CN110985000A - Vertical shaft annular steel support assembly and construction method - Google Patents
Vertical shaft annular steel support assembly and construction method Download PDFInfo
- Publication number
- CN110985000A CN110985000A CN201911194832.0A CN201911194832A CN110985000A CN 110985000 A CN110985000 A CN 110985000A CN 201911194832 A CN201911194832 A CN 201911194832A CN 110985000 A CN110985000 A CN 110985000A
- Authority
- CN
- China
- Prior art keywords
- annular steel
- steel support
- shaft
- vertical
- annular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 155
- 239000010959 steel Substances 0.000 title claims abstract description 155
- 238000010276 construction Methods 0.000 title claims abstract description 34
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 8
- 239000004567 concrete Substances 0.000 claims description 25
- 230000002787 reinforcement Effects 0.000 claims description 18
- 238000009412 basement excavation Methods 0.000 claims description 11
- 238000003466 welding Methods 0.000 claims description 9
- 230000003014 reinforcing effect Effects 0.000 claims description 5
- 239000011378 shotcrete Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 5
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/11—Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/12—Accessories for making shaft linings, e.g. suspended cradles, shutterings
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Wood Science & Technology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a shaft annular steel support assembly, which comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in a shaft, the fore shaft ring beam is arranged at a well mouth position, the well wall steel bar is bound below the fore shaft ring beam, a horizontal sliding rail is arranged outside the shaft, at least two vertical sliding grooves which are communicated up and down are reserved on the fore shaft ring beam along the circumferential direction, and each annular steel support is provided with a guide lug which corresponds to the vertical sliding grooves on the fore shaft ring beam one by one; after the annular steel support is formed outside the vertical shaft, the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail in a sliding mode, after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled out of the horizontal sliding rail, and the annular steel support can penetrate through the locking collar beam and slide to the position of a well wall reinforcing steel bar to be bound and fixed. Meanwhile, the invention also discloses a construction method of the vertical shaft annular steel support component. The method has the characteristics of safety, reliability, high construction progress, high construction quality and low cost.
Description
Technical Field
The invention relates to the technical field of tunnel vertical shaft construction, in particular to a vertical shaft annular steel support component and a construction method thereof.
Background
At present, an annular steel support used for shaft excavation mainly adopts large machinery to hoist a steel member to a foundation pit operation surface, and field assembling and welding are carried out in a shaft. There are major problems: large-scale mechanical hoisting operation and on-site assembling and welding in a vertical shaft have large safety risk; the vertical shaft is assembled, the operation environment is complex, the consistency of products of all annular steel supports is poor, the construction speed is slow, the construction quality is not easy to control, and the construction cost is relatively high; when assembling in the well, next earthwork excavation can not be carried out, and the construction progress is influenced.
Disclosure of Invention
The invention aims to provide the annular steel supporting component for the vertical shaft, which is safe and reliable, has quick construction progress, high construction quality and low cost.
Therefore, the technical scheme adopted by the invention is as follows: a shaft annular steel support assembly comprises a fore shaft ring beam, a well wall steel bar and annular steel supports, wherein the fore shaft ring beam, the well wall steel bar and the annular steel supports are arranged in a shaft, the fore shaft ring beam is arranged at a position of a well head, the well wall steel bar is bound below the fore shaft ring beam, a horizontal sliding rail is arranged outside the shaft, at least two vertical sliding grooves which are communicated up and down are reserved on the fore shaft ring beam along the circumferential direction, and each annular steel support is provided with a guide lug which is in one-to-one correspondence with the vertical sliding grooves on the fore shaft ring beam; the annular steel support can be conveyed to the opening of the vertical shaft along the horizontal sliding rail after being molded outside the vertical shaft, and after the guide lugs are aligned with the vertical sliding grooves one by one, the annular steel support is pulled away from the horizontal sliding rail and can pass through the locking collar beam to slide to the position of a well wall reinforcing steel bar for binding and fixing; an assembling field is arranged outside the vertical shaft, and the annular steel support is formed by connecting or welding a guide lug and an arc-shaped block in the assembling field through a bolt;
the diameters of all the annular steel supports arranged in the same vertical shaft and the guide lugs are sequentially reduced from top to bottom along the vertical shaft, and the specification size of the vertical sliding groove is matched with the guide lugs of the largest annular steel support.
