CN110281347A - A kind of construction site small-size concrete prefabricated section production method - Google Patents

A kind of construction site small-size concrete prefabricated section production method Download PDF

Info

Publication number
CN110281347A
CN110281347A CN201910731259.6A CN201910731259A CN110281347A CN 110281347 A CN110281347 A CN 110281347A CN 201910731259 A CN201910731259 A CN 201910731259A CN 110281347 A CN110281347 A CN 110281347A
Authority
CN
China
Prior art keywords
concrete
steel die
construction site
prefabricated section
small
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910731259.6A
Other languages
Chinese (zh)
Inventor
吴文兵
何海英
张传浩
何强
柳健
王亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
General Contracting Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201910731259.6A priority Critical patent/CN110281347A/en
Publication of CN110281347A publication Critical patent/CN110281347A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/04Producing shaped prefabricated articles from the material by tamping or ramming
    • B28B1/045Producing shaped prefabricated articles from the material by tamping or ramming combined with vibrating or jolting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/093Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/38Treating surfaces of moulds, cores, or mandrels to prevent sticking
    • B28B7/388Treating surfaces of moulds, cores, or mandrels to prevent sticking with liquid material, e.g. lubricating

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)

Abstract

The present invention proposes a kind of construction site small-size concrete prefabricated section production method.Production steel die selects the place of surfacing using as the bottom plate of steel die, mold cleaning and brushing release agent, concreting pour in two times on side wall and reamer is closely knit, the concrete for being higher by steel die upper surface is struck off floating by floating tool at the construction field (site);According to the conditions such as temperature after setting time climbing form, conserved according to temperature and place situation concrete precast block.Have the advantages that require working space low, construction efficiency is high, it is at low cost, can be recycled, is simple to operate, finished surface quality it is high.

