CN110306531A - High water level erratic boulder stratum construction of diaphragm wall technique - Google Patents

High water level erratic boulder stratum construction of diaphragm wall technique Download PDF

Info

Publication number
CN110306531A
CN110306531A CN201910606990.6A CN201910606990A CN110306531A CN 110306531 A CN110306531 A CN 110306531A CN 201910606990 A CN201910606990 A CN 201910606990A CN 110306531 A CN110306531 A CN 110306531A
Authority
CN
China
Prior art keywords
construction
wall
water level
high water
erratic boulder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910606990.6A
Other languages
Chinese (zh)
Inventor
樊延祥
关辉
王永全
王有旗
朱连臣
陈庆忠
李苗
辛柱桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN201910606990.6A priority Critical patent/CN110306531A/en
Publication of CN110306531A publication Critical patent/CN110306531A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to a kind of high water level erratic boulder stratum construction of diaphragm wall techniques, belong to subway construction technical field of construction, the main points of its technical scheme are that including: step S1, by cutting box drilling to completion;Step S2, TRD engineering method builds Soil-cement Wall;It is initially injected and excavates liquid and excavates in advance, loosen soil layer a distance, then withdraw and excavate to original place, reinject solidify liquid and push ahead and stir into wall;Step S3, cutting box, which is extracted, to be decomposed;Traditional colonnade formula Soil-cement diaphragm wall is solved in high water level erratic boulder earth formation, the problem ineffective with earth-retaining is held in the main structure progress supporting that good cannot be excavated to subway, antiseepage;Antiseepage retaining support well can be carried out to subway constructing structure main body.

Description

High water level erratic boulder stratum construction of diaphragm wall technique
Technical field
The present invention relates to subway construction technical field of construction, more particularly, to a kind of high water level erratic boulder stratum construction of diaphragm wall Technique.
Background technique
When iron-based station is built over the ground, need to build diaphram wall in the underground structure of excavation.Underground is continuous Wall is that foundation engineering uses a kind of trench machine on the ground, along the periphery axis of deep excavation project, in mud off condition Under, it excavates out a long and narrow deep trouth, after clear slot, steel reinforcement cage is hung in slot, is then built with tremie method underwater concreting with tremie method At a unit groove section, so carry out paragraph by paragraph, build up continuous armored concrete wall together in underground, as intercept water, antiseepage, Load-bearing, water-retaining structure.On the ground, it using some extraordinary trench machines, is acted on, is dug out in underground narrow by means of the retaining wall of mud And deep foundation trench, and one for being poured material appropriate in it and being formed has the continuous of antiseepage, earth-retaining and weight-bearing function Underground wall body.
Existing erratic boulder bottom construction of diaphragm wall technique can refer to the Chinese invention that application publication number is CN108951609A Patent application document, it discloses one kind suitable for soft or hard uneven ovum gravel erratic boulder stratum construction method of underground continuous wall, including compared with Soft ovum gravel erratic boulder stratum grooving, be drilled with perpendicular drilling, native grooving is grabbed on harder ovum gravel erratic boulder stratum and construction of diaphragm wall four steps Suddenly, after the softer ovum gravel erratic boulder stratum being hollowed out, grooving operation directly is carried out using chute forming machine, it is more applying brill at groove location A to extend perpendicular drilling, the entire depth of perpendicular drilling diaphram wall foundation trench along harder ovum gravel erratic boulder stratum extends.
Existing construction of diaphragm wall technique is primarily directed to common earth formation, when subway is being built in coastal cities When, coastal stratum is mostly high water level erratic boulder earth formation.Construction of diaphragm wall traditional at present mostly uses uniaxial or multiaxis spiral shell Drilling machine is revolved, the colonnade formula Soil-cement diaphragm wall for formation of constructing, this colonnade formula Soil-cement diaphragm wall is in high water level In erratic boulder earth formation, the main structure progress supporting that good cannot be excavated to subway, antiseepage is held ineffective with earth-retaining.
Summary of the invention
The purpose of the present invention is to provide a kind of high water level erratic boulder head stratum construction of diaphragm wall techniques, can be well to subway Constructing structure main body carries out antiseepage retaining support.
Foregoing invention purpose of the invention has the technical scheme that a kind of high water level erratic boulder stratum connects Continuous wall construction technology, comprises the following methods:
Step S1, by cutting box drilling to completion;
Step S2, TRD engineering method builds Soil-cement Wall;It is initially injected excavation liquid to excavate in advance, loosen soil layer a distance, so After withdraw excavation to original place, reinject solidify liquid and push ahead and stir into wall;
Step S3, cutting box, which is extracted, to be decomposed.
It by using above-mentioned technical proposal, is excavated by being initially injected excavation liquid, is excavated going out preliminary structure of completing in advance Afterwards, excavation is withdrawn at a distance, to reduce the structure collapses as caused by earth formation low-intensity and Thief zone characteristic, is then led to It crosses injection solidify liquid and pushes ahead and stir into wall, and then the construction quality of diaphragm wall.
The present invention is further arranged to: in step s 2, after cutting box drilling to completion, passing through cutting box bottom end first The bentonite slurry of injection high concentration carries out excavation stratum setting distance in advance and is mixed for the first time with the soil body in situ, then returns After removing excavation to starting point, slurry backstage replacement cement grout is mixed, cutting box bottom end is injected by mudjack and excavates liquid mixed soil Slurry is mixed, is solidified into wall.
It is cut in work progress for different construction procedures is different to cutting configuration by using above-mentioned technical proposal Liquid is cut, and then is had on the basis of improving wall construction speed, the effective construction quality for guaranteeing wall.
The present invention is further arranged to: being tried into wall on the outside of foundation pit and tested, determines the excavation liquid swelling actually used The construction parameter of native volume, solidify liquid cement mixing content.
By using above-mentioned technical proposal, wall is tried on the outside of foundation pit in construction and is tested, and then simulated in advance The parameters of current position diaphragm wall are solved, and then to the construction parameter for excavating liquid bentonite volume, solidify liquid cement mixing content It is configured, to preferably carry out construction excavation.
The present invention is further arranged to: according to the coordinate basis of design drawing point, being calculated examination and is sat at center line of wall angle point Mark;Laying steel plate is carried out to construction site after examination is at center line of wall setting-out according to weight of equipment.
By using above-mentioned technical proposal, behind the accurate job location of determination, by carrying out laying steel on construction ground Plate, and then the earth's surface intensity of job location can be effectively improved, it is convenient that installation fixation is carried out to equipment.
The present invention is further arranged to: in step s 2, soil property is explored in timing in work progress, according to soil property feelings Condition, to the ratio of mud of cutting liquid, solidify liquid, cutting liquid mixing mud, solidify liquid mixing mud TF value be adjusted.
By using above-mentioned technical proposal, in the construction process, periodically soil property is explored, and then understands applying in time During work, whether soil property changes, and then in time to the ratio of mud of cutting liquid, solidify liquid, cutting liquid mixing mud, solidification The TF value of liquid mixing mud is adjusted, to preferably carry out excavation construction.
The present invention is further arranged to: in step s3, using extraction cutting box technique outside wall.
By using above-mentioned technical proposal, corner construction, which has, extracts within the walls and extracts two kinds of techniques of cutting box outside wall, uses To extract technique outside wall, the influence for extracting cutting box to wall can be reduced.
The present invention is further arranged to: every corner should all increase construction surplus to wall outer side when construction, be formed " Ten " corner coupling head of font formula.
It is formed " ten " by using above-mentioned technical proposal by the corner should all increase construction surplus to wall outer side The corner coupling head of font formula, and then facilitate staff to extract technique outside using wall, and then can preferably guarantee seam quality.
The present invention is further arranged to: in step s 2, installing two pieces of transparent panels on TRD construction machine host different location And management point is set, the laser beam of laser transit beats the position monitoring that wall center is carried out on management point.
