CN110700241A - Cast-in-situ bored pile and construction method thereof - Google Patents

Cast-in-situ bored pile and construction method thereof Download PDF

Info

Publication number
CN110700241A
CN110700241A CN201910948751.9A CN201910948751A CN110700241A CN 110700241 A CN110700241 A CN 110700241A CN 201910948751 A CN201910948751 A CN 201910948751A CN 110700241 A CN110700241 A CN 110700241A
Authority
CN
China
Prior art keywords
pile
concrete
cast
hole
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910948751.9A
Other languages
Chinese (zh)
Inventor
朱毅敏
徐磊
王彬楠
张文军
张佳
陈宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN201910948751.9A priority Critical patent/CN110700241A/en
Publication of CN110700241A publication Critical patent/CN110700241A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a cast-in-situ bored pile and a construction method thereof, wherein the construction method comprises the steps of burying a pile casing downwards along a position line, drilling an upper soil layer, a pressure-bearing water layer and a lower soil layer through the pile casing by adopting drilling equipment to form a pile hole, and injecting high-specific-gravity slurry into the pile hole by grouting equipment in the drilling process to resist the upward gushing of underground water in the pressure-bearing water layer, wherein the slurry specific gravity of the high-specific-gravity slurry is 12kN/m3Stopping grouting, hoisting the steel reinforcement cage, pouring concrete in the pile hole through the concrete guide pipe, and extruding the mud with large specific gravity in the pile hole in the concrete pouring process; after the concrete pouring is finished, pulling out the concrete guide pipe; after the concrete reaches the preset strength to form the reinforced concrete column, pulling out the pile casing; and removing the reinforced concrete column above the ground level to form the cast-in-situ bored pile. The invention can be constructed in the soil body environment with the pressure-bearing water layer, and reduces the construction of the cast-in-situ bored pileDifficulty.

