CN110985000B - Vertical shaft annular steel support assembly and construction method - Google Patents

Vertical shaft annular steel support assembly and construction method Download PDF

Info

Publication number
CN110985000B
CN110985000B CN201911194832.0A CN201911194832A CN110985000B CN 110985000 B CN110985000 B CN 110985000B CN 201911194832 A CN201911194832 A CN 201911194832A CN 110985000 B CN110985000 B CN 110985000B
Authority
CN
China
Prior art keywords
annular steel
steel support
shaft
annular
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911194832.0A
Other languages
Chinese (zh)
Other versions
CN110985000A (en
Inventor
张川
刘小荣
郭玉山
陈郁平
丁远振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Construction Engineering Co Ltd
Jiangsu CRRC Urban Development Co Ltd
Original Assignee
Suzhou CRRC Construction Engineering Co Ltd
CRRC Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou CRRC Construction Engineering Co Ltd, CRRC Construction Engineering Co Ltd filed Critical Suzhou CRRC Construction Engineering Co Ltd
Priority to CN201911194832.0A priority Critical patent/CN110985000B/en
Publication of CN110985000A publication Critical patent/CN110985000A/en
Application granted granted Critical
Publication of CN110985000B publication Critical patent/CN110985000B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/11Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Wood Science & Technology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a shaft annular steel support assembly, which comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in a shaft, the fore shaft ring beam is arranged at a well mouth position, the well wall steel bar is bound below the fore shaft ring beam, a horizontal sliding rail is arranged outside the shaft, at least two vertical sliding grooves which are communicated up and down are reserved on the fore shaft ring beam along the circumferential direction, and each annular steel support is provided with a guide lug which corresponds to the vertical sliding grooves on the fore shaft ring beam one by one; after the annular steel support is formed outside the vertical shaft, the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail in a sliding mode, after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled out of the horizontal sliding rail, and the annular steel support can penetrate through the locking collar beam and slide to the position of a well wall reinforcing steel bar to be bound and fixed. Meanwhile, the invention also discloses a construction method of the vertical shaft annular steel support component. The method has the characteristics of safety, reliability, high construction progress, high construction quality and low cost.