Management by using above-mentioned technical proposal, by laser longitude and latitude to the transparent panel that TRD construction machine host is arranged in Point is detected, and then the position at the center of stirring wall carries out accurately monitoring measurement in construction traveling process.
In conclusion advantageous effects of the invention are as follows:
1. being excavated in advance by being initially injected excavation liquid, after preliminary completion structure is excavated out, withdraws and excavate to distant place, to subtract Then the small structure collapses as caused by earth formation low-intensity and Thief zone characteristic push ahead stirring by injecting solidify liquid At wall, and then the construction quality of diaphragm wall;
2. using cutting box technique is extracted outside wall, and in construction, every corner should all increase more than construction to wall outer side Amount, forms the corner coupling head of " ten " font formula, and then can preferably guarantee seam quality;
3. being detected by management point of the laser longitude and latitude to the transparent panel that TRD construction machine host is arranged in, and then go in construction Accurately monitoring measurement is carried out into the position at the center for stirring wall in the process.
Detailed description of the invention
Fig. 1 is the flow chart of high water level erratic boulder stratum construction of diaphragm wall technique.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment: a kind of high water level erratic boulder stratum construction of diaphragm wall technique, comprising: cutting box is drilled into design by step S1 Depth;Step S2, TRD engineering method builds Soil-cement Wall;Step S3, cutting box, which is extracted, to be decomposed.
Step S1, by cutting box drilling to completion.(1) surveying setting-out.Before construction, first mentioned according to design drawing and owner The coordinate basis point of confession accurately calculates TRD engineering method water-stop curtain (examination at wall) center line angular coordinate, using measuring instrument into Row setting-out, and coordinate data review is carried out, while carrying out fender pile.And relevant unit is notified to carry out unwrapping wire review.(2) guiding is excavated Slot is laid with construction site after the building site TRD water-stop curtain (examination is at wall) center line setting-out according to TRD engineering method weight of equipment The Reinforcement Measures such as steel plate, it is ensured that construction site meets requirement of the mechanical equipment to foundation bearing capacity, it is ensured that the stabilization of stake machine Property.Guide groove, groove width about 1.0m, groove depth about 1.0m are excavated at center line of wall parallel direction along examination with excavator.(3) it hangs pre-buried Case.With the pre-buried cave of excavator cutting depth about 4.9m, length about 2m, width about 1m, using crane and by provided box hang into In pre-buried cave.(4) stake machine sees the feelings of upper and lower, left and right various aspects clearly in place by stake machine is in place when squad leader assumes unified command of before mobile Condition, discovery have barrier that should remove in time, check positioning scenarios and timely correction after mobile, stake machine Ying Pingwen, straight and even. (5) cutting box is connect with host.Cutting box is hung paragraph by paragraph into pre-buried cave with specified crane, is fixed using supporting table;TRD master Machine is moved to pre-buried acupuncture point and sets connection cutting box, and host returns again to predetermined construction location progress cutting box and voluntarily squeezes into digger Sequence.By projected depth requirement, the cutting cabinet that one section of a section is connected is cut vertically downward in indentation ground.It hangs down in cutting cabinet Vertical cut is cut while ensuring vertical precision in indentation ground, also will be in viscosity by the controlling of injecting quantity of cutting fluid in minimum range Formation variation sharply is prevented in high mixing mud.(6) inclinometer is installed.After cutting box is voluntarily driven into projected depth, peace Fill inclinometer.By the multisection type inclinometer being mounted on inside cutting box, the vertical precision management of wall can be carried out, it usually can be true Protect the precision within 1/250.
Step S2, TRD engineering method builds Soil-cement Wall.Wall is tried on the outside of foundation pit to test, and determines practical use Excavate liquid bentonite volume, solidify liquid cement mixing content construction parameter.According to the coordinate basis of design drawing point, calculate Try into center line of wall angular coordinate;Laying steel is carried out to construction site after examination is at center line of wall setting-out according to weight of equipment Plate.After the installation is completed, host is connect inclinometer with cutting box.Excavation liquid, which is injected, in cutting box bottom cuts one section of soil layer in advance Distance, then excavation is withdrawn to original place, injecting solidify liquid makes it and excavates the stirring of liquid mixing mud Forced Mixing, the solid cements such as formation Soil stirring diaphragm wall.The control of liquid grout pressure is excavated in 1~1.5Mpa, solidify liquid grouting pressure 2Mpa.By equal thickness soil cement Stir the unified stacking of the discarded slurry generated during construction of diaphragm wall, centralized processing.
TRD engineering method builds Soil-cement Wall and needs to carry out verticality management to cutting box, is to reach big depth construction Purpose, the management project that ensures good sealing and carry out.It can be managed by the multistage inclinometer installed inside cutting box At the vertical precision of wall, the precision within 1/250 generally can ensure that.The vertical line of the wall of TRD diaphragm wall and wall center Management method is to install two pieces of transparent panels on TRD construction machine host different location and management point is arranged, laser transit swashs Light ray plays the monitoring position management that wall center is carried out on management point.
Step S3, cutting box, which is extracted, to be decomposed.After trying into wall and each active section construction of Soil-cement Wall, crane is utilized Cutting box is segmented and is extracted, equipment is transferred to subsequent work face and prepares construction.Under normal circumstances cut cabinet extraction operation, be After the completion of building cutting, the injection, mixing, whipping procedure of wall, host is separated with cutting cabinet immediately, uses crawler type Crane extracts cutting cabinet.According to the length, the elevating capacity of crawler crane and operating radius of cutting cabinet, (operation is empty Between), determine that each unit extracts the specific joint number of cutting cabinet.Generally with 2~3 sections cutting cabinet for a unit.To make to cut The liquid level for cutting solidify liquid mixing mud when cabinet is extracted will not decline, and need to adjust solidify liquid injection rate and extract speed matching It closes.The extraction position of cutting cabinet is determined when formulating construction plan, which must assure that operation can be gone on smoothly.One As in the case of, the extraction position for cutting cabinet is each construction surface into wall final position.In order not to concentrate on corner location.
When transfering to cutting box, using extracting cutting box technique outside wall, when construction, every corner all should be to wall External side increases construction surplus, forms the corner coupling head of " ten " font formula.The whirl spraying of a φ 1000 should be used at the cold seam of connector Stake carries out impervious reinforcement.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (9)

1. a kind of high water level erratic boulder stratum construction of diaphragm wall technique, it is characterised in that comprise the following methods:
Step S1, by cutting box drilling to completion;
Step S2, TRD engineering method builds Soil-cement Wall;It is initially injected excavation liquid to excavate in advance, loosen soil layer a distance, so After withdraw excavation to original place, reinject solidify liquid and push ahead and stir into wall;
Step S3, cutting box, which is extracted, to be decomposed.
2. high water level erratic boulder according to claim 1 stratum construction of diaphragm wall technique, it is characterised in that: in step s 2, After cutting box drilling to completion, carry out excavating stratum in advance by the bentonite slurry that high concentration is injected in cutting box bottom end first Setting distance is mixed for the first time with the soil body in situ, then is withdrawn and excavated to starting point, and slurry backstage replacement cement grout is mixed, Cutting box bottom end, which is injected, by mudjack and excavates liquid mixing mud is mixed, is solidified into wall.
3. high water level erratic boulder according to claim 2 stratum construction of diaphragm wall technique, it is characterised in that: on the outside of foundation pit into Row examination is tested at wall, determines that is actually used excavates the construction parameter of liquid bentonite volume, solidify liquid cement mixing content.
4. high water level erratic boulder according to claim 3 stratum construction of diaphragm wall technique, it is characterised in that: according to design drawing Coordinate basis point, calculate examination at center line of wall angular coordinate;It is right after examination is at center line of wall setting-out according to weight of equipment Construction site carries out laying steel plate.
5. high water level erratic boulder according to claim 4 stratum construction of diaphragm wall technique, it is characterised in that: in step s 2, Soil property is explored in timing in work progress, according to soil property situation, to the ratio of mud of cutting liquid, solidify liquid, cutting liquid mixing Mud, solidify liquid mixing mud TF value be adjusted.
6. high water level erratic boulder according to claim 5 stratum construction of diaphragm wall technique, it is characterised in that: in step s 2, Suitable particle, which is added, in arenaceous stratum construction adjusts material.
7. high water level erratic boulder according to claim 1 stratum construction of diaphragm wall technique, it is characterised in that: in step s3, Using extraction cutting box technique outside wall.
8. high water level erratic boulder according to claim 7 stratum construction of diaphragm wall technique, it is characterised in that: every turn when construction Construction surplus should all be increased at angle to wall outer side, form the corner coupling head of " ten " font formula.
9. high water level erratic boulder according to claim 1 stratum construction of diaphragm wall technique, it is characterised in that: in step s 2, Two pieces of transparent panels are installed on TRD construction machine host different location and management point is set, the laser beam of laser transit is beaten The position monitoring at wall center is carried out on management point.
CN201910606990.6A 2019-07-06 2019-07-06 High water level erratic boulder stratum construction of diaphragm wall technique Pending CN110306531A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910606990.6A CN110306531A (en) 2019-07-06 2019-07-06 High water level erratic boulder stratum construction of diaphragm wall technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910606990.6A CN110306531A (en) 2019-07-06 2019-07-06 High water level erratic boulder stratum construction of diaphragm wall technique

