CN111724070A - Information repeating method for power scheduling instruction - Google Patents
Information repeating method for power scheduling instruction Download PDFInfo
- Publication number
- CN111724070A CN111724070A CN202010574706.4A CN202010574706A CN111724070A CN 111724070 A CN111724070 A CN 111724070A CN 202010574706 A CN202010574706 A CN 202010574706A CN 111724070 A CN111724070 A CN 111724070A
- Authority
- CN
- China
- Prior art keywords
- repeating
- scheduling
- dispatching
- order
- station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 31
- 238000012790 confirmation Methods 0.000 claims description 12
- 230000008569 process Effects 0.000 claims description 7
- 230000008707 rearrangement Effects 0.000 claims description 3
- 238000006243 chemical reaction Methods 0.000 claims description 2
- 230000005540 biological transmission Effects 0.000 description 4
- 230000006870 function Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000010076 replication Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- G—PHYSICS
- G10—MUSICAL INSTRUMENTS; ACOUSTICS
- G10L—SPEECH ANALYSIS TECHNIQUES OR SPEECH SYNTHESIS; SPEECH RECOGNITION; SPEECH OR VOICE PROCESSING TECHNIQUES; SPEECH OR AUDIO CODING OR DECODING
- G10L15/00—Speech recognition
- G10L15/26—Speech to text systems
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
- H02J13/00001—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the display of information or by user interaction, e.g. supervisory control and data acquisition systems [SCADA] or graphical user interfaces [GUI]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J13/00—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
- H02J13/00006—Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L63/00—Network architectures or network communication protocols for network security
- H04L63/08—Network architectures or network communication protocols for network security for authentication of entities
- H04L63/0876—Network architectures or network communication protocols for network security for authentication of entities based on the identity of the terminal or configuration, e.g. MAC address, hardware or software configuration or device fingerprint
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L63/00—Network architectures or network communication protocols for network security
- H04L63/12—Applying verification of the received information
- H04L63/123—Applying verification of the received information received data contents, e.g. message integrity
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/40—Display of information, e.g. of data or controls
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S40/00—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
- Y04S40/12—Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Computer Security & Cryptography (AREA)
- Physics & Mathematics (AREA)
- Power Engineering (AREA)
- Health & Medical Sciences (AREA)
- Strategic Management (AREA)
- General Engineering & Computer Science (AREA)
- Human Computer Interaction (AREA)
- Signal Processing (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Computing Systems (AREA)
- Computer Hardware Design (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- Quality & Reliability (AREA)
- General Health & Medical Sciences (AREA)
- Water Supply & Treatment (AREA)
- Educational Administration (AREA)
- Public Health (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Primary Health Care (AREA)
- Computational Linguistics (AREA)
- Audiology, Speech & Language Pathology (AREA)
- Acoustics & Sound (AREA)
- Multimedia (AREA)
- Mobile Radio Communication Systems (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses an information repeating method of a power dispatching instruction, which comprises the following steps: scheduling and ordering: the dispatching end sends a complete dispatching instruction to the plant station end in advance, wherein the complete dispatching instruction comprises a dispatching number, preset operation time and operation content; signing in a factory station prearranged order, issuing a scheduling formal order, repeating a factory station, confirming a scheduling, returning a factory station, receiving a scheduling order and confirming the factory station. The information repeating method of the power dispatching instruction disclosed by the invention is more reliable and rigorous, and can effectively ensure that the dispatching instruction is correctly transmitted and completed.
Description
Technical Field
The invention relates to an information repeating method of a power dispatching instruction.
Background
The dispatching network command is to realize electronic issuing and replying of dispatching command via network instead of traditional telephone command mode. The network dispatching and issuing mode fully utilizes the advantages of rapidness and convenience of a network, standardizes the dispatching work flow, realizes the functions of start-up and completion of normal dispatching business and advanced application and dispatching and replication of corresponding dispatching instructions, and replaces the traditional telephone dispatching and issuing mode to realize the network circulation of the dispatching instructions. The dispatching network command not only greatly improves the working efficiency of a dispatcher, but also enables a dispatching object to clearly master the operation content, avoids the defects of traditional telephone command modes such as harmonic tone error interference, environmental interference, step operation and the like, enhances the monitoring function and greatly enhances the safety of power grid dispatching operation.
Disclosure of Invention
The invention aims to provide a novel reliable information repeating method of a power dispatching instruction, which is more reliable and rigorous in repeating and can effectively ensure that the dispatching instruction is correctly transmitted and completed.
