CN110952985B - Sliding type vertical shaft annular steel support assembly and construction method - Google Patents

Sliding type vertical shaft annular steel support assembly and construction method Download PDF

Info

Publication number
CN110952985B
CN110952985B CN201911194827.XA CN201911194827A CN110952985B CN 110952985 B CN110952985 B CN 110952985B CN 201911194827 A CN201911194827 A CN 201911194827A CN 110952985 B CN110952985 B CN 110952985B
Authority
CN
China
Prior art keywords
annular steel
steel support
vertical
shaft
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911194827.XA
Other languages
Chinese (zh)
Other versions
CN110952985A (en
Inventor
张川
郭玉山
刘小荣
陈郁平
朱国鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Construction Engineering Co Ltd
Jiangsu CRRC Urban Development Co Ltd
Original Assignee
Suzhou CRRC Construction Engineering Co Ltd
CRRC Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou CRRC Construction Engineering Co Ltd, CRRC Construction Engineering Co Ltd filed Critical Suzhou CRRC Construction Engineering Co Ltd
Priority to CN201911194827.XA priority Critical patent/CN110952985B/en
Publication of CN110952985A publication Critical patent/CN110952985A/en
Application granted granted Critical
Publication of CN110952985B publication Critical patent/CN110952985B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/11Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft
    • E21D7/02Arrangement of guides for cages in shafts; Connection of guides for cages to shaft walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Wood Science & Technology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a sliding type annular steel support assembly for a vertical shaft, which comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in the vertical shaft; after the annular steel support is formed outside the vertical shaft, the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail in a sliding mode, after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled out of the horizontal sliding rail, and the annular steel support can penetrate through the locking collar beam and slide to the position of a well wall reinforcing steel bar to be bound and fixed. Meanwhile, the invention also discloses a construction method of the sliding type vertical shaft annular steel support component. The method has the characteristics of safety, reliability, high construction progress, high construction quality and low cost.

Description

Sliding type vertical shaft annular steel support assembly and construction method
Technical Field
The invention relates to the technical field of tunnel vertical shaft construction, in particular to a sliding type vertical shaft annular steel supporting assembly and a construction method thereof.
Background
At present, an annular steel support used for shaft excavation mainly adopts large machinery to hoist a steel member to a foundation pit operation surface, and field assembling and welding are carried out in a shaft. There are major problems: large-scale mechanical hoisting operation and on-site assembling and welding in a vertical shaft have large safety risk; the vertical shaft is assembled, the operation environment is complex, the consistency of products of all annular steel supports is poor, the construction speed is slow, the construction quality is not easy to control, and the construction cost is relatively high; when assembling in the well, next earthwork excavation can not be carried out, and the construction progress is influenced.
Disclosure of Invention
The invention aims to provide a sliding type vertical shaft annular steel supporting component which is safe and reliable, quick in construction progress, high in construction quality and low in cost.
Therefore, the technical scheme adopted by the invention is as follows: a sliding type shaft annular steel support assembly comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in a shaft, the fore shaft ring beam is arranged at a well mouth position, the well wall steel bar is bound below the fore shaft ring beam, a horizontal sliding rail is arranged outside the shaft, at least two vertical sliding grooves which are communicated up and down are reserved on the fore shaft ring beam along the circumferential direction, and each annular steel support is provided with a guide lug which corresponds to the vertical sliding grooves on the fore shaft ring beam one to one; after the annular steel support is formed outside the vertical shaft, the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail in a sliding mode, after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled out of the horizontal sliding rail, and the annular steel support can penetrate through the locking collar beam and slide to the position of a well wall reinforcing steel bar to be bound and fixed.
Preferably, an assembling field is arranged outside the vertical shaft, and the annular steel support is formed by connecting or welding the guide lugs and the arc-shaped blocks on the assembling field through bolts.
Preferably, the number of the guide lugs and the number of the arc-shaped blocks are four, and every two arc-shaped blocks are spliced through the guide lugs.
More preferably, the horizontal slide rail comprises two slide rail bars which are arranged in parallel at intervals from left to right.
Meanwhile, the invention also provides a construction method of the sliding type vertical shaft annular steel support component, which comprises the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam, continuing to excavate the earthwork downwards after the construction of the locking collar beam is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support, and binding a first section of well wall steel reinforcement cage; meanwhile, assembling the first annular steel support in an assembling site;
the locking collar beam is arranged at a wellhead position, and at least two vertical sliding grooves which are communicated up and down are reserved on the locking collar beam along the circumferential direction; the annular steel support is formed by connecting or welding a guide lug and an arc-shaped block through a bolt, the whole annular steel support is annular, and the guide lug corresponds to the vertical sliding groove on the locking collar beam one by one;
secondly, after the horizontal slide rail is in place, the assembled first annular steel support is conveyed to the opening of the vertical shaft in a sliding mode along the horizontal slide rail, the guide lugs are aligned with the vertical slide grooves one by one, finally the horizontal slide rail is pulled out, the annular steel support penetrates through the locking collar beam and slides to the designed position of the first annular steel support, the annular steel support and the first section of well wall reinforcement cage are bound and fixed temporarily, and concrete pouring of the first section of well wall reinforcement cage is carried out;
thirdly, when a second annular steel support is assembled, excavating the earthwork to the design position of the second annular steel support, binding a second section of well wall reinforcement cage, moving the annular steel support in the vertical well downwards to the design position of the next annular steel support, temporarily binding and fixing, sliding the second annular steel support assembled outside the well to the opening of the vertical well through a horizontal sliding rail, and then falling to the design position of the first annular steel support for binding and fixing to finish the concrete pouring of the second section of well wall reinforcement cage; and analogizing until the concrete of the well wall reinforcement cage of all sections is poured, finally binding and fixing all the annular steel supports, and pouring all the annular steel supports.
The invention has the beneficial effects that:
(1) the steel members are not required to be hoisted by large machinery, and the assembled annular steel supports are conveyed to the opening of the vertical shaft by adopting a simple and safe horizontal sliding rail, so that the method is safe and reliable, and the construction cost is reduced;
(2) the annular steel supports are assembled outside the vertical shaft, and field assembling and welding are not needed in the vertical shaft, so that the safety risk of operation is further reduced; the shaft is assembled outside, so that the consistency of the product is easy to control;
(3) when the annular steel supports are assembled outside the vertical shaft, earth excavation and steel bar binding in the shaft are carried out, and the construction speed is accelerated and the construction period is shortened by the mode of synchronous construction outside the shaft in the shaft.
Drawings
FIG. 1 is a top view of the present invention.
Fig. 2 is a simplified perspective view of the invention.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
referring to fig. 1 and 2, the sliding type annular steel support assembly for the shaft mainly comprises a locking collar beam 1, shaft wall reinforcing steel bars (not shown in the figure), an annular steel support 3, horizontal sliding rails 2 and the like.
The locking collar beam 1, the well wall reinforcing steel bars and the annular steel supports 3 are arranged in the shaft, the annular steel supports 3 are assembled outside the shaft, and then are conveyed to the position of a well mouth in a sliding mode through the horizontal sliding rails 2.
The fore shaft collar tie beam 1 is arranged at a well mouth position, the fore shaft collar tie beam 1 is composed of bound fore shaft collar tie beam reinforcing steel bars and poured concrete, and the fore shaft collar tie beam 1 is used for ensuring the strength of the well mouth position. And the well wall reinforcing steel bars are bound below the locking collar beam 1, and concrete also needs to be poured for ensuring the strength of the well wall.
