CN111340458A - 一种施工进度信息化管理的方法 - Google Patents

一种施工进度信息化管理的方法 Download PDF

Info

Publication number
CN111340458A
CN111340458A CN202010185340.1A CN202010185340A CN111340458A CN 111340458 A CN111340458 A CN 111340458A CN 202010185340 A CN202010185340 A CN 202010185340A CN 111340458 A CN111340458 A CN 111340458A
Authority
CN
China
Prior art keywords
progress
construction
project
plan
bim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010185340.1A
Other languages
English (en)
Inventor
曾乐
张鑫全
朱贤明
黎升腾
杨科
李涛
胡炼军
王亚伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Urban Construction Group Co Ltd
General Contracting Branch of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway Urban Construction Group Co Ltd
General Contracting Branch of China Railway Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Urban Construction Group Co Ltd, General Contracting Branch of China Railway Urban Construction Group Co Ltd filed Critical China Railway Urban Construction Group Co Ltd
Priority to CN202010185340.1A priority Critical patent/CN111340458A/zh
Publication of CN111340458A publication Critical patent/CN111340458A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公布了一种施工进度信息化管理的方法,它包括以下步骤:1)应用BIM软件编制项目进度计划,直观查看关键路径和自由时差;2)将进度计划与合同清单导入BIM***,与信息模型关联,进行5D施工模拟;3)结合施工总进度计划与月度计划,在BIM网页端排布周进度计划,并推送至项目现场管理人员手机端;4)项目部每周应用BIM***自动生成的施工数字周报;5)项目部每月月末应用BIM***前锋线动态管控功能,进行实际进度与计划进度对比分析;6)根据进度滞后原因,调整项目劳务人员、材料、大型机械等资源配比。本发明方法能够实现制定合理的施工进度计划,并结合项目实际情况进行优化,保证施工组织流畅进行,保障项目工期目标。