Description

A kind of construction site small-size concrete prefabricated section production method
Technical field
The present invention relates to a kind of construction site small-size concrete prefabricated section production methods.
Background technique
In building engineering construction, it is often necessary to some small-sized concrete precast blocks, since dosage is little, if using Batch production is customized, then is transported to construction site, and will increase construction cost.At this point, often all carrying out prefabricated processing at the construction field (site). When carrying out prefabricated processing at the construction field (site), traditional way is, using plank sheathing processing and fabricating mold, mold by baffle, partition, Fixture and split bolt composition.It is slotted on baffle according to the size of prefabricated section, partition is stuck in the slot of baffle by when installation, group It is reinforced after the completion of dress with split bolt.When one group of concrete precast block after processing is completed removes mold, then production is installed Next group of concrete precast block.The method installation and demolishing process it is cumbersome, time-consuming, low efficiency, after a period of use due to Mold is damaged, must re-start mold processing and prepare.Dismounting mold is completed the process in one group of concrete precast block to re-assembly When, the concrete being bonded on baffle and partition is not easily cleaned, and the concrete cleaning being especially bonded in baffle plate groove is got up more troublesome. Due to being assembled mold, concrete precast block is caused to deform if reinforcing and loosely will cause mold distortion, due to needing to use when removing Iron hammer beats, and therefore, it is longer to remove the time, dismountable, iron hammer when dismounting of generally completing 24 hours rears in concreting It beats and be easy to cause concrete precast block losing fangle, influence the presentation quality of concrete precast block.
Summary of the invention
The present invention proposes a kind of construction site small-size concrete prefabricated section production method, to solve existing construction site processing The concrete that existing mold attaching/detaching is inconvenient when small-size concrete prefabricated section, consuming time is long, processing efficiency is low, processes Prefabricated section there is technical issues that deformation, losing fangle etc..
The technical scheme of the present invention is realized as follows: construction site small-size concrete prefabricated section production method, including with Lower step:
S1, make steel die according to the prefabricated block size of small-size concrete, steel die include the coaming plate being fixed to each other, partition and Handle, coaming plate and partition surround the mold cavity of multiple upper/lower terminal openings;
S2, select the place of surfacing using the bottom plate as steel die at the construction field (site), to the flatness in the place of selection It is required that being not more than 2mm;
S3, cleaning and the brushing release agent on side wall are carried out to mold cavity;
S4, by concreting in each mold cavity, until covering the medium line of short transverse of mold cavity, pass through shake Dynamic device shock to it closely knit, continues the casting concrete into mold cavity, shock to it again by vibrator closely knit;
S5, by side be scraper plate, the floating tool that side is slicking-in roller strikes off the concrete for being higher by steel die upper surface;
S6, according to the slump of temperature and concrete, after reaching setting time after the completion of concreting, by handle by steel The separation to realize steel die and concrete precast block is proposed on molding jig;
S7, the concrete precast block after separating in S6 is conserved according to temperature and place situation.
On the basis of above scheme, further improvement is as follows, and in S6, the setting time of summer is 1-1.5 hours, The setting time of spring and autumn is 2-2.5 hours, and the setting time in winter is 4-4.5 hours.Need to according to the slump of concrete and Temperature height, grasps the demoulding time of concrete, too early, be easy to cause concrete Collapse Deformation, too late, be easy to cause demoulding It is difficult.
It on the basis of above scheme, is further improved as follows, when winter construction, is added and early resists by force in concrete production Freeze agent, in maintenance, the sprinkling maintenance time is not less than 14 days.
On the basis of above scheme, further improvement is as follows, and in S7, the sprinkling maintenance time is not less than 7 days, is making When narrow field, stacking is concentrated to conserve concrete precast block after concrete precast block demoulds 24 hours.
On the basis of above scheme, further improvement is as follows, in S2, carries out coagulation to the place that construction site is chosen Native cure process carries out press polish processing to surface.
On the basis of above scheme, further improvement is as follows, and the scraper plate two sides of the floating tool used in S5 are set Have for the baffle with the limit cooperation of the two sides side guide of steel die, and the distance before two baffles is adjustable.It is convenient Floating tool and can disposably be completed to smooth out along the length direction guiding movement of steel die, improve and smooth out efficiency.
Using above-mentioned technical proposal, the invention has the benefit that
(1) working space is required low, particular/special requirement is not done to working space size, place only need it is smooth, due to demoulding Fastly, batch production, mass production have been basically reached, construction efficiency is improved, has accelerated construction speed;
(2) plank sheathing assembly mold way is used compared to traditional, since mold is steel die, is prepared without recycling, once Investment, is used for a long time, and saves Master Cost and mold processing charges, and the climbing form time is short, highly shortened prefabricated components Climbing form time and fabrication cycle save a large amount of cost of labor expenses, and cost of labor reduces, low in cost;