At least two vertical sliding grooves 1a which are communicated up and down are reserved on the fore shaft ring beam 1 along the circumferential direction, and each annular steel support 3 is provided with a guide lug 3a which is in one-to-one correspondence with the vertical sliding grooves 1a on the fore shaft ring beam 1. And a horizontal sliding rail 2 is arranged outside the shaft.
The annular steel support 3 can be conveyed to the opening part of the vertical shaft along the horizontal sliding rail 2 after being formed in an assembling field outside the vertical shaft. After the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, the horizontal sliding rails 2 are pulled away, and the annular steel supports 3 can penetrate through the locking collar beams 1 and slide to the position of the well wall reinforcing steel bar for binding and fixing. The wall of a well guarantees intensity jointly through wall of a well ligature reinforcing bar and a plurality of annular steel shotcrete 3 that the interval set up from top to bottom, ligatures the wall of a well reinforcing bar earlier, slides down behind the design position with every annular steel shotcrete 3 again, respectively with wall of a well reinforcing bar ligature fixed back together, carries out concrete placement at last.
An assembling field is arranged outside the vertical shaft, and the annular steel support 3 is formed by connecting or welding the guide lugs 3a and the arc blocks 3b through bolts in the assembling field. Of course, the method is not limited to the assembly mode, and the method can also be integrally formed. The horizontal sliding rail 2 is used as a rail for sliding the assembled annular steel support 3 to the position of a wellhead.
The number of the guide lugs 3a and the number of the arc-shaped blocks 3b are four, and every two arc-shaped blocks 3b are spliced through the guide lugs 3 a. But is not limited to four, and may be three or more. The horizontal sliding rail 2 comprises two sliding rail bars which are arranged in parallel at intervals left and right, and the distance between the two sliding rail bars is larger than the diameter of the annular steel support 3.
A construction method of a sliding type vertical shaft annular steel support assembly comprises the following steps:
firstly, earth excavation is carried out in a construction site, steel bars of the fore shaft ring beam are bound, concrete is poured, and construction of the fore shaft ring beam 1 is completed. Continuing to excavate the earthwork downwards after the construction of the locking collar beam 1 is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of the first annular steel support 3, and binding a first section of well wall reinforcement cage; meanwhile, the first annular steel support 3 is assembled in an assembling field.
The locking collar beam 1 is arranged at a wellhead position, and at least two vertical sliding grooves 1a which are communicated up and down are reserved on the locking collar beam 1 along the circumferential direction. The annular steel support 3 is formed by connecting or welding a guide lug 3a and an arc block 3b through bolts, the whole annular steel support is annular, and the guide lug 3a corresponds to the vertical sliding groove 1a on the locking collar beam 1 one by one. The number of the vertical sliding chutes 1a is at least two, and preferably 3 or 4; accordingly, the number of the guide lugs 3a is also 3 or 4.
And secondly, the horizontal sliding rail 2 is in place, one end of the horizontal sliding rail 2 is connected to the assembly site, and the other end of the horizontal sliding rail is connected to the construction site. After the horizontal sliding rail 2 is in place, the assembled first annular steel support 3 is conveyed to the opening of the vertical shaft in a sliding mode along the horizontal sliding rail 2, the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, finally the horizontal sliding rail 2 is pulled out, the annular steel support 3 penetrates through the locking collar beam 1 and slides to the design position of the first annular steel support 3, the annular steel support 3 and the first section of well wall reinforcement cage are bound and fixed temporarily, and concrete pouring of the first section of well wall reinforcement cage is carried out. The first annular steel support 3 is fixed by temporary binding, and on one hand, the first annular steel support plays a role in supporting and reinforcing a well wall reinforcement cage during pouring; on the other hand, the steel support is convenient to fall to the design position of the next annular steel support 3 again so as to vacate the design position of the first annular steel support 3 for other annular steel supports 3 to occupy.
Thirdly, when the second annular steel support 3 is assembled, excavating earth to the design position of the second annular steel support 3, and binding a second section of well wall reinforcement cage; and then the annular steel support 3 in the shaft is moved downwards to the design position of the next annular steel support 3 and is temporarily bound and fixed. And (3) sliding and conveying the second annular steel support 3 assembled outside the well to the opening part of the vertical shaft through the horizontal sliding rail 2, and then falling to the designed position of the first annular steel support 3 for binding and fixing to complete the concrete pouring of the second section of well wall reinforcement cage. And analogizing until the concrete of the well wall reinforcement cage of all sections is poured, finally binding and fixing all the annular steel supports 3, and pouring all the annular steel supports 3. Before each annular steel support 3 is placed, the annular steel supports 3 which are placed are all moved downwards one position in sequence.
The cautions in the construction process are as follows: (1) after each annular steel support is put down in place, temporary binding and fixing are adopted, concrete of each section of well wall is poured without pouring the annular steel support, and finally secondary pouring is carried out after all the annular steel supports are bound and fixed; (2) when one annular steel support is placed, all the placed annular steel supports are sequentially moved downwards one position; (3) all the annular steel supports are consistent in size and specification.
The slip type annular steel support construction method is characterized in that on the basis of an original construction method, the assembling of annular steel supports is changed into the pre-assembling of an assembling site outside a vertical shaft, then the annular steel supports slide to the vertical shaft through a horizontal slide rail, and then the annular steel supports slide to a designed supporting position along the wall of the vertical shaft under the guiding action of a guide lug and a vertical slide groove to be fixed, so that the number of large-scale hoisting machinery of the annular steel supports is reduced, the safety risk is reduced, the quality and the size precision of annular steel support components can be guaranteed due to the pre-assembling, the time for influencing earth excavation due to the assembling of a construction site operation surface is shortened, the earth excavation and the assembling of the annular steel supports can be simultaneously carried out, and the construction period can be shortened.

