CN108360525A - A kind of per-fore pouring liquid with small pipe construction technology and equipment - Google Patents

A kind of per-fore pouring liquid with small pipe construction technology and equipment Download PDF

Info

Publication number
CN108360525A
CN108360525A CN201810178464.XA CN201810178464A CN108360525A CN 108360525 A CN108360525 A CN 108360525A CN 201810178464 A CN201810178464 A CN 201810178464A CN 108360525 A CN108360525 A CN 108360525A
Authority
CN
China
Prior art keywords
grouting
pipe
per
ductule
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810178464.XA
Other languages
Chinese (zh)
Inventor
蔡志勇
杨祥亮
郭玉海
张亮
薛春苗
***
王涛
杨海健
王牧月
张晟源
陈雪峰
李星晨
吕金彪
张涛
王英波
苏世宗
石文正
王越
张建珍
李文新
庞梦月
姜宁宁
李丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201810178464.XA priority Critical patent/CN108360525A/en
Publication of CN108360525A publication Critical patent/CN108360525A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of per-fore pouring liquid with small pipe construction technology and equipment, including grouting pump, inlet pipe and ductule, the input terminal of shown grouting pump is connected to the connection of slurries reserve pit by inlet pipe, and valve is installed on inlet pipe, the output end of grouting pump is connected to Grouting Pipe, pressure gauge and flowmeter are installed, Grouting Pipe is connected to slurries reserve pit by return pipe, and slip casting tube end connects floral tube by articulation in Grouting Pipe;Leading pre-supporting is by grouting with small pipe strengthening stratum when excavation, and advance support is 40 × 2.75 pre-grouting with micropipe of Φ, and tube wall interlocks jewel hole every 100~200mm, eyelet diameter 10mm, vault ductule sets a ring, mono- Pin of grid spacing 0.5m per Pin grids, circumferential spacing 0.3m, when first Zhi Houdu is 0.3m, 0.35m thickness, joint length 2m, 20 °~25 ° of first level inclination, grouting pressure is 0.4~0.6MPa, and stop grouting plug is arranged at aperture;Grouting pressure is controlled well, slurries is effectively prevent to leak outside, per-fore pouring liquid with small pipe effect is good.