(3) construction technology is simple, is easily mastered, and compared to wood mould and other steel assembly molds, this engineering method construction technology is extremely Simply, it is not required to train, be easily mastered without assembled and dismounting, operator;
(4) finish is good, presentation quality is good, and mold is made of steel plate, indeformable, and is easy cleaning, and the concrete of production is pre- Scantling processed is correct, upright, and presentation quality is good;
(5) effect is high, and compared with other molds need assembled and dismounting, this engineering method is without recycling assembled and removing, by original " demoulding " is changed to " climbing form " method, highly shortened " climbing form " time and the fabrication cycle of prefabricated components, and effect is high.According to scene Comparison makes concrete prefabricated element using this engineering method, and effect can be improved 300% or more.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention without any creative labor, may be used also for those of ordinary skill in the art To obtain other drawings based on these drawings.
Fig. 1 is small-size concrete prefabricated section production method a kind of process flow of specific embodiment in construction site of the invention Figure;
Fig. 2 is the top view of steel die;
Fig. 3 is the cross-sectional view in Fig. 2 at A-A;
Fig. 4 is the usage state diagram of floating tool;
Fig. 5 is the partial enlarged view in Fig. 4 at A;
Fig. 6 is the usage state diagram of baffle;
Wherein: 1- steel die, 11- coaming plate, 12- partition, 13- handle, 14- mold cavity, 2- concrete precast block, 3- smooth out work Tool, 31- handle, 32- scraper plate, 33- slicking-in roller, 34- baffle, 35- adjust stud, 36- shaft.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The specific embodiment of construction site small-size concrete prefabricated section production method of the invention: the small-sized coagulation in construction site Native prefabricated section production method, comprising the following steps:
S1, steel die is made according to the prefabricated block size of small-size concrete, as Figure 2-3, steel die 1 includes being fixed to each other Coaming plate 11, partition 12 and handle 13, coaming plate 11 and partition 12 surround the mold cavity 14 of multiple upper/lower terminals openings, steel die Has 1 lower part without bottom surface, whole use is welded;
S2, select the place of surfacing using the bottom plate as steel die 1 at the construction field (site), to the flatness in the place of selection It is required that being not more than 2mm;
S3, cleaning and the brushing release agent on side wall are carried out to mold cavity 14;
S4, by concreting in each mold cavity 14, until covering the medium line of short transverse of mold cavity 14, lead to It crosses vibrator and it shock closely knit, continue the casting concrete into mold cavity 14, it is shaken again by vibrator Puddling is real;
S5, as Figure 4-Figure 6, steel die 1 will be higher by by the floating tool 3 that side is scraper plate 32, side is slicking-in roller 33 The concrete of upper surface strikes off, and smoothing out tool 3 includes the slicking-in roller of handle 31, base shaft, shaft 36, rolling assembling in shaft 36 33, the scraper plate 32 fixed relative to base shaft, scraper plate 32 two sides be equipped with that threaded hole, there are two baffles by adjusting the installation of stud 35 34, the outer end for adjusting stud 35 is equipped with annular groove, and 34 rolling assembling of baffle is at annular groove with just axial block, circumferential direction can Rotation adjusts stud 35 and can realize the adjusting of distance between two baffles 34 by screwing, and when use is blocked by two baffles 34 In the two sides of the width direction of steel die 1, concrete is flattened in steel die 1 by slicking-in roller 33, passes through scraper plate 32 The concrete for being higher by 1 upper surface of steel die is struck off below, realizes and smoothes out;
S6, according to the slump of temperature and concrete, after reaching setting time after the completion of concreting, pass through handle 13 will Steel die 1 above proposes the separation to realize steel die 1 Yu concrete precast block 2;
S7, the concrete precast block 2 after separating in S6 is conserved according to temperature and place situation.
In S6, the setting time of summer is 1-1.5 hours, and the setting time of spring and autumn is 2-2.5 hours, winter Setting time is 4-4.5 hours.The demoulding time of concrete, mistake need to be grasped according to slump and the temperature height of concrete It is early, it is be easy to cause concrete Collapse Deformation, too late, be easy to cause demoulding difficult.
When winter construction, early strong antifreeze is added in concrete production, in maintenance, the sprinkling maintenance time is not less than 14 It.
In S7, the sprinkling maintenance time is not less than 7 days, small in the demoulding 24 of concrete precast block 2 when making narrow field When after by concrete precast block 2 concentrate pile up conserve.
In S2, concrete hardening processing is carried out to the place that construction site is chosen, press polish processing is carried out to surface.
32 two sides of scraper plate of floating tool 3 used in S5 are equipped with for the two sides side guide with steel die 1 The baffle 34 of cooperation is limited, and the distance before two baffles 34 is adjustable.Facilitate floating tool 3 along the length of steel die 1 Direction guiding movement is spent, and can disposably complete to smooth out, improves and smoothes out efficiency.
The characteristics of this method:
(1) working space is required low, particular/special requirement is not done to working space size, place only need it is smooth, due to demoulding Fastly, batch production, mass production have been basically reached, construction efficiency is improved, has accelerated construction speed;
(2) plank sheathing assembly mold way is used compared to traditional, since mold is steel die, is prepared without recycling, once Investment, is used for a long time, and saves Master Cost and mold processing charges, and the climbing form time is short, highly shortened prefabricated components Climbing form time and fabrication cycle save a large amount of cost of labor expenses, and cost of labor reduces, low in cost;
(3) construction technology is simple, is easily mastered, and compared to wood mould and other steel assembly molds, this engineering method construction technology is extremely Simply, it is not required to train, be easily mastered without assembled and dismounting, operator;
(4) finish is good, presentation quality is good, and mold is made of steel plate, indeformable, and is easy cleaning, and the concrete of production is pre- Scantling processed is correct, upright, and presentation quality is good;
(5) effect is high, and compared with other molds need assembled and dismounting, this engineering method is without recycling assembled and removing, by original " demoulding " is changed to " climbing form " method, highly shortened " climbing form " time and the fabrication cycle of prefabricated components, and effect is high.According to scene Comparison makes concrete prefabricated element using this engineering method, and effect can be improved 300% or more.
Technological principle: carrying out mold according to the specification size of concrete prefabricated element using 3mm thick steel plate and be welded, the mold It is made of surrounding baffle, intermediate bulkhead and handle, no bed die.It, only need to be in smooth location when making concrete prefabricated element On, one layer of release agent is brushed after steel mold inner surface is cleaned out, and then concrete is poured into and pour in steel die smashing It is closely knit, when climbing form, the ambilateral handle of mould is held, mold is gently lifted.It should be noted that when one group of prefabricated component After the completion of concreting, the demoulding time of concrete need to be grasped according to slump and the temperature height of concrete, too early, It is be easy to cause concrete Collapse Deformation, too late, be easy to cause demoulding difficult.It is learnt according to site operation experience, under normal circumstances The climbing form time carries out between 1~1.5 hour after the completion of concreting when summer makes, and the climbing form time exists when spring and autumn makes It is carried out between 2~2.5 hours after the completion of concreting, the climbing form time is 4~5 small after the completion of concreting when winter makes When between carry out.
When Specific construction, as shown in Figure 1:
1 preparation of construction: place where prefabricated component template must keep smooth, template bottom flatness≤2mm.Mould inner wall is cleared up Completely, and brushing release agent.
2 filling concretes: commerical ready-mixed concrete being poured into two times, and is poured dense respectively, and pouring should use after smashing in time Wooden float, which is rubbed with the hands, puts down, and removes extra laitance.
3 climbing forms: when climbing form, the ambilateral handle of mould is held, mold is vertically gently lifted.It should be noted that when one After the completion of group prefabricated components concreting, the climbing form of concrete need to be grasped according to slump and the temperature height of concrete Time be easy to cause concrete Collapse Deformation too early, too late, be easy to cause demoulding difficult.It is learnt according to site operation experience, The climbing form time carries out between 1~1.5 hour after the completion of concreting when summer makes under normal circumstances, when spring and autumn makes The climbing form time carries out between 2~2.5 hours after the completion of concreting, and the climbing form time is complete in concreting when winter makes At being carried out between latter 4~5 hours.
4 maintenances: after climbing form, according to temperature situation in time to finished product sprinkling maintenance, curing time is no less than 7d.If Narrow field is made, prefabricated components can be concentrated after demoulding 24 hours and continue maintenance to 7 days after piling up.Such as winter construction, a side Early strong antifreeze is added in face in concrete production, on the other hand carries out and reinforces Insulation after pouring, curing time is many In 14d.
Construction embodiment:
1 certain city's urgent disorder in orthopaedics hospital Inpatient Building engineering
The engineering is located at certain city hongli main road 389, basement one, 17 layers of ground, frame structure, overall floorage: 29902 Square metre.Starting date: on March 18th, 2011, time of accomplishment: on September 9th, 2012.Total construction period: 542 days.
2 certain county town Long Yuanxin Cheap Renting Houses
The project is located at certain city, new district Huashan road, Plain and Jia Lingjiang River road intersection, shear wall structure, including 13 22~32 floor Starting date: skyscraper and building for commercial use, underground garage, 16.51 ten thousand m2 of overall floorage are completed day on March 20th, 2013 Phase: on March 1st, 2015.
3 certain city, new district, Plain " town Long Yuanxin second phase " peasant's housing for survivor project
The project is located at certain city, new district Plain main road, Plain and Central Region main road intersection Bei Duan northeast corner, by plot four and plot five Composition, wherein plot four is the town Long Yuanxin primary school, and frame structure, construction area is 9764.49 13 ㎡;Plot five includes 8 17 ~26 storey buildings and building for commercial use, underground garage, Community Service Center, shear wall structure, construction area 124366.99 ㎡.Overall floorage is 134131.48 ㎡, December 25 2014 starting date, time of accomplishment: on November 20th, 2017.
Engineering evaluation:
The above engineering is all made of this method processing small-size concrete prefabricated component, buys compared to from precast plant, has saved prefabricated component Transport and loading-unloading vehicle expense.Compared to other wooden model assembly molds, production need to be prepared since wooden model breakage turnover rate is low repeatedly by reducing Raw artificial and Master Cost.Product size is correct, and climbing form is fast, and perception is good.Batch production, mass production are reached.Ensuring Work efficiency improves 300% or more while product quality, obtains the one of other units of taking part in building and local administrative department for construction Cause favorable comment.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (6)

1. construction site small-size concrete prefabricated section production method, which comprises the following steps:
S1, make steel die according to the prefabricated block size of small-size concrete, steel die include the coaming plate being fixed to each other, partition and Handle, coaming plate and partition surround the mold cavity of multiple upper/lower terminal openings;
S2, select the place of surfacing using the bottom plate as steel die at the construction field (site), to the flatness in the place of selection It is required that being not more than 2mm;
S3, cleaning and the brushing release agent on side wall are carried out to mold cavity;
S4, by concreting in each mold cavity, until covering the medium line of short transverse of mold cavity, pass through shake Dynamic device shock to it closely knit, continues the casting concrete into mold cavity, shock to it again by vibrator closely knit;
S5, by side be scraper plate, the floating tool that side is slicking-in roller strikes off the concrete for being higher by steel die upper surface;
S6, according to the slump of temperature and concrete, after reaching setting time after the completion of concreting, by handle by steel The separation to realize steel die and concrete precast block is proposed on molding jig;
S7, the concrete precast block after separating in S6 is conserved according to temperature and place situation.
2. small-size concrete prefabricated section production method in construction site according to claim 1, which is characterized in that in S6, The setting time of summer is 1-1.5 hours, and the setting time of spring and autumn is 2-2.5 hours, and the setting time in winter is 4-4.5 Hour.
3. small-size concrete prefabricated section production method in construction site according to claim 1 or 2, which is characterized in that winter When construction, early strong antifreeze is added in concrete production, in maintenance, the sprinkling maintenance time is not less than 14 days.
4. small-size concrete prefabricated section production method in construction site according to claim 1 or 2, which is characterized in that in S7 In, the sprinkling maintenance time is not less than 7 days, when making narrow field, by concrete after concrete precast block demoulds 24 hours Prefabricated section is concentrated to pile up and be conserved.
5. small-size concrete prefabricated section production method in construction site according to claim 1 or 2, which is characterized in that in S2 In, concrete hardening processing is carried out to the place that construction site is chosen, press polish processing is carried out to surface.
6. small-size concrete prefabricated section production method in construction site according to claim 1 or 2, which is characterized in that in S5 Used in the scraper plate two sides of floating tool be equipped with for the baffle with the limit cooperation of the two sides side guide of steel die, and And the distance before two baffles is adjustable.
CN201910731259.6A 2019-08-08 2019-08-08 A kind of construction site small-size concrete prefabricated section production method Pending CN110281347A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910731259.6A CN110281347A (en) 2019-08-08 2019-08-08 A kind of construction site small-size concrete prefabricated section production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910731259.6A CN110281347A (en) 2019-08-08 2019-08-08 A kind of construction site small-size concrete prefabricated section production method

