, Wenhua East Road, Lixia District, Jinan City, Shandong Province

Applicant before: THE SECOND CONSTRUCTION LIMITED COMPANY OF CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION

GR01 Patent grant