CN110295738A - Shear wall formwork structure and construction method - Google Patents

Shear wall formwork structure and construction method Download PDF

Info

Publication number
CN110295738A
CN110295738A CN201910541392.5A CN201910541392A CN110295738A CN 110295738 A CN110295738 A CN 110295738A CN 201910541392 A CN201910541392 A CN 201910541392A CN 110295738 A CN110295738 A CN 110295738A
Authority
CN
China
Prior art keywords
template
fastener
sizing
shear wall
press strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910541392.5A
Other languages
Chinese (zh)
Inventor
刘奎
刘明周
廖红玉
余珊
孙广宏
桂祁东
黄达锴
方慧琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201910541392.5A priority Critical patent/CN110295738A/en
Publication of CN110295738A publication Critical patent/CN110295738A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0651One-piece elements
    • E04G17/0652One-piece elements fully recoverable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention belongs to rooms to build, piping lane construction field, more particularly to a kind of shear wall formwork structure, mainly formed by several template splicings, row's template erection positioned at bottom is on sizing bottom fastener, the sizing bottom fastener is L-type, it is uniformly provided with several first fore shaft plates along its length on the inside of the fastener of the sizing bottom, offers split bolt hole at each first fore shaft plate;Fastener in sizing is equipped between two layers neighbouring of template, fastener includes the second press strip of strip in the sizing, and second press strip side is uniformly provided with several second fore shaft plates along its length, is designed with split bolt hole at each second fore shaft plate;It is each to draw at bolt hole through the template of the fixed shear wall two sides of Screw arbor with nut at both-ends.The present invention reduces the process punched in template, cost has been saved, while having accelerated the duration, work progress is simple, and worker is easy to operate.

Description

Shear wall formwork structure and construction method
Technical field
The invention belongs to rooms to build, piping lane construction field, and in particular to a kind of shear wall formwork structure and construction method.
Background technique
Plank sheathing, the lumps of wood and steel pipe combination installation form are mostly used greatly in the shear wall formwork installation of civil buildings at present, Or the typified form formed with plank sheathing, the lumps of wood.Shi Douhui perforating in template is reinforced in installation, is added with Screw arbor with nut at both-ends Gu.As shown in fig. 7, when carrying out secondary turnover and reinforcing, but can to template perforating, while will also template to last time to pulling eye envelope It is stifled, and often closure is not tight, is easy spillage, causes coagulation soil flow pendant, sand holes, honeycomb, pitted skin etc., influence the appearance matter of concrete Amount.After multiple turnover, template is riddled with gaping wounds, not only influences the Forming Quality of concrete, has an effect on the number of turnover.And Template perforating blocks, and increases workload, also delays the duration.There are also use combined steel formworks to be installed, steel form weight Greatly, manually it is difficult to move, it is sometimes desirable to which lifting installation causes machine cost to increase, while steel form does not absorb water, concrete construction When bubble difficulty be discharged, concrete is easy to produce bubble, influences Surface Quality of Concrete.
Summary of the invention
In view of the above technical problems, the purpose of the present invention is to provide a kind of shear wall formwork structure and construction methods, originally Invention reduces the process punched in template, has saved cost, while accelerating the duration, work progress is simple, and worker easily grasps Make.
To achieve the above object, the technical solution used in the present invention is:
A kind of shear wall formwork structure is mainly spliced by several templates 4, it is characterised in that: positioned at row's mould of bottom Plate 4 is erected on sizing bottom fastener 1, and sizing bottom fastener 1 is L-type, and fastener 1 inside in the sizing bottom is uniform along its length Equipped with several first fore shaft plates 12, split bolt hole is offered at each first fore shaft plate 12;Neighbouring two layers of template 4 Between be equipped with fastener 3 in sizing, fastener 3 includes the second press strip 14 of strip, 14 side of the second press strip in the sizing It is uniformly provided with several second fore shaft plates 15 along its length, is designed with split bolt hole at each second fore shaft plate 15;Each drawing All pass through the template 4 of the fixed shear wall two sides of Screw arbor with nut at both-ends 5 at bolt hole.
Further, the vertical edge joint position of the template 4 is equipped with pressing plate 2.
Further, several flitch back cords 6 arranged vertically are uniformly provided on the outside of the template 4, the Screw arbor with nut at both-ends 5 Horizontally disposed steel pipe 7 is equipped between butterfly card 8 and flitch back cord 6.
Further, the sizing bottom fastener 1 includes horizontally disposed pressure foot 10 and the first press strip 11 arranged vertically, First press strip 11 connects l-shaped by nail with pressure foot 10, and the first fore shaft plate 12 is arranged vertically at the first press strip 11 inside.
Further, the triangle stiffener 13 for reinforcing is equipped between first press strip 11 and pressure foot 10.
Further, 10 bottom of pressure foot is equipped with foam mat 16.
A kind of construction method of shear wall formwork structure, it is characterised in that the following steps are included:
S1, sizing bottom fastener 1 make: the first press strip 11 and pressure foot 10 are respectively cut, with iron nail by the first press strip 11 and presser feet Plate 10 fixes l-shaped, the first fore shaft plate 12 is then fixed on 11 inside of the first press strip at a certain distance, then in the first fore shaft plate Split bolt hole is drilled out at 12, foam mat 16 is fixed on 10 bottom of pressure foot, and stiffener 13 is finally uniformly fixed on to Between one press strip 11 and pressure foot 10;
Fastener 3 makes in S2, sizing: the second fore shaft plate 15 is fixed on by the second press strip 14 of cutting between two parties up and down at a certain distance Then second press strip, 14 side drills out split bolt hole on the centre of the second fore shaft plate 15 again;
S3, the reinforcing bar binding for first carrying out shear wall, release template on wall ground floor plate and install control line, exist then along control line Sponge strip is pasted on floor;
S4, the sizing bottom fastener 1 that shear wall two sides are installed along sponge strip, while wearing Screw arbor with nut at both-ends 5;
S5, the assembly of one layer of template 4 is carried out in shear wall two sides, then pressing plate 2 is followed closely in the vertical edge joint position of template 4, with stent Plate 4;
Carry out shaping that middle fastener 3 is assembled on S6, template 4 then in step s 5, then in sizing fastener 3 prepared screw-bolt hole Wear split bolt 5;
S7, repeat step S4, S5 until the template 4 of whole face wall is installed;
S8, the installation for first carrying out flitch back cord 6, then the installation of steel pipe 7 of 5 two sides of split bolt is carried out, with the fixed steel of butterfly card 8 Then pipe is installed nut 9 on split bolt 5 and is reinforced to template 4, completes until the template 4 of whole face wall is reinforced.
The invention has the benefit that
1, the present invention allows all Screw arbor with nut at both-ends to pass through from sizing fastener, reinforces without punching in template, ensure that template Integrality improves the number of turnover of template, ensure that the molded appearance quality of concrete, reduces the work punched in template Sequence has saved cost, while having accelerated the duration, and work progress is simple, and worker is easy to operate.
2, template erecting bed of the present invention directly carries out the progress of assembled quickening, can form pipelining.
3, present invention sizing fastener is that carpenter processing factory is processed and formed at one time, and scene does not construct and makes an uproar without beating pulling eye Sound, green construction.
Detailed description of the invention
Fig. 1 is whole elevational schematic view of the invention.
Fig. 2 is schematic cross-section of the invention.
Fig. 3 is the schematic diagram in the present invention after local template assembly.
Fig. 4 be the present invention in sizing bottom fastener and be formed in fastener and template positional relationship stereoscopic schematic diagram.
Fig. 5 is the full-page proof schematic diagram of sizing bottom fastener in the present invention.
Fig. 6 is the full-page proof schematic diagram of fastener in sizing in the present invention.
Fig. 7 is that existing template plays the schematic diagram behind split bolt hole.
In figure: 1 sizing bottom fastener, 2 pressing plates, 3 sizing in fastener, 4 templates, 5 Screw arbor with nut at both-ends, 6 flitch back cords, 7 steel pipes, 8 Butterfly card, 9 nuts, 10 pressure foots, 11 first press strips, 12 first fore shaft plates, 13 stiffeners, 14 second press strips, 15 second fore shafts Plate, 16 foam mats.
Specific embodiment
For a better understanding of the present invention, technical solution of the present invention is done further below with reference to embodiment and attached drawing Explanation.
A kind of shear wall formwork structure is mainly spliced by several templates 4, and row's template 4 positioned at bottom is set up On sizing bottom fastener 1, sizing bottom fastener 1 is L-type, if fastener 1 inside in the sizing bottom is uniformly provided with along its length The first fore shaft plate 12 is done, offers split bolt hole at each first fore shaft plate 12;Sizing bottom fastener 1 includes horizontal cloth The pressure foot 10 set and the first press strip 11 arranged vertically, first press strip 11 connect l-shaped by nail with pressure foot 10 (i.e. angle steel type structure), the first fore shaft plate 12 are arranged vertically at the inside of the first press strip 11;First press strip 11 and pressure The triangle stiffener 13 for reinforcing is equipped between sole 10;10 bottom of pressure foot is equipped with foam mat 16.Phase up and down Fastener 3 in sizing is equipped between adjacent two layers of template 4, fastener 3 includes the second press strip 14 of strip in the sizing, and described the Two press strips, 14 side is uniformly provided with several second fore shaft plates 15 along its length, is designed at each second fore shaft plate 15 to drawing spiral shell Keyhole;It is each to draw the template 4 for passing through the fixed shear wall two sides of Screw arbor with nut at both-ends 5 at bolt hole.The vertical edge joint position of the template 4 Equipped with pressing plate 2;Several flitch back cords 6 arranged vertically, the butterfly card 8 of the Screw arbor with nut at both-ends 5 are uniformly provided on the outside of the template 4 Horizontally disposed steel pipe 7 is equipped between flitch back cord 6.
A kind of construction method of shear wall formwork structure, it is characterised in that the following steps are included:
