CN111185456A - Stabilization landfill method for fly ash chelate - Google Patents

Stabilization landfill method for fly ash chelate Download PDF

Info

Publication number
CN111185456A
CN111185456A CN202010083534.0A CN202010083534A CN111185456A CN 111185456 A CN111185456 A CN 111185456A CN 202010083534 A CN202010083534 A CN 202010083534A CN 111185456 A CN111185456 A CN 111185456A
Authority
CN
China
Prior art keywords
landfill
fly ash
area
road
covering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010083534.0A
Other languages
Chinese (zh)
Inventor
蒋舒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Taimeirui Environmental Protection Technology Co Ltd
Original Assignee
Shenzhen Taimeirui Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Taimeirui Environmental Protection Technology Co Ltd filed Critical Shenzhen Taimeirui Environmental Protection Technology Co Ltd
Priority to CN202010083534.0A priority Critical patent/CN111185456A/en
Publication of CN111185456A publication Critical patent/CN111185456A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B1/00Dumping solid waste
    • B09B1/004Covering of dumping sites
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B2101/00Type of solid waste
    • B09B2101/30Incineration ashes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/30Landfill technologies aiming to mitigate methane emissions

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses a fly ash chelate stabilization landfill method, which comprises the following steps: step one, arranging a bank in a landfill reservoir area to divide the bank into a plurality of operation areas and operation units; step two, paving a temporary approach road and an operation platform, planning a route of the temporary approach road according to the position of an operation area, and then paving the temporary approach road and hoisting the platform; and step three, landfill and covering are carried out on the bagged fly ash, a crane is adopted to hoist the bagged fly ash, an excavator is used for paving and compacting the bagged fly ash to be buried to an operation area, and a covering mode combining daily coverage and middle coverage is adopted on the bagged fly ash which is buried, wherein the middle coverage refers to a landfill operation area which is completed in stages. The method is a landfill method for stabilized fly ash, which can not only ensure the stability of a fly ash pile body, but also make 100% use of a fly ash landfill area.