Description

一种施工进度信息化管理的方法
技术领域
本发明涉及房屋建筑、市政设施等工程技术领域,尤其是涉及一种施工进度信息化管理的方法。
背景技术
在房屋建筑、市政建设等工程项目施工领域,进度管理是项目管理三大目标之一,同时项目工期滞后是制约建筑企业发展的一大难题。如何制定合理的施工进度计划,并结合项目实际情况进行优化,保证施工组织流畅进行,实现项目工期目标是行业普遍性难题。
发明内容
本发明的目的是针对以上问题,提供一种施工进度信息化管理的方法,它能够实现快速制定施工进度计划,通过5D模拟验证其合理性、可行性,并快速进行进度优化与调整。
为实现以上目的,本发明采用的技术方案是:一种施工进度信息化管理的方法,包括以下步骤:
1)应用BIM软件编制项目进度计划,直观查看关键路径和自由时差;
2)将进度计划与合同清单导入BIM***,与信息模型关联,进行5D施工模拟;
3)结合施工总进度计划与月度计划,在BIM网页端排布周进度计划,并推送至项目现场管理人员手机端;
4)项目部每周应用BIM***生成施工数字周报;
5)项目部每月月末应用BIM***前锋线动态管控功能,进行实际进度与计划进度对比分析;
6)根据进度滞后原因,调整项目劳务人员、材料、大型机械等资源配比。
进一步的,所述步骤1)中的进度计划包括各个施工任务,且施工任务之间的逻辑关系直观,特别有利于发现漏洞,抓住工程主要矛盾,优化工期,平衡资源,预防风险。
进一步的,所述步骤2)在BIM***中模拟施工全过程中的任意时间段的资源曲线、资金曲线、进度计划,根据曲线数据分析进度计划排定的合理性。
进一步的,所述步骤3)施工员在BIM手机端每日填报现场实际进度与劳动力数量,采集现场照片。项目领导层通过BIM手机端实时查看本周生产任务已完数量、延迟开始、延迟完成情况,及时发现施工生产过程中制约进度的因素,实时督导、落实,并采取对应解决措施。
进一步的,所述步骤4)中项目管理人员在手机端实时查看本周生产任务完成百分比及延期原因,找出共性问题,减少记录工作,高效进行进度优化或资源优化。
进一步的,所述步骤6)中为了充分保证关键线路、关键工作资源供应来调整资源配比,及时完成现场施工等相关工作,确保实现项目工期目标。
本发明解决了进度计划制定不合理、相应的资源计划调整不及时、项目管理人员进度管控意识不强的问题,实现了快速制定施工进度计划,通过5D模拟验证其合理性、可行性,并快速进行进度优化与调整的目的,本发明具有如下的有益效果:
1、快速制定施工进度计划,在BIM***中通过5D模拟验证其合理性、可行性,并快速进行进度优化与调整,较传统进度计划编制与优化流程,节约时间4.5天左右。
2、实现了在周进度计划维度进行施工进度精细化管控与资源配比调整,缩小了管理尺度,快速掌握进度滞后情况,利于项目领导层决策,保障工期目标顺利完成。
3、将施工生产任务派分至具体责任人,极大地增强了项目管理人员的责任意识,实时反馈现场进度情况,提高管理工作效率。
综上所述,采用本发明的项目进度管理方法,解决了进度计划制定不合理、相应的资源计划调整不及时、项目管理人员进度管控意识不强的问题,实现了快速制定施工进度计划,通过5D模拟验证其合理性、可行性,并快速进行进度优化与调整的目的。
具体实施方式
为了更好地理解本发明,下面结合具体实施实例,对发明作进一步详细说明,但本发明的实施方式不仅限于此,本发明的保护范围也涉及本领域技术人员根据本发明构思所能够想到的等同技术手段。
一种快速进行项目成本分析的方法,包括以下步骤:
1)应用BIM软件编制项目进度计划,直观查看关键路径和自由时差;
2)将进度计划与合同清单导入BIM***,与信息模型关联,进行5D施工模拟;
3)结合施工总进度计划与月度计划,在BIM网页端排布周进度计划,并推送至项目现场管理人员手机端;
4)项目部每周应用BIM***生成施工数字周报;
5)项目部每月月末应用BIM***前锋线动态管控功能,进行实际进度与计划进度对比分析;
6)根据进度滞后原因,调整项目劳务人员、材料、大型机械等资源配比。
优选的,所述步骤1)中的进度计划的成本科目包含项目主要材料、机械设备、劳务分包、专业分包、管理费等基础数据,后续的施工图预算、责任预算和实际成本均按照该成本科目计算。
优选的,所述步骤1)中的进度计划包括各个施工任务,且施工任务之间的逻辑关系直观,特别有利于发现漏洞,抓住工程主要矛盾,优化工期,平衡资源,预防风险。
优选的,所述步骤2)在BIM***中模拟施工全过程中的任意时间段的资源曲线、资金曲线、进度计划,根据曲线数据分析进度计划排定的合理性。
优选的,所述步骤3)施工员在BIM手机端每日填报现场实际进度与劳动力数量,采集现场照片。项目领导层通过BIM手机端实时查看本周生产任务已完数量、延迟开始、延迟完成情况,及时发现施工生产过程中制约进度的因素,实时督导、落实,并采取对应解决措施。
优选的,所述步骤4)中项目管理人员在手机端实时查看本周生产任务完成百分比及延期原因,找出共性问题,减少记录工作,高效进行进度优化或资源优化。
优选的,所述步骤6)中为了充分保证关键线路、关键工作资源供应来调整资源配比,及时完成现场施工等相关工作,确保实现项目工期目标。
本项目成本分析方法的一种具体实施例情况如:应用BIM软件编制项目进度计划,直观查看关键路径和自由时差。将进度计划与合同清单导入BIM***,与模型关联,进行5D施工模拟,根据资金、资源曲线数据分析进度计划排定的合理性。将总进度计划和月进度计划逐层分解至周进度计划,通过BIM网页端推送至各楼栋施工员手机端,施工员在BIM手机端每日填报现场实际进度与劳动力数量,采集现场照片。项目领导层通过BIM手机端实时查看本周生产任务已完数量、延迟开始、延迟完成情况。项目管理人员每周五应用BIM***自动生成的数字周报,在BIM生产周例会上,分析进度差异原因,安排下周工作。每月末应用前锋线动态管控功能进行实际进度与计划进度对比分析,深入剖析进度滞后的原因,并制定整改措施。根据进度滞后原因,调整项目劳务人员、材料、大型机械的配比,充分保证关键线路、关键工作资源供应,及时完成现场施工等相关工作,确保实现项目工期目标。
需要说明的是,在本文中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
本文中对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处,综上所述,本说明书内容不应理解为对本发明的限制。

Claims (6)

1.一种施工进度信息化管理的方法,其特征在于,所述分析方法包括以下步骤:
1)应用BIM软件编制项目进度计划,直观查看关键路径和自由时差;
2)将进度计划与合同清单导入BIM***,与信息模型关联,进行5D施工模拟;
3)结合施工总进度计划与月度计划,在BIM网页端排布周进度计划,并推送至项目现场管理人员手机端;
4)项目部每周应用BIM***生成施工数字周报;
5)项目部每月月末应用BIM***前锋线动态管控功能,进行实际进度与计划进度对比分析;
6)根据进度滞后原因,调整项目劳务人员、材料、大型机械等资源配比。
2.根据权利要求1所述的一种施工进度信息化管理的方法,其特征在于,所述步骤1)中的进度计划包括各个施工任务,且施工任务之间的逻辑关系直观,特别有利于发现漏洞,抓住工程主要矛盾,优化工期,平衡资源,预防风险。
3.根据权利要求1所述的一种施工进度信息化管理的方法,其特征在于,所述步骤2)在BIM***中模拟施工全过程中的任意时间段的资源曲线、资金曲线、进度计划,根据曲线数据分析进度计划排定的合理性。
4.根据权利要求1所述的一种施工进度信息化管理的方法,其特征在于,所述步骤3)施工员在BIM手机端每日填报现场实际进度与劳动力数量,采集现场照片,项目领导层通过BIM手机端实时查看本周生产任务已完数量、延迟开始、延迟完成情况,及时发现施工生产过程中制约进度的因素,实时督导、落实,并采取对应解决措施。
5.根据权利要求1所述的一种施工进度信息化管理的方法,其特征在于,所述步骤4)中项目管理人员在手机端实时查看本周生产任务完成百分比及延期原因,找出共性问题,减少记录工作,高效进行进度优化或资源优化。
6.根据权利要求1所述的一种施工进度信息化管理的方法,其特征在于,所述步骤6)中为了充分保证关键线路、关键工作资源供应来调整资源配比,及时完成现场施工等相关工作,确保实现项目工期目标。
CN202010185340.1A 2020-03-17 2020-03-17 一种施工进度信息化管理的方法 Pending CN111340458A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010185340.1A CN111340458A (zh) 2020-03-17 2020-03-17 一种施工进度信息化管理的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010185340.1A CN111340458A (zh) 2020-03-17 2020-03-17 一种施工进度信息化管理的方法

Publications (1)

Publication Number Publication Date
CN111340458A true CN111340458A (zh) 2020-06-26

Family

ID=71182382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010185340.1A Pending CN111340458A (zh) 2020-03-17 2020-03-17 一种施工进度信息化管理的方法

Country Status (1)

Country Link
CN (1) CN111340458A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111967838A (zh) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 一种基于bim的智能4d计划管控方法
CN112307548A (zh) * 2020-11-02 2021-02-02 中国电建集团华东勘测设计研究院有限公司 基于bim的轨道交通施工可视化进度管理方法及***
CN112381522A (zh) * 2020-11-24 2021-02-19 正太集团有限公司 一种基于bim的场地布置动态管控方法以及***
CN112465390A (zh) * 2020-12-10 2021-03-09 中铁一局集团第二工程有限公司 一种基于bim的地铁车站施工进度管理方法
CN112541749A (zh) * 2020-12-29 2021-03-23 大成数据科技(河南)有限公司 基于bim技术的施工进度管理***
CN112711788A (zh) * 2020-12-30 2021-04-27 中交千方信息科技(苏州)有限公司 一种基于bim技术的桥梁架设过程动态预测与控制方法
CN112766720A (zh) * 2021-01-19 2021-05-07 广东淡水河谷艺术工程有限公司 一种主体类娱乐项目艺术工程的管控***
CN113450086A (zh) * 2021-08-10 2021-09-28 中国华能集团清洁能源技术研究院有限公司 一种基于关键路径的海上风机吊装进度管理方法及***
CN113570339A (zh) * 2021-07-30 2021-10-29 中国电建集团成都勘测设计研究院有限公司 基于信息***的全方位进度管理方法
CN113780730A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度管控方法
CN113780729A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度预警方法
CN117010841A (zh) * 2023-08-31 2023-11-07 广东中联建建筑工程有限公司 施工进度计划与bim模型集成控制关键线路方法

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106022587A (zh) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 一种基于挣值原理的bim项目进度及成本管理***
CN107818198A (zh) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 一种基于bim技术的桥梁工程管理平台
CN108932383A (zh) * 2018-07-04 2018-12-04 成都希盟科技有限公司 基于bim技术的工程施工组织方案综合辅助决策方法
CN109377066A (zh) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 一种基于三维模型的现场进度监控***及方法
CN109447481A (zh) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 一种基于三维模型的现场成本监控***及方法
CN109710990A (zh) * 2018-12-05 2019-05-03 三峡大学 基于bim技术的碾压混凝土坝施工进度-成本协同控制方法
CN110084526A (zh) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 一种基于bim+wbs的可视化项目管理监控***
CN110750827A (zh) * 2019-10-10 2020-02-04 贵州百胜工程建设咨询有限公司 一种基于bim的进度管理方法
CN110866738A (zh) * 2019-11-20 2020-03-06 上海宝冶集团有限公司 一种基于bim技术的施工现场进度分析方法及其***