S1, sizing bottom fastener 1 make: the first press strip 11 of 100mm wide and the pressure foot 10 of 50mm wide is respectively cut, it will with iron nail The first fore shaft of 50mm*100mm plate 12, is then fixed on by the first press strip 11 and the fixed l-shaped of pressure foot 10 by the spacing of 200mm First press strip, 11 inside, then split bolt hole is drilled out at the first fore shaft plate 12, foam mat 16 is fixed on 10 bottom of pressure foot Stiffener 13 is finally uniformly fixed between the first press strip 11 and pressure foot 10 by portion;
Fastener 3 makes in S2, sizing: the second press strip 14 of cutting 30mm wide presses the second fore shaft plate 15 of 50mm*100mm The spacing of 200mm is fixed on 14 side of the second press strip between two parties up and down, then drills out on the centre of the second fore shaft plate 15 to drawing again Bolt hole;
S3, the reinforcing bar binding for first carrying out shear wall, release template on wall ground floor plate and install control line, exist then along control line Sponge strip is pasted on floor;
S4, the sizing bottom fastener 1 that shear wall two sides are installed along sponge strip, while wearing Screw arbor with nut at both-ends 5;
S5, the assembly of one layer of template 4 is carried out in shear wall two sides, then pressing plate 2 is followed closely in the vertical edge joint position of template 4, with stent Plate 4;
Carry out shaping that middle fastener 3 is assembled on S6, template 4 then in step s 5, then in sizing fastener 3 prepared screw-bolt hole Wear split bolt 5;
S7, repeat step S4, S5 until the template 4 of whole face wall is installed;
S8, the installation for first carrying out flitch back cord 6, then the installation of steel pipe 7 of 5 two sides of split bolt is carried out, with the fixed steel of butterfly card 8 Then pipe is installed nut 9 on split bolt 5 and is reinforced to template 4, completes until the template 4 of whole face wall is reinforced.
Screw arbor with nut at both-ends uses Three-section water stop screw rod if any waterproof requirement according to technique in the above method, and no waterproof requirement is adopted With plastic bushing and common screw.
After adopting the above method the advantages of:
1, all Screw arbor with nut at both-ends 5 are allowed to pass through from sizing fastener (including fastener 3 in sizing bottom fastener 1 and sizing), without in mould It punches and reinforces on plate 4, ensure that the integrality of template 4, improve the number of turnover of template 4, improve outside the molding of concrete Appearance quality.And reduce and repeat perforating after template 4 is had enough to meet the need, block workload, construction efficiency is improved, construction stream is optimized Journey.
2, setting sizing bottom fastener 1 at the bottom of the shear wall wears Screw arbor with nut at both-ends 5 in the middle part of bottom fastener 1 of being formed, Screw arbor with nut at both-ends 5 from Ground is closer, prevents bottom from rising mould, rotten.
3, being formed in bottom fastener 1 has pressure foot 10, and pressure foot 10 installs level for the levelling guarantee template 4 in root, simultaneously The lower foam mat 16 of pressure foot 10, can prevent root spillage and bad root phenomenon to effectively being blocked at local out-of-flatness Generation;Pressure foot 10, foam mat 16 are set up directly on sizing bottom fastener 1, reduce each installation procedure, and can be with Recycling.
4, the press strip (including the first press strip 11 with the second press strip 14) of fastener of being formed can be connected using tongue and groove, improve mould 4 stability of plate, the quality of piece, mortar leakage prevention.
5, be formed bottom fastener 1, be equipped with fore shaft plate (the first fore shaft plate 12 and the second fore shaft plate 15) in fastener 3 in sizing, both Facilitate the assembly of template 4, it is also ensured that flatness, the verticality of template entirety, while preventing typified form from eating mould.
6, it is provided with pressing plate 2 between the vertical piece of template 4, improves piece leakproofness, prevents metope faulting of slab ends, improve smooth Degree;Fixed form 4 when helping template 4 assembled simultaneously, improves the stability of template 4;
7, sizing fastener is all made of live leftover pieces and is process, and gathers materials on the spot, and stock utilization is high;It is reusable, turnover Rate is high, meets green construction theory.
Described above is only Application Example of the invention, cannot limit the right model of the present invention with this certainly It encloses, therefore according to equivalence changes made by scope of the present invention patent, still belongs to protection scope of the present invention.

Claims (7)

1. a kind of shear wall formwork structure is mainly spliced, it is characterised in that: positioned at the one of bottom by several templates (4) Row template (4) is erected in sizing bottom fastener (1), and the sizing bottom fastener (1) is L-type, the interior lateral edge of sizing bottom fastener (1) Length direction is uniformly provided with several first fore shaft plates (12), offers split bolt hole at each first fore shaft plate (12);On Under be equipped with fastener (3) in sizing between adjacent two layers of template (4), fastener (3) includes the second pressure of strip in the sizing Item (14), the second press strip (14) side are uniformly provided with several second fore shaft plates (15), each second fore shaft along its length Plate is designed with split bolt hole at (15);It is each to draw the template for passing through Screw arbor with nut at both-ends (5) fixed shear wall two sides at bolt hole (4).
2. shear wall formwork structure according to claim 1, it is characterised in that: the vertical edge joint position of the template (4) is set There are pressing plate (2).
3. shear wall formwork structure according to claim 1, it is characterised in that: the template (4) is if outside is uniformly provided with The dry flitch back cord (6) arranged vertically is equipped with horizontal cloth between the butterfly card (8) and flitch back cord (6) of the Screw arbor with nut at both-ends (5) The steel pipe (7) set.
4. shear wall formwork structure according to claim 1, it is characterised in that: the sizing bottom fastener (1) includes level The pressure foot (10) of arrangement and the first press strip (11) arranged vertically, first press strip (11) and pressure foot (10) pass through nail L-shaped is connected, the first fore shaft plate (12) is arranged vertically at the inside of the first press strip (11).
5. shear wall formwork structure according to claim 4, it is characterised in that: first press strip (11) and pressure foot (10) the triangle stiffener (13) for reinforcing is equipped between.
6. shear wall formwork structure according to claim 4, it is characterised in that: pressure foot (10) bottom is equipped with sponge It pads (16).
7. a kind of construction method of shear wall formwork structure, it is characterised in that the following steps are included:
S1, sizing bottom fastener (1) production: the first press strip (11) and pressure foot (10) is respectively cut, with iron nail by the first press strip (11) and pressure foot (10) fixes l-shaped, and then the first fore shaft plate (12) is fixed at a certain distance in the first press strip (11) Side, then split bolt hole is drilled out at the first fore shaft plate (12), foam mat (16) is fixed on pressure foot (10) bottom, finally Stiffener (13) is uniformly fixed between the first press strip (11) and pressure foot (10);
Fastener (3) makes in S2, sizing: cutting the second press strip (14), and the second fore shaft plate (15) is placed in the middle up and down at a certain distance It is fixed on the second press strip (14) side, then drills out split bolt hole on the centre of the second fore shaft plate (15) again;
S3, the reinforcing bar binding for first carrying out shear wall, release template on wall ground floor plate and install control line, exist then along control line Sponge strip is pasted on floor;
S4, the sizing bottom fastener (1) that shear wall two sides are installed along sponge strip, while wearing Screw arbor with nut at both-ends (5);
S5, the assembly of one layer of template (4) is carried out in shear wall two sides, then follows closely pressing plate (2) in the vertical edge joint position of template (4), with Fixed form (4);
Middle fastener (3) assembly is carried out shaping on S6, template (4) then in step s 5, then in sizing fastener (3) it is reserved Bolt hole wears split bolt (5);
S7, repeat step S4, S5 until the template (4) of whole face wall is installed;
S8, the installation for first carrying out flitch back cord (6), then steel pipe (7) installation of split bolt (5) two sides is carried out, block (8) with butterfly Then fixed steel pipe is installed nut (9) on split bolt (5) and is reinforced to template (4), until the template (4) of whole face wall It reinforces and completes.
CN201910541392.5A 2019-06-21 2019-06-21 Shear wall formwork structure and construction method Pending CN110295738A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910541392.5A CN110295738A (en) 2019-06-21 2019-06-21 Shear wall formwork structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910541392.5A CN110295738A (en) 2019-06-21 2019-06-21 Shear wall formwork structure and construction method

Publications (1)

Publication Number Publication Date
CN110295738A true CN110295738A (en) 2019-10-01

Family

ID=68028385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910541392.5A Pending CN110295738A (en) 2019-06-21 2019-06-21 Shear wall formwork structure and construction method

Country Status (1)

Country Link
CN (1) CN110295738A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236306A (en) * 2020-01-17 2020-06-05 中国十七冶集团有限公司 Root rot treatment and construction method for shear wall root
CN111549690A (en) * 2020-04-10 2020-08-18 哈尔滨工业大学 Low-cost and high-performance rainwater box culvert combined structure and construction method thereof
CN112144887A (en) * 2020-09-16 2020-12-29 北京九洋建设工程有限公司 Concrete member slurry leakage prevention structure
CN112443159A (en) * 2020-12-02 2021-03-05 中建三局集团有限公司 Template tapping-free clamp and construction method thereof
CN113266144A (en) * 2021-05-26 2021-08-17 五冶集团上海有限公司 Improved shear wall template reinforcing method
CN114046039A (en) * 2021-10-13 2022-02-15 北京市第三建筑工程有限公司 Template reinforcing structure at wall joint and construction method thereof
CN114351745A (en) * 2021-12-01 2022-04-15 中建八局第二建设有限公司 Intercepting device for shear wall dam of post-cast strip of ultra-thick raft plate and construction method of intercepting device
CN114892960A (en) * 2022-04-25 2022-08-12 中国一冶集团有限公司 Oil-immersed reinforced shear wall shaping wood formwork and construction method thereof
CN115772994A (en) * 2021-09-06 2023-03-10 瑞洲建设集团有限公司 Frame structure basement wall wood formwork installation construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202990418U (en) * 2012-08-10 2013-06-12 中国二冶集团有限公司 Slurry-leaking protection device preventing cast-in-place concrete column root from rotting
CN203034795U (en) * 2013-01-30 2013-07-03 浙江凯雄科技有限公司 Plate and strip combined type stand wall formwork
CN203769300U (en) * 2014-01-09 2014-08-13 苏鸿飞 Building template
CN204081483U (en) * 2014-09-23 2015-01-07 中建四局第三建筑工程有限公司 A kind of structure of rotten when preventing pouring reinforcement concrete post suspension column
CN204186070U (en) * 2014-08-26 2015-03-04 深圳市程捷模架科技有限公司 Anti-rotten aluminum alloy mould plate system and L-type template
CN105275198A (en) * 2014-07-02 2016-01-27 中国华冶科工集团有限公司 A shear wall formwork reinforcing construction method
CN105649321A (en) * 2016-03-17 2016-06-08 中国五冶集团有限公司 Assembly system and assembly method for shear wall templates
CN106639301A (en) * 2017-02-17 2017-05-10 中国五冶集团有限公司 Aluminum cyclostyle and concrete wall bottom rot protective structure
JP2017133290A (en) * 2016-01-29 2017-08-03 Jfe建材株式会社 Detachment prevention metal for flat deck plate and construction method of concrete floor
CN107965138A (en) * 2017-11-22 2018-04-27 南通四建集团有限公司 A kind of aluminum alloy mould plate wall bottom caulking joint constructing structure
CN208168363U (en) * 2018-03-30 2018-11-30 中国十七冶集团有限公司 A kind of device preventing concrete column mould bottom spillage
CN109736562A (en) * 2019-02-16 2019-05-10 中建一局集团第一建筑有限公司 Cast-in-place concrete shear wall template punching-free reinforcing system and construction method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202990418U (en) * 2012-08-10 2013-06-12 中国二冶集团有限公司 Slurry-leaking protection device preventing cast-in-place concrete column root from rotting
CN203034795U (en) * 2013-01-30 2013-07-03 浙江凯雄科技有限公司 Plate and strip combined type stand wall formwork
CN203769300U (en) * 2014-01-09 2014-08-13 苏鸿飞 Building template
CN105275198A (en) * 2014-07-02 2016-01-27 中国华冶科工集团有限公司 A shear wall formwork reinforcing construction method
CN204186070U (en) * 2014-08-26 2015-03-04 深圳市程捷模架科技有限公司 Anti-rotten aluminum alloy mould plate system and L-type template
CN204081483U (en) * 2014-09-23 2015-01-07 中建四局第三建筑工程有限公司 A kind of structure of rotten when preventing pouring reinforcement concrete post suspension column
JP2017133290A (en) * 2016-01-29 2017-08-03 Jfe建材株式会社 Detachment prevention metal for flat deck plate and construction method of concrete floor
CN105649321A (en) * 2016-03-17 2016-06-08 中国五冶集团有限公司 Assembly system and assembly method for shear wall templates
CN106639301A (en) * 2017-02-17 2017-05-10 中国五冶集团有限公司 Aluminum cyclostyle and concrete wall bottom rot protective structure
CN107965138A (en) * 2017-11-22 2018-04-27 南通四建集团有限公司 A kind of aluminum alloy mould plate wall bottom caulking joint constructing structure
CN208168363U (en) * 2018-03-30 2018-11-30 中国十七冶集团有限公司 A kind of device preventing concrete column mould bottom spillage
CN109736562A (en) * 2019-02-16 2019-05-10 中建一局集团第一建筑有限公司 Cast-in-place concrete shear wall template punching-free reinforcing system and construction method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236306A (en) * 2020-01-17 2020-06-05 中国十七冶集团有限公司 Root rot treatment and construction method for shear wall root
CN111549690A (en) * 2020-04-10 2020-08-18 哈尔滨工业大学 Low-cost and high-performance rainwater box culvert combined structure and construction method thereof
CN112144887B (en) * 2020-09-16 2022-03-11 北京九洋建设工程有限公司 Concrete member slurry leakage prevention structure
CN112144887A (en) * 2020-09-16 2020-12-29 北京九洋建设工程有限公司 Concrete member slurry leakage prevention structure
CN112443159A (en) * 2020-12-02 2021-03-05 中建三局集团有限公司 Template tapping-free clamp and construction method thereof
CN113266144A (en) * 2021-05-26 2021-08-17 五冶集团上海有限公司 Improved shear wall template reinforcing method
CN115772994A (en) * 2021-09-06 2023-03-10 瑞洲建设集团有限公司 Frame structure basement wall wood formwork installation construction method
CN114046039A (en) * 2021-10-13 2022-02-15 北京市第三建筑工程有限公司 Template reinforcing structure at wall joint and construction method thereof
CN114046039B (en) * 2021-10-13 2023-11-21 北京市第三建筑工程有限公司 Template reinforcing structure at joint of wall and construction method thereof
CN114351745A (en) * 2021-12-01 2022-04-15 中建八局第二建设有限公司 Intercepting device for shear wall dam of post-cast strip of ultra-thick raft plate and construction method of intercepting device
CN114351745B (en) * 2021-12-01 2023-10-13 中建八局第二建设有限公司 Super-thick raft post-pouring strip shear wall dam interception device and construction method thereof
CN114892960A (en) * 2022-04-25 2022-08-12 中国一冶集团有限公司 Oil-immersed reinforced shear wall shaping wood formwork and construction method thereof
CN114892960B (en) * 2022-04-25 2023-10-24 中国一冶集团有限公司 Oil-immersed reinforced shear wall shaping wood template and construction method thereof