Publications (1)

Publication Number Publication Date
CN110281347A true CN110281347A (en) 2019-09-27

Family

ID=68025095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910731259.6A Pending CN110281347A (en) 2019-08-08 2019-08-08 A kind of construction site small-size concrete prefabricated section production method

Country Status (1)

Country Link
CN (1) CN110281347A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114505940A (en) * 2021-12-29 2022-05-17 苏州良浦住宅工业有限公司 Process for forming rough surface of prefabricated part by using steel plate
CN114589794A (en) * 2022-01-21 2022-06-07 中铁二十局集团有限公司 Concrete prefabricated small component mold and using method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0433591A2 (en) * 1989-12-22 1991-06-26 Fear S.P.A. Method and means for forming blocks from concrete mix at a high production rate and with high shape definition, and the product obtained
CN204935857U (en) * 2015-08-19 2016-01-06 长江宜昌航道工程局 A kind of large area integrated units row mould
CN205347937U (en) * 2015-12-09 2016-06-29 重庆飞强混凝土有限公司 Concrete paving device
CN206158352U (en) * 2016-09-08 2017-05-10 河北省高速公路青银管理处 Isolated gate basis prefabricated mould
CN207031978U (en) * 2017-05-26 2018-02-23 马文涛 A kind of construction concrete flattening device
CN108247812A (en) * 2018-01-31 2018-07-06 舒子杨 A kind of production method of precast concrete

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0433591A2 (en) * 1989-12-22 1991-06-26 Fear S.P.A. Method and means for forming blocks from concrete mix at a high production rate and with high shape definition, and the product obtained
CN204935857U (en) * 2015-08-19 2016-01-06 长江宜昌航道工程局 A kind of large area integrated units row mould
CN205347937U (en) * 2015-12-09 2016-06-29 重庆飞强混凝土有限公司 Concrete paving device
CN206158352U (en) * 2016-09-08 2017-05-10 河北省高速公路青银管理处 Isolated gate basis prefabricated mould
CN207031978U (en) * 2017-05-26 2018-02-23 马文涛 A kind of construction concrete flattening device
CN108247812A (en) * 2018-01-31 2018-07-06 舒子杨 A kind of production method of precast concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114505940A (en) * 2021-12-29 2022-05-17 苏州良浦住宅工业有限公司 Process for forming rough surface of prefabricated part by using steel plate
CN114589794A (en) * 2022-01-21 2022-06-07 中铁二十局集团有限公司 Concrete prefabricated small component mold and using method thereof

Similar Documents

Publication Publication Date Title
CN104963289B (en) A kind of abnormity pier stud mass concrete overall time pouring construction method
CN100469995C (en) Construction method for after-pouring band beam-slab template
CN110281347A (en) A kind of construction site small-size concrete prefabricated section production method
CN106113230B (en) The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need
Safa et al. A decision-making method for choosing concrete forming systems
CN110126064B (en) Double-skin wall production method
CN104972550A (en) Multilateral mould of site precast concrete pile and manufacturing method of precast concrete pile
CN109267585A (en) Assembled prismoid shaped basis and rod structure and assembly method
CN108930361A (en) Prefabricated superposed column, assembled architecture body and assembled architecture body method of construction
AU2010257396A1 (en) A method of forming protrusions on a masonry block
CN209686711U (en) Prefabricated laminated superposed column, reinforced column and assembled architecture body
JP7112635B1 (en) U-shaped throwaway formwork for rising foundations of buildings
CN107938845A (en) A kind of concrete prefabricated assembling combining structures of FRP
CN208502251U (en) A kind of assembly type step type pump line mouth can formwork
CN106968366A (en) A kind of construction method for pouring constructional column free removal template
CN102220808A (en) Beam lowering construction method of frame structure
CN105625190B (en) Bridge combination type construction method
CN112681750A (en) Concrete pouring construction method for large steel mould independent high and large column with column cap
CN106914984A (en) A kind of construction method of prefabricated composite construction board
CN208996313U (en) Prefabricated superposed column, reinforced column and assembled architecture body
CN101240569A (en) In-situ integrated placing construction method for aerated concrete wall
CN209350490U (en) A kind of construction site small-size concrete prefabricated section producing device
JP2552435B2 (en) Installation method of retaining wall
CN105986623A (en) Construction method for concrete embedded parts
CN110185254A (en) A kind of Combined aluminum alloy template system and its application method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 450000 No. 116 Chengdong Road, Jinshui District, Henan, Zhengzhou

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20210423

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Applicant after: China Construction Seventh Bureau General Contracting Co.,Ltd.

Address before: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190927

RJ01 Rejection of invention patent application after publication