Description

A kind of per-fore pouring liquid with small pipe construction technology and equipment
Technical field
The present invention relates to technical field of tunnel construction, specifically a kind of per-fore pouring liquid with small pipe construction technology and equipment.
Background technology
In constructing tunnel, V grades of country rocks generally take advance support, advance support generally to use grouting with small pipe to weakness Body country rock carries out pre-reinforcement processing, to ensure to excavate safety.It must install and note in ductule end before per-fore pouring liquid with small pipe Mouth is starched, ductule and Grouting Pipe are connected by grouting nozzle.Current grouting nozzle mounting means is all by one piece of diameter slightly larger than small The circular seal steel plate site welding of catheter outer diameter seals the hole that a Φ 20 or so is opened among steel plate in the end of ductule, The grouting nozzle of Φ 20 is welded at hole again.It is counted according to site operation, each grouting nozzle and the time of ductule welding about need 5 Minute or so, the ductule quantity that the construction of conventional bore tunnel each recycles is mostly at 40 or more, the time of grouting nozzle welding About 200min or so, therefore this process consumes the plenty of time, has seriously affected Tunnel Construction Schedule.And each slip casting Mouth can not be reused after being welded with ductule, cause centainly to waste, improve construction cost.
Invention content
The purpose of the present invention is to provide a kind of per-fore pouring liquid with small pipe construction technology and equipment, to solve above-mentioned background skill The problem of being proposed in art.
To achieve the above object, the present invention provides the following technical solutions:
A kind of per-fore pouring liquid with small pipe construction equipment, including grouting pump, inlet pipe and ductule, the input of shown grouting pump End is connected to the connection of slurries reserve pit by inlet pipe, and valve is equipped on inlet pipe, and the output end of grouting pump is connected to Grouting Pipe, Pressure gauge and flowmeter are installed, Grouting Pipe is connected to slurries reserve pit by return pipe, and slip casting tube end passes through work in Grouting Pipe Connector connects floral tube.
As a further solution of the present invention:The ductule isT=2.75mm steel welded tubes are process, tube head 25~35 ° of centrums are processed into, tube wall has injected hole, 6~10mm of aperture, 100~200mm of pitch-row, quincuncial arrangement, tail portion 0.5m It does not drill in range, end welderingRing-shaped stirrup.
As a further solution of the present invention:The installation of the ductule is first drilled with electric drill, is inserted into ductule, is then used Pneumatic pick heads into ductule.
A kind of per-fore pouring liquid with small pipe construction technology, including following construction technology:
1) transverse passage-way vault
For leading pre-supporting by grouting with small pipe strengthening stratum, advance support is that 40 × 2.75 ductules of Φ are noted in advance when excavation Slurry, tube wall interlock jewel hole every 100~200mm, eyelet diameter 10mm, vault ductule, set a ring per Pin grids, between grid Away from mono- Pin of 0.5m, when circumferential spacing 0.3m, first Zhi Houdu are 0.3m, 0.35m thickness, joint length 2m, 20 ° of first level inclination~ 25 °, grouting pressure is 0.4~0.6MPa, and stop grouting plug is arranged at aperture;
2) ingate outer profile
Launching shaft building enclosure isCast-in-situ bored pile add bracing members system, later stage to perform thick 700mm's Structure side wall, and carry out ingate according to design requirement and reserve, after the completion of the construction of shield well construction, progress ingate is small in advance to lead Pipe grouting and reinforcing.
As a further solution of the present invention:Construction arch advanced tubule, pre-pouring grout strengthening stratum;Excavate the arch soil body The top soil body retains Core Soil, and upper section mesh paving erects grid steel frame, dowel construction, and gunite concrete is locked foot anchor tube and applied Work excavates Core Soil, and is arranged as required to interim inverted arch, and upper half section is made to close early, and is backfilled behind to first branch in time Slip casting.
Compared with prior art, the beneficial effects of the invention are as follows:After the present invention is connected by Grouting Pipe, first pressed before slip casting Whether water test pipeline is unimpeded, then starts grouting pump, is pressed into stratum by ductule, controls grouting pressure well, have Effect prevents slurries from leaking outside, and per-fore pouring liquid with small pipe effect is good.
Description of the drawings
Fig. 1 is the grouting with small pipe construction process figure of the present invention.
Fig. 2 is the medium and small catheter fabrication schematic diagram of the present invention.
Fig. 3 is grouting construction process and equipment drawing in the present invention.
Fig. 4 is middle drift top of the present invention excavation and per-fore pouring liquid with small pipe figure.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the embodiment of the present invention, a kind of per-fore pouring liquid with small pipe construction technology and equipment, including closing working face, drilling, Ductule, slip casting, validity check etc. are installed, construction technology process please refers to Fig.1 shown.
Wherein, ductule processing and fabricating:Ductule usesT=2.75mm steel welded tubes are process, and tube head is processed into 25~35 ° of centrums so as to inserting piling, and prevent slurries preshoot.Tube wall has an injected hole, 6~10mm of aperture, 100~200mm of pitch-row, Quincuncial arrangement does not drill within the scope of the 0.5m of tail portion, mortar leakage prevention, end welderingRing-shaped stirrup, end when to prevent setting ductule Portion cracks, and influences Grouting Pipe connection, please refers to shown in Fig. 2.
Ductule is installed:It is first drilled with electric drill, is inserted into ductule, is then headed into ductule with pneumatic pick.
Grouting process and equipment:After Grouting Pipe is connected, whether first packer permeability test pipeline is unimpeded before slip casting, then starts note Stock pump is pressed into stratum by ductule, please refers to shown in Fig. 3.Wherein, the input terminal of grouting pump is connected to slurries storage by inlet pipe Stock tank is connected to, and valve is equipped on inlet pipe, and the output end of grouting pump is connected to Grouting Pipe, be equipped in Grouting Pipe pressure gauge and Flowmeter, Grouting Pipe are connected to slurries reserve pit by return pipe, and slip casting tube end connects floral tube by articulation.
Grouting with small pipe Divisional construction technique:
1) transverse passage-way vault
Leading pre-supporting uses grouting with small pipe strengthening stratum when excavation.Advance support is pre- using 40 × 2.75 ductules of Φ Slip casting, tube wall interlock jewel hole every 100~200mm, eyelet diameter 10mm, in addition to special indicate, vault ductule, per Pin grids Set a ring, mono- Pin of grid spacing 0.5m, when circumferential spacing 0.3m, first Zhi Houdu are 0.3m, 0.35m thickness, joint length 2m, just 20 °~25 ° of level inclination.Grouting serous fluid is selected according to strata condition, and Mortar mix proportion is determined by field test, and according to horizontal logical Wall rock condition around road controls grouting pressure (0.4~0.6MPa).To prevent slurries from leaking outside, can be set at aperture when necessary Stop grouting plug is set, is please referred to shown in Fig. 4.
It should be noted that:Construction arch advanced tubule, pre-pouring grout strengthening stratum;Excavate arch soil body top soil Body, retains Core Soil, and upper section mesh paving erects grid steel frame, dowel construction, gunite concrete, lock foot anchor tube construction.It excavates Core Soil.And it is arranged as required to interim inverted arch, so that upper half section is closed early, and in time to the backfill slip casting behind of first branch.
2) ingate outer profile
Launching shaft building enclosure usesCast-in-situ bored pile add bracing members system, later stage to perform thick 700mm Structure side wall.And carry out ingate according to design requirement and reserve, after the completion of the construction of shield well construction, dismounting structure Construction Support System simultaneously sets up one-shot job platform, carries out ingate per-fore pouring liquid with small pipe reinforcing, is enclosed according to each pilot tunnel sequence of construction Fender pile is abolished, and supporting grid enters transverse passage-way excavation after the completion of abolishing, and shield well transverse passage-way is divided into southern side transverse passage-way and north side goes out Native channel abolishes the unearthed tunnel fender post in north side and abolishes southern side shield successively after unearthed tunnel excavation completes 15m successively first Structure originates transverse passage-way fender post, carries out adit construction.
Grouting with small pipe key measures
1) stringent control match ratio and gel time after primary election match ratio, controls to adjust match ratio, and survey with gel time Determine the intensity of grouting soil, selectes optimum mix.
2) during slip casting, grouting pressure is strictly controlled, final grouting pressure must reach design requirement, and 1~2min of voltage stabilizing, Ensure the penetration range of slurries.Grouting pressure must not exceed the maximum pressure of setting, prevents malformation, grout leaking, jeopardizes The abnormal phenomenon of underground structure, above ground structure.When there is abnormal phenomenon, following control measure are taken:
1. reducing grouting pressure or using interval slip casting;
2. changing injecting paste material or shortening slurries gel time, slip casting embodiment is adjusted;
3. slip casting effect inspection:First, slip casting effect is checked with grout absorption, second is that using inspection technique is disclosed.Because of ductule Slip casting is the single consolidation slip casting in periphery, and the working face soil body detects the effect of grouting soil after disclosing, and if effect is bad, is adjusted in time Whole Mortar mix proportion improves grouting process;
4. to prevent aperture spillage, the gap of drilling and floral tube is blocked with cement-silicate colloid in floral tube tail end;
5. Grouting Pipe uses flare connection with floral tube, ensure rapid-assembling/disassembling;
6. the order of slip casting is symmetrically carried out to centre from both sides, hole-specifically slip casting from bottom to top;
7. after removing articulation, quickly blocking floral tube mouth with cement-roll, prevent the slurries not coagulated from outflowing;
8. slip casting reaches need intensity after can carry out excavation operation.
The invention is not limited in above-described embodiments, on the basis of technical solution disclosed by the invention, the skill of this field For art personnel according to disclosed technology contents, one can be made to some of which technical characteristic by not needing performing creative labour A little simple modification, equivalent change and modifications, belong in the range of technical solution of the present invention.