Similar Documents

Publication Publication Date Title
CN110295738A (en) Shear wall formwork structure and construction method
CN105888108B (en) Built-in positioning prefabricated component reinforced concrete shear wall and construction method
CN107700710A (en) Fill wall construction column template design checking and construction method
CN110374322A (en) A kind of assembled waffle beam plate device
CN103696359A (en) Prefabricated and cast-in-place bridge pier structure and construction method
CN107893529A (en) Suitable for deep basal pit outer wall of basement PC template systems and its construction method
CN207988490U (en) A kind of easy device that deformation joint shear wall formwork installs
CN104088473A (en) Construction structure and method used for underpinning load-bearing wall
CN206319592U (en) A kind of post-cast strip concrete side plugging structure
CN205134664U (en) A upper and lower double -deck concrete slab structure for girder steel
CN107761759A (en) A kind of L-type concrete guard wall
CN108035544A (en) Expansion joint position shear wall side formwork reinforcing device and construction method
CN104563485B (en) Building formwork system
CN115525954A (en) Special-shaped column template accurate manufacturing, installing and constructing method based on BIM technology
CN206110422U (en) Prefabricated sound insulation floor that keeps warm of lattice formula
CN207813014U (en) Turnover type dense rib plate plastic film shell seam processing device
CN204040457U (en) Wood frame plastic formwork system
CN212835512U (en) Circular inspection shaft template
CN104131697B (en) Tool type formwork system for kitchen and bath concrete waterproof guide wall and construction method of tool type formwork system
CN209384636U (en) A kind of cylinder connect formwork reinforcement structure with shear wall
CN207484961U (en) A kind of novel wall column steel form
CN207582762U (en) Top has the steel column external wrapping concrete constructing structure of floor support plate
US2217675A (en) Concrete building structure
CN207568175U (en) Beams of concrete side template it is non-to pull-type screw bolt reinforcing structure
CN104264992A (en) High-rise building inter-pipeline construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191001