Preferably, the number of the guide lugs and the number of the arc-shaped blocks are four, and every two arc-shaped blocks are spliced through the guide lugs.
More preferably, the horizontal slide rail comprises two slide rail bars which are arranged in parallel at intervals from left to right.
Meanwhile, the invention also provides a construction method of the vertical shaft annular steel support component, which comprises the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam, continuing to excavate the earthwork downwards after the construction of the locking collar beam is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support, and binding a first section of well wall steel reinforcement cage; meanwhile, assembling the first annular steel support in an assembling site;
the locking collar beam is arranged at a wellhead position, and at least two vertical sliding grooves which are communicated up and down are reserved on the locking collar beam along the circumferential direction; the annular steel support is formed by connecting or welding a guide lug and an arc-shaped block through a bolt, the whole annular steel support is annular, and the guide lug corresponds to the vertical sliding groove on the locking collar beam one by one;
secondly, after the horizontal slide rail is in place, the assembled first annular steel support is conveyed to the opening of the vertical shaft in a sliding mode along the horizontal slide rail, the guide lugs are aligned with the vertical slide grooves one by one, finally the horizontal slide rail is pulled out, the annular steel support penetrates through the locking collar beam and slides to the designed position of the first annular steel support, the annular steel support and the first section of well wall reinforcement cage are bound and fixed, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and a channel for the second annular steel support to pass through is reserved when concrete of the annular steel support is poured;
thirdly, when the second annular steel support is assembled, excavating earthwork to the design position of the second annular steel support, binding a second section of well wall reinforcement cage, then placing the second annular steel support at the design position of the second annular steel support in the same mode as the first annular steel support for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the second annular steel support, and reserving a channel for the third annular steel support to pass through when pouring concrete of the annular steel support; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all annular steel supports that same shaft was equipped with, its diameter and direction lug decrease progressively from top to bottom along the shaft in proper order, the specification size of vertical spout matches with the direction lug of the biggest annular steel support to ensure that the annular steel support of transferring afterwards can pass the annular steel support of transferring earlier and fall to the design position, and the thickness of pouring of wall of a well concrete is greater than 50 cm.
The invention has the beneficial effects that:
(1) the steel members are not required to be hoisted by large machinery, and the assembled annular steel supports are conveyed to the opening of the vertical shaft by adopting a simple and safe horizontal sliding rail, so that the method is safe and reliable, and the construction cost is reduced;
(2) the annular steel supports are assembled outside the vertical shaft, and field assembling and welding are not needed in the vertical shaft, so that the safety risk of operation is further reduced; the shaft is assembled outside, so that the consistency of the product is easy to control;
(3) when the annular steel supports are assembled outside the vertical shaft, earth excavation and steel bar binding in the shaft are carried out, and the construction speed is accelerated and the construction period is shortened by the mode of synchronous construction outside the shaft in the shaft.
Drawings
FIG. 1 is a top view of the present invention.
Fig. 2 is a simplified perspective view of the invention.
Fig. 3 is a simplified front view of the invention.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
referring to fig. 1-3, an annular steel support assembly for a shaft is mainly composed of a locking collar beam 1, well wall reinforcing steel bars (not shown), an annular steel support 3, horizontal sliding rails 2 and the like.
The locking collar beam 1, the well wall reinforcing steel bars and the annular steel supports 3 are arranged in the shaft, the annular steel supports 3 are assembled outside the shaft, and then are conveyed to the position of a well mouth in a sliding mode through the horizontal sliding rails 2.
The fore shaft collar tie beam 1 is arranged at a well mouth position, the fore shaft collar tie beam 1 is composed of bound fore shaft collar tie beam reinforcing steel bars and poured concrete, and the fore shaft collar tie beam 1 is used for ensuring the strength of the well mouth position. And the well wall reinforcing steel bars are bound below the locking collar beam 1, and concrete also needs to be poured for ensuring the strength of the well wall.
At least two vertical sliding grooves 1a which are communicated up and down are reserved on the fore shaft ring beam 1 along the circumferential direction, and each annular steel support 3 is provided with a guide lug 3a which is in one-to-one correspondence with the vertical sliding grooves 1a on the fore shaft ring beam 1. And a horizontal sliding rail 2 is arranged outside the shaft.
The annular steel support 3 can be conveyed to the opening part of the vertical shaft along the horizontal sliding rail 2 after being formed in an assembling field outside the vertical shaft. After the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, the horizontal sliding rails 2 are pulled away, and the annular steel supports 3 can penetrate through the locking collar beams 1 and slide to the position of the well wall reinforcing steel bar for binding and fixing. The wall of a well guarantees intensity jointly through wall of a well ligature reinforcing bar and a plurality of annular steel shotcrete 3 that the interval set up from top to bottom, ligatures the wall of a well reinforcing bar earlier, slides down behind the design position with every annular steel shotcrete 3 again, respectively with wall of a well reinforcing bar ligature fixed back together, carries out concrete placement at last.
An assembling field is arranged outside the vertical shaft, and the annular steel support 3 is formed by connecting or welding the guide lugs 3a and the arc blocks 3b through bolts in the assembling field. Of course, the method is not limited to the assembly mode, and the method can also be integrally formed. The horizontal sliding rail 2 is used as a rail for sliding the assembled annular steel support 3 to the position of a wellhead.
All the annular steel supports 3 equipped in the same shaft have the diameters and the guide lugs 3a which are gradually reduced from top to bottom along the shaft, and the specification size of the vertical sliding chute 1a is matched with the guide lugs 3a of the largest annular steel support 3.
The number of the guide lugs 3a and the number of the arc-shaped blocks 3b are four, and every two arc-shaped blocks 3b are spliced through the guide lugs 3 a. But is not limited to four, and may be three or more. The horizontal sliding rail 2 comprises two sliding rail bars which are arranged in parallel at intervals left and right, and the distance between the two sliding rail bars is larger than the diameter of the annular steel support 3.
A construction method of a vertical shaft annular steel support assembly comprises the following steps:
firstly, earth excavation is carried out in a construction site, steel bars of the fore shaft ring beam are bound, concrete is poured, and construction of the fore shaft ring beam 1 is completed. Continuing to excavate the earthwork downwards after the construction of the locking collar beam 1 is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of the first annular steel support 3, and binding a first section of well wall reinforcement cage; meanwhile, the first annular steel support 3 is assembled in an assembling field.
The locking collar beam 1 is arranged at a wellhead position, and at least two vertical sliding grooves 1a which are communicated up and down are reserved on the locking collar beam 1 along the circumferential direction. The annular steel support 3 is formed by connecting or welding a guide lug 3a and an arc block 3b through bolts, the whole annular steel support is annular, and the guide lug 3a corresponds to the vertical sliding groove 1a on the locking collar beam 1 one by one. The number of the vertical sliding chutes 1a is at least two, and preferably 3 or 4; accordingly, the number of the guide lugs 3a is also 3 or 4.
And secondly, the horizontal sliding rail 2 is in place, one end of the horizontal sliding rail 2 is connected to the assembly site, and the other end of the horizontal sliding rail is connected to the construction site. After the horizontal sliding rail 2 is in place, the assembled first annular steel support 3 is conveyed to the opening of a vertical shaft in a sliding mode along the horizontal sliding rail 2, the guide lugs 3a are aligned with the vertical sliding grooves 1a one by one, finally the horizontal sliding rail 2 is pulled out, the annular steel support 3 penetrates through the locking ring beam 1 and slides to the design position of the first annular steel support 3, the annular steel support 3 and the first section of well wall reinforcement cage are bound and fixed, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and when the annular steel support concrete is poured, a channel for the second annular steel support 3 to pass through is reserved.
Thirdly, when the second annular steel support 3 is assembled, excavating earthwork to the design position of the second annular steel support 3, binding a second section of well wall reinforcement cage, then placing the second annular steel support 3 to the design position of the second annular steel support 3 in the same mode as the first annular steel support 3 for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the annular steel support, and reserving a channel for the third annular steel support 3 to pass through when pouring the annular steel support concrete; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all the annular steel supports 3 equipped in the same vertical shaft have diameters and guide lugs 3a which are sequentially decreased from top to bottom along the vertical shaft, the specification size of the vertical sliding chute 1a is matched with the guide lugs 3a of the largest annular steel support 3, so that the annular steel supports 3 which are placed later can pass through the annular steel supports 3 which are placed first and fall to the designed position, and the pouring thickness of the well wall concrete is more than 50 cm.
The cautions in the construction process are as follows: (1) after each annular steel support is put down in place, binding and fixing are adopted, the annular steel support is required to be poured when concrete for each section of well wall is poured, and a channel for the next annular steel support to pass through is reserved; (2) when one annular steel support is placed, all the placed annular steel supports are fixed, and the placed annular steel supports fall to the designed position after penetrating through all the placed annular steel supports; (3) the diameters of all the annular steel supports and the guide lugs are sequentially reduced from top to bottom along the vertical shaft, and the specification size of the vertical sliding groove is matched with the guide lugs of the largest annular steel support.
The slip type annular steel support construction method is characterized in that on the basis of an original construction method, the assembling of annular steel supports is changed into the pre-assembling of an assembling site outside a vertical shaft, then the annular steel supports slide to the vertical shaft through a horizontal slide rail, and then the annular steel supports slide to a designed supporting position along the wall of the vertical shaft under the guiding action of a guide lug and a vertical slide groove to be fixed, so that the number of large-scale hoisting machinery of the annular steel supports is reduced, the safety risk is reduced, the quality and the size precision of annular steel support components can be guaranteed due to the pre-assembling, the time for influencing earth excavation due to the assembling of a construction site operation surface is shortened, the earth excavation and the assembling of the annular steel supports can be simultaneously carried out, and.
Claims (4)
1. The utility model provides a shaft annular steel supporting component, is including setting up fore shaft collar tie roof beam (1), wall of a well reinforcing bar and annular steel shotcrete (3) in the shaft, fore shaft collar tie roof beam (1) sets up in well head position department, and the ligature of wall of a well reinforcing bar is in fore shaft collar tie roof beam (1) below, its characterized in that: a horizontal sliding rail (2) is arranged outside the vertical shaft, at least two vertical sliding grooves (1a) which are communicated up and down are reserved on the fore shaft ring beam (1) along the circumferential direction, and each annular steel support (3) is provided with guide lugs (3a) which are in one-to-one correspondence with the vertical sliding grooves (1a) on the fore shaft ring beam (1); the annular steel supports (3) can be slidingly conveyed to the opening part of the vertical shaft along the horizontal sliding rails (2) after being formed outside the vertical shaft, and when the guide lugs (3a) are aligned with the vertical sliding grooves (1a) one by one, the horizontal sliding rails (2) are pulled away, and the annular steel supports (3) can pass through the fore shaft ring beam (1) and slide to the position of a well wall reinforcing steel bar for binding and fixing; an assembling field is arranged outside the vertical shaft, and the annular steel support (3) is formed by connecting or welding a guide lug (3a) and an arc-shaped block (3b) on the assembling field through bolts;
all the annular steel supports (3) arranged in the same shaft have the diameters and the guide lugs (3a) which are sequentially reduced from top to bottom along the shaft, and the specification and the size of the vertical sliding groove (1a) are matched with the guide lugs (3a) of the largest annular steel support (3).
2. The shaft ring steel support assembly of claim 1, wherein: the number of the guide lugs (3a) and the number of the arc-shaped blocks (3b) are four respectively, and every two arc-shaped blocks (3b) are spliced through the guide lugs (3 a).
3. The shaft ring steel support assembly of claim 1, wherein: the horizontal slide rail (2) comprises two slide rail bars which are arranged in parallel at intervals.
4. The construction method of the annular steel support component of the vertical shaft is characterized by comprising the following steps:
firstly, carrying out earthwork excavation on a construction site, binding steel bars of a locking collar beam and pouring concrete, completing construction of the locking collar beam (1), continuing to excavate the earthwork downwards after the construction of the locking collar beam (1) is completed, stopping the earthwork excavation after the earthwork is excavated to the design position of a first annular steel support (3), and binding a first section of well wall reinforcement cage; meanwhile, assembling the first annular steel support (3) in an assembling field;
the locking collar beam (1) is arranged at a wellhead position, and at least two vertical sliding grooves (1a) which are communicated up and down are reserved on the locking collar beam (1) along the circumferential direction; the annular steel support (3) is formed by connecting or welding a guide lug (3a) and an arc-shaped block (3b) through bolts, the whole annular steel support is annular, and the guide lugs (3a) correspond to the vertical sliding grooves (1a) on the fore shaft ring beam (1) one by one;
secondly, after the horizontal sliding rail (2) is in place, the assembled first annular steel support (3) is conveyed to the opening of a vertical shaft in a sliding mode along the horizontal sliding rail (2), then the guide lugs (3a) are aligned with the vertical sliding grooves (1a) one by one, finally the horizontal sliding rail (2) is pulled out, the annular steel support (3) penetrates through the locking ring beam (1) and slides to the design position of the first annular steel support (3), the annular steel support (3) is bound and fixed with the first section of well wall reinforcement cage, concrete pouring of the first section of well wall reinforcement cage and the annular steel support is carried out, and a channel for the second annular steel support (3) to pass through is reserved when concrete of the annular steel support is poured;
thirdly, when the second annular steel support (3) is assembled, excavating earthwork to the design position of the second annular steel support (3), binding a second section of well wall reinforcement cage, then placing the second annular steel support (3) to the design position of the second annular steel support (3) in the same mode of the first annular steel support (3) for binding and fixing, pouring concrete of the second section of well wall reinforcement cage and the annular steel support, and reserving a channel for the third annular steel support (3) to pass through when pouring concrete of the annular steel support; and so on until the concrete of the well wall reinforcement cage and the annular steel support of all sections is poured;
all annular steel supports (3) that same shaft was equipped with, its diameter and direction lug (3a) decrease progressively from top to bottom in proper order along the shaft, the specification size of vertical spout (1a) matches with direction lug (3a) of the biggest annular steel support (3) to ensure that annular steel support (3) of transferring afterwards can pass annular steel support (3) of transferring earlier and fall to the design position, and the pouring thickness of wall of a well concrete is greater than 50 cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911194832.0A CN110985000B (en) | 2019-11-28 | 2019-11-28 | Vertical shaft annular steel support assembly and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911194832.0A CN110985000B (en) | 2019-11-28 | 2019-11-28 | Vertical shaft annular steel support assembly and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110985000A true CN110985000A (en) | 2020-04-10 |
CN110985000B CN110985000B (en) | 2021-06-15 |
Family
ID=70087884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911194832.0A Active CN110985000B (en) | 2019-11-28 | 2019-11-28 | Vertical shaft annular steel support assembly and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110985000B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112627509A (en) * | 2020-12-11 | 2021-04-09 | 中国核工业第二二建设有限公司 | Assembly type wedge-shaped inner support device for shaft-shaped steel-clad concrete wall and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1178899A1 (en) * | 1982-05-14 | 1985-09-15 | Novik Evgenij B | Arrangement for working bearing hitches in mine shafts |
JP4448152B2 (en) * | 2007-03-12 | 2010-04-07 | 村本建設株式会社 | Curing fence device for opening |
CN204646240U (en) * | 2015-05-26 | 2015-09-16 | 中国电建集团中南勘测设计研究院有限公司 | Underground shaft supporting and protection structure in a kind of loose media |
CN207700185U (en) * | 2017-12-04 | 2018-08-07 | 辽河石油勘探局 | A kind of retaining wall device for manual hole digging pile |
