CN111088989A - Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam - Google Patents

Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam Download PDF

Info

Publication number
CN111088989A
CN111088989A CN201911270298.7A CN201911270298A CN111088989A CN 111088989 A CN111088989 A CN 111088989A CN 201911270298 A CN201911270298 A CN 201911270298A CN 111088989 A CN111088989 A CN 111088989A
Authority
CN
China
Prior art keywords
multiplied
anchor
row
distance
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911270298.7A
Other languages
Chinese (zh)
Inventor
张兴国
郭慧军
赵杰
刘建伟
张琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Datong Coal Mine Group Co Ltd
Original Assignee
Datong Coal Mine Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Datong Coal Mine Group Co Ltd filed Critical Datong Coal Mine Group Co Ltd
Priority to CN201911270298.7A priority Critical patent/CN111088989A/en
Publication of CN111088989A publication Critical patent/CN111088989A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D17/00Caps for supporting mine roofs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention relates to the technical field of coal mining, in particular to a gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam; the method comprises the following supporting method and a temporary cavity treatment method; the supporting method comprises the following steps: a. and (4) top plate supporting: adopting a left-handed non-longitudinal-bar threaded steel anchor rod HRB335 with the diameter of 20mm multiplied by 2600mm to be matched with a W-shaped steel belt and paving an 8# metal net; two rows of anchor cables are circulated, the first row of anchor cables is matched with No. 16 channel steel, and the row distance is 1800 mm; the second row of anchor cables is matched with 16 # channel steel and a single anchor cable support combined support with the diameter of 21.8mm multiplied by 8300mm, and the row spacing is 1800 mm; b. and (3) coal side supporting: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods to match with W-shaped steel belts and 8# diamond metal nets, arranging anchor cables with phi 21.8mm multiplied by 5200mm between two adjacent rows of anchor rods, and arranging the anchor cables in a triple arrangement along the axial direction of a roadway, wherein the row spacing is 900 mm; the invention provides a method for supporting the top plate and two sides of a gob-side roadway of a fully mechanized caving section of an extra-thick coal seam, which is beneficial to controlling the stability of surrounding rocks of the gob-side roadway and ensuring the stability and safety of the roadway; the mining efficiency of the fully mechanized caving area is improved.