Description

Cast-in-situ bored pile and construction method thereof
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a cast-in-situ bored pile and a construction method thereof.
Background
In the process of developing the underground space of a building, a vertical supporting system formed by engineering piles and cast-in-situ bored piles is generally adopted. In the process of constructing the cast-in-situ bored pile for the existing basement or the newly-built basement, when the cast-in-situ bored pile penetrates through a pressure-bearing water layer along a soil body by drilling downwards, pressure-bearing water can gush upwards, so that the cast-in-situ bored pile cannot be constructed in the soil body environment with the pressure-bearing water layer. Thereby improving the difficulty of the downward continuous drilling construction of the cast-in-situ bored pile.
Disclosure of Invention
The invention aims to solve the technical problem of providing a cast-in-situ bored pile and a construction method thereof, so as to solve the problem of difficult construction when a pressure-bearing water layer is penetrated.
In order to solve the above technical problems, the present invention provides a method for constructing a cast-in-situ bored pile,
discharging a position line of the bored pile to be constructed on the ground plane;
embedding a protective cylinder downwards along the position line to enable the protective cylinder to be partially exposed above the ground plane;
drilling an upper soil layer, a confined water layer and a lower soil layer below a ground level through a pile casing by using drilling equipment to form a pile hole, and injecting high-specific-gravity slurry into the pile hole through grouting equipment in the drilling process to resist the upward gushing of underground water in the confined water layer, wherein the slurry specific gravity of the high-specific-gravity slurry is more than 12kN/m 3;
after the drilling equipment penetrates through the lower soil layer to drill holes so that the pile holes reach a preset depth, stopping grouting by the grouting equipment, and hoisting a reinforcement cage into the pile holes;
after the reinforcement cage is installed, inserting a concrete guide pipe into the pile hole, pouring concrete into the pile hole through the concrete guide pipe, and extruding out the large-proportion slurry injected into the pile hole in the concrete pouring process;
after concrete pouring in the pile hole is finished, pulling out the concrete guide pipe;
after the concrete in the pile hole reaches the preset strength to form a reinforced concrete column, pulling out the pile casing;
and removing the reinforced concrete column above the ground level to form the cast-in-situ bored pile.
Further, according to the construction method of the cast-in-situ bored pile provided by the invention, after grouting equipment stops grouting and before a reinforcement cage is installed, hole cleaning is carried out on a pile hole for the first time.
Furthermore, the construction method of the cast-in-situ bored pile provided by the invention is used for performing secondary hole cleaning on the pile hole after the concrete guide pipe is inserted.
Further, according to the construction method of the cast-in-situ bored pile provided by the invention, when concrete is poured in the pile hole, the concrete guide pipe is gradually lifted upwards until the concrete is poured in the pile hole, and then the concrete guide pipe is pulled out from the pile hole.
Further, the construction method of the bored pile provided by the invention comprises the steps that the grouting equipment comprises a grouting pump, a grouting pipe and a slurry outlet pipe which are communicated with the grouting pump, and a mud box which is communicated with the grouting pipe and the slurry outlet pipe, wherein the mud box comprises a mud settling tank and a mud circulating tank, the grouting pipe is communicated with the mud circulating tank, and the slurry outlet pipe is communicated with the mud settling tank.
Further, according to the construction method of the cast-in-situ bored pile provided by the invention, the drilling equipment is a water drilling machine, and the water drilling machine comprises a drill rod and a drill bit.
Further, according to the construction method of the cast-in-situ bored pile provided by the invention, when the ground plane comprises the concrete laminate, the position line is drawn on the concrete laminate, and the hole is formed by drilling and cutting the thinner concrete laminate along the position line in a circular matrix manner; drilling holes in a circular matrix mode along the position line and drilling and cutting holes in the position line for the thicker concrete layer plate to form holes; and (4) removing the redundant concrete on the inner side of the hole by using a hand hammer and a drill rod, removing the concrete in the hole, and embedding a protective cylinder downwards in the hole.
In order to solve the technical problems, the invention provides a cast-in-situ bored pile which comprises a pile hole penetrating through an upper soil layer, a confined water layer and a lower soil layer below the ground level in sequence, wherein a steel reinforcement cage and a reinforced concrete column formed by replacing concrete for resisting high-specific gravity mud gushing upwards from the confined water layer are arranged in the pile hole.
Furthermore, the cast-in-situ bored pile provided by the invention is arranged below a bottom floor slab of an existing basement.
Further, according to the cast-in-situ bored pile provided by the invention, the cast-in-situ bored pile is arranged below a foundation pit of a newly-built basement.
Compared with the prior art, the cast-in-situ bored pile and the construction method thereof provided by the invention have the advantages that the large-specific-gravity slurry is injected into the pile hole to resist the upward gushing of underground water in the confined water layer, so that the cast-in-situ bored pile is constructed by penetrating the confined water layer. The large-specific-gravity slurry not only presses underground water gushing caused by a bearing water layer, but also can ensure the stability of the hole wall of the pile hole, prevent the pile hole from collapsing and reduce the construction difficulty of the cast-in-situ bored pile. The cast-in-situ bored pile provided by the invention is positioned on an upper soil body layer, a pressure-bearing water layer and a lower soil body layer below the ground level, and can be constructed in a soil body environment with the pressure-bearing water layer. The cast-in-situ bored pile provided by the invention is used for replacing concrete with large specific gravity mud and a reinforced concrete column formed by a reinforcement cage, and the stability of the cast-in-situ bored pile is improved.
Drawings
Fig. 1 to 9 are schematic views illustrating a construction process of a cast-in-situ bored pile according to an embodiment of the present invention;
fig. 10 to 11 are schematic structural views illustrating the distribution of concrete floor drilling holes according to an embodiment of the present invention;
fig. 12 is a flow chart of a cast-in-situ bored pile according to an embodiment of the present invention.
Shown in the figure: 101. the method comprises the following steps of casing, 102, grouting equipment, 103, drilling equipment, 104, mud with large specific gravity, 105, a reinforcement cage, 106, a concrete guide pipe, 107, concrete, 200, a ground level, 201, an upper soil layer, 202, a pressure water layer, 203, a lower soil layer, 204, pile holes, 300, a position line, 400 and drilling.
Detailed Description
The invention is described in detail below with reference to the attached drawing figures:
referring to fig. 12, an embodiment of the present invention provides a method for constructing a cast-in-situ bored pile, including:
step 501, please refer to fig. 1, a position line of the bored pile to be constructed is released on the ground level 200.
Step 502, referring to fig. 1, burying the casing 101 downwards along the position line, so that the casing 101 is partially exposed above the ground plane 200.
Step 503, referring to fig. 2 to 3, drilling the upper soil layer 201, the confined water layer 202 and the lower soil layer 203 below the ground level 200 through the casing 101 by using the drilling equipment 103 to form a pile hole 204, and injecting high-specific-gravity slurry 104 into the pile hole 204 through the grouting equipment 102 during drilling to resist the upward gushing of the underground water in the confined water layer 202, wherein the slurry specific gravity of the high-specific-gravity slurry 104 is more than 12kN/m 3.
In step 504, referring to fig. 4, after the drilling equipment 103 drills holes through the lower soil layer 203 to make the pile holes 204 reach a predetermined depth, the grouting equipment 102 stops grouting, and the reinforcement cage 105 is hung in the pile holes 204.
Step 505, referring to fig. 5 to 7, after the reinforcement cage 105 is installed, the concrete guide pipe 106 is inserted into the pile hole 204, the concrete 107 is poured into the pile hole 204 through the concrete guide pipe 106, and the mud 104 with large specific gravity injected into the pile hole 204 is squeezed out during the process of pouring the concrete 107.
In step 506, referring to fig. 8, after the concrete 107 is poured into the pile hole 204, the concrete pipe 106 is pulled out.
In step 507, referring to fig. 9, after the concrete 107 in the pile hole 204 reaches the predetermined strength to form the reinforced concrete column, the casing 101 is pulled out. For example, the pile casing 101 is pulled out after concrete pouring is completed for 2 hours, and the reinforced concrete column head is cut off by using a hydraulic splitter, so that the reinforced concrete column head is integrally broken. The predetermined strength may be that the reinforced concrete column is completely solidified or that the reinforced concrete column is not completely solidified.
Step 508, referring to fig. 9, removing the reinforced concrete column above the ground level 200 to form a bored pile.
According to the construction method of the cast-in-situ bored pile provided by the embodiment of the invention, after grouting of the grouting equipment 102 is stopped and before the reinforcement cage 105 is installed, the pile hole 204 is cleaned for the first time. After the concrete pipe 106 is inserted, the pile hole 204 is cleaned a second time. Cleaning the pile hole 204 can remove larger soil blocks or obstacles in the pile hole 204, so as to improve the formation of the reinforced concrete column with stable structure by pouring concrete 107 in the pile hole 204.
Referring to fig. 7, in the construction method of the cast-in-situ bored pile according to the embodiment of the present invention, when the concrete 107 is poured into the pile hole 204, the concrete guide pipe 106 is gradually lifted upward until the concrete 107 is poured into the pile hole 204, and then the concrete guide pipe 106 is pulled out from the pile hole 204. Gradually pulling up the concrete pipe 106 enables the concrete 107 to gradually displace the heavy weight mud 104 from the bottom of the pile hole 204 upwards.
In the construction method of the bored pile provided by the embodiment of the present invention, the grouting equipment 102 includes a grouting pump, a grouting pipe and a grout outlet pipe which are communicated with the grouting pump, and a mud tank which is communicated with the grouting pipe and the grout outlet pipe, the mud tank includes a mud settling tank and a mud circulation tank, the grouting pipe is communicated with the mud circulation tank, and the grout outlet pipe is communicated with the mud settling tank.
Referring to fig. 3, in the method for constructing a cast-in-place bored pile according to the embodiment of the present invention, the drilling equipment 103 is a water drilling machine, and the water drilling machine includes a drill rod and a drill bit. The drilling apparatus 103 may employ a drilling machine known in the art.
Referring to fig. 10 to 11, in the method for constructing a cast-in-place bored pile according to the embodiment of the present invention, when a concrete slab is included on a ground plane 200, a position line is positioned on the concrete slab, and holes are cut in a circular matrix manner 400 along the position line 300 for the thinner concrete slab, as shown in fig. 10; drilling 400 in a circular matrix along the location line 300 for the thicker concrete slab and cutting the holes 400 into openings within the location line 300, as shown in FIG. 11; and (3) removing the redundant concrete 107 on the inner side of the hole by using a hand hammer and a drill rod, removing the concrete 107 in the hole, and burying the pile casing 101 downwards in the hole. The purpose of drilling and cutting the concrete layer plate to form the opening is to remove the concrete layer plate at the corresponding position of the position line, so as to embed the pile casing 101 and construct the pile hole 204. Drilling holes in a circular matrix and cutting holes 400 in the position lines 300 are suitable for the construction of concrete slabs of any thickness.
Referring to fig. 7 and 9, an embodiment of the invention provides a cast-in-situ bored pile, which includes a pile hole 204 penetrating an upper soil layer 201, a confined water layer 202, and a lower soil layer 203 below a ground level 200 in sequence, and a steel reinforcement cage 105 and a steel reinforcement concrete column formed of concrete 107 for replacing a large-gravity slurry 104 for resisting upward gushing of the confined water layer 202 are disposed in the pile hole 204.
According to the cast-in-situ bored pile provided by the embodiment of the invention, the cast-in-situ bored pile is arranged below a bottom floor slab of an existing basement. Namely, the cast-in-situ bored pile provided by the embodiment of the invention can be suitable for the maintenance of the vertical supporting system of the existing basement, the reconstruction engineering of the existing basement such as storey addition and the like.
According to the cast-in-situ bored pile provided by the embodiment of the invention, the cast-in-situ bored pile is arranged below a foundation pit of a newly-built basement. Namely, the embodiment of the invention can be applied to new construction of buildings or structures.
According to the cast-in-situ bored pile and the construction method thereof provided by the embodiment of the invention, the large-specific-gravity slurry 104 is injected into the pile hole 204 to resist the upward gushing of underground water in the confined water layer, so that the cast-in-situ bored pile is constructed by penetrating the confined water layer 202. The large-specific gravity mud 104 not only suppresses the groundwater gushing caused by the confined water layer 202, but also can ensure the stability of the hole wall of the pile hole 204 and prevent the pile hole 204 from collapsing, thereby reducing the construction difficulty of the cast-in-situ bored pile. The cast-in-situ bored pile provided by the embodiment of the invention is positioned on an upper soil layer 201, a confined water layer 202 and a lower soil layer 203 below a ground level 200, and can be constructed in a soil environment with the confined water layer 202. The cast-in-situ bored pile provided by the embodiment of the invention is used for replacing a reinforced concrete 107 pile body formed by concrete 107 of large-specific-weight mud 104 and a reinforcement cage 105, and the stability of the cast-in-situ bored pile is improved.
The present invention is not limited to the above-described embodiments, and any variations and modifications thereof by those skilled in the art are intended to fall within the scope of the appended claims.

Claims (10)

1. A construction method of a cast-in-situ bored pile is characterized in that,
discharging a position line of the bored pile to be constructed on the ground plane;
embedding a protective cylinder downwards along the position line to enable the protective cylinder to be partially exposed above the ground plane;
drilling an upper soil layer, a confined water layer and a lower soil layer below a ground level through a pile casing by using drilling equipment to form a pile hole, and injecting high-specific-gravity slurry into the pile hole through grouting equipment in the drilling process to resist the upward gushing of underground water in the confined water layer, wherein the slurry specific gravity of the high-specific-gravity slurry is more than 12kN/m 3;
after the drilling equipment penetrates through the lower soil layer to drill holes so that the pile holes reach a preset depth, stopping grouting by the grouting equipment, and hoisting a reinforcement cage into the pile holes;
after the reinforcement cage is installed, inserting a concrete guide pipe into the pile hole, pouring concrete into the pile hole through the concrete guide pipe, and extruding out the large-proportion slurry injected into the pile hole in the concrete pouring process;
after concrete pouring in the pile hole is finished, pulling out the concrete guide pipe;
after the concrete in the pile hole reaches the preset strength to form a reinforced concrete column, pulling out the pile casing;
and removing the reinforced concrete column above the ground level to form the cast-in-situ bored pile.
2. The cast-in-situ bored pile construction method according to claim 1, wherein after the grouting of the grouting equipment is stopped and before the completion of the reinforcement cage installation, a first hole cleaning is performed on the pile hole.
3. The cast-in-situ bored pile construction method according to claim 1, wherein the pile hole is subjected to a second hole cleaning after the concrete pipe is inserted.
4. The cast-in-situ bored pile construction method according to claim 1, wherein the concrete guide pipe is gradually pulled upward while the concrete is cast in the pile hole until the concrete is cast in the pile hole, and then the concrete guide pipe is pulled out from the pile hole.
5. The method of constructing a bored pile according to claim 1, wherein the grouting apparatus includes a grouting pump, a grouting pipe and a grout outlet pipe communicating with the grouting pump, and a mud tank communicating with the grouting pipe and the grout outlet pipe, the mud tank includes a mud settling tank and a mud circulation tank, the grouting pipe communicates with the mud circulation tank, and the grout outlet pipe communicates with the mud settling tank.
6. The method of constructing a bored pile according to claim 1, wherein the drilling equipment is a water drilling machine including a drill pipe and a drill bit.
7. The cast-in-situ bored pile construction method according to claim 1, wherein when a concrete slab is included on the ground plane, a position line is drawn on the concrete slab, and the opening is bored and cut in a circular matrix along the position line for a thin concrete slab; drilling holes in a circular matrix mode along the position line and drilling and cutting holes in the position line for the thicker concrete layer plate to form holes; and (4) removing the redundant concrete on the inner side of the hole by using a hand hammer and a drill rod, removing the concrete in the hole, and embedding a protective cylinder downwards in the hole.
8. A cast-in-situ bored pile is characterized by comprising a pile hole which sequentially penetrates through an upper soil layer, a pressure-bearing water layer and a lower soil layer below a ground level, wherein a steel reinforcement cage and a reinforced concrete column which is used for replacing concrete of large-proportion mud for resisting upward gushing of the pressure-bearing water layer are arranged in the pile hole.
9. The bored pile of claim 8, wherein the bored pile is disposed below a floor slab of an existing basement.
10. The cast-in-situ pile as recited in claim 8, wherein the cast-in-situ pile is disposed below a foundation pit of a newly-built basement.
CN201910948751.9A 2019-10-08 2019-10-08 Cast-in-situ bored pile and construction method thereof Pending CN110700241A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910948751.9A CN110700241A (en) 2019-10-08 2019-10-08 Cast-in-situ bored pile and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910948751.9A CN110700241A (en) 2019-10-08 2019-10-08 Cast-in-situ bored pile and construction method thereof

Publications (1)

Publication Number Publication Date
CN110700241A true CN110700241A (en) 2020-01-17

Family

ID=69196531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910948751.9A Pending CN110700241A (en) 2019-10-08 2019-10-08 Cast-in-situ bored pile and construction method thereof

Country Status (1)

Country Link
CN (1) CN110700241A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720186A (en) * 2012-07-10 2012-10-10 上海港务工程公司 Underwater once pouring method for variable cross-section bored cast-in-place pile
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN104895054A (en) * 2015-04-23 2015-09-09 侨健新能源科技(苏州)有限公司 Construction method of fiber rib concrete uplift pile
CN105442532A (en) * 2015-11-19 2016-03-30 杭州江润科技有限公司 Construction method for pile-head-expanded bored pile
CN107524142A (en) * 2017-09-20 2017-12-29 中国二十冶集团有限公司 A kind of holing with slurry wall protection cast-in-place pile construction method
CN109914455A (en) * 2019-03-29 2019-06-21 广西鑫豪建筑工程有限公司 A kind of structure foundation cast-in-place pile construction method
CN211646351U (en) * 2019-10-08 2020-10-09 上海建工一建集团有限公司 Cast-in-situ bored pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720186A (en) * 2012-07-10 2012-10-10 上海港务工程公司 Underwater once pouring method for variable cross-section bored cast-in-place pile
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN104895054A (en) * 2015-04-23 2015-09-09 侨健新能源科技(苏州)有限公司 Construction method of fiber rib concrete uplift pile
CN105442532A (en) * 2015-11-19 2016-03-30 杭州江润科技有限公司 Construction method for pile-head-expanded bored pile
CN107524142A (en) * 2017-09-20 2017-12-29 中国二十冶集团有限公司 A kind of holing with slurry wall protection cast-in-place pile construction method
CN109914455A (en) * 2019-03-29 2019-06-21 广西鑫豪建筑工程有限公司 A kind of structure foundation cast-in-place pile construction method
CN211646351U (en) * 2019-10-08 2020-10-09 上海建工一建集团有限公司 Cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN106320333B (en) Combined drainage type water filling pile device and construction method
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN108978644B (en) Energy-saving and environment-friendly construction method for cast-in-situ bored pile
CN111395330B (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN108166483A (en) Bored pile construction method
CN110761265A (en) Karst cave disposal method for deep foundation pit pile foundation construction in karst area
CN111236216A (en) Construction method of bridge drilled pile
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN211646351U (en) Cast-in-situ bored pile
CN108222054A (en) Tower-crane foundation structure and its construction method
CN217352573U (en) Fixed quicksand layer combined pile foundation structure
CN116716879A (en) Construction method of underwater double-pile-casing cast-in-place pile suitable for seabed with hard stratum
CN218148483U (en) Tower crane foundation structure
CN110792077A (en) Supporting disc pile device suitable for muddy soft soil and construction process thereof
CN110700241A (en) Cast-in-situ bored pile and construction method thereof
CN112081158A (en) Construction process for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN115075249A (en) Pile foundation clearing device and pile foundation clearing process
CN211735404U (en) Anti-over-irrigation system for long spiral bored pile
CN113653052A (en) Obstacle clearing construction method for large-diameter underground steel-concrete composite structure
CN109989415B (en) Construction method of fabricated foundation
CN106759377A (en) The construction method of recyclable building enclosure
CN114197453B (en) Bored pile adopting prefabricated high-strength concrete pile head
CN114607187B (en) Shaft type underground parking garage construction method of cast-in-situ supporting structure under slurry
CN220377259U (en) Construction device for rotary digging hole-forming fender post through deep buried culvert double sleeve

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination