CN113187498A - TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method - Google Patents

TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method Download PDF

Info

Publication number
CN113187498A
CN113187498A CN202110521151.1A CN202110521151A CN113187498A CN 113187498 A CN113187498 A CN 113187498A CN 202110521151 A CN202110521151 A CN 202110521151A CN 113187498 A CN113187498 A CN 113187498A
Authority
CN
China
Prior art keywords
grouting
pipe
pipe shed
construction
shed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110521151.1A
Other languages
Chinese (zh)
Other versions
CN113187498B (en
Inventor
张立龙
郭震
魏飞
谭忠盛
任运仲
肖海晖
周振梁
杨刚
李珂
郑笑天
朱鹏程
李林峰
曾盼锋
刘彦章
周发成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Erqisi River Investment And Development Group Co ltd
Beijing Jiaotong University
China Railway 16th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
XINJIANG IRTYSH RIVER BASIN DEVELOPMENT ENGINEERING CONSTRUCTION ADMINISTRATION
Beijing Jiaotong University
China Railway 16th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINJIANG IRTYSH RIVER BASIN DEVELOPMENT ENGINEERING CONSTRUCTION ADMINISTRATION, Beijing Jiaotong University, China Railway 16th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical XINJIANG IRTYSH RIVER BASIN DEVELOPMENT ENGINEERING CONSTRUCTION ADMINISTRATION
Priority to CN202110521151.1A priority Critical patent/CN113187498B/en
Publication of CN113187498A publication Critical patent/CN113187498A/en
Application granted granted Critical
Publication of CN113187498B publication Critical patent/CN113187498B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • E21D9/0873Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method, which comprises the following steps of firstly, using blasting explosive to cooperate with manual expansion and excavation of a tunnel in a peripheral stratum of the tunnel; after the expanding excavation is finished, installing a pipe shed drilling machine rack and a pipe shed drilling machine in the hole shed drilling machine rack, and finishing the drilling operation on the upper part of the hole chamber; using a pipe shed drilling machine to drill backfill holes in the front collapse cavity, burying backfill pipes and exhaust pipes, and backfilling for three times; then, constructing the pipe shed, and repeatedly impacting the rock mass through a drill bit to form a hole; installing a guide pipe, installing a pipe shed by using a pipe shed drilling machine, and connecting grouting equipment to perform grouting on the constructed pipe shed; during grouting, the hole is pressed into grouting, after the grouting end standard is reached for the first time, pipe following grouting is carried out, the grouting end standard is reached again, and finally the pipe roof grouting construction is finished. According to the invention, innovative technical schemes and detail measures are provided in the aspects of cavity collapse backfill, pipe shed construction and pipe shed grouting construction, so that the construction safety is ensured, and the construction efficiency is improved.