Description

Vertical shaft annular steel support assembly and construction method
Technical Field
The invention relates to the technical field of tunnel vertical shaft construction, in particular to a vertical shaft annular steel support component and a construction method thereof.
Background
At present, an annular steel support used for shaft excavation mainly adopts large machinery to hoist a steel member to a foundation pit operation surface, and field assembling and welding are carried out in a shaft. There are major problems: large-scale mechanical hoisting operation and on-site assembling and welding in a vertical shaft have large safety risk; the vertical shaft is assembled, the operation environment is complex, the consistency of products of all annular steel supports is poor, the construction speed is slow, the construction quality is not easy to control, and the construction cost is relatively high; when assembling in the well, next earthwork excavation can not be carried out, and the construction progress is influenced.
Disclosure of Invention
The invention aims to provide the annular steel supporting component for the vertical shaft, which is safe and reliable, has quick construction progress, high construction quality and low cost.
Therefore, the technical scheme adopted by the invention is as follows: a shaft annular steel support assembly comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in a shaft, the fore shaft ring beam is arranged at a position of a well head, the well wall steel bar is bound below the fore shaft ring beam, a horizontal sliding rail is arranged outside the shaft, at least two vertical sliding grooves which are communicated up and down are reserved on the fore shaft ring beam along the circumferential direction, and each annular steel support is provided with a guide lug which is in one-to-one correspondence with the vertical sliding grooves on the fore shaft ring beam; the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail after being molded outside the vertical shaft, and after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled away from the horizontal sliding rail and can pass through the locking collar beam to slide to the position of a well wall reinforcing steel bar for binding and fixing; an assembling field is arranged outside the vertical shaft, and the annular steel support is formed by connecting or welding a guide lug and an arc-shaped block in the assembling field through a bolt;
the diameters of all the annular steel supports arranged in the same vertical shaft and the guide lugs are sequentially reduced from top to bottom along the vertical shaft, and the specification size of the vertical sliding groove is matched with the guide lugs of the largest annular steel support.
Preferably, the number of the guide lugs and the number of the arc-shaped blocks are four, and every two arc-shaped blocks are spliced through the guide lugs.
More preferably, the horizontal slide rail comprises two slide rail bars which are arranged in parallel at intervals from left to right.
Meanwhile, the invention also provides a construction method of the vertical shaft annular steel support component, which comprises the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam, continuing to excavate the earthwork downwards after the construction of the locking collar beam is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support, and binding a first section of well wall steel reinforcement cage; meanwhile, assembling the first annular steel support in an assembling site;
the locking collar beam is arranged at a wellhead position, and at least two vertical sliding grooves which are communicated up and down are reserved on the locking collar beam along the circumferential direction; the annular steel support is formed by connecting or welding a guide lug and an arc-shaped block through a bolt, the whole annular steel support is annular, and the guide lug corresponds to the vertical sliding groove on the locking collar beam one by one;
secondly, after the horizontal slide rail is in place, the assembled first annular steel support is conveyed to the opening of the vertical shaft in a sliding mode along the horizontal slide rail, the guide lugs are aligned with the vertical slide grooves one by one, finally the horizontal slide rail is pulled out, the annular steel support penetrates through the locking collar beam and slides to the designed position of the first annular steel support, the annular steel support and the first section of well wall reinforcement cage are bound and fixed, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and a channel for the second annular steel support to pass through is reserved when concrete of the annular steel support is poured;
thirdly, when the second annular steel support is assembled, excavating earthwork to the design position of the second annular steel support, binding a second section of well wall reinforcement cage, then placing the second annular steel support at the design position of the second annular steel support in the same mode as the first annular steel support for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the second annular steel support, and reserving a channel for the third annular steel support to pass through when pouring concrete of the annular steel support; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all annular steel supports that same shaft was equipped with, its diameter and direction lug decrease progressively from top to bottom along the shaft in proper order, the specification size of vertical spout matches with the direction lug of the biggest annular steel support to ensure that the annular steel support of transferring afterwards can pass the annular steel support of transferring earlier and fall to the design position, and the thickness of pouring of wall of a well concrete is greater than 50 cm.
The invention has the beneficial effects that:
(1) the steel members are not required to be hoisted by large machinery, and the assembled annular steel supports are conveyed to the opening of the vertical shaft by adopting a simple and safe horizontal sliding rail, so that the method is safe and reliable, and the construction cost is reduced;
(2) the annular steel supports are assembled outside the vertical shaft, and field assembling and welding are not needed in the vertical shaft, so that the safety risk of operation is further reduced; the shaft is assembled outside, so that the consistency of the product is easy to control;
(3) when the annular steel supports are assembled outside the vertical shaft, earth excavation and steel bar binding in the shaft are carried out, and the construction speed is accelerated and the construction period is shortened by the mode of synchronous construction outside the shaft in the shaft.
Drawings
FIG. 1 is a top view of the present invention.
Fig. 2 is a simplified perspective view of the invention.
Fig. 3 is a simplified front view of the invention.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
referring to fig. 1-3, an annular steel support assembly for a shaft is mainly composed of a locking collar beam 1, well wall reinforcing steel bars (not shown), an annular steel support 3, horizontal sliding rails 2 and the like.
The locking collar beam 1, the well wall reinforcing steel bars and the annular steel supports 3 are arranged in the shaft, the annular steel supports 3 are assembled outside the shaft, and then are conveyed to the position of a well mouth in a sliding mode through the horizontal sliding rails 2.
The fore shaft collar tie beam 1 is arranged at a well mouth position, the fore shaft collar tie beam 1 is composed of bound fore shaft collar tie beam reinforcing steel bars and poured concrete, and the fore shaft collar tie beam 1 is used for ensuring the strength of the well mouth position. And the well wall reinforcing steel bars are bound below the locking collar beam 1, and concrete also needs to be poured for ensuring the strength of the well wall.