The technical scheme adopted by the invention for solving the technical problems is as follows: a method for repeating information of power dispatching instructions comprises the following steps: scheduling and ordering: the dispatching end sends a complete dispatching instruction to the plant station end in advance, wherein the complete dispatching instruction comprises a dispatching number, preset operation time and operation content;
signing in a factory station prearranged order: the factory station end receives a complete scheduling instruction pre-sent by the scheduling end and then performs pre-order sign-in; when the pre-order is signed, firstly, the identity of an operator needs to be identified, and the pre-order signing can be carried out only after the identification is passed; in the process of the pre-order sign-in, complete information repeating needs to be carried out on the scheduling command, and repeating contents comprise a sequence number repeating, a preset operation time repeating and an operation content repeating; the repeating of the pre-order sign-in process is completed in two steps, the first step is repeated with the order number and the preset operation time, the second step is repeated with the operation content, the second step can be started after the first step is correctly repeated, the sign-in is completed after the second step is correctly repeated, and the scheduling end is fed back; the signing can be carried out only once, and repeated signing can not be carried out;
and (3) scheduling and formally ordering: the dispatching end carries out dispatching formal ordering according to the fed-back signing information;
repeating the station: the station side receives the complete scheduling instruction pre-sent by the scheduling side and then repeats the instruction, and after the repeating is finished, the scheduling side feeds back the instruction;
scheduling confirmation: after receiving the station repeat, the scheduling terminal completes scheduling confirmation work;
factory station command returning: after the scheduling is confirmed, the plant station side can carry out field operation according to the contents in the scheduling formal order, and after the completion, reports repeating work, repeats the contents in the scheduling formal order, and adds an execution completion word eye at the end to complete the plant station return order;
scheduling and order receiving: after receiving the station return order, the dispatching end determines whether the operation changes simultaneously according to the on-off state and the on-off current quantity in the SCADA system, if so, the dispatching end indicates that the work is finished, releases the issuing of the next dispatching order and sends out dispatching order receiving information to the station end; if the current quantity of the on-off state and the current quantity of the on-off current in the SCADA system are changed simultaneously, the dispatching order receiving information is sent to the plant station end, and the next dispatching order is issued;
plant station confirmation: and after receiving the dispatching order receiving information, the station terminal feeds back the information to the dispatching terminal after confirming the information.
In order to facilitate archiving management, after the confirmation of the factory station, the operation ticket archiving is further included, and after the operation ticket archiving, the operation ticket information can be screened and consulted according to the ticket planning time, the operation task and the operation ticket number.
Furthermore, the repeating mode can adopt one of a filling repeating mode and a splicing repeating mode.
In order to ensure the correct transmission of the scheduling instruction, the repeating mode adopts a filling repeating mode and a splicing repeating mode to be used simultaneously; it requires both to be repeated correctly to complete the repeat.
Furthermore, the error of the repeat can be indicated by color marks and sound reminders.
Furthermore, the check-in of factory station prearranged, the check-out, the export and the printing of the operation ticket can be carried out in the repeat of factory station.
In order to improve the transmission accuracy of the scheduling instruction, in the filling-in repeating mode, the keywords in the scheduling instruction are set as items to be filled in the blank space, and during repeating, missing keywords are required to be filled in the blank space according to the scheduling instruction so as to finish repeating; in the splicing repeating mode, the command is disordered and interrupted, the disordered and interrupted command needs to be rearranged to form a correct command during repeating, and the rearrangement mode can adopt a dragging mode and a sequential clicking mode.
In order to improve the convenience and ensure the correct transmission of the instructions, the method also comprises voice repeating, wherein the voice repeating adopts a mode of converting voice input into characters, and in the mode, only the keyword is verified to be consistent with the scheduling instructions; meanwhile, when one of the filling repeating mode and the splicing repeating mode and the voice repeating mode are correct at the same time, the repeating of the scheduling command is completed.
The invention has the beneficial effects that: firstly, the attendance can be signed only by identification, so that only direct personnel who are instructed can operate the attendance, and the dispatching instruction is guaranteed to be ready to be transmitted to a target; the pre-order sign-in is repeated in two steps, so that the accuracy of scheduling instruction transmission is improved, the operation time and the operation content are separated, and the reciver is facilitated to deepen the memory of the reciting person and the reciting person. In the dispatching and order receiving process, the on-off state and the on-off current amount of the SCADA system are combined for checking, whether the dispatching instruction is completed correctly or not is confirmed, and the rigor of the method is improved. The information repeating method of the power dispatching instruction is more reliable and rigorous, and can effectively guarantee that the dispatching instruction is correctly transmitted and completed.
The present invention will be described in more detail with reference to the following examples.
Detailed Description
The embodiment discloses an information repeating method of a power dispatching instruction, which comprises the following steps:
scheduling and ordering: the dispatching end sends a complete dispatching instruction to the plant station end in advance, wherein the complete dispatching instruction comprises a dispatching number, preset operation time and operation content;
signing in a factory station prearranged order: the factory station end receives a complete scheduling instruction pre-sent by the scheduling end and then performs pre-order sign-in; when the pre-order is signed, firstly, the identity of an operator needs to be identified, and the pre-order signing can be carried out only after the identification is passed; in the process of the pre-order sign-in, complete information repeating needs to be carried out on the scheduling command, and repeating contents comprise a sequence number repeating, a preset operation time repeating and an operation content repeating; the repeating of the pre-order sign-in process is completed in two steps, the first step is repeated with the order number and the preset operation time, the second step is repeated with the operation content, the second step can be started after the first step is correctly repeated, the sign-in is completed after the second step is correctly repeated, and the scheduling end is fed back; the signing can be carried out only once, and repeated signing can not be carried out;
and (3) scheduling and formally ordering: the dispatching end carries out dispatching formal ordering according to the fed-back signing information;
repeating the station: the station side receives the complete scheduling instruction pre-sent by the scheduling side and then repeats the instruction, and after the repeating is finished, the scheduling side feeds back the instruction;
scheduling confirmation: after receiving the station repeat, the scheduling terminal completes scheduling confirmation work;
factory station command returning: after the scheduling is confirmed, the plant station side can carry out field operation according to the contents in the scheduling formal order, and after the completion, reports repeating work, repeats the contents in the scheduling formal order, and adds an execution completion word eye at the end to complete the plant station return order;
scheduling and order receiving: after receiving the station return order, the dispatching end determines whether the operation changes simultaneously according to the on-off state and the on-off current quantity in the SCADA system, if so, the dispatching end indicates that the work is finished, releases the issuing of the next dispatching order and sends out dispatching order receiving information to the station end; if the current quantity of the on-off state and the current quantity of the on-off current in the SCADA system are changed simultaneously, the dispatching order receiving information is sent to the plant station end, and the next dispatching order is issued;
plant station confirmation: and after receiving the dispatching order receiving information, the station terminal feeds back the information to the dispatching terminal after confirming the information.
The information retrieval method for the power scheduling command as recited in claim 1, wherein: after the plant station confirms, operation ticket filing is further included, and operation ticket information can be screened and consulted according to the ticket drawing time, the operation tasks and the operation ticket numbers after the operation ticket filing.
The repeating mode can adopt one of filling repeating mode and splicing repeating mode. The repeating mode can also be combined with the filling repeating mode and the splicing repeating mode simultaneously, and when the filling repeating mode and the splicing repeating mode are used simultaneously, the filling repeating mode and the splicing repeating mode need both to be repeated correctly to complete the repeating.
The repeat of the related scheduling instructions can be indicated by color marks and voice prompts when the repeat is wrong. The reminding manner is not limited to the above-mentioned design manner, and other manners easily conceivable in the field should be included in the protection scope of the present application.
The station is prearranged for signing in, the station is repeated, and the operation tickets can be consulted, exported and printed. The authority can be selectively opened in different links according to the requirements of looking up, exporting and printing the operation ticket.
In the filling and repeating mode, the keywords in the scheduling instruction are set as items to be filled with blank space, and when repeating, missing keywords are required to be repeated in the blank space according to the scheduling instruction so as to finish repeating; in the splicing repeating mode, the command is disordered and interrupted, the disordered and interrupted command needs to be rearranged to form a correct command during repeating, and the rearrangement mode can adopt a dragging mode and a sequential clicking mode. The keywords may be the device name, location, time, duration, device model, etc. some key quantity. When the instruction is interrupted and disordered, the keywords need to be interrupted separately, so that the memory of the reciting person is deepened during splicing.
The repeating mode also comprises voice repeating, wherein the voice repeating adopts a mode of voice input to character conversion, and in the mode, only whether the keywords are consistent with the scheduling instruction is verified; meanwhile, when one of the filling repeating mode and the splicing repeating mode and the voice repeating mode are correct at the same time, the repeating of the scheduling command is completed.
The method comprises the steps of scheduling pre-order issuing, station pre-order signing, scheduling formal order issuing, station repeating, scheduling confirmation, station returning, scheduling order receiving and station confirmation, wherein the identity of an operator is identified in each step, and relevant operation can be carried out after the identification is passed.
The present invention has been described above by way of example. It is to be understood that the specific implementations of the invention are not limited in this respect. Various insubstantial improvements are made by adopting the method conception and the technical scheme of the invention; the present invention is not limited to the above embodiments, and can be modified in various ways.