Description

TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method
Technical Field
The invention relates to the technical field of civil engineering construction, in particular to a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method.
Background
With the promotion of informatization and the development of intelligent equipment, tunnel engineering for tunneling through TBM is more and more, and although the mechanical construction efficiency is high and manpower is relatively reduced, the construction cost is not low, the fault handling is troublesome, and difficulties caused by poor geological conditions are caused, so that the technology for solving the problem of tunnel tunneling construction difficulty of TBM is imperative for the industry. Therefore, the construction method is particularly suitable for solving the problem that the cavity collapse occurs in the TBM tunneling tunnel.
Disclosure of Invention
Aiming at the technical problems in the prior art, the invention provides a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method, which can overcome the defects of the prior art.
In order to achieve the technical purpose, the technical scheme of the invention is realized as follows:
a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method comprises the following steps:
s1, in the peripheral stratum of the tunnel at the shield tail of the shield, expanding and excavating the tunnel manually by using silent blasting explosive and an air pick to provide a working room for a subsequent drilling machine;
s2, after the drilling machine workshop is excavated, installing a pipe shed drilling machine rack and a pipe shed drilling machine in the workshop, and rotating a cantilever beam through an arch frame assembler to drive the drilling machine to rotate so as to complete drilling operation within 120 degrees of the upper part of the cavern;
s3, using an installed pipe shed drilling machine to drill backfill holes from the tail part of the shield to the front collapsed cavity, embedding backfill pipes and exhaust pipes, and backfilling by adopting light concrete three times within the estimated range of the collapsed cavity;
s4, constructing the pipe shed by using the partition holes, replacing a pipe shed drilling machine corresponding to the pipe shed construction, repeatedly impacting a rock body through a drill bit to form holes after replacing and installing the pipe shed drilling machine, then installing a guide pipe, and filling gaps between the hole wall and the rock body by using an anchoring agent after the mould is rechecked to be correct;
s5, after the filler between the guide pipe and the rock wall is finally solidified, installing a pipe shed by using a pipe shed drilling machine, arranging small steel pipes and reinforcing steel bars in the pipe shed for reinforcement, plugging a gap between the pipe shed and the guide pipe by using an anchoring agent, and connecting grouting equipment to perform grouting on the constructed pipe shed after the filler is finally solidified;
s6, when grouting the constructed pipe shed, the principle of first dilution and then concentration is followed, the grouting construction adopts an in-pipe large circulation construction process, the hole opening is pressed into grouting, the exhaust pipe is used for hole washing, exhaust, slurry return and slurry injection, the conditions of slurry leakage and grouting parameters are observed constantly in the grouting process, after the grouting end standard is reached for the first time, pipe following grouting is carried out according to the slurry shielding principle, the grouting end standard is reached again, and finally the grouting construction of the pipe shed is finished.
Further, in step S3, when the tube shed drilling machine is used to drill the backfill hole from the tail of the shield to the front collapsing cavity, the initial drill hole camber angle is 30 °, the secondary drill hole camber angle is 45 °, and light concrete is used to perform backfill in three times.
Further, in step S5, a pipe shed is installed by using a pipe shed drilling machine, the pipe shed is arranged within 120 ° of the crown, and the material is a heat treatment quality-adjusting pipe.
Further, in step S6, when grouting is performed for the pipe shed, the exhaust pipe provided in the pipe shed also serves as a hole washing pipe and a grout injection pipe, and when grouting is performed through the grouting pipe, the grouting pressure increases and the grout consumption is small, but when no grout flows out from the exhaust pipe, press-in grouting is performed through the exhaust pipe.
Further, in step S6, when grouting can be stopped when the grouting end standard is reached, grout needs to be injected to shield grout before closing the grout, the principle of shielding grout is to fill the pipe shed until the pipe shed is full, grout is injected into the pipe shed again after 30min of grout closing, grout is injected by using grout, double-liquid grout is injected to seal the hole after the grouting end standard is reached again, and the grouting valve is closed to complete pipe following grouting.
Further, in step S6, if slurry leakage occurs during the grouting process, the slurry mix ratio and the setting time are adjusted by adding parameters of a regulator, the slurry is gradually changed from thin to thick, and for the phenomena of slurry overflow and slurry leakage, caulking, surface plugging, low pressure, thick slurry, flow limitation, quantity limitation and intermittent pouring are adopted according to the situation for treatment.
Further, in step S6, when the grouting rate of the pipe roof is high and there is no leakage, the grouting is performed by using a stepped pressure-increasing or intermittent pressure-increasing method to balance the grouting pressure and the grouting rate.
Further, in step S6, during grouting construction, the vault is constructed from two ends, grouting construction is performed in two steps, holes of the second step are poured after all holes of the first step are poured, and grouting conditions of the pipe shed are checked according to grouting conditions of the holes of the second step.
The invention has the beneficial effects that: by using the mechanical equipment, the problem of cavity collapse in front of the face is solved, the construction efficiency is high, and the stability of the stratum in front of the face is ensured; during grouting, the air exhaust pipe is used for performing press-in grouting, so that the problem of insufficient grouting is solved; the method provides a more innovative technical scheme and detail measures in the aspects of cavity collapse backfill, pipe shed construction and pipe shed grouting construction, ensures construction safety and improves construction efficiency.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a schematic enlarged excavation section of a method for cavity collapse backfill and advanced pipe shed construction of a TBM tunnel according to an embodiment of the present invention.
Fig. 2 is a schematic installation diagram of a drilling machine for a method for cavity collapse backfill and advanced pipe shed construction of a TBM tunnel according to an embodiment of the invention.
Fig. 3 is a schematic diagram of a backfill pipe and an exhaust pipe of a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method according to an embodiment of the invention.
Fig. 4 is a schematic cross-sectional view of pipe shed construction of a method for cavity collapse backfill and advanced pipe shed construction of a TBM tunnel according to an embodiment of the present invention.
Fig. 5 is a schematic cross-sectional view of pipe shed construction by a method for cavity collapse backfill and advanced pipe shed construction of a TBM tunnel according to an embodiment of the invention.
Fig. 6 is a schematic diagram illustrating arrangement of pipe shed tendons according to the method for cavity collapse backfill and advanced pipe shed construction of a TBM tunnel according to an embodiment of the present invention.
Fig. 7 is a schematic diagram of pipe shed grouting in a TBM tunnel collapsed cavity backfill and advanced pipe shed construction method according to an embodiment of the present invention.
In the figure: 1. the construction method comprises the following steps of a first working ring, a second working ring, a third working ring, a shield, a third working ring, a cutter head, a first expanding excavation section, a second expanding excavation section, a support section, a third support beam, a cantilever beam, a first support plate, a second arc beam, a first backfill area, a second backfill area, a third exhaust pipe, a backfill pipe, a collapse contour line, a collapsed contour line, a cutter head, a second support plate, a first support plate, a second support plate, a first support plate, a second support plate, a support plate, a support, a.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments obtained by a person of ordinary skill in the art based on the embodiments of the present invention belong to the protection scope of the present invention, and for the convenience of understanding the above technical solutions of the present invention, the above technical solutions of the present invention are described in detail below by specific use modes.
According to the TBM tunnel collapsed cavity backfill and advanced pipe shed construction method provided by the embodiment of the invention, firstly, a working room is provided for a pipe shed drilling machine, a silent blasting explosive is required to be matched with an air pick to manually expand and dig the tunnel in a tunnel peripheral stratum at the tail of a shield 3, and as shown in figure 1, a working circle I1 in an expansion and excavation range is taken as 124 degrees, and the length indicated by a working circle II 2 is taken as an example.
After the expanding excavation is finished, installing a pipe shed drilling machine rack and a 90A pipe shed drilling machine in a drilling machine workshop, referring to the length of an expanding excavation section 11 and a supporting section 12 as shown in figure 2, fixing the pipe shed drilling machine on a front arc beam 15 and a rear arc beam 17 through a supporting plate 14, a supporting plate II 16 and U-shaped bolts, separating the front part of the pipe shed drilling machine from the front arc beam 15 during movement, fixing the pipe shed drilling machine on a cantilever beam, and rotating the cantilever beam 13 through an arch assembling device to drive the drilling machine to rotate so as to finish the drilling operation on the upper part of the cavern within 120 degrees.
As shown in fig. 3, a 90A pipe shed drilling machine is adopted to drill backfill holes from the tail part of the second shield 28 to the front collapsed cavity consolidated area 210, the initial drill hole camber angle is 30 degrees, the secondary drill hole camber angle is 45 degrees, backfill pipes 25 are embedded in the holes, the backfill pipes 25 are embedded with reference to the collapse contour line 26, exhaust pipes 24 are embedded in the backfill pipes 25, light concrete is adopted to backfill in three times within the estimated range of the collapsed cavities, the backfill pipes are filled into the first backfill area 21, the secondary backfill area 22 and the third backfill area 23, and the collapse contour line 26 comprises the virtual slag 211 of the collapsed cavities.
As shown in fig. 4-6, the pipe shed is constructed by adopting partition holes on the working surface 34, steel pipes 41, steel bars 42 and steel bars 43 are arranged in the pipe shed for reinforcement, a pipe shed drilling machine corresponding to the pipe shed construction is replaced, after the pipe shed drilling machine is installed, a YT-28 drilling machine drill bit is used for repeatedly impacting a rock mass to form holes, then a guide pipe 52 is installed, after the hole wall and the rock mass are rechecked by a mould, a gap between the hole wall and the periphery of the rock mass is blocked by an anchoring agent, after filling materials between the guide pipe 52 and a rock wall are finally set, the pipe shed is installed by a 90A pipe shed drilling machine, the pipe shed is arranged in a top arch within 120 degrees, a heat treatment quality adjusting pipe is selected as a material, after the pipe shed is installed, the gap between the pipe shed and the guide pipe 52 (the rock wall) is blocked by the anchoring agent, the blocking length is not less than 50cm, and after the blocked anchoring agent reaches the final set, grouting equipment is connected to perform grouting on the constructed pipe shed.
If the drilling jamming condition is found in the drilling process, the smooth completion of the pipe shed installation can be ensured by reducing the thrust and increasing the rotating speed.
As shown in fig. 7, when the pipe shed is grouted through the grouting pipe 45 or the grouting pipe two 53, the pipe shed is internally provided with the exhaust pipe two 51 and also serves as a hole washing pipe and a grout injection pipe, the grouting needs to follow the principle of first dilution and then concentration, the grouting construction adopts a pipe-in large-cycle construction process, the hole opening is pressed for grouting, the exhaust pipe 44 or the exhaust pipe two 51 is used for hole washing, exhaust, grout return and grout injection, the grouting process is constantly observed for the situations of grout leakage, grout injection parameters and the like, after the grouting end standard is reached for the first time, the grouting can be stopped, the grouting is carried out before closing the grout, the pipe following grouting is carried out according to the grout shielding principle, after the grouting end standard is reached again, double-fluid grout is injected for hole sealing, and finally the grouting construction of the pipe shed is completed.
In conclusion, by means of the technical scheme, the cavity collapse problem in front of the face is solved by using the mechanical equipment, the construction efficiency is high, and the stability of the stratum in front of the face is guaranteed; during grouting, the air exhaust pipe is used for performing press-in grouting, so that the problem of insufficient grouting is solved; the method provides a more innovative technical scheme and detail measures in the aspects of cavity collapse backfill, pipe shed construction and pipe shed grouting construction, ensures construction safety and improves construction efficiency.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (8)