At least two vertical sliding grooves 1a which are communicated up and down are reserved on the fore shaft ring beam 1 along the circumferential direction, and each annular steel support 3 is provided with a guide lug 3a which is in one-to-one correspondence with the vertical sliding grooves 1a on the fore shaft ring beam 1. And a horizontal sliding rail 2 is arranged outside the shaft.
The annular steel support 3 can be conveyed to the opening part of the vertical shaft along the horizontal sliding rail 2 after being formed in an assembling field outside the vertical shaft. After the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, the horizontal sliding rails 2 are pulled away, and the annular steel supports 3 can penetrate through the locking collar beams 1 and slide to the position of the well wall reinforcing steel bar for binding and fixing. The wall of a well guarantees intensity jointly through wall of a well ligature reinforcing bar and a plurality of annular steel shotcrete 3 that the interval set up from top to bottom, ligatures the wall of a well reinforcing bar earlier, slides down behind the design position with every annular steel shotcrete 3 again, respectively with wall of a well reinforcing bar ligature fixed back together, carries out concrete placement at last.
An assembling field is arranged outside the vertical shaft, and the annular steel support 3 is formed by connecting or welding the guide lugs 3a and the arc blocks 3b through bolts in the assembling field. Of course, the method is not limited to the assembly mode, and the method can also be integrally formed. The horizontal sliding rail 2 is used as a rail for sliding the assembled annular steel support 3 to the position of a wellhead.
All the annular steel supports 3 equipped in the same shaft have the diameters and the guide lugs 3a which are gradually reduced from top to bottom along the shaft, and the specification size of the vertical sliding chute 1a is matched with the guide lugs 3a of the largest annular steel support 3.
The number of the guide lugs 3a and the number of the arc-shaped blocks 3b are four, and every two arc-shaped blocks 3b are spliced through the guide lugs 3 a. But is not limited to four, and may be three or more. The horizontal sliding rail 2 comprises two sliding rail bars which are arranged in parallel at intervals left and right, and the distance between the two sliding rail bars is smaller than the diameter of the annular steel support 3.
A construction method of a vertical shaft annular steel support assembly comprises the following steps:
firstly, earth excavation is carried out in a construction site, steel bars of the fore shaft ring beam are bound, concrete is poured, and construction of the fore shaft ring beam 1 is completed. Continuing to excavate the earthwork downwards after the construction of the locking collar beam 1 is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of the first annular steel support 3, and binding a first section of well wall reinforcement cage; meanwhile, the first annular steel support 3 is assembled in an assembling field.
The locking collar beam 1 is arranged at a wellhead position, and at least two vertical sliding grooves 1a which are communicated up and down are reserved on the locking collar beam 1 along the circumferential direction. The annular steel support 3 is formed by connecting or welding a guide lug 3a and an arc block 3b through bolts, the whole annular steel support is annular, and the guide lug 3a corresponds to the vertical sliding groove 1a on the locking collar beam 1 one by one. The number of the vertical sliding chutes 1a is at least two, and preferably 3 or 4; accordingly, the number of the guide lugs 3a is also 3 or 4.
And secondly, the horizontal sliding rail 2 is in place, one end of the horizontal sliding rail 2 is connected to the assembly site, and the other end of the horizontal sliding rail is connected to the construction site. After the horizontal sliding rail 2 is in place, the assembled first annular steel support 3 is conveyed to the opening of a vertical shaft in a sliding mode along the horizontal sliding rail 2, the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, finally the horizontal sliding rail 2 is pulled out, the annular steel support 3 penetrates through the locking ring beam 1 and slides to the design position of the first annular steel support 3, the annular steel support 3 and the first section of well wall reinforcement cage are bound and fixed, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and when the annular steel support concrete is poured, a channel for the second annular steel support 3 to pass through is reserved.
Thirdly, when the second annular steel support 3 is assembled, excavating earthwork to the design position of the second annular steel support 3, binding a second section of well wall reinforcement cage, then placing the second annular steel support 3 to the design position of the second annular steel support 3 in the same mode as the first annular steel support 3 for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the annular steel support, and reserving a channel for the third annular steel support 3 to pass through when pouring the annular steel support concrete; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all the annular steel supports 3 equipped in the same vertical shaft have diameters and guide lugs 3a which are sequentially decreased from top to bottom along the vertical shaft, the specification size of the vertical sliding chute 1a is matched with the guide lugs 3a of the largest annular steel support 3, so that the annular steel supports 3 which are placed later can pass through the annular steel supports 3 which are placed first and fall to the designed position, and the pouring thickness of the well wall concrete is more than 50 cm.
The cautions in the construction process are as follows: (1) after each annular steel support is put down in place, binding and fixing are adopted, the annular steel support is required to be poured when concrete for each section of well wall is poured, and a channel for the next annular steel support to pass through is reserved; (2) when one annular steel support is placed, all the placed annular steel supports are fixed, and the placed annular steel supports fall to the designed position after penetrating through all the placed annular steel supports; (3) the diameters of all the annular steel supports and the guide lugs are sequentially reduced from top to bottom along the vertical shaft, and the specification size of the vertical sliding groove is matched with the guide lugs of the largest annular steel support.
The slip type annular steel support construction method is characterized in that on the basis of an original construction method, the assembling of annular steel supports is changed into the pre-assembling of an assembling site outside a vertical shaft, then the annular steel supports slide to the vertical shaft through a horizontal slide rail, and then the annular steel supports slide to a designed supporting position along the wall of the vertical shaft under the guiding action of a guide lug and a vertical slide groove to be fixed, so that the number of large-scale hoisting machinery of the annular steel supports is reduced, the safety risk is reduced, the quality and the size precision of annular steel support components can be guaranteed due to the pre-assembling, the time for influencing earth excavation due to the assembling of a construction site operation surface is shortened, the earth excavation and the assembling of the annular steel supports can be simultaneously carried out, and.