Claims (8)
1. A method for repeating information of power dispatching instructions is characterized in that: the method comprises the following steps:
scheduling and ordering: the dispatching end sends a complete dispatching instruction to the plant station end in advance, wherein the complete dispatching instruction comprises a dispatching number, preset operation time and operation content;
signing in a factory station prearranged order: the factory station end receives a complete scheduling instruction pre-sent by the scheduling end and then performs pre-order sign-in; when the pre-order is signed, firstly, the identity of an operator needs to be identified, and the pre-order signing can be carried out only after the identification is passed; in the process of the pre-order sign-in, complete information repeating needs to be carried out on the scheduling command, and repeating contents comprise a sequence number repeating, a preset operation time repeating and an operation content repeating; the repeating of the pre-order sign-in process is completed in two steps, the first step is repeated with the order number and the preset operation time, the second step is repeated with the operation content, the second step can be started after the first step is correctly repeated, the sign-in is completed after the second step is correctly repeated, and the scheduling end is fed back; the signing can be carried out only once, and repeated signing can not be carried out;
and (3) scheduling and formally ordering: the dispatching end carries out dispatching formal ordering according to the fed-back signing information;
repeating the station: the station side receives the complete scheduling instruction pre-sent by the scheduling side and then repeats the instruction, and after the repeating is finished, the scheduling side feeds back the instruction;
scheduling confirmation: after receiving the station repeat, the scheduling terminal completes scheduling confirmation work;
factory station command returning: after the scheduling is confirmed, the plant station side can carry out field operation according to the contents in the scheduling formal order, and after the completion, reports repeating work, repeats the contents in the scheduling formal order, and adds an execution completion word eye at the end to complete the plant station return order;
scheduling and order receiving: after receiving the station return order, the dispatching end determines whether the operation changes simultaneously according to the on-off state and the on-off current quantity in the SCADA system, if so, the dispatching end indicates that the work is finished, releases the issuing of the next dispatching order and sends out dispatching order receiving information to the station end; if the current quantity of the on-off state and the current quantity of the on-off current in the SCADA system are changed simultaneously, the dispatching order receiving information is sent to the plant station end, and the next dispatching order is issued;
plant station confirmation: and after receiving the dispatching order receiving information, the station terminal feeds back the information to the dispatching terminal after confirming the information.
2. The information retrieval method for the power scheduling command as recited in claim 1, wherein: after the plant station confirms, operation ticket filing is further included, and operation ticket information can be screened and consulted according to the ticket drawing time, the operation tasks and the operation ticket numbers after the operation ticket filing.
3. The information retrieval method of the power scheduling instruction according to claim 1 or 2, characterized in that: the repeating mode can adopt one of filling repeating mode and splicing repeating mode.
4. The information retrieval method of the power scheduling instruction according to claim 1 or 2, characterized in that: the repeating mode adopts a filling repeating mode and a splicing repeating mode to be used simultaneously; it requires both to be repeated correctly to complete the repeat.
5. The information retrieval method of the power scheduling instruction according to claim 1 or 2, characterized in that: the error of repeating can be indicated by color mark and sound.
6. The information retrieval method of the power scheduling instruction according to claim 1 or 2, characterized in that: the check-in of factory station prearranged, the check-out, export and printing of operation order can be carried out in the factory station repeating.
7. The information retrieval method for the power scheduling command as recited in claim 4, wherein: in the filling and repeating mode, the keywords in the scheduling instruction are set as items to be filled with blank space, and when repeating, missing keywords are required to be repeated in the blank space according to the scheduling instruction so as to finish repeating; in the splicing repeating mode, the command is disordered and interrupted, the disordered and interrupted command needs to be rearranged to form a correct command during repeating, and the rearrangement mode can adopt a dragging mode and a sequential clicking mode.