CN207891895U (en) * | 2017-12-22 | 2018-09-21 | 武汉市市政建设集团有限公司 | Walkway shaft excavation supporting construction |
CN208586606U (en) * | 2018-07-09 | 2019-03-08 | 保利新联***工程集团有限公司 | A kind of retaining wall device for manual hole digging pile |
-
2019
- 2019-11-28 CN CN201911194832.0A patent/CN110985000B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1178899A1 (en) * | 1982-05-14 | 1985-09-15 | Novik Evgenij B | Arrangement for working bearing hitches in mine shafts |
JP4448152B2 (en) * | 2007-03-12 | 2010-04-07 | 村本建設株式会社 | Curing fence device for opening |
CN204646240U (en) * | 2015-05-26 | 2015-09-16 | 中国电建集团中南勘测设计研究院有限公司 | Underground shaft supporting and protection structure in a kind of loose media |
CN207700185U (en) * | 2017-12-04 | 2018-08-07 | 辽河石油勘探局 | A kind of retaining wall device for manual hole digging pile |
CN207891895U (en) * | 2017-12-22 | 2018-09-21 | 武汉市市政建设集团有限公司 | Walkway shaft excavation supporting construction |
CN208586606U (en) * | 2018-07-09 | 2019-03-08 | 保利新联***工程集团有限公司 | A kind of retaining wall device for manual hole digging pile |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112627509A (en) * | 2020-12-11 | 2021-04-09 | 中国核工业第二二建设有限公司 | Assembly type wedge-shaped inner support device for shaft-shaped steel-clad concrete wall and construction method thereof |
CN112627509B (en) * | 2020-12-11 | 2022-04-22 | 中国核工业第二二建设有限公司 | Assembly type wedge-shaped inner support device for shaft-shaped steel-clad concrete wall and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN110985000B (en) | 2021-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102704939B (en) | Combined steel temporary supporting excavation method for tunnel with extra-large section | |
CN103775092B (en) | Tunnels in Shallow Buried tunneling remaining core soil in advance improvement CRD construction | |
CN105178968B (en) | Rock tunnel(ling) machine pushing tow support meanss and construction method | |
CN110761797B (en) | Construction method for shield air-pushing through mine tunnel | |
CN101864963A (en) | Large-section loess tunnel construction method | |
CN106988750B (en) | Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel | |
CN103244130A (en) | Quick excavation and expanding construction method of herringbone tunnel section | |
CN109630126A (en) | A kind of rotary shaft excavation machine of sinking method | |
CN110242305B (en) | Construction process method for constructing main tunnel by inclined shaft entering single side wall pit guiding method | |
CN109209490B (en) | Working face withdrawing method for gangue filling auxiliary end mining stage | |
CN106968691A (en) | Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel | |
CN101545376A (en) | Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally | |
CN109505609A (en) | Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery | |
CN110863841A (en) | Two-lining three-step construction method for large-span shallow-buried underground excavation tunnel | |
CN104831733A (en) | Arch bridge abutment tunnel type large-angle inclined pile construction method | |
CN110230495A (en) | A kind of subway station double -side approach construction Core Soil excavation method | |
CN110985000B (en) | Vertical shaft annular steel support assembly and construction method | |
CN110439574A (en) | It is originated for shield lateral translation and the tunnel structure and construction method of haul of slagging tap | |
CN104564091A (en) | Method and device for removing anchor rods from shield crossing area | |
CN110952985B (en) | Sliding type vertical shaft annular steel support assembly and construction method | |
CN108915714A (en) | The double TBM installation methods in one hole | |
CN108643193A (en) | A kind of pattern foundation pit supporting structure prestress anchorage cable Drilling draw out method | |
CN203499697U (en) | Trolley used for concrete construction of various cross sections through mining method | |
KR100902083B1 (en) | System of casting a wall contruction and descending the same into teh groudnd, and a driving apparatus for stepwise descending the wall construction into teh groudnd | |
EP0887512B1 (en) | Method for widening road, superhighway or railway tunnels, without interrupting the traffic |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address |
Address after: 214104 room 301-218, block a, Xidong chuangrong building, No. 78, Danshan Road, anzhen street, Xishan District, Wuxi City, Jiangsu Province Patentee after: Jiangsu CRRC Urban Development Co.,Ltd. Patentee after: CRRC Construction Engineering Co., Ltd Address before: 215000 NO.115 Yinsheng Road, Shengpu Town, Suzhou Industrial Park, Jiangsu Province Patentee before: SUZHOU CHINA VEHICLE CONSTRUCTION ENGINEERING Co.,Ltd. Patentee before: CRRC Construction Engineering Co., Ltd |
|
CP03 | Change of name, title or address |