Description

Stabilization landfill method for fly ash chelate
Technical Field
The invention relates to a stabilization landfill method for a fly ash chelate, and particularly relates to the technical field of garbage treatment.
Background
With the improvement of physical life, the daily yield of domestic garbage in a common city can reach hundreds of tons, and the daily yield of domestic garbage in a large city can reach thousands of tons. Urban waste incineration is more and more common, domestic waste is recycled, waste incineration is used for power generation, and a large amount of fly ash is generated in the incineration process. The fly ash is chelated into fly ash chelates and finally buried in a fly ash landfill.
The existing fly ash treatment mode is landfill according to the traditional domestic garbage landfill operation mode. The method specifically comprises the following steps: the fly ash chelate is hoisted and unloaded to a landfill area bag by a crane, and if uneven places exist in the hoisting and unloading process, the fly ash chelate is filled with sand bags. A larger gap exists between the ash bags during operation, and although the plane is padded by the sand bags, the storage capacity utilization rate is lower.
Disclosure of Invention
The invention aims to provide a fly ash chelate stabilization landfill method to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a fly ash chelate stabilization landfill method comprises the following steps: step one, arranging a bank in a landfill reservoir area to divide the bank into a plurality of operation areas and operation units; the landfill reservoir area is divided by taking the operation area and the operation unit as a unit, so that drainage and diversion of rainwater in the reservoir area can be effectively controlled;
step two, paving a temporary approach road and an operation platform, planning a route of the temporary approach road according to the position of an operation area, and then paving the temporary approach road and hoisting the platform;
in the landfill stage, a temporary operation road is built on the surface of the pile body to meet the requirement of flying ash ton bag lifting pile, the operation road is connected with the approach road and the landfill operation unit and is continuously extended or heightened along with the landfill operation;
according to a landfill plan, at the initial stage of landfill, the rotary platform of an entrance road is filled with piles, a layer of ton bags are quickly paved, and then a steel plate road foundation box is erected to carry out landfill lifting towards the northeast direction;
the width of the temporary operation road needs to be ensured to be 6m, the temporary operation road is far away from the seepage-proof side slope and the platform thereof by more than 10 m, the edge of the temporary operation road needs to have enough safety distance from the fly ash filling edge, and the slope ratio of the outer side slope is not steeper than 1: 2, covering a soil layer with the thickness of 10-20cm on the filled area before covering with the geomembrane, and laying steel plates only by adopting a liner made of materials such as geotextile or canvas and the like above the geomembrane after covering with the geomembrane so as to avoid the damage of the geomembrane caused by the steel plates;
considering the load of crane and transport vehicle, steel plate road base box is used to construct temporary road and unload
A platform;
and step three, landfill and covering are carried out on the bagged fly ash, a crane is adopted to hoist the bagged fly ash, an excavator is used for paving and compacting the bagged fly ash to be buried to an operation area, and a covering mode combining daily coverage and middle coverage is adopted on the bagged fly ash which is buried, wherein the middle coverage refers to a landfill operation area which is completed in stages.
Preferably, the size of the steel plate roadbed box in the second step can be set to be 6m × 1.5m or 8m × 1.5 m.
Preferably, the filling work amount which can be satisfied by the work area is 3 to 12 times of the filling work amount which can be satisfied by the work unit.
Preferably, in the third step, the tonnage of the crane can be selected from 35t, 50t or 80t, 2 or 4 bags are hung in each time, and the maximum tonnage is not more than 6 bags.
Preferably, the stacking operation of each layer of fly ash in the third step is performed in the order from bottom to top. Preferably, the inclination of the slope of the daily landfill completion surface in the third step is not more than 1
(V): 5 (H), the slope of the front side slope consisting of compacted fly ash must not exceed 1 (V): 3 (H), the slope of the side slope is not more than 1 (V): 2 (H), the vertical working surface and the non-compacted working surface do not allow the fly ash to be lifted upwards, and all the inclined surfaces of the pile are maintained in a stable condition.
Preferably, the specific steps of the third step, the middle day coverage and the middle coverage are as follows: covering the fly ash stack body by adopting a 1.0mm HDPE film in an overlapping way, and completely covering the surface of a landfill area, wherein a 0.3mm impermeable film is adopted for daily covering of a daily operation area, a part of the covering film is uncovered for landfill operation during operation, and the film is covered immediately after the daily landfill is finished;
for the HDPE film adopted to cover the middle area, the HDPE film is laid along the slope and welded by a special welding machine, waste tires are matched with anti-aging sand bags to carry out ballasting after the welding is finished, and 8mm nylon ropes are adopted to connect and fix the tires so as to prevent the tires from being blown away by wind.
Compared with the prior art, the invention has the beneficial effects that: the method is a landfill method for stabilized fly ash, which can not only ensure the stability of a fly ash pile body, but also make 100% use of a fly ash landfill area.
Drawings
FIG. 1 is a schematic diagram illustrating a separation state of a landfill region 1 in step one according to the present invention;
FIG. 2 is a schematic structural diagram illustrating planning of a temporary approach road according to the location of a work area in step two according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of the filling and covering status of bagged fly ash in step three according to the embodiment of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
the invention provides a technical scheme that: a fly ash chelate stabilization landfill method comprises the following steps: the method comprises the following steps: a bank is arranged in the landfill reservoir area 1 and is divided into a plurality of operation areas and operation units; the landfill reservoir area 1 is divided by taking the operation area and the operation unit as a unit, so that drainage and diversion of rainwater in the reservoir area can be effectively controlled. Referring to fig. 1, the partition division has the function of dividing the landfill area 1 into a working area and an area to be worked, the unit division embankment has the function of subdividing the working area into a plurality of working units, and the landfill work amount which can be met by the working area is 3-12 times of that which can be met by the working units. For example, one work area can satisfy the requirement of 1-3 months of landfill operation amount, one work unit can satisfy the requirement of 3-7 days of landfill operation amount, the height of the partition bank 2 is set to be 1m-2m, and the height of the partition bank 3 is set to be 0.5m-1 m.
Step two, paving a temporary approach road and an operation platform: referring to fig. 2, a route of the temporary approach road 2 is planned according to the position of the working area, and then the temporary approach road and the hoisting platform are laid.
In the landfill stage, a temporary operation road is built on the surface of the pile body to meet the requirement of hoisting and stacking the fly ash ton bags. The operation road is connected with the approach road and the landfill operation unit and is continuously lengthened or heightened along with the landfill operation.
According to a landfill plan, at the initial stage of landfill, the rotary platform of the temporary working road starts to perform landfill, a layer of ton bags is quickly paved, and then a steel plate road foundation box is erected to perform landfill lifting towards the northeast direction.
The width of the temporary operation road needs to be ensured to be 6m, the temporary operation road is far away from the seepage-proof side slope and the platform thereof by more than 10 m, the edge of the temporary operation road needs to have enough safety distance from the fly ash filling edge, and the slope ratio of the outer side slope is not steeper than 1: 2 to ensure the stability of the stack.
Considering the load when the crane and the transport vehicle travel, a temporary road and a discharging platform are constructed by using steel plate roadbed boxes (the size of each steel plate roadbed box can be set to be 6m multiplied by 1.5m or 8m multiplied by 1.5 m).
In order to ensure the stability of the temporary road, in the filled area, a soil layer with the thickness of 10-20cm needs to be covered before the film covering is carried out, after the film covering is carried out, a steel plate can be laid only by adopting a liner made of materials such as geotextile or canvas and the like above the geomembrane, and the damage of the steel plate to the geomembrane is avoided.
The edge of the temporary road has enough safety distance from the fly ash filling edge, and the slope ratio of the outer side slope is not steeper than 1: 2 to ensure the stability of the stack.
Step three, landfill and covering are carried out on bagged fly ash: a crane is adopted to hoist the bagged fly ash, and the tonnage of the common crane can be 35t, 50t or 80 t. The effective operation radius of a 35t crane is about 15m, the effective operation radius of a 50t crane is about 25m, the effective operation radius of an 80t crane is about 40m, in order to fully consider the factors of hoisting safety, efficiency, cost and the like, 2 or 4 bags are hung in each time, and the maximum number is not more than 6 bags (1 t-1.4 t/bag); and then, paving and compacting the fly ash to a working area by using a digging machine, and covering the bagged fly ash which is filled in the working area by combining daily coverage and middle coverage. The intermediate coverage refers to a landfill area that is completed in stages. The daily coverage and the intermediate coverage steps are as follows: in order to reduce the generation amount of percolate in a fly ash landfill and prevent rainwater from directly entering a fly ash pile body, 1.0mm HDPE film is adopted to overlap and cover the fly ash pile body to completely cover the surface of a landfill area, wherein 0.3mm impermeable film is adopted to cover a daily operation area, part of the covering film is uncovered to perform landfill operation during operation, and the film is covered immediately after the daily landfill operation is completed. The stacking operation of each layer of fly ash is carried out from bottom to top, the operation area of each unit is 200 square meters, the height of the fly ash of each unit is preferably 3m, and the maximum height is not more than 5 m. Filling the bottom layer, stacking from the second layer, and breaking bag and compacting with excavator, wherein the thickness of the spread fly ash is not more than 1m, the excavator must level the fly ash within the operation range, and the distance from the operation boundary must be more than 2 m.
For the HDPE film adopted to cover the middle area, the HDPE film is laid along the slope and welded by a special welding machine, waste tires are matched with anti-aging sand bags to carry out ballasting after the welding is finished, and 8mm nylon ropes are adopted to connect and fix the tires so as to prevent the tires from being blown away by wind.
Inclination of inclined surface of daily landfill completion surface is not more than 1 (V): 5 (H), the slope of the front side slope consisting of compacted fly ash must not exceed 1 (V): 3 (H), the slope of the side slope is not more than 1 (V): 2 (H). Both the vertical and non-compacted surfaces do not allow the fly ash to be lifted upwards and all the stack slopes will remain in a stable condition, as shown in figure 3.
Different landfill methods and rain-proof, dust-proof and wind-proof measures are provided for different weathers and different seasons in the operation process: (1) pushing the landfill operation surface into an inclined surface of 1-2% to facilitate drainage; (2) during landfill operation, the fly ash solidified bodies are centralized in one area for landfill, a certain gradient is kept on the landfill surface, drainage is enhanced in rainy season, rainwater is prevented from entering the fly ash pile body, and the production amount of percolate is increased; (3) and (4) forbidding operation in heavy rain weather, and implementing landfill after the weather is changed well.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. A fly ash chelate stabilization landfill method is characterized in that: the landfill method comprises the following steps: step one, arranging a bank in a landfill reservoir area to divide the bank into a plurality of operation areas and operation units; the landfill reservoir area is divided by taking the operation area and the operation unit as a unit, so that drainage and diversion of rainwater in the reservoir area can be effectively controlled;
step two, paving a temporary approach road and an operation platform, planning a route of the temporary approach road according to the position of an operation area, and then paving the temporary approach road and hoisting the platform;
in the landfill stage, a temporary operation road is built on the surface of the pile body to meet the requirement of flying ash ton bag lifting pile, the operation road is connected with the approach road and the landfill operation unit and is continuously extended or heightened along with the landfill operation;
according to a landfill plan, at the initial stage of landfill, the rotary platform of an entrance road is filled with piles, a layer of ton bags are quickly paved, and then a steel plate road foundation box is erected to carry out landfill lifting towards the northeast direction;
the width of the temporary operation road needs to be ensured to be 6m, the temporary operation road is far away from the seepage-proof side slope and the platform thereof by more than 10 m, the edge of the temporary operation road needs to have enough safety distance from the fly ash filling edge, and the slope ratio of the outer side slope is not steeper than 1: 2, covering a soil layer with the thickness of 10-20cm on the filled area before covering with the geomembrane, and laying steel plates only by adopting a liner made of materials such as geotextile or canvas and the like above the geomembrane after covering with the geomembrane so as to avoid the damage of the geomembrane caused by the steel plates;
considering the load of crane and transport vehicle, steel plate road base box is used to construct temporary road and unload
A platform;
and step three, landfill and covering are carried out on the bagged fly ash, a crane is adopted to hoist the bagged fly ash, an excavator is used for paving and compacting the bagged fly ash to be buried to an operation area, and a covering mode combining daily coverage and middle coverage is adopted on the bagged fly ash which is buried, wherein the middle coverage refers to a landfill operation area which is completed in stages.
2. A fly ash chelate stabilization landfill method according to claim 1, characterized in that: the size of the steel plate roadbed box in the second step can be set to be 6m multiplied by 1.5m or 8m multiplied by 1.5 m.
3. A fly ash chelate stabilization landfill method according to claim 1, characterized in that: the landfill workload which can be met by the operation area is 3-12 times of that which can be met by the operation unit.
4. A fly ash chelate stabilization landfill method according to claim 1, characterized in that: the tonnage of the crane in the third step can be selected from 35t, 50t or 80t, 2 or 4 bags are hung in each time, and the maximum tonnage does not exceed 6 bags.
5. The method of claim 1, wherein the fly ash chelate is stabilized in landfill
In the following steps: and the stacking operation of each layer of fly ash in the third step is carried out in the sequence from bottom to top.
6. The method of claim 1, wherein the fly ash chelate is stabilized in landfill
In the following steps: the slope of the inclined plane of the daily landfill completion surface in the third step is not more than 1 (V): 5 (H), the slope of the front side slope consisting of compacted fly ash must not exceed 1 (V): 3 (H), the slope of the side slope is not more than 1 (V): 2 (H), the vertical working surface and the non-compacted working surface do not allow the fly ash to be lifted upwards, and all the inclined surfaces of the pile are maintained in a stable condition.
7. The method of claim 1, wherein the fly ash chelate is stabilized in landfill
In the following steps: the method comprises the following specific steps of day coverage and middle coverage in the third step: covering the fly ash stack body by adopting a 1.0mm HDPE film in an overlapping way, and completely covering the surface of a landfill area, wherein a 0.3mm impermeable film is adopted for daily covering of a daily operation area, a part of the covering film is uncovered for landfill operation during operation, and the film is covered immediately after the daily landfill is finished;
for the HDPE film adopted to cover the middle area, the HDPE film is laid along the slope and welded by a special welding machine, waste tires are matched with anti-aging sand bags to carry out ballasting after the welding is finished, and 8mm nylon ropes are adopted to connect and fix the tires so as to prevent the tires from being blown away by wind.
CN202010083534.0A 2020-02-09 2020-02-09 Stabilization landfill method for fly ash chelate Pending CN111185456A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010083534.0A CN111185456A (en) 2020-02-09 2020-02-09 Stabilization landfill method for fly ash chelate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010083534.0A CN111185456A (en) 2020-02-09 2020-02-09 Stabilization landfill method for fly ash chelate

Publications (1)

Publication Number Publication Date
CN111185456A true CN111185456A (en) 2020-05-22

Family

ID=70686052

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010083534.0A Pending CN111185456A (en) 2020-02-09 2020-02-09 Stabilization landfill method for fly ash chelate

Country Status (1)

Country Link
CN (1) CN111185456A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114260282A (en) * 2021-12-03 2022-04-01 灌南新苏国丰新能源有限公司 Fly ash landfill method for waste incineration power plant
CN116140322A (en) * 2022-09-22 2023-05-23 江苏生久环境科技有限公司 Landfill fly ash landfill method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000005721A (en) * 1998-06-19 2000-01-11 Mutsumi:Kk Treatment of waste and device therefor
CN103357643A (en) * 2013-07-12 2013-10-23 上海野马环保设备工程有限公司 Household waste landfill pollution control technology
CN107876547A (en) * 2017-11-17 2018-04-06 中国科学院城市环境研究所 One kind landfill body and preparation method thereof and equipment
CN109590305A (en) * 2018-05-31 2019-04-09 史东晓 A kind of burying method stabilizing flying dust
CN209177871U (en) * 2018-10-29 2019-07-30 上海二十冶建设有限公司 Platform structure for memorial archway continuously hoisting
CN110420961A (en) * 2019-05-14 2019-11-08 广州环投环境服务有限公司 A kind of flying dust landfill process

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000005721A (en) * 1998-06-19 2000-01-11 Mutsumi:Kk Treatment of waste and device therefor
CN103357643A (en) * 2013-07-12 2013-10-23 上海野马环保设备工程有限公司 Household waste landfill pollution control technology
CN107876547A (en) * 2017-11-17 2018-04-06 中国科学院城市环境研究所 One kind landfill body and preparation method thereof and equipment
CN109590305A (en) * 2018-05-31 2019-04-09 史东晓 A kind of burying method stabilizing flying dust
CN209177871U (en) * 2018-10-29 2019-07-30 上海二十冶建设有限公司 Platform structure for memorial archway continuously hoisting
CN110420961A (en) * 2019-05-14 2019-11-08 广州环投环境服务有限公司 A kind of flying dust landfill process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114260282A (en) * 2021-12-03 2022-04-01 灌南新苏国丰新能源有限公司 Fly ash landfill method for waste incineration power plant
CN114260282B (en) * 2021-12-03 2024-04-12 灌南新苏国丰新能源有限公司 Fly ash landfill method for garbage incineration power plant
CN116140322A (en) * 2022-09-22 2023-05-23 江苏生久环境科技有限公司 Landfill fly ash landfill method

Similar Documents

Publication Publication Date Title
CN208695907U (en) A kind of landfill structure stabilizing flying dust
CN101775821B (en) Device and method for vertically transporting earthwork by reverse construction method
CN111185456A (en) Stabilization landfill method for fly ash chelate
CN113502824B (en) Rapid soil-discharging construction method combining trestle bridge with annular road in deep foundation pit
CN112982447A (en) Strip mine refuse dump with ecological step slope surface structure
CN206902491U (en) A kind of precast concrete roads plate
CN109797730B (en) Comprehensive compaction filling method for filling and land building in loess hilly gully region
CN1951707B (en) Scene-making process in gangue ground emission
CN112458813A (en) Temporary road structure and construction method thereof
CN202610677U (en) Auxiliary tool for soft soil earthwork construction
CN110438857B (en) Mountain heavy-hill area reinforcement cage gabion pile and construction process thereof
CN1631560A (en) Refuse landfilling process in rainy season
CN109083442B (en) Construction method of dynamic load bearing structure during butt joint of existing building and newly-built foundation
CN213173170U (en) Highway gangue roadbed structure
CN110905519A (en) Strip mine dumping method
CN107262488A (en) A kind of the soot platform and its application method, building method of subregion unloading
CN105887949B (en) A kind of reverse construction mechanical device
CN210558981U (en) Multi-girder door type hoisting earthwork conveyor
RU2022105C1 (en) Method for construction of embankment
CN102485360A (en) Tianziling garbage landfill method
CN218668593U (en) Material transportation system in construction process of semi-underground workshop of hybrid pumped storage power station
CN212129850U (en) Temporary operation dumping platform laying structure on film of refuse landfill
CN220057604U (en) Temporary bridge capable of being quickly built and used for transportation of river and highway across seasons
CN204356779U (en) Support the deep foundation ditch vertical cut equipment of support form
CN214819538U (en) Transverse bridge direction prefabricated beam yard located at bridge tail road base section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200522

RJ01 Rejection of invention patent application after publication