8. The information retrieval method for the power scheduling command as recited in claim 3, wherein: the method also comprises voice repeating, wherein the voice repeating adopts a mode of voice input to character conversion, and only checks whether the keywords are consistent with the scheduling instruction; meanwhile, when one of the filling repeating mode and the splicing repeating mode and the voice repeating mode are correct at the same time, the repeating of the scheduling command is completed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010574706.4A CN111724070B (en) | 2020-06-22 | 2020-06-22 | Information repeating method of power dispatching instruction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010574706.4A CN111724070B (en) | 2020-06-22 | 2020-06-22 | Information repeating method of power dispatching instruction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111724070A true CN111724070A (en) | 2020-09-29 |
CN111724070B CN111724070B (en) | 2023-12-19 |
Family
ID=72569885
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010574706.4A Active CN111724070B (en) | 2020-06-22 | 2020-06-22 | Information repeating method of power dispatching instruction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111724070B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112990793A (en) * | 2021-05-11 | 2021-06-18 | 国网浙江省电力有限公司金华供电公司 | Scheduling instruction identification and repeating method |
CN114091694A (en) * | 2021-11-09 | 2022-02-25 | 深圳供电局有限公司 | Intelligent dispatching management system and method for distribution network live working |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104376440A (en) * | 2014-12-12 | 2015-02-25 | 广西电网有限责任公司 | Automatic power grid dispatching electronic token confirming method based on network token issuing |
WO2015136705A1 (en) * | 2014-03-14 | 2015-09-17 | 株式会社日立システムズ | System and method for verifying and registering work check sheets, voice recognition control system, and voice recognition control method |
CN110956357A (en) * | 2019-10-10 | 2020-04-03 | 国网浙江省电力有限公司宁波供电公司 | Intelligent regulation and control networked interaction system applied to power company |
-
2020
- 2020-06-22 CN CN202010574706.4A patent/CN111724070B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2015136705A1 (en) * | 2014-03-14 | 2015-09-17 | 株式会社日立システムズ | System and method for verifying and registering work check sheets, voice recognition control system, and voice recognition control method |
CN104376440A (en) * | 2014-12-12 | 2015-02-25 | 广西电网有限责任公司 | Automatic power grid dispatching electronic token confirming method based on network token issuing |
CN110956357A (en) * | 2019-10-10 | 2020-04-03 | 国网浙江省电力有限公司宁波供电公司 | Intelligent regulation and control networked interaction system applied to power company |
Non-Patent Citations (2)
Title |
---|
张中超等: "基于自动化安全区隔离交互的电网调令防误控制方法及应用", 《机电信息》 * |
李鸿文: "惠州调度操作防误网络***在电力调度中的应用", 《中国电力教育》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112990793A (en) * | 2021-05-11 | 2021-06-18 | 国网浙江省电力有限公司金华供电公司 | Scheduling instruction identification and repeating method |
CN112990793B (en) * | 2021-05-11 | 2021-07-23 | 国网浙江省电力有限公司金华供电公司 | Scheduling instruction identification and repeating method |
CN114091694A (en) * | 2021-11-09 | 2022-02-25 | 深圳供电局有限公司 | Intelligent dispatching management system and method for distribution network live working |
Also Published As
Publication number | Publication date |
---|---|
CN111724070B (en) | 2023-12-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109034659A (en) | A kind of grid dispatching management system | |
CN111724070A (en) | Information repeating method for power scheduling instruction | |
CN106815681B (en) | Transformer substation secondary equipment closed-loop management platform based on two-dimensional code and management system thereof | |
CN107749811B (en) | Power distribution terminal access adaptive debugging analysis method based on power distribution master station | |
CN102117444A (en) | System for comprehensive arrangement and execution management of production equipment maintenance plan | |
CN107591892B (en) | Intelligent substation operation and maintenance method and system | |
CN104700192A (en) | Aided intelligent management and control system for power transmission and transformation project and management and control method thereof | |
CN113258669B (en) | Networked intelligent scheduling method and terminal based on distribution network maintenance | |
CN109598640A (en) | A kind of user power utilization information query system and its application method based on wechat public platform | |
CN116308139A (en) | Intelligent misoperation prevention and networked command issuing platform for regulation and control | |
CN111583465A (en) | Intelligent key working method for electric power switching operation | |
CN110782146A (en) | Scheduling operation task ticketing method and device based on power grid new equipment job scheduling | |
CN111524031B (en) | Implementation method and system for intelligently generating operation steps based on analysis operation task | |
CN201974848U (en) | Management system for comprehensively arranging and executing maintenance plan of production equipment | |
CN109299843A (en) | A kind of Risk Pre-control analysis intelligent management | |
CN110852406A (en) | Transformer substation protection equipment ledger management system based on mobile communication | |
CN111242578A (en) | Method, device and system for distributing operation program | |
CN114039769B (en) | Internet-based enterprise internal information management coordination system and method | |
CN114065794B (en) | Production and work reporting method, system and equipment based on multi-dimensional two-dimensional code | |
CN113794754A (en) | Electronic operation ticket control system and method based on mobile application | |
CN109919517B (en) | Power station equipment maintenance welding operation flow control method | |
CN114158217A (en) | Customized value streaming method of master station system | |
CN112053138A (en) | Electronic work package rule recording system and method | |
CN204331859U (en) | Substation gate operation management system | |
CN112165170A (en) | Intelligent sequential control method and system for substation equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |