CN112593482A - Prefabricated assembled concrete diaphragm structure and construction method - Google Patents
Prefabricated assembled concrete diaphragm structure and construction method Download PDFInfo
- Publication number
- CN112593482A CN112593482A CN202011410741.9A CN202011410741A CN112593482A CN 112593482 A CN112593482 A CN 112593482A CN 202011410741 A CN202011410741 A CN 202011410741A CN 112593482 A CN112593482 A CN 112593482A
- Authority
- CN
- China
- Prior art keywords
- plate
- diaphragm
- transverse
- steel bar
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011410741.9A CN112593482B (en) | 2020-12-04 | 2020-12-04 | Prefabricated assembled concrete diaphragm structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011410741.9A CN112593482B (en) | 2020-12-04 | 2020-12-04 | Prefabricated assembled concrete diaphragm structure and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112593482A true CN112593482A (en) | 2021-04-02 |
CN112593482B CN112593482B (en) | 2022-07-12 |
Family
ID=75188368
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011410741.9A Active CN112593482B (en) | 2020-12-04 | 2020-12-04 | Prefabricated assembled concrete diaphragm structure and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112593482B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114737485A (en) * | 2022-05-13 | 2022-07-12 | 福建第一公路工程集团有限公司 | Construction method for preventing transverse partition plate from being dislocated by prefabricated box girder |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1636501A1 (en) * | 1989-01-17 | 1991-03-23 | Грузинский политехнический институт | Prefabricated reinforced concrete span structure of bridge |
US6345403B1 (en) * | 1995-05-08 | 2002-02-12 | Schuylkill Products, Inc. | Method of bridge construction using concrete diaphragms |
CN103321153A (en) * | 2013-06-19 | 2013-09-25 | 江苏科技大学 | Construction method for medium and small span trough girder bridge |
CN204212043U (en) * | 2014-11-18 | 2015-03-18 | 湖南大学 | Prefabricated ultra-high performance concrete π ellbeam unit |
KR20160019286A (en) * | 2014-08-11 | 2016-02-19 | 고재복 | Psc girder with end diaphragm and semi-integral abutment bridge construction method therewith |
CN105755960A (en) * | 2016-03-14 | 2016-07-13 | 沈阳建筑大学 | Method for preventing middle beam of T-shaped beam bridge from generating lateral bending deformation |
CN206589121U (en) * | 2017-02-24 | 2017-10-27 | 中国建筑第六工程局有限公司 | It is a kind of to be used for precast beam, the diaphragm plate horizontal reinforcement mounting and positioning device of plate |
CN108867310A (en) * | 2018-07-12 | 2018-11-23 | 浙江省交通规划设计研究院有限公司 | The short rib T beam bridge of pretensioning prestressed concrete and its construction method |
CN109235222A (en) * | 2018-10-17 | 2019-01-18 | 湖南大学 | Light-duty full assembled great cantilever ultra-high performance concrete index chain and its construction method |
CN109487674A (en) * | 2018-12-04 | 2019-03-19 | 中交公路规划设计院有限公司 | Assembling tank-shaped composite beam bridge |
CN208899299U (en) * | 2018-03-21 | 2019-05-24 | 重庆交通大学 | A kind of Novel transverse baffle plate configuration form for existing prefabricated assembled small box girder |
CN110965484A (en) * | 2019-12-17 | 2020-04-07 | 中交路桥建设有限公司 | New and old bridge widening reinforcing method |
CN110983942A (en) * | 2019-12-23 | 2020-04-10 | 同济大学建筑设计研究院(集团)有限公司 | Transverse connecting structure and connecting method for precast beams |
CN111058479A (en) * | 2019-12-23 | 2020-04-24 | 中铁第一勘察设计院集团有限公司 | Anti-floating system for connecting subway station structure and underground diaphragm wall by using shear-resistant steel bars |