Claims (3)

1. The construction method of the annular steel support component of the vertical shaft is characterized by comprising the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam (1), continuing to excavate the earthwork downwards after the construction of the locking collar beam (1) is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support (3), and binding a first section of well wall reinforcement cage; meanwhile, assembling the first annular steel support (3) in an assembling field;
the locking collar beam (1) is arranged at a wellhead position, and at least two vertical sliding grooves (1a) which are communicated up and down are reserved on the locking collar beam (1) along the circumferential direction; the annular steel support (3) is formed by connecting or welding a guide lug (3a) and an arc-shaped block (3b) through bolts, the whole annular steel support is annular, and the guide lugs (3a) correspond to the vertical sliding grooves (1a) on the fore shaft ring beam (1) one by one;
secondly, after the horizontal sliding rail (2) is in place, the assembled first annular steel support (3) is conveyed to the opening of a vertical shaft in a sliding mode along the horizontal sliding rail (2), then the guide lugs (3a) are aligned with the vertical sliding grooves (1a) one by one, finally the horizontal sliding rail (2) is pulled out, the annular steel support (3) penetrates through the locking ring beam (1) and slides to the design position of the first annular steel support (3), the annular steel support (3) is bound and fixed with the first section of well wall reinforcement cage, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and a channel for the second annular steel support (3) to pass through is reserved when concrete of the annular steel support is poured;
thirdly, when the second annular steel support (3) is assembled, excavating earthwork to the design position of the second annular steel support (3), binding a second section of well wall reinforcement cage, then placing the second annular steel support (3) to the design position of the second annular steel support (3) in the same mode of the first annular steel support (3) for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the annular steel support, and reserving a channel for the third annular steel support (3) to pass through when pouring concrete of the annular steel support; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all annular steel supports (3) that same shaft was equipped with, its diameter and direction lug (3a) decrease progressively from top to bottom in proper order along the shaft, the specification size of vertical spout (1a) matches with direction lug (3a) of the biggest annular steel support (3) to ensure that annular steel support (3) of transferring afterwards can pass annular steel support (3) of transferring earlier and fall to the design position, and the pouring thickness of wall of a well concrete is greater than 50 cm.
2. The method for constructing a shaft ring-shaped steel support assembly according to claim 1, wherein: the number of the guide lugs (3a) and the number of the arc-shaped blocks (3b) are four respectively, and every two arc-shaped blocks (3b) are spliced through the guide lugs (3 a).
3. The method for constructing a shaft ring-shaped steel support assembly according to claim 1, wherein: the horizontal slide rail (2) comprises two slide rail bars which are arranged in parallel at intervals.
CN201911194832.0A 2019-11-28 2019-11-28 Vertical shaft annular steel support assembly and construction method Active CN110985000B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911194832.0A CN110985000B (en) 2019-11-28 2019-11-28 Vertical shaft annular steel support assembly and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911194832.0A CN110985000B (en) 2019-11-28 2019-11-28 Vertical shaft annular steel support assembly and construction method

Publications (2)

Publication Number Publication Date
CN110985000A CN110985000A (en) 2020-04-10
CN110985000B true CN110985000B (en) 2021-06-15

Family

ID=70087884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911194832.0A Active CN110985000B (en) 2019-11-28 2019-11-28 Vertical shaft annular steel support assembly and construction method

Country Status (1)