Claims (5)

1. The utility model provides a sliding shaft annular steel supporting component, is including setting up fore shaft circle roof beam (1), wall of a well reinforcing bar and annular steel shotcrete (3) in the shaft, fore shaft circle roof beam (1) sets up in well head position department, and the wall of a well reinforcing bar ligature is in fore shaft circle roof beam (1) below, its characterized in that: a horizontal sliding rail (2) is arranged outside the vertical shaft, at least two vertical sliding grooves (1a) which are communicated up and down are reserved on the fore shaft ring beam (1) along the circumferential direction, and each annular steel support (3) is provided with guide lugs (3a) which are in one-to-one correspondence with the vertical sliding grooves (1a) on the fore shaft ring beam (1); annular steel shotcrete (3) can follow horizontal slide rail (2) and slide and send to the shaft mouth portion outside the shaft shaping back, after direction lug (3a) and vertical spout (1a) are aimed at one by one, takes out horizontal slide rail (2), and annular steel shotcrete (3) can pass fore shaft collar tie beam (1) landing to wall of a well reinforcing bar position department and carry out the ligature fixed.
2. The slip type vertical ring steel support assembly of claim 1, wherein: an assembling field is arranged outside the vertical shaft, and the annular steel support (3) is formed by connecting or welding a guide lug (3a) and an arc-shaped block (3b) on the assembling field through bolts.
3. The slip type vertical ring steel support assembly of claim 2, wherein: the number of the guide lugs (3a) and the number of the arc-shaped blocks (3b) are four respectively, and every two arc-shaped blocks (3b) are spliced through the guide lugs (3 a).
4. The slip type vertical ring steel support assembly of claim 1, wherein: the horizontal slide rail (2) comprises two slide rail bars which are arranged in parallel at intervals.
5. The construction method of the sliding type vertical shaft annular steel support component is characterized by comprising the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam (1), continuing to excavate the earthwork downwards after the construction of the locking collar beam (1) is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support (3), and binding a first section of well wall reinforcement cage; meanwhile, assembling the first annular steel support (3) in an assembling field;
the locking collar beam (1) is arranged at a wellhead position, and at least two vertical sliding grooves (1a) which are communicated up and down are reserved on the locking collar beam (1) along the circumferential direction; the annular steel support (3) is formed by connecting or welding a guide lug (3a) and an arc-shaped block (3b) through bolts, the whole annular steel support is annular, and the guide lugs (3a) correspond to the vertical sliding grooves (1a) on the fore shaft ring beam (1) one by one;
secondly, after the horizontal sliding rail (2) is in place, the assembled first annular steel support (3) is conveyed to the opening of a vertical shaft in a sliding mode along the horizontal sliding rail (2), then the guide lugs (3a) are aligned with the vertical sliding grooves (1a) one by one, finally the horizontal sliding rail (2) is pulled out, the annular steel support (3) penetrates through the locking collar beam (1) and slides to the design position of the first annular steel support (3), the annular steel support (3) and a first section of well wall reinforcement cage are temporarily bound and fixed, and concrete pouring of the first section of well wall reinforcement cage is carried out;
thirdly, when a second annular steel support (3) is assembled, excavating earth to the design position of the second annular steel support (3), binding a second section of well wall reinforcement cage, moving the annular steel support (3) in the vertical well downwards to the design position of the next annular steel support (3), temporarily binding and fixing, sliding the second annular steel support (3) assembled outside the well to the opening of the vertical well through a horizontal sliding rail (2), and then falling to the design position of the first annular steel support (3) for binding and fixing to finish the concrete pouring of the second section of well wall reinforcement cage; and analogizing until the concrete of the well wall reinforcement cage of all sections is poured, finally binding and fixing all the annular steel supports (3), and pouring all the annular steel supports (3).
CN201911194827.XA 2019-11-28 2019-11-28 Sliding type vertical shaft annular steel support assembly and construction method Active CN110952985B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911194827.XA CN110952985B (en) 2019-11-28 2019-11-28 Sliding type vertical shaft annular steel support assembly and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911194827.XA CN110952985B (en) 2019-11-28 2019-11-28 Sliding type vertical shaft annular steel support assembly and construction method