CN111636286A (en) * | 2020-05-12 | 2020-09-08 | 济南市市政工程设计研究院(集团)有限责任公司 | Pretensioned broken line prestressed I-beam bridge and construction method |
CN111730738A (en) * | 2020-06-30 | 2020-10-02 | 中国一冶集团有限公司 | Prefabricated box girder diaphragm plate connecting structure and construction method thereof |
CN111778864A (en) * | 2020-07-20 | 2020-10-16 | 上海市城市建设设计研究总院(集团)有限公司 | Bridge with small box girders prefabricated in longitudinal sections and construction method |
CN211897811U (en) * | 2020-03-02 | 2020-11-10 | 上海市城市建设设计研究总院(集团)有限公司 | Transverse segmented prefabricated prestressed concrete bent cap structure |
-
2020
- 2020-12-04 CN CN202011410741.9A patent/CN112593482B/en active Active
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1636501A1 (en) * | 1989-01-17 | 1991-03-23 | Грузинский политехнический институт | Prefabricated reinforced concrete span structure of bridge |
US6345403B1 (en) * | 1995-05-08 | 2002-02-12 | Schuylkill Products, Inc. | Method of bridge construction using concrete diaphragms |
CN103321153A (en) * | 2013-06-19 | 2013-09-25 | 江苏科技大学 | Construction method for medium and small span trough girder bridge |
KR20160019286A (en) * | 2014-08-11 | 2016-02-19 | 고재복 | Psc girder with end diaphragm and semi-integral abutment bridge construction method therewith |
CN204212043U (en) * | 2014-11-18 | 2015-03-18 | 湖南大学 | Prefabricated ultra-high performance concrete π ellbeam unit |
CN105755960A (en) * | 2016-03-14 | 2016-07-13 | 沈阳建筑大学 | Method for preventing middle beam of T-shaped beam bridge from generating lateral bending deformation |
CN206589121U (en) * | 2017-02-24 | 2017-10-27 | 中国建筑第六工程局有限公司 | It is a kind of to be used for precast beam, the diaphragm plate horizontal reinforcement mounting and positioning device of plate |
CN208899299U (en) * | 2018-03-21 | 2019-05-24 | 重庆交通大学 | A kind of Novel transverse baffle plate configuration form for existing prefabricated assembled small box girder |
CN108867310A (en) * | 2018-07-12 | 2018-11-23 | 浙江省交通规划设计研究院有限公司 | The short rib T beam bridge of pretensioning prestressed concrete and its construction method |
CN109235222A (en) * | 2018-10-17 | 2019-01-18 | 湖南大学 | Light-duty full assembled great cantilever ultra-high performance concrete index chain and its construction method |
CN109487674A (en) * | 2018-12-04 | 2019-03-19 | 中交公路规划设计院有限公司 | Assembling tank-shaped composite beam bridge |
CN110965484A (en) * | 2019-12-17 | 2020-04-07 | 中交路桥建设有限公司 | New and old bridge widening reinforcing method |
CN110983942A (en) * | 2019-12-23 | 2020-04-10 | 同济大学建筑设计研究院(集团)有限公司 | Transverse connecting structure and connecting method for precast beams |
CN111058479A (en) * | 2019-12-23 | 2020-04-24 | 中铁第一勘察设计院集团有限公司 | Anti-floating system for connecting subway station structure and underground diaphragm wall by using shear-resistant steel bars |
CN211897811U (en) * | 2020-03-02 | 2020-11-10 | 上海市城市建设设计研究总院(集团)有限公司 | Transverse segmented prefabricated prestressed concrete bent cap structure |
CN111636286A (en) * | 2020-05-12 | 2020-09-08 | 济南市市政工程设计研究院(集团)有限责任公司 | Pretensioned broken line prestressed I-beam bridge and construction method |
CN111730738A (en) * | 2020-06-30 | 2020-10-02 | 中国一冶集团有限公司 | Prefabricated box girder diaphragm plate connecting structure and construction method thereof |
CN111778864A (en) * | 2020-07-20 | 2020-10-16 | 上海市城市建设设计研究总院(集团)有限公司 | Bridge with small box girders prefabricated in longitudinal sections and construction method |
Non-Patent Citations (3)
Title |
---|
周秀峰: "预应力T梁预制安装施工技术", 《交通科技与经济》 * |
深圳市建筑科技促进中心主编: "《装配式混凝土建筑常见问题防治指南》", 31 May 2020, 同济大学出版社 * |
穆阿立: "《高速铁路施工与维护》", 31 January 2019, 西南交通大学出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114737485A (en) * | 2022-05-13 | 2022-07-12 | 福建第一公路工程集团有限公司 | Construction method for preventing transverse partition plate from being dislocated by prefabricated box girder |
CN114737485B (en) * | 2022-05-13 | 2023-06-23 | 福建第一公路工程集团有限公司 | Construction method for preventing dislocation of diaphragm plate of prefabricated box girder |
Also Published As
Publication number | Publication date |
---|---|
CN112593482B (en) | 2022-07-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101652664B1 (en) | Precast deckplate and composite slab and concrete slab manufacturing method using the same | |
CN109457801B (en) | Connecting node of prefabricated reinforced concrete beam and construction method thereof | |
KR101026118B1 (en) | Truss structure with high bearing capacity against secondary moment at inner supports and construction method of truss bridge using it | |
CN108978856B (en) | Assembly type honeycomb beam-slab structure system | |
CN112593482B (en) | Prefabricated assembled concrete diaphragm structure and construction method | |
CN114135000B (en) | Beam column connecting node of assembled type partially-encased U-shaped steel and construction method thereof | |
CN111648468A (en) | Ultrahigh space utilization rate fabricated building system and efficient construction method thereof | |
CN111411721A (en) | Assembly type prefabricated floor slab secondary beam combined component | |
CN111236091B (en) | Concrete lining reinforcing structure of corrugated steel web box girder bridge | |
CN210086022U (en) | Assembled single-box multi-chamber corrugated steel web box girder | |
JP2523447B2 (en) | Floor slab installation structure in bridge | |
CN218346250U (en) | Connecting structure of crossbeam-free high-penetrating V-shaped column joint | |
CN110820976A (en) | Assembly structure and method of damping damper, prefabricated pier joist and assembly type building | |
CN203475609U (en) | Connecting structure of composite floor slab and steel tube shear wall of building | |
CN214696353U (en) | S-shaped connecting node of full precast concrete floor slab | |
KR20030094195A (en) | Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam | |
CN211646957U (en) | Assembled house ground reinforcing plate structure | |
CN101230668A (en) | Force-bearing type underplate component | |
CN110029729B (en) | Splicing joint of prefabricated reinforced concrete main beam and secondary beam and construction method | |
CN113530051A (en) | Prefabricated rib-free laminated slab | |
CN206859464U (en) | The attachment means of fabricated shear wall horizontal joint | |
CN111305066A (en) | Hybrid combination beam steel-concrete combination section and mounting method thereof | |
KR20140140954A (en) | Steel concrete composite girder bridge and construction method thereof | |
CN218540358U (en) | Wind brace and cross beam | |
CN220814551U (en) | Assembled prefabricated reinforced concrete constructional column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20230329 Address after: 610000 nine Xing Xing Road 12, hi tech Zone, Sichuan, Chengdu Patentee after: SICHUAN ROAD & BRIDGE (Group) Co.,Ltd. Address before: 610041 nine Xing Xing Road 12, hi tech Zone, Sichuan, Chengdu Patentee before: Zou Yu Patentee before: Zhang Haichen Patentee before: Lu Wei Patentee before: Shi Xuefei Patentee before: Yu Zhibing Patentee before: Liu Wanchun Patentee before: Liu Chao Patentee before: Yang Zhi Patentee before: Song Jun Patentee before: Liu Zhiquan |