Publications (1)

Publication Number Publication Date
CN110306531A true CN110306531A (en) 2019-10-08

Family

ID=68079635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910606990.6A Pending CN110306531A (en) 2019-07-06 2019-07-06 High water level erratic boulder stratum construction of diaphragm wall technique

Country Status (1)

Country Link
CN (1) CN110306531A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN111844358A (en) * 2020-06-12 2020-10-30 上海市基础工程集团有限公司 Method for manufacturing cement test block in cement continuous wall construction
CN112942310A (en) * 2021-01-26 2021-06-11 上海兴庚基础工程有限公司 Construction process of equal-thickness cement-soil stirring continuous wall
CN115627788A (en) * 2022-12-19 2023-01-20 中铁二十二局集团轨道工程有限公司 TRD (blast furnace pressure recovery device) reinforcement construction method for metro section connection channel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565945A (en) * 2009-05-19 2009-10-28 上海隧道工程股份有限公司 Application method of composite sodium-based bentonite on construction of underground continuous wall
CN108071128A (en) * 2018-01-10 2018-05-25 上海智平基础工程有限公司 A kind of chain saw type cutting box and its application in ultra-deep TRD engineering methods
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method
CN108951609A (en) * 2018-08-29 2018-12-07 北京市政建设集团有限责任公司 One kind being suitable for soft or hard uneven ovum gravel erratic boulder stratum construction method of underground continuous wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565945A (en) * 2009-05-19 2009-10-28 上海隧道工程股份有限公司 Application method of composite sodium-based bentonite on construction of underground continuous wall
CN108071128A (en) * 2018-01-10 2018-05-25 上海智平基础工程有限公司 A kind of chain saw type cutting box and its application in ultra-deep TRD engineering methods
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method
CN108951609A (en) * 2018-08-29 2018-12-07 北京市政建设集团有限责任公司 One kind being suitable for soft or hard uneven ovum gravel erratic boulder stratum construction method of underground continuous wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海市基础工程集团有限公司: "《等厚度水泥土搅拌墙技术规程》", 31 March 2018, 同济大学出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN111844358A (en) * 2020-06-12 2020-10-30 上海市基础工程集团有限公司 Method for manufacturing cement test block in cement continuous wall construction
CN112942310A (en) * 2021-01-26 2021-06-11 上海兴庚基础工程有限公司 Construction process of equal-thickness cement-soil stirring continuous wall
CN115627788A (en) * 2022-12-19 2023-01-20 中铁二十二局集团轨道工程有限公司 TRD (blast furnace pressure recovery device) reinforcement construction method for metro section connection channel

Similar Documents

Publication Publication Date Title
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN110306531A (en) High water level erratic boulder stratum construction of diaphragm wall technique
CN104846829B (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN106759379A (en) A kind of construction method of the asymmetric water-stop curtain of foundation ditch
CN110080237A (en) It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
CN104153352A (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN104564128A (en) Deformation monitoring method for shallow-buried excavation tunnel construction
CN106088099B (en) A kind of subway foundation pit anchor cable processing method
CN108589699A (en) A kind of interpolation H profile steel TRD walls and its construction method
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN106381864A (en) Cell wall strengthening method for underground diaphragm wall
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN102966110A (en) Vertically-combined type impermeable waterproof curtain structure and construction method thereof
CN111636455A (en) Comprehensive construction method of TRD (Top gas recovery device) and rotary drilling lead hole depth waterproof curtain
CN109403338A (en) A kind of assembly lattice configuration steel TRD engineering method diaphram wall and its construction method
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN105064381A (en) High-low cutting edge double-wall steel cofferdam reinforced concrete once bottom sealing construction method
CN108842802A (en) Piles in Karst Region base construction method
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN107956220A (en) A kind of prefabricated construction method for diaphragm walls based on TRD grooving
CN202954371U (en) Vertical combined type seepage-proofing waterproof curtain structure
CN103850261A (en) In-rock deep foundation pit rock-socketed water-stop curtain construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191008