Description

Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam
Technical Field
The invention relates to the technical field of coal mining, in particular to a gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam.
Background
The gob-side entry driving is a driving way in which a stoping roadway of a lower section drives along the edge of a goaf of an upper section after the goaf of the upper section is collapsed, compacted and stabilized.
Compared with the gob-side entry driving of thin and medium-thickness coal seams, the fully mechanized caving gob-side entry driving has a larger difference. The coal seam thickness of the fully mechanized caving face is thick, the mining height is large, and the top coal is discharged mainly under the action of the dead weight of the top coal and the pressure of the overlying strata on the top coal, so that the top coal is crushed and discharged through the coal discharging port. Therefore, the caving height and the crushing degree of the top plate are much larger and more serious compared with those of thin and medium-thickness coal beds; the stress concentration at the edge of the goaf is higher than that at the edge of the goaf, and the width of each plastic zone of a crushing zone formed at the edge of the goaf is much larger; the rotary subsidence of the coal seam with thinner overlying strata and medium thickness above the coal seam is large; the fully mechanized gob-side entry driving is generally positioned in a broken coal body at the edge of a goaf. Due to the particularity of fully mechanized caving gob-side entry driving in the extra-thick coal seam, the surrounding rock stability principle and the control technology are not mature.
Disclosure of Invention
The invention provides a gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam, aiming at solving the technical problems of controlling gob-side entry surrounding rock deformation and ensuring stability and safety of an entry.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows: a gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam comprises the following support method and a temporary cavity treatment method;
the supporting method comprises the following steps: a. and (4) top plate supporting: adopting a left-handed non-longitudinal bar threaded steel anchor rod HRB335 with the diameter of 20mm multiplied by 2600mm, and the spacing row distance of 950mm multiplied by 900 mm; preparing 5100X 250X 3mmW steel belts and paving an 8# metal net; two rows of anchor cables are circulated, wherein the first row adopts 21.8mm phi by 8300mm anchor cables, each row of anchor cables is matched with No. 16 channel steel, and the row distance is 1800 mm; anchor cables with the diameter of 21.8mm multiplied by 8300mm are adopted in the second row, each row of anchor cables is provided with 16-number channel steel and a single anchor cable support with the diameter of 21.8mm multiplied by 8300mm for combined support, and the row spacing is 1800 mm;
b. and (3) coal side supporting: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods to match 4500 multiplied by 250 multiplied by 3mmW type steel belts and 8# diamond metal nets, arranging row distance between the left-handed non-longitudinal rib thread anchor rods is 1000mm multiplied by 900mm, distance between the upper anchor rods and a top plate is 200mm, distance between the bottom anchor rods and a bottom plate is 500mm, phi 21.8mm multiplied by 5200mm anchor cables are arranged between two adjacent rows of anchor rods, and are arranged in a three-three way mode along the axial direction of a roadway, and the row distance is;
the method for treating the temporary cavern comprises the following steps:
a. installing a monitoring and monitoring system at the position of the adjacent empty chamber, digging a detection hole in advance when the position is tunneled to be 20m away from the adjacent empty chamber, detecting harmful gas in a goaf and preparing for timely hole sealing;
b. when the working face is 5m away from the empty chamber, Marilsan is injected;
c. after a working face passes through an empty chamber influence area, building a reinforced concrete wall immediately, building a reinforced concrete wall on the side of a small coal pillar at a corresponding position of the chamber to reinforce the small coal pillar and isolate a goaf, and adopting an upper anchor rod as a main body and matching an iron wire mesh for reinforcing steel bars; the thickness of the concrete wall is 500 mm.
A gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam comprises the following support method and a temporary cavity treatment method;
the supporting method comprises the following steps:
a. and (4) top plate supporting: adopting a left-handed non-longitudinal bar threaded steel anchor rod HRB335 with the diameter of 20mm multiplied by 2600mm, and the spacing row distance of 950mm multiplied by 900 mm; welding a reinforcing steel bar ladder beam by matching phi 14mmQ235 round steel and paving an 8# metal net; anchor cables with the diameter of 21.8mm multiplied by 8250mm are adopted, each row of anchor cables is matched with No. 16 channel steel, and the row distance is 1800 mm; the distance between the anchor cables close to the coal pillar slope and the coal pillar slope is 800mm, the distance between the anchor cables close to the solid coal slope and the coal pillar slope is 1400mm, and the distance between the middle anchor cable and the coal pillar slope is 500mm away from the center line of the roadway;
b. solid coal side supporting: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods, matching 8# diamond metal mesh, arranging distance between rows of bolts is 1000mm multiplied by 900mm, distance between upper anchor rods and a top plate is 200mm, distance between bottom anchor rods and a bottom plate is 500mm, and each row of anchor rods is connected by a reinforcing steel bar beam welded by phi 12mm Q235 # round steel;
c. and (3) supporting the small coal pillar side: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods matched with 8# diamond metal mesh, the row spacing is 1000mm multiplied by 900mm, the distance between the upper anchor rods and the top plate is 200mm, the distance between the bottom anchor rods and the bottom plate is 500mm, and each row of anchor rods are connected by a reinforcing steel bar beam welded by phi 12mm Q235 # round steel; anchor cables with the diameter of 21.8mm multiplied by 5250mm are arranged between two adjacent rows of anchor rods and are arranged in a three-flower mode along the axial direction of a roadway, and the row spacing is 900 mm;
the method for treating the temporary cavern comprises the following steps:
a. installing a monitoring and monitoring system at the position of the adjacent empty chamber, digging a detection hole in advance when the position is tunneled to be 20m away from the adjacent empty chamber, detecting harmful gas in a goaf and preparing for timely hole sealing;
b. when the working face is 5m away from the empty chamber, Marilsan is injected;
c. after a working face passes through an empty chamber influence area, building a reinforced concrete wall immediately, building a reinforced concrete wall on the side of a small coal pillar at a corresponding position of the chamber to reinforce the small coal pillar and isolate a goaf, and adopting an upper anchor rod as a main body and matching an iron wire mesh for reinforcing steel bars; the thickness of the concrete wall is 500 mm.
Compared with the prior art, the invention has the following beneficial effects:
the invention provides a method for supporting the top plate and two sides of a gob-side roadway of a fully mechanized caving section of an extra-thick coal seam, which is beneficial to controlling the stability of surrounding rocks of the gob-side roadway and provides scientific basis for reserving coal pillars of the fully mechanized caving section of the extra-thick coal seam and engineering of the gob-side roadway; the method controls the deformation of surrounding rocks of the gob-side roadway, and ensures the stability and safety of the roadway; the mining efficiency of the fully mechanized caving area is improved.
Detailed Description
The present invention is further illustrated by the following specific examples.
Example 1
In the embodiment, the fairway coal industry of the university and coal mine group company, llc, is taken as an example:
the surrounding rock control early-stage support method comprises the following steps:
and (4) top plate supporting: left-handed non-longitudinal-bar threaded steel anchor rods HRB335 with the diameter of 20mm multiplied by 2600mm are adopted, the spacing between rows is 950mm multiplied by 900mm, and 6 anchor rods are arranged in each row. A5200 mm reinforcing steel bar ladder beam welded by phi 14mmQ235 round steel is matched and a # 8 metal mesh is laid. Anchor cables with the diameter of 21.8mm multiplied by 8250mm are arranged, 5 anchor cables in each row are provided with No. 16 channel steel with the thickness of 5000mm, and the row spacing is 1800 mm; 3600mm of No. 16 channel steel is matched with 3 anchor cables in each row of anchor cables with the diameter of 21.8mm multiplied by 8250mm, the row distance is 1800mm, the distance between the anchor cables close to the coal pillar side and the coal pillar side is 800mm, the distance between the anchor cables close to the solid coal pillar side and the coal pillar side is 1400mm, and the distance between the middle anchor cables and the coal pillar side is 500mm away from the center line of a roadway.
Solid coal side supporting: adopt phi 20mm x 2600mm levogyration to have no longitudinal bar screw thread stock, join in marriage 8# rhombus metal mesh, row spacing 1000mm x 900mm, upper portion stock is apart from roof 200mm, bottom stock is apart from bottom plate 500mm, every row arranges that 4 stock adopts, reinforcing bar ladder roof beam specification: the steel bar beams welded by phi 12mmQ235 round steel are adopted for connection, and the length is 3400 mm.
And (3) supporting the small coal pillar side: the left-handed non-longitudinal-rib threaded anchor rods with the diameter of 20mm multiplied by 2600mm are matched with 8# diamond metal nets, the row spacing is 1000mm multiplied by 900mm, the distance between the upper anchor rods and the top plate is 200mm, the distance between the bottom anchor rods and the bottom plate is 500mm, 4 anchor rods are arranged in each row, the reinforcing steel bar ladder beams are connected through reinforcing steel bar beams welded by phi 12mmQ235 round steel, and the length is 3400 mm. Anchor cables with the diameter of 21.8mm multiplied by 5250mm are arranged between two adjacent rows of anchor rods and are arranged in a three-flower mode along the axial direction of a roadway, and the row spacing is 900 mm.
5211 when the tunnel is excavated to 176m, due to the influence of the coal monitor in the goaf of the adjacent 8210 working face, the tunnel is excavated back, and a series of phenomena of bottom bulging, longitudinal cracking of the top plate and the development of the coal monitor under pressure occur. During the tunneling process of the tunnel, longitudinal cracks of a bottom heave and a top plate extend forwards along with the advancing of a working face, the bottom heave and the top plate crack appear at the position with the mileage of 40-200 m, the average height of the bottom heave is 200mm, the most serious position of the bottom heave is located at the position with the mileage of 125-130 m (meeting the first shunting chamber of 5210 tunnels and a small coal pillar of 3 m), and the bottom heave is 600 mm. The longitudinal crack of the top plate is positioned on the solid coal side, and the crack width is 3-5 mm; in addition, the solid coal side has a moving-close phenomenon, and the average moving-close phenomenon is 200 mm. According to the mine pressure theory, the reason for the close of the solid movement and the cracking of the roof is considered to be that the fracture position of the 8210 working face roof is positioned above the 5211 roadway solid coal side.
In addition, the defects of small top protection area, uneven welding point strength, weak bending strength, small deformation resistance and the like of the steel bar ladder cause the problems of fracture, distortion deformation, damaged welding point of the steel bar ladder and the like of the on-site steel bar ladder.
By the mining electronic drilling peeping instrument, the crack development condition of the surrounding rock in the anchoring range of the anchor rod and the anchor cable can be clearly and visually observed; and comparing the crack distribution and development conditions of the top plate and the two sides of the roadway, establishing a geological structure foundation for supporting the narrow coal pillar along the empty roadway, and being used as a basis for improving the existing supporting scheme to ensure the supporting quality along the empty coal roadway. The lithology and the destruction degree in different depths of the drill holes of the measuring points can be visually obtained by arranging and analyzing the peeping video.
The observation shows that: the top plate crack is located in the range of the anchor cable support control top plate due to the fact that 0.2m of separation phenomenon occurs at 0.6m and 2.7m of the top plate upwards. The small coal pillar side and the solid coal side are broken within 4m, and the side anchor cables are required to be added to control the integrity and stability of the two sides.
Aiming at the problems, the support method is changed according to the actual reinforcement support of the excavated section on site and the support method of the non-excavated section at the later stage.
The later-stage supporting method for the surrounding rock control comprises the following steps:
design of reinforcing support of tunneled section
And (4) top plate supporting: a single anchor cable with the specification of phi 17.8mm multiplied by 8300mm (1 multiplied by 7) is added on the top plate, and the anchor cable channel steel combined structure are arranged in the same row with one beam and three anchors and are 400mm away from the solid coal side.
Solid coal side supporting: anchor cables with the diameter of 21.8mm multiplied by 5200mm (1 multiplied by 19) are added, the row spacing is 900mm multiplied by 900mm, the upper anchor cable is 600mm away from the top plate and inclines upwards for 15 degrees; the bottom anchor cable is 700mm away from the bottom plate and is inclined downwards by 5 degrees; the middle anchor cables are vertically arranged; each row is provided with 3 anchor cables.
And (3) supporting the small coal pillar side: anchor cable reinforcing supports are added on the coal pillar sides, two rows of anchor cables are circulated, wherein the anchor cables with the diameter of 21.8mm multiplied by 5200mm (1 multiplied by 19) are selected for the first row of anchor cable supports, the row spacing is 1800mm, the distance between the upper anchor cables and a top plate is 600mm, and the upper anchor cables are inclined upwards by 15; the bottom anchor cable is 700mm away from the bottom plate and is inclined downwards by 5 degrees; the middle anchor cable is inclined upwards for 15 degrees; each row is provided with 3 anchor cables.
The anchor cables with the diameter of 21.8mm multiplied by 5250mm (1 multiplied by 19) are selected for supporting the anchor cables in the second row, the row distance is 1800mm, the distance between the upper anchor cables and the top plate is 600mm, and the anchor cables are inclined upwards by 15 degrees; the bottom anchor cable is 1200mm away from the bottom plate and is inclined downwards by 15 degrees; the middle anchor cables are vertically arranged; each row is provided with 3 anchor cables.
Non-tunneling section changing support method
And (4) top plate supporting: left-handed non-longitudinal-bar threaded steel anchor rods HRB335 with the diameter of 20mm multiplied by 2600mm are adopted, the spacing between rows is 950mm multiplied by 900mm, and 6 anchor rods are arranged in each row. 5100X 250X 3mmW steel belt is matched and 8# metal mesh is paved. Two rows of anchor cables are circulated, wherein the first row adopts 21.8mm phi by 8300mm anchor cables, 5 anchor cables in each row are matched with 16 # channel steel with the length of 5000mm, and the row spacing is 1800 mm; and the second row adopts 3 anchor cables with the diameter of 21.8mm multiplied by 8300mm in each row to be matched with 16-number channel steel with the diameter of 4000mm and a single anchor cable with the diameter of 21.8mm multiplied by 8300mm to support and support in a combined way, and the row spacing is 1800 mm.
And (3) coal side supporting: the left-handed non-longitudinal-rib threaded anchor rods with the diameter of 20mm multiplied by 2600mm are matched with 4500 multiplied by 250 multiplied by 3mmW type steel belts and 8# diamond metal nets, the interval row spacing is 1000mm multiplied by 900mm, the distance between the upper anchor rods and the top plate is 200mm, the distance between the bottom anchor rods and the bottom plate is 500mm, 4 anchor rods are arranged in each row, anchor cables with the diameter of 21.8mm multiplied by 5200mm are arranged between two adjacent rows of anchor rods and are arranged in a three-row mode along the axial direction of a roadway, and the row spacing is 900.
Method for treating temporary cavern
5210 5 chambers (4 shunting chambers with a depth of 5 m; 1 water sump with a depth of 3 m) are constructed on the left side of the whole roadway in the roadway entry direction, so that the width of the small coal pillars is changed to 3m at the minimum when the 5211 roadway tunneled by the original 8m small coal pillars meets the chambers. The current 5211 lane adopts forward and reverse tunneling and simultaneously tunnels, and the horizontal distances between the chamber of the 5210 lane and the forward and reverse tunneling head of the 5211 lane are 69.5m, 158m and 272.5m from the forward tunneling opening respectively; the distance from the back-digging opening is 124.5m, 325.5 m. In order to ensure safe and efficient tunneling of 5211 lane 3m small coal pillars, preventive measures are taken in advance.
(1) A monitoring and monitoring system is arranged at the position of the 5211 lane near-empty chamber, and when the 5211 lane is tunneled to a position 20m away from the near-empty chamber, a detection hole is drilled in advance, harmful gas in a goaf is detected, and timely hole sealing preparation is made. Through detection by punching detection holes, the goaf has no water and normal gas content, 0.2 of carbon monoxide, 0.63 of carbon dioxide and 0.09 of methane.
(2) And when the working face is 5m away from the empty chamber, injecting Marilyn according to the Marilyn injection scheme. The Marilsan protocol is determined according to the diffusion radius.
(3) And immediately building the reinforced concrete wall after the working face passes through the influence area of the adjacent empty chamber. Building a reinforced concrete wall on the side of the small coal pillar at the corresponding position of the 5210 roadway chamber to reinforce the small coal pillar and isolate the goaf, wherein the reinforcing steel bars adopt side anchor rods as main bodies and are matched with iron wire meshes; the thickness of the concrete wall is 500 mm.
After the series of measures are taken, 5211 roadways are smoothly communicated, the deformation of the roadways is obviously weakened through reinforcement support and support change, the support strength meets the stress and deformation characteristics of surrounding rocks, the current 8211 working face has stable installation conditions, and equipment on the working face is stably installed.

Claims (2)

1. A gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam is characterized by comprising the following support method and a temporary cavity treatment method;
the supporting method comprises the following steps: a. and (4) top plate supporting: adopting a left-handed non-longitudinal bar threaded steel anchor rod HRB335 with the diameter of 20mm multiplied by 2600mm, and the spacing row distance of 950mm multiplied by 900 mm; preparing 5100X 250X 3mmW steel belts and paving an 8# metal net; two rows of anchor cables are circulated, wherein the first row adopts 21.8mm phi by 8300mm anchor cables, each row of anchor cables is matched with No. 16 channel steel, and the row distance is 1800 mm; anchor cables with the diameter of 21.8mm multiplied by 8300mm are adopted in the second row, each row of anchor cables is provided with 16-number channel steel and a single anchor cable support with the diameter of 21.8mm multiplied by 8300mm for combined support, and the row spacing is 1800 mm;
b. and (3) coal side supporting: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods to match 4500 multiplied by 250 multiplied by 3mmW type steel belts and 8# diamond metal nets, arranging row distance between the left-handed non-longitudinal rib thread anchor rods is 1000mm multiplied by 900mm, distance between the upper anchor rods and a top plate is 200mm, distance between the bottom anchor rods and a bottom plate is 500mm, phi 21.8mm multiplied by 5200mm anchor cables are arranged between two adjacent rows of anchor rods, and are arranged in a three-three way mode along the axial direction of a roadway, and the row distance is;
the method for treating the temporary cavern comprises the following steps:
a. installing a monitoring and monitoring system at the position of the adjacent empty chamber, digging a detection hole in advance when the position is tunneled to be 20m away from the adjacent empty chamber, detecting harmful gas in a goaf and preparing for timely hole sealing;
b. when the working face is 5m away from the empty chamber, Marilsan is injected;
c. after a working face passes through an empty chamber influence area, building a reinforced concrete wall immediately, building a reinforced concrete wall on the side of a small coal pillar at a corresponding position of the chamber to reinforce the small coal pillar and isolate a goaf, and adopting an upper anchor rod as a main body and matching an iron wire mesh for reinforcing steel bars; the thickness of the concrete wall is 500 mm.
2. A gob-side entry driving surrounding rock control method for a fully mechanized caving section of an extra-thick coal seam is characterized by comprising the following support method and a temporary cavity treatment method;
the supporting method comprises the following steps:
a. and (4) top plate supporting: adopting a left-handed non-longitudinal bar threaded steel anchor rod HRB335 with the diameter of 20mm multiplied by 2600mm, and the spacing row distance of 950mm multiplied by 900 mm; welding a reinforcing steel bar ladder beam by matching phi 14mmQ235 round steel and paving an 8# metal net; anchor cables with the diameter of 21.8mm multiplied by 8250mm are adopted, each row of anchor cables is matched with No. 16 channel steel, and the row distance is 1800 mm; the distance between the anchor cables close to the coal pillar slope and the coal pillar slope is 800mm, the distance between the anchor cables close to the solid coal slope and the coal pillar slope is 1400mm, and the distance between the middle anchor cable and the coal pillar slope is 500mm away from the center line of the roadway;
b. solid coal side supporting: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods, matching 8# diamond metal mesh, arranging distance between rows of bolts is 1000mm multiplied by 900mm, distance between upper anchor rods and a top plate is 200mm, distance between bottom anchor rods and a bottom plate is 500mm, and each row of anchor rods is connected by a reinforcing steel bar beam welded by phi 12mm Q235 # round steel;
c. and (3) supporting the small coal pillar side: adopting phi 20mm multiplied by 2600mm left-handed non-longitudinal rib thread anchor rods matched with 8# diamond metal mesh, the row spacing is 1000mm multiplied by 900mm, the distance between the upper anchor rods and the top plate is 200mm, the distance between the bottom anchor rods and the bottom plate is 500mm, and each row of anchor rods are connected by a reinforcing steel bar beam welded by phi 12mm Q235 # round steel; anchor cables with the diameter of 21.8mm multiplied by 5250mm are arranged between two adjacent rows of anchor rods and are arranged in a three-flower mode along the axial direction of a roadway, and the row spacing is 900 mm;
the method for treating the temporary cavern comprises the following steps:
a. installing a monitoring and monitoring system at the position of the adjacent empty chamber, digging a detection hole in advance when the position is tunneled to be 20m away from the adjacent empty chamber, detecting harmful gas in a goaf and preparing for timely hole sealing;
b. when the working face is 5m away from the empty chamber, Marilsan is injected;
c. after a working face passes through an empty chamber influence area, building a reinforced concrete wall immediately, building a reinforced concrete wall on the side of a small coal pillar at a corresponding position of the chamber to reinforce the small coal pillar and isolate a goaf, and adopting an upper anchor rod as a main body and matching an iron wire mesh for reinforcing steel bars; the thickness of the concrete wall is 500 mm.
CN201911270298.7A 2019-12-12 2019-12-12 Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam Pending CN111088989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911270298.7A CN111088989A (en) 2019-12-12 2019-12-12 Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911270298.7A CN111088989A (en) 2019-12-12 2019-12-12 Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam

Publications (1)

Publication Number Publication Date
CN111088989A true CN111088989A (en) 2020-05-01

Family

ID=70394950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911270298.7A Pending CN111088989A (en) 2019-12-12 2019-12-12 Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam

Country Status (1)

Country Link
CN (1) CN111088989A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343627A (en) * 2020-11-03 2021-02-09 中国平煤神马能源化工集团有限责任公司 Method for controlling stability of surrounding rock of deep ultra-large section dense chamber group
CN112943264A (en) * 2021-02-19 2021-06-11 国家能源集团宁夏煤业有限责任公司 Construction method for fully-mechanized mining face retraction channel
CN113503179A (en) * 2021-08-02 2021-10-15 太原理工大学 Method for controlling large-section open-off cut tunneling surrounding rock of overlying goaf ultra-close coal seam

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202064981U (en) * 2011-05-07 2011-12-07 山西晋城无烟煤矿业集团有限责任公司 Soft coal layer roadway supporting structure
CN102817620A (en) * 2012-08-13 2012-12-12 大同煤矿集团有限责任公司 Method for supporting ultra-thick and fluffy coal roadway
CN103899342A (en) * 2014-04-15 2014-07-02 中国矿业大学(北京) Gob-side entrydriving coal pillar anchor cable through reinforcing method
CN204175317U (en) * 2014-10-22 2015-02-25 四川广旺能源发展(集团)有限责任公司 Export supporting under large-inclination-angle coal bed working face to arrange
CN104533482A (en) * 2014-10-28 2015-04-22 淮浙煤电有限责任公司顾北煤矿分公司 Reinforcing method for improving stability of gob-side entry driving small coal pillar
CN105370299A (en) * 2015-11-27 2016-03-02 山东新巨龙能源有限责任公司 Kilometers-deep thick coal seam narrow coal pillar gob-side entry supporting process
CN205936636U (en) * 2016-08-19 2017-02-08 淮南矿业(集团)有限责任公司 High seam tunnels support system along sky
CN206636603U (en) * 2017-04-07 2017-11-14 兖州煤业股份有限公司 Face sky old working compound closure wall
CN109441503A (en) * 2018-11-19 2019-03-08 中国矿业大学(北京) A kind of method for protecting support that thin coal pillar is controlled along empty coal road mine pressure inversion

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202064981U (en) * 2011-05-07 2011-12-07 山西晋城无烟煤矿业集团有限责任公司 Soft coal layer roadway supporting structure
CN102817620A (en) * 2012-08-13 2012-12-12 大同煤矿集团有限责任公司 Method for supporting ultra-thick and fluffy coal roadway
CN103899342A (en) * 2014-04-15 2014-07-02 中国矿业大学(北京) Gob-side entrydriving coal pillar anchor cable through reinforcing method
CN204175317U (en) * 2014-10-22 2015-02-25 四川广旺能源发展(集团)有限责任公司 Export supporting under large-inclination-angle coal bed working face to arrange
CN104533482A (en) * 2014-10-28 2015-04-22 淮浙煤电有限责任公司顾北煤矿分公司 Reinforcing method for improving stability of gob-side entry driving small coal pillar
CN105370299A (en) * 2015-11-27 2016-03-02 山东新巨龙能源有限责任公司 Kilometers-deep thick coal seam narrow coal pillar gob-side entry supporting process
CN205936636U (en) * 2016-08-19 2017-02-08 淮南矿业(集团)有限责任公司 High seam tunnels support system along sky
CN206636603U (en) * 2017-04-07 2017-11-14 兖州煤业股份有限公司 Face sky old working compound closure wall
CN109441503A (en) * 2018-11-19 2019-03-08 中国矿业大学(北京) A kind of method for protecting support that thin coal pillar is controlled along empty coal road mine pressure inversion

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343627A (en) * 2020-11-03 2021-02-09 中国平煤神马能源化工集团有限责任公司 Method for controlling stability of surrounding rock of deep ultra-large section dense chamber group
CN112943264A (en) * 2021-02-19 2021-06-11 国家能源集团宁夏煤业有限责任公司 Construction method for fully-mechanized mining face retraction channel
CN113503179A (en) * 2021-08-02 2021-10-15 太原理工大学 Method for controlling large-section open-off cut tunneling surrounding rock of overlying goaf ultra-close coal seam

Similar Documents

Publication Publication Date Title
CN110700883B (en) Gob-side entry driving prevention and control method for large-dip-angle coal seam composite disaster small coal pillar
CN111088989A (en) Gob-side entry driving surrounding rock control method for fully mechanized caving section of extra-thick coal seam
CN112282806B (en) Thick coal seam forced mining roadway blasting pressure relief and long anchor rod cooperative roof control method
CN112610218B (en) Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method
CN109707422B (en) High-pressure grouting reinforcing and supporting method for small coal pillars along empty conveying roadway
CN103195443A (en) Deep mining method capable of optimizing support parameters and preventing roadway delaying water gushing
CN115749713A (en) Rock stratum frequency conversion pulse fracture network fracturing method and equipment
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN113202473A (en) Underground mine broken rock downward mining method
CN113605893B (en) Control method for pre-filling full gob-side entry driving surrounding rock
CN212716647U (en) Arrangement system of pre-digging withdrawing channel
CN111022050B (en) Fully-closed blasting pressure relief and self-retained roadway method for grouting reconstruction of composite roof
CN109958459B (en) Soft thick coal seam bottom tunneling method
CN108952715B (en) Gob-side entry driving top coal supporting and reinforcing method for inclined thick/extra-thick coal seam entry top
CN111271077A (en) High-ground-stress three-soft-roadway surrounding rock bolting-grouting combined reinforcement method
CN113217044B (en) Upward and oblique scattering type grouting water plugging method for deep large fault tunnel
CN111502663B (en) Tunneling method for collapse column in over-stress concentration area
CN114575844A (en) Roadway roof segmented pressure relief and reinforcement control method based on double-roadway excavation
CN113250715A (en) Gob-side entry retaining method for layered mining under coal mine
CN112855170A (en) Method for excavating and supporting lower cut hole of goaf
CN117248915B (en) Method for constructing drift sand stratum roadway
CN113847055B (en) Roadway arrangement and support method for extremely-short-distance coal seam group downlink exploitation
CN114183141B (en) Method for controlling surrounding rock of short-distance coal seam mining replacement roadway
CN116733469B (en) Deep well high-stress fully-mechanized caving and fully-mechanized caving collaborative mining technical method
CN117780349A (en) Method for dense drilling, roof cutting, pressure relief and gob-side entry retaining under close-range coal seam goaf

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200501