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106022587A (zh) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 一种基于挣值原理的bim项目进度及成本管理***
CN107818198A (zh) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 一种基于bim技术的桥梁工程管理平台
CN108932383A (zh) * 2018-07-04 2018-12-04 成都希盟科技有限公司 基于bim技术的工程施工组织方案综合辅助决策方法
CN109377066A (zh) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 一种基于三维模型的现场进度监控***及方法
CN109447481A (zh) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 一种基于三维模型的现场成本监控***及方法
CN109710990A (zh) * 2018-12-05 2019-05-03 三峡大学 基于bim技术的碾压混凝土坝施工进度-成本协同控制方法
CN110084526A (zh) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 一种基于bim+wbs的可视化项目管理监控***
CN110750827A (zh) * 2019-10-10 2020-02-04 贵州百胜工程建设咨询有限公司 一种基于bim的进度管理方法
CN110866738A (zh) * 2019-11-20 2020-03-06 上海宝冶集团有限公司 一种基于bim技术的施工现场进度分析方法及其***

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
荀杨: "BIM 技术在工程项目进度管理中的应用研究", 《硕士电子期刊》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111967838A (zh) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 一种基于bim的智能4d计划管控方法
CN112307548A (zh) * 2020-11-02 2021-02-02 中国电建集团华东勘测设计研究院有限公司 基于bim的轨道交通施工可视化进度管理方法及***
CN112381522A (zh) * 2020-11-24 2021-02-19 正太集团有限公司 一种基于bim的场地布置动态管控方法以及***
CN112465390A (zh) * 2020-12-10 2021-03-09 中铁一局集团第二工程有限公司 一种基于bim的地铁车站施工进度管理方法
CN112541749A (zh) * 2020-12-29 2021-03-23 大成数据科技(河南)有限公司 基于bim技术的施工进度管理***
CN112711788B (zh) * 2020-12-30 2024-05-31 中交简石数字科技(苏州)有限公司 一种基于bim技术的桥梁架设过程动态预测与控制方法
CN112711788A (zh) * 2020-12-30 2021-04-27 中交千方信息科技(苏州)有限公司 一种基于bim技术的桥梁架设过程动态预测与控制方法
CN112766720A (zh) * 2021-01-19 2021-05-07 广东淡水河谷艺术工程有限公司 一种主体类娱乐项目艺术工程的管控***
CN113570339A (zh) * 2021-07-30 2021-10-29 中国电建集团成都勘测设计研究院有限公司 基于信息***的全方位进度管理方法
CN113570339B (zh) * 2021-07-30 2023-05-09 中国电建集团成都勘测设计研究院有限公司 基于信息***的全方位进度管理方法
CN113780730A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度管控方法
CN113780729A (zh) * 2021-08-04 2021-12-10 中国二十冶集团有限公司 一种基于工程管控平台的进度预警方法
CN113450086A (zh) * 2021-08-10 2021-09-28 中国华能集团清洁能源技术研究院有限公司 一种基于关键路径的海上风机吊装进度管理方法及***
CN117010841A (zh) * 2023-08-31 2023-11-07 广东中联建建筑工程有限公司 施工进度计划与bim模型集成控制关键线路方法

Similar Documents

Publication Publication Date Title
CN111340458A (zh) 一种施工进度信息化管理的方法
Shrivastava et al. A systematic review on extreme programming
Aziz et al. Applying lean thinking in construction and performance improvement
US8799210B2 (en) Framework for supporting transition of one or more applications of an organization
CN102073927A (zh) 基于协同办公的项目型工作计划管理***
laili Jabar et al. Construction manager's competency in managing the construction process of IBS projects
Lee et al. Building information modeling for quality management in infrastructure construction projects
Yang How the critical chain scheduling method is working for construction
Lapidus et al. Construction project organizational and technological parameters analysis
Ratajczak et al. Mobile application for collaborative scheduling and monitoring of construction works according to lean construction methods
Locatelli et al. Controlling the delivering of projects in mega-events: An application on EXPO 2015
Javed et al. A system dynamics framework of drivers and constraints to enhancing productivity of the Hong Kong construction industry
AU2009233598B2 (en) System and method for managing implementations
Desai et al. Value stream mapping as a lean construction tool–a case study
Marengo et al. Process management in construction: expansion of the Bolzano hospital
Dalibi et al. The Fundamentals of Earned Value Management in Construction Projects: Applications and Simulations
Uy et al. Migrating from SharePoint to a better scrum tool
CN116070877B (zh) 一种驾驶舱的智慧建造方法和***
Rofdzi et al. Key Elements Towards Automation and Robotics in Industrialised Building System (IBS)
Lee Dynamic quality and change management for large scale concurrent design and construction projects
Evbuomwan A Tale of Two Utility Companies-Towards an Enterprise Asset Management (EAM) Transformation Assessment
Tezel et al. BIM based design management of a building project collaboratively designed with a foreign design firm in China: a case study
Herbst The role of the project engineer in work package based engineering design projects
Shin et al. Critical success factors for nuclear power plant construction projects
Lindblad Project and Service Management methodologies in IT environments

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200626

RJ01 Rejection of invention patent application after publication