Claims (5)

1. a kind of per-fore pouring liquid with small pipe construction equipment, including grouting pump, inlet pipe and ductule, which is characterized in that shown note The input terminal of stock pump is connected to the connection of slurries reserve pit by inlet pipe, and valve is equipped on inlet pipe, the output end of grouting pump It is connected to Grouting Pipe, pressure gauge and flowmeter are installed in Grouting Pipe, Grouting Pipe is connected to slurries reserve pit, Grouting Pipe by return pipe End connects floral tube by articulation.
2. a kind of per-fore pouring liquid with small pipe construction equipment according to claim 1, which is characterized in that the ductule isT=2.75mm steel welded tubes are process, and tube head is processed into 25~35 ° of centrums, and tube wall has an injected hole, 6~10mm of aperture, 100~200mm of pitch-row, quincuncial arrangement do not drill within the scope of the 0.5m of tail portion, end welderingRing-shaped stirrup.
3. a kind of per-fore pouring liquid with small pipe construction equipment according to claim 2, which is characterized in that the peace of the ductule Dress is first drilled with electric drill, is inserted into ductule, is then headed into ductule with pneumatic pick.
4. a kind of per-fore pouring liquid with small pipe construction technology, which is characterized in that including following construction technology:
1) transverse passage-way vault
For leading pre-supporting by grouting with small pipe strengthening stratum, advance support is 40 × 2.75 pre-grouting with micropipe of Φ when excavation, Tube wall interlocks jewel hole every 100~200mm, eyelet diameter 10mm, vault ductule, and a ring, grid spacing are set per Pin grids Mono- Pin of 0.5m, when circumferential spacing 0.3m, first Zhi Houdu are 0.3m, 0.35m thickness, joint length 2m, 20 °~25 ° of first level inclination, Grouting pressure is 0.4~0.6MPa, and stop grouting plug is arranged at aperture;
2) ingate outer profile
Launching shaft building enclosure isCast-in-situ bored pile add bracing members system, later stage to perform the structure of thick 700mm Side wall, and carry out ingate according to design requirement and reserve, after the completion of the construction of shield well construction, carry out ingate advanced tubule note Slurry is reinforced.
5. a kind of per-fore pouring liquid with small pipe construction technology according to claim 4, which is characterized in that construction arch is small in advance Conduit, pre-pouring grout strengthening stratum;The arch soil body top soil body is excavated, Core Soil is retained, upper section mesh paving erects grid steel frame, Dowel is constructed, gunite concrete, and lock foot anchor tube construction excavates Core Soil, and be arranged as required to interim inverted arch, keeps upper half disconnected Face is closed early, and in time to the backfill slip casting behind of first branch.
CN201810178464.XA 2018-03-05 2018-03-05 A kind of per-fore pouring liquid with small pipe construction technology and equipment Pending CN108360525A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810178464.XA CN108360525A (en) 2018-03-05 2018-03-05 A kind of per-fore pouring liquid with small pipe construction technology and equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810178464.XA CN108360525A (en) 2018-03-05 2018-03-05 A kind of per-fore pouring liquid with small pipe construction technology and equipment