1. A TBM tunnel collapsed cavity backfill and advanced pipe shed construction method is characterized by comprising the following steps:
s1, in the peripheral stratum of the tunnel at the shield tail of the shield (3), expanding and digging the tunnel manually by using silent blasting explosive and an air pick to provide a working room for a subsequent drilling machine;
s2, after the drilling machine workshop is excavated, installing a pipe shed drilling machine rack and a pipe shed drilling machine in the workshop, and rotating a cantilever beam (13) through an arch truss assembler to drive the drilling machine to rotate so as to complete drilling operation within 120 degrees of the upper part of the cavern;
s3, using an installed pipe shed drilling machine to drill backfill holes from the tail part of the shield (3) to the front collapsing cavity, embedding backfill pipes (25) and exhaust pipes (44), and backfilling by adopting light concrete three times within the estimated range of the collapsing cavity;
s4, constructing the pipe shed by using the partition holes, replacing a pipe shed drilling machine corresponding to the pipe shed construction, repeatedly impacting a rock body through a drill bit to form holes after replacing and installing the pipe shed drilling machine, then installing a guide pipe (52), and filling gaps between the hole wall and the rock body by using an anchoring agent after the mould is rechecked to be correct;
s5, after the filling material between the guide pipe (52) and the rock wall is finally solidified, installing a pipe shed by using a pipe shed drilling machine, arranging small steel pipes and reinforcing steel bars in the pipe shed for reinforcement, plugging a gap between the pipe shed and the guide pipe (52) by using an anchoring agent, and connecting grouting equipment to perform grouting on the constructed pipe shed after the filling material is finally solidified;
s6, when grouting the constructed pipe shed, the principle of first dilution and then concentration is followed, the grouting construction adopts an in-pipe large circulation construction process, the hole opening is pressed into grouting, the exhaust pipe (44) is used for hole washing, exhaust, slurry return and slurry injection, the conditions of slurry leakage and grouting parameters are observed at any time in the grouting process, after the grouting end standard is reached for the first time, pipe following grouting is carried out according to the slurry shielding principle, the grouting end standard is reached again, and finally the grouting construction of the pipe shed is completed.
2. The TBM tunnel collapsed cavity backfilling and advancing pipe shed construction method according to claim 1, wherein in step S3, when a backfill hole is drilled from the tail part of the shield (3) to the front collapsed cavity by using a pipe shed drilling machine, the initial drill hole camber angle is 30 degrees, the secondary drill hole camber angle is 45 degrees, and backfilling is performed three times by using light concrete.
3. The method for cavity-collapsing backfill and advanced pipe shed construction of a TBM tunnel according to claim 1, wherein in step S5, a pipe shed drill is adopted to install the pipe shed, the pipe shed is arranged in a 120-degree range of a top arch, and heat-treatment quality-adjusting pipes are selected as materials.
4. The method for the construction of the TBM tunnel collapsed cavity backfill and the advanced pipe shed as claimed in claim 1, wherein in step S6, when grouting the pipe shed, the exhaust pipe (44) arranged in the pipe shed is used as a hole washing pipe and a grouting pipe, when grouting is performed through the grouting pipe (45), the grouting pressure is increased, the grouting amount is small, but when no grout flows out from the exhaust pipe (44), the pressure grouting is performed through the exhaust pipe (44).
5. The method for TBM tunnel collapsed cavity backfill and advanced pipe shed construction according to claim 1, wherein in step S6, when grouting can be stopped after the grouting end standard is reached, grout needs to be injected for shielding before closing the grout, the principle of shielding the grout is to fill the pipe shed until the pipe shed is full, the pipe shed is grouted again after 30min of grout closing, the grouting is performed by using the grout, double-liquid grout is injected for sealing after the grouting end standard is reached again, a grouting valve is closed, and pipe following grouting is completed.
6. The method for the cavity collapse backfill and the advanced pipe shed construction of the TBM tunnel according to the claim 1, wherein in the step S6, if slurry leakage occurs in the grouting process, the slurry mixing ratio and the setting time are adjusted by adding parameters of regulators, the slurry is gradually changed from thin to thick, and for the phenomena of slurry leakage and slurry leakage, the measures of caulking, surface plugging, low pressure, thick slurry, flow limitation, quantity limitation and intermittent perfusion are adopted according to the situation for treatment.
7. The method for backfill of collapsed cavities and leading pipe sheds in TBM tunnels as claimed in claim 1, wherein in step S6, grouting the pipe sheds with a high grout injection rate and without leakage, grouting by using a staged pressure boosting or intermittent pressure boosting method to balance grouting pressure and injection rate.
8. The method for the cavity collapse backfill and the advance pipe shed construction of the TBM tunnel according to the claim 1, wherein in the step S6, the construction from two ends to the vault is carried out during grouting construction, the grouting construction is carried out in two steps, holes of the second step are poured after all holes of the first step are poured, and the grouting condition of the pipe shed is checked through the grouting condition of the holes of the second step.
CN202110521151.1A 2021-05-13 2021-05-13 TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method Active CN113187498B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110521151.1A CN113187498B (en) 2021-05-13 2021-05-13 TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110521151.1A CN113187498B (en) 2021-05-13 2021-05-13 TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method

Publications (2)

Publication Number Publication Date
CN113187498A true CN113187498A (en) 2021-07-30
CN113187498B CN113187498B (en) 2022-11-04

Family

ID=76981394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110521151.1A Active CN113187498B (en) 2021-05-13 2021-05-13 TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method

Country Status (1)

Country Link
CN (1) CN113187498B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931662A (en) * 2021-11-05 2022-01-14 中国水利水电第六工程局有限公司 Reinforced supporting method for composite supporting arch stress body

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182472A (en) * 2011-04-02 2011-09-14 中国建筑第五工程局有限公司 Backfill repairing method for tunnel collapse cavity
CN104481550A (en) * 2014-10-23 2015-04-01 中国二十冶集团有限公司 Tunnel collapse treatment advance support method
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
CN109441479A (en) * 2018-10-23 2019-03-08 北京市城远市政工程有限责任公司 A kind of bored tunnel sump remedy method
CN110043295A (en) * 2019-04-24 2019-07-23 五冶集团上海有限公司 It is a kind of first to encircle the Tunnel Landslide processing method filled out afterwards
CN112502723A (en) * 2020-12-04 2021-03-16 中铁十九局集团第一工程有限公司 Single shield TBM (tunnel boring machine) card machine escaping construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182472A (en) * 2011-04-02 2011-09-14 中国建筑第五工程局有限公司 Backfill repairing method for tunnel collapse cavity
CN104481550A (en) * 2014-10-23 2015-04-01 中国二十冶集团有限公司 Tunnel collapse treatment advance support method
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
CN109441479A (en) * 2018-10-23 2019-03-08 北京市城远市政工程有限责任公司 A kind of bored tunnel sump remedy method
CN110043295A (en) * 2019-04-24 2019-07-23 五冶集团上海有限公司 It is a kind of first to encircle the Tunnel Landslide processing method filled out afterwards
CN112502723A (en) * 2020-12-04 2021-03-16 中铁十九局集团第一工程有限公司 Single shield TBM (tunnel boring machine) card machine escaping construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈勃文等: "北疆长距离疏水隧洞TBM卡机快速解脱措施探析", 《水利水电技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113931662A (en) * 2021-11-05 2022-01-14 中国水利水电第六工程局有限公司 Reinforced supporting method for composite supporting arch stress body
CN113931662B (en) * 2021-11-05 2023-08-04 中国水利水电第六工程局有限公司 Reinforced support method for composite support arch stress body

Also Published As

Publication number Publication date
CN113187498B (en) 2022-11-04

Similar Documents

Publication Publication Date Title
CN102278130B (en) Process method for reinforcing and grouting of high-pressure water-rich solution cavity of tunnel
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN111396067B (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN107725056A (en) One kind passes through silly stratum tunnel loopful quick grouting construction method in advance
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN111335901A (en) Construction method for auxiliary small-diameter open TBM tunneling of pipe shed at unfavorable geological tunnel section
CN113187498B (en) TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method
CN111156005A (en) Construction method for tunnel to pass through subway station at close distance
CN114352292A (en) Shallow-buried bias-pressure multi-arch tunnel construction method for weathering phyllite stratum
CN113187499A (en) Weathering alteration belt TBM card machine escaping method
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN108360525A (en) A kind of per-fore pouring liquid with small pipe construction technology and equipment
CN106640098B (en) A kind of subway tunnel shield construction method
CN110043284A (en) The Urban Underground Passage excavating construction method of major hazard source is worn under a kind of
CN113404517B (en) Construction method for tunnel mud bursting and water flushing
CN214787376U (en) Cast-in-place and prefabricated tunnel shaft inner wall structure that combines together
CN110374631B (en) Advanced grouting construction method for backward tunnel of small clear distance tunnel in weak stratum
CN113914874A (en) Large-scale geological abnormal fault zone roadway surrounding rock ultra-long distance pre-reinforcement method
CN111997623A (en) Tunnel curtain grouting construction method
CN219260861U (en) Karst cave seepage-proofing reinforcing structure of diversion tunnel and construction branch hole crossing part
CN114109421B (en) Construction method for open TBM through long fault fracture zone
CN215256219U (en) Shield tunnel broken zone stratum grouting reinforcement equipment
CN113340169B (en) Joint fissure surrounding rock smooth blasting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20220824

Address after: 300162 District 3, Wanxin village, Hedong District, Tianjin

Applicant after: THE 2ND ENGINEERING CO., LTD. OF CHINA RAILWAY 16TH BUREAU GROUP Co.,Ltd.

Applicant after: CHINA RAILWAY 16TH BUREAU GROUP Co.,Ltd.

Applicant after: Beijing Jiaotong University

Applicant after: Xinjiang Erqisi River Investment and development (Group) Co.,Ltd.

Address before: 300162 District 3, Wanxin village, Hedong District, Tianjin

Applicant before: THE 2ND ENGINEERING CO., LTD. OF CHINA RAILWAY 16TH BUREAU GROUP Co.,Ltd.

Applicant before: CHINA RAILWAY 16TH BUREAU GROUP Co.,Ltd.

Applicant before: Beijing Jiaotong University

Applicant before: XINJIANG IRTYSH RIVER BASIN DEVELOPMENT ENGINEERING CONSTRUCTION ADMINISTRATION

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant