CN111270612A - Auxiliary via-hole method for front end of long-span T-beam bridge girder erection machine over-span truck crane - Google Patents

Auxiliary via-hole method for front end of long-span T-beam bridge girder erection machine over-span truck crane Download PDF

Info

Publication number
CN111270612A
CN111270612A CN202010091819.9A CN202010091819A CN111270612A CN 111270612 A CN111270612 A CN 111270612A CN 202010091819 A CN202010091819 A CN 202010091819A CN 111270612 A CN111270612 A CN 111270612A
Authority
CN
China
Prior art keywords
erection machine
bridge
girder erection
bridge girder
span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010091819.9A
Other languages
Chinese (zh)
Other versions
CN111270612B (en
Inventor
付祥能
王万华
陈勇
冯果
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Construction Bridge Engineering Co ltd
CHONGQING URBAN CONSTRUCTION HOLDING (GROUP) CO LTD
Chongqing Construction Engineering Group Co Ltd
Original Assignee
Chongqing Construction Bridge Engineering Co ltd
CHONGQING URBAN CONSTRUCTION HOLDING (GROUP) CO LTD
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Construction Bridge Engineering Co ltd, CHONGQING URBAN CONSTRUCTION HOLDING (GROUP) CO LTD, Chongqing Construction Engineering Group Co Ltd filed Critical Chongqing Construction Bridge Engineering Co ltd
Priority to CN202010091819.9A priority Critical patent/CN111270612B/en
Publication of CN111270612A publication Critical patent/CN111270612A/en
Application granted granted Critical
Publication of CN111270612B publication Critical patent/CN111270612B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses an auxiliary via-passing method for the front end of a long-span T-beam bridge crane across-span truck crane, which comprises the following steps: s1: moving the bridge girder erection machine to a fulcrum; s2: the bridge girder erection machine is in a balanced state; s3: arranging a crane on the axle of the tail end bridge of the main girder of the main bridge; s4: starting a lifting rope of the automobile crane until the lifting force reaches the lifting force required by a main truss of the bridge girder erection machine; s5: checking the elevation change condition of the lifting end of the bridge girder erection machine and the self condition of the automobile crane; s6: after the bridge girder erection machine moves forwards to the designed position, the front support rod and the track beam are placed on the main girder of the main bridge and are reliably fixed. The invention has the beneficial effects that the auxiliary hole passing method which is simple and easy to operate is provided, the safety degree of construction is improved, the construction period is shortened, and higher economic benefit is achieved.

Description

Auxiliary via-hole method for front end of long-span T-beam bridge girder erection machine over-span truck crane
Technical Field
The invention relates to the field of bridging, in particular to a method for assisting in passing through a front end of a cross-span truck crane by a large-span T-beam bridge girder erection machine.
Background
The span of the large-span T beam is large, the weight of the single-piece beam is heavy, the length of a cantilever extending out of the wing plate is large, the load of the conventional construction method is large and far exceeds the bearing capacity of the wing plate, so that a bridge girder erection machine needs to be used for passing holes during construction, but the conventional hole passing method still causes the problems.
Disclosure of Invention
In view of the above, in order to overcome the above problems, the invention provides an auxiliary via-hole method for a front end of a large-span T bridge girder erection machine across-span truck crane.
The purpose of the invention is realized by the following technical scheme:
the auxiliary via-passing method for the front end of the long-span T-beam bridge girder erection machine across-span truck crane comprises the following steps:
s1: adjusting the position of a fulcrum on the beam body with the last span completed, and moving the bridge girder erection machine to the fulcrum;
s2: arranging two overhead cranes and a beam transporting vehicle on the bridge girder erection machine to specified positions, lifting a beam by using the overhead crane, moving the bridge girder erection machine to a position close to 50-3 meters of the standard span in the direction close to the standard span, and stopping the bridge girder erection machine, wherein the bridge girder erection machine is in a balanced state;
s3: arranging an automobile crane on the axle of the tail end bridge of the main beam of the main bridge, determining the position of the automobile crane and the angle of a suspension arm according to the strength of the hoisting load, so that the automobile crane can meet the requirement of the hoisting load, and selecting the diameter of a hoisting rope and the factor of safety factor according to the use angle of the hoisting rope;
s4: connecting and tightening a lifting rope of the automobile crane and a lifting rope with one end of the bridge girder erection machine close to the standard span, and then starting the lifting rope of the automobile crane until the lifting force reaches the lifting force required by a main truss girder of the bridge girder erection machine;
s5: checking the elevation change condition of the lifting end of the bridge girder erection machine and the self condition of the automobile crane, and continuously moving the bridge girder erection machine to the design position in the direction of the standard span under the assistance of the automobile crane after no problem exists;
s6: after the bridge girder erection machine moves forwards to the designed position, the front support rod and the track beam are placed on the main girder of the main bridge and are reliably fixed, and the lifting rope of the truck crane is removed after no problem exists, and the truck crane exits.
Further, before the construction of the via holes of the bridge girder erection machine, the bridge girder erection machine needs to be subjected to a load test so as to ensure the safety of the operation of the hanging beam of the bridge girder erection machine.
Further, the movement process of the bridge erecting machine in the step S5 should be performed slowly, and care should be taken to control the mutual matching of the bridge erecting machine and the car crane.
The invention has the beneficial effects that:
the invention has the beneficial effects that the auxiliary hole passing method which is simple and easy to operate is provided, the safety degree of construction is improved, the construction period is shortened, and higher economic benefit is achieved.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention. The objectives and other advantages of the invention may be realized and attained by the means of the instrumentalities and/or embodiments described below.
Detailed Description
The following is a detailed description of preferred embodiments of the invention. It should be understood that the preferred embodiments are illustrative of the invention only and are not limiting upon the scope of the invention.
The embodiment provides an auxiliary via hole method for a front end of a large-span T-beam bridge girder erection machine across-span truck crane, which is used for solving the practical problem of engineering, and the general outline of the engineering is as follows: the approach bridge is a 9-span simply-supported prefabricated T-shaped beam, the span of 1 st span to 7 th span is 50.0m, the width of a single beam is 1.8 m, the height of the single beam is 2.7 m, and the maximum beam weight of the single beam is 174.4 tons; the 8 th span is 47.5m, the width of the single beam is 1.8 m, the height of the single beam is 2.7 m, and the maximum beam weight of the single beam is 167.4 tons; the span of the 9 th span is 52.5m, the width of the single beam is 1.8 m, the height of the single beam is 2.9 m, and the maximum beam of the single beam weighs 188.8 tons.
The plane arrangement of each simply supported T beam of the approach bridge is as follows: the 1 st span to the 3 rd span and the 7 th span to the 9 th span adopt a sector arrangement mode so as to adapt to the connection requirements of the upper ramp and the lower ramp. The spans 4-6 are all arranged in parallel.
The number of the arranged pieces of each simply supported T beam of the approach bridge is as follows: the 1 st span to the 2 nd span is 11 pieces, the 3 rd span is 12 pieces, the 4 th span to the 6 th span is 9 pieces, the 7 th span is 13 pieces, the 8 th span to the 9 th span is 12 pieces, and the bridge approach 9 spans 98 pieces in total for simply supporting the prefabricated installation T beam.
The difficulty of the project is that: the 9 th span of the approach bridge is the final 1-span T-shaped beam bridge section at the tail end of the approach bridge, the design span is 52.5m, and 12T beams are erected and installed. The maximum span of the bridge approach T-beam installation is 188.8 tons at the maximum. The front end of the cross T-beam is connected with a pier No. P8 of the main bridge and placed on the capping beam, the highest height of a pier No. P8 is about 60 meters, and the rear end of the cross T-beam is connected with a pier No. P7 of the approach bridge and placed on the capping beam.
When the cross T-shaped beam is erected, the front fulcrum of the bridge girder erection machine is placed on the main beam of the main bridge, and the middle fulcrum of the rear end is placed on the front end of the T-shaped beam finished by the pier P7. The distance from the front fulcrum of the bridge girder erection machine to the center of the middle fulcrum is 55.4 meters.
The height of the tail beam section of the main bridge is 4.5 meters, the width of the bridge deck is 25 meters, the width of the beam bottom is 16 meters, and the thickness of the wing plate cantilever at two sides is 4.5 meters respectively although the thickness of the thickened section of the wing plate reaches 1 meter. However, the length of the cantilever extending out of the wing plate is too large to reach 4.5 meters, and when the load erected by the beam body acts on the wing plate, the bearing capacity of the beam body needs to be considered.
The pier capping beam of the approach bridge P7 is a middle pivot point when a beam body is erected, and the load of the pier capping beam is large, so the bearing capacity of the pier capping beam needs to be considered.
The ANSYS software is used for carrying out stress analysis and calculation (calculation result is omitted) on the tail beam wing section, the track beam, the tail beam section wing plate, the cover beam and the beam body of the main bridge under each working condition of the approach bridge, and then the following scheme is provided for the 9 th span through hole:
in this embodiment, "front" is the direction toward the hole, and "rear" is the direction away from the hole.
The auxiliary via-passing method for the front end of the long-span T-beam bridge girder erection machine across-span truck crane comprises the following steps:
s1: the position of a fulcrum is adjusted on the 8 th span finished beam body, and the bridge girder erection machine moves to the fulcrum, wherein the implementation mode in the embodiment is that the bridge girder erection machine is moved forward by about 27 meters and stopped;
s2: arranging two overhead cranes and a beam transporting vehicle on the bridge girder erection machine to specified positions, lifting a beam by using the overhead cranes, moving the bridge girder erection machine forwards to a position which is close to a standard span of 50-3 meters, and stopping the bridge girder erection machine, wherein the bridge girder erection machine is in a balanced state;
through calculation and analysis, the front ends of the left and right main trusses of the bridge girder erection machine respectively need 25 tons of lifting force in a proper state, and the internal force of the main trusses of the bridge girder erection machine meets the requirement. The lifting force required by the front end of the whole bridge crane is 50 tons (vertical force).
S3: according to the calculation and analysis result (namely the stress analysis of ANSYS), arranging an automobile crane with the rated hoisting capacity of 200 tons on the axle line of the main bridge tail end bridge, determining the position of the automobile crane and the angle of a suspension arm according to the hoisting load force, so that the automobile crane can meet the requirement of hoisting load, and simultaneously selecting the diameter of the lifting rope and the factor of safety coefficient according to the use angle of the lifting rope;
s4: connecting and tightening a lifting rope and a lifting rope of the automobile crane with the front end of the bridge girder erection machine, and then starting the lifting rope of the automobile crane until the lifting force reaches the lifting force (50 tons) required by a main truss girder of the bridge girder erection machine;
s5: checking the elevation change condition of the lifting end of the bridge girder erection machine and the self condition of the automobile crane, after no problem exists, continuously moving the bridge girder erection machine to the designed position in the direction of the standard span under the assistance of the automobile crane, wherein the moving process of the bridge girder erection machine is slowly carried out, and the mutual matching of the bridge girder erection machine and the automobile crane is controlled to be proper;
s6: after the bridge girder erection machine moves forwards to the designed position, the front support rod and the track beam are placed on the main girder of the main bridge and are reliably fixed, and the lifting rope of the truck crane is removed after no problem exists, and the truck crane exits.
Before the hole is drilled, related preparation works such as technical safety traffic, personnel arrangement, material equipment, automobile cranes, sling rope clamps and the like are selected. After the via hole is finished, a careful and complete check is made to determine whether the stable conditions of the supporting points and the structure meet the requirements
Before the construction of the via holes of the bridge girder erection machine, the bridge girder erection machine needs to be subjected to a load test so as to ensure the safety of the operation of the hanging beam of the bridge girder erection machine.
The load test specifically comprises the following steps:
1. after the 8 th span beam body is installed and the transverse connection is finished, the bridge girder erection machine can be transversely moved to the middle of the bridge floor and then is fixed in place,
2. the middle pivot point is moved to a designated position at the rear end, the distance between the front pivot point and the middle pivot point is the same as the installation span of the 9 th span, and the installation span of the 9 th span is 55.40 meters.
3. The stable condition of each pivot is checked, and one-step operation can be carried out after the observation points (the cross-center and front pivots) are set to meet the requirements.
4. And (4) placing the two-day vehicle at a proper beam hanging position, placing the rear supporting point in place and supporting the rear supporting point on the bridge floor, and placing the beam carrying vehicle in place.
5. And (3) taking the 9 th span beam body as a carrier, placing the second-day vehicle lifting beam between the two main girders of the bridge girder erection machine, stopping the vehicle lifting beam when the front overhead vehicle reaches the span of the bridge girder erection machine, checking the two main girders and the front fulcrum of the bridge girder erection machine, and observing the deformation condition. After no problem, one-step operation can be carried out.
6. And stopping when the vehicle continues to move forwards to the installation position for two days, lowering the beam body about 15 cm away from the bridge floor, and preparing the auxiliary support super pier in place for later use. Then, the two main truss diagonal rods (hanging points) and the front pivot of the bridge crane are inspected, and the deformation condition is observed. And after no problem exists, the next operation can be carried out.
7. When the belt beam of the two-day vehicle moves to the maximum point, the vehicle stops, the two main girders of the bridge crane have unbalance loading, inspection and observation are needed, and the deformation condition is observed by inspecting the inclined rod (the hanging point) and the front pivot. And after no problem exists, the next operation can be carried out.
8. And returning the experimental hanging beam according to a reverse method, placing the experimental hanging beam on a beam transporting vehicle for fixing, and finishing the experiment.
9. After the test is finished, the test is carefully and comprehensively checked again, and the test condition and related data are filed and recorded.
Finally, the above embodiments are only intended to illustrate the technical solutions of the present invention and not to limit the present invention, and although the present invention has been described in detail with reference to the preferred embodiments, it will be understood by those skilled in the art that modifications or equivalent substitutions may be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions, and all of them should be covered by the claims of the present invention.

Claims (3)

1. The method for assisting in passing through the front end of the cross-span truck crane of the large-span T-beam bridge girder erection machine is characterized by comprising the following steps of: the via hole method specifically comprises the following steps:
s1: adjusting the position of a fulcrum on the beam body with the last span completed, and moving the bridge girder erection machine to the fulcrum;
s2: arranging two overhead cranes and a beam transporting vehicle on the bridge girder erection machine to specified positions, lifting a beam by using the overhead crane, moving the bridge girder erection machine to a position close to 50-3 meters of the standard span in the direction close to the standard span, and stopping the bridge girder erection machine, wherein the bridge girder erection machine is in a balanced state;
s3: arranging an automobile crane on the axle of the tail end bridge of the main beam of the main bridge, determining the position of the automobile crane and the angle of a suspension arm according to the strength of the hoisting load, so that the automobile crane can meet the requirement of the hoisting load, and selecting the diameter of a hoisting rope and the factor of safety factor according to the use angle of the hoisting rope;
s4: connecting and tightening a lifting rope of the automobile crane and a lifting rope with one end of the bridge girder erection machine close to the standard span, and then starting the lifting rope of the automobile crane until the lifting force reaches the lifting force required by a main truss girder of the bridge girder erection machine;
s5: checking the elevation change condition of the lifting end of the bridge girder erection machine and the self condition of the automobile crane, and continuously moving the bridge girder erection machine to the designed position in the hole direction with the assistance of the automobile crane after no problem exists;
s6: after the bridge girder erection machine moves forwards to the designed position, the front support rod and the track beam are placed on the main girder of the main bridge and are reliably fixed, and the lifting rope of the truck crane is removed after no problem exists, and the truck crane exits.
2. The via method of claim 1, wherein: before the construction of the via holes of the bridge girder erection machine, the bridge girder erection machine needs to be subjected to a load test so as to ensure the safety of the operation of the hanging beam of the bridge girder erection machine.
3. The via method of claim 1, wherein: the movement process of the bridge erecting machine in the step S5 is carried out slowly, and the mutual matching of the bridge erecting machine and the automobile crane is controlled properly.
CN202010091819.9A 2020-02-14 2020-02-14 Auxiliary front-end hole passing method for large-span T-shaped beam bridge erecting machine over-span automobile crane Expired - Fee Related CN111270612B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010091819.9A CN111270612B (en) 2020-02-14 2020-02-14 Auxiliary front-end hole passing method for large-span T-shaped beam bridge erecting machine over-span automobile crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010091819.9A CN111270612B (en) 2020-02-14 2020-02-14 Auxiliary front-end hole passing method for large-span T-shaped beam bridge erecting machine over-span automobile crane

Publications (2)

Publication Number Publication Date
CN111270612A true CN111270612A (en) 2020-06-12
CN111270612B CN111270612B (en) 2021-08-17

Family

ID=70995134

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010091819.9A Expired - Fee Related CN111270612B (en) 2020-02-14 2020-02-14 Auxiliary front-end hole passing method for large-span T-shaped beam bridge erecting machine over-span automobile crane

Country Status (1)

Country Link
CN (1) CN111270612B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575263A (en) * 2022-04-01 2022-06-03 永富建工集团有限公司 Bridge crane hole passing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3542050A1 (en) * 1985-11-28 1987-06-04 Horst Surbeck Scaffolding for manufacturing superstructures
DE10137797A1 (en) * 2001-08-06 2003-02-27 Heinz Von Doellen Lining device used in concreting a longitudinal profile having a uniform or periodically changing cross-section on an existing longitudinal construction is suspended on a vertical holding element on the existing longitudinal construction
CN102704407A (en) * 2012-07-03 2012-10-03 中铁一局集团有限公司 Construction method of lower guide beam type bridge-erecting crane passing through tunnel
CN102797226A (en) * 2012-07-26 2012-11-28 中铁六局集团有限公司 Integral erection construction method of 60m steel box girder
CN105155428A (en) * 2015-10-26 2015-12-16 杭州江润科技有限公司 Operating-railway-crossing construction method for large assembly-type prestress concrete continuous T beam
CN105648916A (en) * 2016-01-04 2016-06-08 秦皇岛天业通联重工科技有限公司 Bridge girder erection machine and erection method of bridge girder erection machine
CN106968160A (en) * 2017-04-12 2017-07-21 中交第二公路勘察设计研究院有限公司 The short side that a kind of steel truss girder is mixed with beams of concrete is across Cable-Stayed Bridge Structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3542050A1 (en) * 1985-11-28 1987-06-04 Horst Surbeck Scaffolding for manufacturing superstructures
DE10137797A1 (en) * 2001-08-06 2003-02-27 Heinz Von Doellen Lining device used in concreting a longitudinal profile having a uniform or periodically changing cross-section on an existing longitudinal construction is suspended on a vertical holding element on the existing longitudinal construction
CN102704407A (en) * 2012-07-03 2012-10-03 中铁一局集团有限公司 Construction method of lower guide beam type bridge-erecting crane passing through tunnel
CN102797226A (en) * 2012-07-26 2012-11-28 中铁六局集团有限公司 Integral erection construction method of 60m steel box girder
CN105155428A (en) * 2015-10-26 2015-12-16 杭州江润科技有限公司 Operating-railway-crossing construction method for large assembly-type prestress concrete continuous T beam
CN105648916A (en) * 2016-01-04 2016-06-08 秦皇岛天业通联重工科技有限公司 Bridge girder erection machine and erection method of bridge girder erection machine
CN106968160A (en) * 2017-04-12 2017-07-21 中交第二公路勘察设计研究院有限公司 The short side that a kind of steel truss girder is mixed with beams of concrete is across Cable-Stayed Bridge Structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575263A (en) * 2022-04-01 2022-06-03 永富建工集团有限公司 Bridge crane hole passing method
CN114575263B (en) * 2022-04-01 2024-03-15 永富建工集团有限公司 Bridge machine via hole method

Also Published As

Publication number Publication date
CN111270612B (en) 2021-08-17

Similar Documents

Publication Publication Date Title
CN106930541B (en) Construction method of hanging type steel corridor
CN107012949A (en) Lifting method of large-span steel corridor
CN109763569B (en) Construction method of cantilever awning
CN102797226A (en) Integral erection construction method of 60m steel box girder
CN101736700A (en) Construction method for hoisting broad width steel box girder cantilever
CN111139749A (en) Large-span bearing type continuous steel truss girder cantilever erection construction method
CN111139743A (en) Method for improving speed of highway beam frame and installation method of gantry crane
JP2021031884A (en) Bridge upper structure removal method
CN111270612B (en) Auxiliary front-end hole passing method for large-span T-shaped beam bridge erecting machine over-span automobile crane
CN114215170A (en) Method for lifting super-altitude giant hanging multi-layer connected structure
CN117328367A (en) Integral hoisting construction method for super-large overweight steel box girder floating crane of cross-sea bridge
US5940916A (en) Bridge span-by-span construction apparatus and method
CN111779274A (en) Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack
WO2022233226A1 (en) Three-span cable crane for installation of cable-stayed bridge main girder and construction method therefor
Rosignoli Self-launching erection machines for precast concrete bridges.
CN113833126A (en) Roof installation method
WO2024148717A1 (en) Swing method for dual-deck curved girder bridge
CN112429651B (en) Installation construction process for 1000-ton lifting frame equipment
CN213121143U (en) Bridge girder erection machine load test system
CN111535146B (en) Method for installing steel truss girder of suspension bridge
CN115897416A (en) Method for erecting continuous steel truss girder bridge
CN112627355B (en) Petal-shaped large-span roof truss assembling method
CN218932916U (en) Cable-stayed bridge front fulcrum hanging basket upper box type bearing main truss
CN112709146B (en) Construction method for erecting continuous steel truss girder
CN212836706U (en) Template supporting structure at floor discharge pit of warehouse prefabricated reinforced concrete integral casting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210817

Termination date: 20220214

CF01 Termination of patent right due to non-payment of annual fee