Publications (2)

Publication Number Publication Date
CN110952985A CN110952985A (en) 2020-04-03
CN110952985B true CN110952985B (en) 2021-10-26

Family

ID=69978845

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911194827.XA Active CN110952985B (en) 2019-11-28 2019-11-28 Sliding type vertical shaft annular steel support assembly and construction method

Country Status (1)

Country Link
CN (1) CN110952985B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794249B (en) * 2020-07-20 2022-03-15 中国铁建重工集团股份有限公司 Construction method of shaft locking structure and shaft locking structure

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101363224A (en) * 2008-09-05 2009-02-11 上海隧道工程股份有限公司 Movable foundation pit support system and construction method
CN103628883A (en) * 2013-12-18 2014-03-12 中铁隧道集团二处有限公司 Non-bracket overlong steel bar binding mobile molding method of deep-narrow vertical shaft
CN105240018A (en) * 2015-10-30 2016-01-13 中铁上海工程局集团有限公司 Vertical shaft construction device and method
CN108203981A (en) * 2018-01-18 2018-06-26 上海隧道工程有限公司 It is used to install the system and method for bracing members in cap excavation method
CN207700185U (en) * 2017-12-04 2018-08-07 辽河石油勘探局 A kind of retaining wall device for manual hole digging pile
CN207891895U (en) * 2017-12-22 2018-09-21 武汉市市政建设集团有限公司 Walkway shaft excavation supporting construction
CN109183807A (en) * 2018-09-17 2019-01-11 江苏东合南岩土科技股份有限公司 Removable bracing members and its construction method
CN208379600U (en) * 2018-04-25 2019-01-15 广东省基础工程集团有限公司 A kind of slip steel supporting system
CN208816844U (en) * 2018-09-17 2019-05-03 中国石油天然气集团公司 A kind of underground water seal cave depot Shaft bank pipe-supporting device
CN208917831U (en) * 2018-07-16 2019-05-31 中铁二十五局集团第二工程有限公司 A kind of pile foundation breast wall structure
CN106400799B (en) * 2016-11-10 2019-06-18 中国电建集团华东勘测设计研究院有限公司 A kind of cast-in-place dado structure and construction method for artificial digging pile
CN110043264A (en) * 2019-05-17 2019-07-23 中铁第六勘察设计院集团有限公司 A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN110439004A (en) * 2019-08-29 2019-11-12 哈尔滨工大建研工程咨询有限公司 A kind of the packaged type inner supporting device and its application method of pattern foundation pit supporting structure
CN110485430A (en) * 2019-07-24 2019-11-22 青岛理工大学 A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3578850B2 (en) * 1995-10-27 2004-10-20 大豊建設株式会社 Drilling rigs for building shafts or foundations for structures