Publications (1)

Publication Number Publication Date
CN108360525A true CN108360525A (en) 2018-08-03

Family

ID=63003519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810178464.XA Pending CN108360525A (en) 2018-03-05 2018-03-05 A kind of per-fore pouring liquid with small pipe construction technology and equipment

Country Status (1)

Country Link
CN (1) CN108360525A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630157A (en) * 2018-11-09 2019-04-16 中铁二十二局集团轨道工程有限公司 A kind of regulator control system of Tunnel Engineering and ground water regime
CN110005442A (en) * 2019-04-26 2019-07-12 中铁二十三局集团第六工程有限公司 Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique
CN111042824A (en) * 2020-01-08 2020-04-21 华东交通大学 Intelligent grouting guide pipe with pressure detection device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000145398A (en) * 1998-09-11 2000-05-26 Bridgestone Corp Injection pipe used for consolidation and reinforcement of ground
CN201763349U (en) * 2010-09-17 2011-03-16 中铁十九局集团轨道交通工程有限公司 Two-liquid grouting device
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN205778881U (en) * 2016-06-30 2016-12-07 中交第四公路工程局有限公司 A kind of quick grouting device for tunnel per-fore pouring liquid with small pipe

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000145398A (en) * 1998-09-11 2000-05-26 Bridgestone Corp Injection pipe used for consolidation and reinforcement of ground
CN201763349U (en) * 2010-09-17 2011-03-16 中铁十九局集团轨道交通工程有限公司 Two-liquid grouting device
CN104196537A (en) * 2014-08-26 2014-12-10 广东省建筑工程机械施工有限公司 Construction method of three parallel metro tunnels with ultra-small clear distance
CN205778881U (en) * 2016-06-30 2016-12-07 中交第四公路工程局有限公司 A kind of quick grouting device for tunnel per-fore pouring liquid with small pipe

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
曹建新: "浅埋偏压软岩大跨隧道环形开挖预留核心土法施工技术探讨", 《西部探矿工程》 *
朱永全、宋玉香: "《地下铁道》", 31 December 2015, 中国铁道出版社 *
郭志飚 等: "《地下工程稳定性控制及工程实例》", 31 May 2015, 冶金工业出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630157A (en) * 2018-11-09 2019-04-16 中铁二十二局集团轨道工程有限公司 A kind of regulator control system of Tunnel Engineering and ground water regime
CN110005442A (en) * 2019-04-26 2019-07-12 中铁二十三局集团第六工程有限公司 Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique
CN111042824A (en) * 2020-01-08 2020-04-21 华东交通大学 Intelligent grouting guide pipe with pressure detection device

Similar Documents

Publication Publication Date Title
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
KR101500667B1 (en) steel pipe grouting device and tunnel reinforcement andbarrier grouting method using this
CN108643935A (en) The construction method in tunnel under rich water shallow embedding geology
CN111396067B (en) Comprehensive shield steel sleeve receiving construction method in complex environment
CN110005442A (en) Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique
CN110878696B (en) Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN109356162B (en) OPT occlusion pile side grouting water stopping method and grouting pipe device
CN105715296A (en) Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN108661650A (en) A kind of rich water magmatic body area depth pozo shaft construction method
CN108360525A (en) A kind of per-fore pouring liquid with small pipe construction technology and equipment
CN109026026A (en) Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method
CN208965598U (en) The Anti-seeping technology structure of grout curtain and underground chamber intersection area
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN106351312A (en) Pipeline and construction method thereof
CN105134254B (en) A kind of tunnel surface drilling sleeve pipe sealing device and its operating procedure
CN109630193A (en) Subway Tunnel service channel excavates the administering method for water burst phenomenon occur
CN110905527B (en) Construction method of tunnel with upper soft and lower hard strata
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN116816389A (en) Tunnel water-rich karst collapse cavity treatment method
CN108005662A (en) A kind of processing method of underground water seal cave depot bank area geology crushed zone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803

RJ01 Rejection of invention patent application after publication