Country Link
CN (1) CN110985000B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627509B (en) * 2020-12-11 2022-04-22 中国核工业第二二建设有限公司 Assembly type wedge-shaped inner support device for shaft-shaped steel-clad concrete wall and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1178899A1 (en) * 1982-05-14 1985-09-15 Novik Evgenij B Arrangement for working bearing hitches in mine shafts
JP4448152B2 (en) * 2007-03-12 2010-04-07 村本建設株式会社 Curing fence device for opening
CN204646240U (en) * 2015-05-26 2015-09-16 中国电建集团中南勘测设计研究院有限公司 Underground shaft supporting and protection structure in a kind of loose media
CN207700185U (en) * 2017-12-04 2018-08-07 辽河石油勘探局 A kind of retaining wall device for manual hole digging pile
CN207891895U (en) * 2017-12-22 2018-09-21 武汉市市政建设集团有限公司 Walkway shaft excavation supporting construction
CN208586606U (en) * 2018-07-09 2019-03-08 保利新联***工程集团有限公司 A kind of retaining wall device for manual hole digging pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1178899A1 (en) * 1982-05-14 1985-09-15 Novik Evgenij B Arrangement for working bearing hitches in mine shafts
JP4448152B2 (en) * 2007-03-12 2010-04-07 村本建設株式会社 Curing fence device for opening
CN204646240U (en) * 2015-05-26 2015-09-16 中国电建集团中南勘测设计研究院有限公司 Underground shaft supporting and protection structure in a kind of loose media
CN207700185U (en) * 2017-12-04 2018-08-07 辽河石油勘探局 A kind of retaining wall device for manual hole digging pile
CN207891895U (en) * 2017-12-22 2018-09-21 武汉市市政建设集团有限公司 Walkway shaft excavation supporting construction
CN208586606U (en) * 2018-07-09 2019-03-08 保利新联***工程集团有限公司 A kind of retaining wall device for manual hole digging pile

Also Published As

Publication number Publication date
CN110985000A (en) 2020-04-10

Similar Documents

Publication Publication Date Title
CN102704939B (en) Combined steel temporary supporting excavation method for tunnel with extra-large section
CN101864963B (en) Large-section loess tunnel construction method
CN105178968B (en) Rock tunnel(ling) machine pushing tow support meanss and construction method
CN110344846B (en) Three-step reserved core soil belt inverted arch one-step excavation method
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN110761797B (en) Construction method for shield air-pushing through mine tunnel
CN109630126A (en) A kind of rotary shaft excavation machine of sinking method
CN110242305B (en) Construction process method for constructing main tunnel by inclined shaft entering single side wall pit guiding method
CN101545376A (en) Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally
CN109505609A (en) Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery
CN104975606B (en) Method for handling high-low strides at adjacent parts of reverse building foundation pit and adjacent foundation pit
CN110985000B (en) Vertical shaft annular steel support assembly and construction method
CN110230495A (en) A kind of subway station double -side approach construction Core Soil excavation method
CN103953355A (en) Receiving construction method in slurry shield tunnel
CN110952985B (en) Sliding type vertical shaft annular steel support assembly and construction method
CN108915714A (en) The double TBM installation methods in one hole
CN108643193A (en) A kind of pattern foundation pit supporting structure prestress anchorage cable Drilling draw out method
EP0887512B1 (en) Method for widening road, superhighway or railway tunnels, without interrupting the traffic
KR100902083B1 (en) System of casting a wall contruction and descending the same into teh groudnd, and a driving apparatus for stepwise descending the wall construction into teh groudnd
CN103334778A (en) Construction technology of step temporary support and partial double side walls
CN105673034A (en) Split starting shield tunneling machine and temporary deslagging system
CN105350575A (en) Reverse construction method for underground continuous wall
CN116591691A (en) Construction method of rectangular pipe pushing jack for improving construction precision
CN104047607A (en) Construction method for lifting out shield tunneling machine under condition of envelop enclosure
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 214104 room 301-218, block a, Xidong chuangrong building, No. 78, Danshan Road, anzhen street, Xishan District, Wuxi City, Jiangsu Province

Patentee after: Jiangsu CRRC Urban Development Co.,Ltd.

Patentee after: CRRC Construction Engineering Co., Ltd

Address before: 215000 NO.115 Yinsheng Road, Shengpu Town, Suzhou Industrial Park, Jiangsu Province

Patentee before: SUZHOU CHINA VEHICLE CONSTRUCTION ENGINEERING Co.,Ltd.

Patentee before: CRRC Construction Engineering Co., Ltd