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101363224A (en) * 2008-09-05 2009-02-11 上海隧道工程股份有限公司 Movable foundation pit support system and construction method
CN103628883A (en) * 2013-12-18 2014-03-12 中铁隧道集团二处有限公司 Non-bracket overlong steel bar binding mobile molding method of deep-narrow vertical shaft
CN105240018A (en) * 2015-10-30 2016-01-13 中铁上海工程局集团有限公司 Vertical shaft construction device and method
CN106400799B (en) * 2016-11-10 2019-06-18 中国电建集团华东勘测设计研究院有限公司 A kind of cast-in-place dado structure and construction method for artificial digging pile
CN207700185U (en) * 2017-12-04 2018-08-07 辽河石油勘探局 A kind of retaining wall device for manual hole digging pile
CN207891895U (en) * 2017-12-22 2018-09-21 武汉市市政建设集团有限公司 Walkway shaft excavation supporting construction
CN108203981A (en) * 2018-01-18 2018-06-26 上海隧道工程有限公司 It is used to install the system and method for bracing members in cap excavation method
CN208379600U (en) * 2018-04-25 2019-01-15 广东省基础工程集团有限公司 A kind of slip steel supporting system
CN208917831U (en) * 2018-07-16 2019-05-31 中铁二十五局集团第二工程有限公司 A kind of pile foundation breast wall structure
CN208816844U (en) * 2018-09-17 2019-05-03 中国石油天然气集团公司 A kind of underground water seal cave depot Shaft bank pipe-supporting device
CN109183807A (en) * 2018-09-17 2019-01-11 江苏东合南岩土科技股份有限公司 Removable bracing members and its construction method
CN110043264A (en) * 2019-05-17 2019-07-23 中铁第六勘察设计院集团有限公司 A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN110485430A (en) * 2019-07-24 2019-11-22 青岛理工大学 A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall
CN110439004A (en) * 2019-08-29 2019-11-12 哈尔滨工大建研工程咨询有限公司 A kind of the packaged type inner supporting device and its application method of pattern foundation pit supporting structure

Also Published As

Publication number Publication date
CN110952985A (en) 2020-04-03

Similar Documents

Publication Publication Date Title
CN102704939B (en) Combined steel temporary supporting excavation method for tunnel with extra-large section
CN101864963A (en) Large-section loess tunnel construction method
CN110424969B (en) Construction method for open cut method station with tunnel before station
CN110344846B (en) Three-step reserved core soil belt inverted arch one-step excavation method
CN103470272B (en) A kind of chassis for the multiple section concrete construction of Mining Method and construction method thereof
CN105178968B (en) Rock tunnel(ling) machine pushing tow support meanss and construction method
CN110761797B (en) Construction method for shield air-pushing through mine tunnel
CN104653229A (en) Shielding sliding shoe curvilinear pushing-up hole-passing construction method
CN105604581A (en) Hoisting and rotating type installation equipment of tunnel ditch cable groove combination template and construction method of hoisting and rotating type installation equipment
CN109505609A (en) Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery
CN107269299A (en) Constructing tunnel integrates chassis
CN110952985B (en) Sliding type vertical shaft annular steel support assembly and construction method
CN109441494A (en) Excavating load double track tunnel gantry type pipe sheet assembling device and method
CN206529708U (en) Hanging Basket running gear
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN110778320A (en) Synchronous excavation supporting construction method for three-step inverted arch of weak surrounding rock tunnel
CN110230495A (en) A kind of subway station double -side approach construction Core Soil excavation method
CN103953355A (en) Method of acceptance construction in slurry shield tunnel
CN110985000B (en) Vertical shaft annular steel support assembly and construction method
CN108915714A (en) The double TBM installation methods in one hole
CN110439574A (en) It is originated for shield lateral translation and the tunnel structure and construction method of haul of slagging tap
CN102777186B (en) Full-hydraulic self-moving type template device of vertical shaft wall
CN203499697U (en) Trolley used for concrete construction of various cross sections through mining method
KR100902083B1 (en) System of casting a wall contruction and descending the same into teh groudnd, and a driving apparatus for stepwise descending the wall construction into teh groudnd
CN103334778A (en) Construction technology of step temporary support and partial double side walls

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 214104 room 301-218, block a, Xidong chuangrong building, No. 78, Danshan Road, anzhen street, Xishan District, Wuxi City, Jiangsu Province

Patentee after: Jiangsu CRRC Urban Development Co.,Ltd.

Patentee after: CRRC CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 215000 NO.115 Yinsheng Road, Shengpu Town, Suzhou Industrial Park, Jiangsu Province

Patentee before: SUZHOU CHINA VEHICLE CONSTRUCTION ENGINEERING Co.,Ltd.

Patentee before: CRRC CONSTRUCTION ENGINEERING Co.,Ltd.

CP03 Change of name, title or address