CN209350490U - A kind of construction site small-size concrete prefabricated section producing device - Google Patents
A kind of construction site small-size concrete prefabricated section producing device Download PDFInfo
- Publication number
- CN209350490U CN209350490U CN201821458405.XU CN201821458405U CN209350490U CN 209350490 U CN209350490 U CN 209350490U CN 201821458405 U CN201821458405 U CN 201821458405U CN 209350490 U CN209350490 U CN 209350490U
- Authority
- CN
- China
- Prior art keywords
- die ontology
- baffle
- prefabricated section
- partition
- transverse
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Moulds, Cores, Or Mandrels (AREA)
Abstract
The utility model discloses a kind of construction site small-size concrete prefabricated section producing devices, including die ontology, the both ends of the die ontology are provided with a handle, the inside of the die ontology includes two longitudinal baffles being parallel to each other and two transverse baffles being parallel to each other, partition is disposed between two transverse baffles, two handles are fixed on the both ends of die ontology by welding, it is connected between the longitudinal baffle and transverse baffle for integral type, it is to be vertically arranged between the partition and transverse baffle, the partition is fixed on by welding between two transverse baffles, it is covered on the inner wall of the die ontology and is connected to release agent.The utility model passes through setting die ontology, handle, longitudinal baffle, transverse baffle, partition and release agent, solve concrete precast block production mould at this stage process is crossed when in use is problem cumbersome, that cleaning is more troublesome and the production quality of prefabricated section is not high.
Description
Technical field
The utility model relates to building material apparatus technical field, specially a kind of construction site small-size concrete prefabricated section
Producing device.
Background technique
With the development of society, especially scientific and technical progress, is greatly facilitated the development of social productive forces;Urbanization
The quickening of process and the high concentration of social dominance's resource, so that many cities need to carry more on limited soil
Population, and the material goods such as place are provided for its life and work, the building for thus having expedited the emergence of building trade are had to high-altitude
Develop with subterranean depth, many building are rised sheer from level ground like the mushrooms after rain.
Currently, in building engineering construction, it is often necessary to some small-sized concrete precast blocks, since dosage is little, such as
Fruit is customized using batch production, then is transported to construction site, and will increase construction cost.At this point, often all carrying out at the construction field (site) pre-
System processing.When carrying out prefabricated processing at the construction field (site), traditional way is that, using plank sheathing processing and fabricating mold, mold is by keeping off
Plate, partition, fixture and split bolt composition.It is slotted on baffle according to the size of prefabricated section, partition is stuck in baffle when installation
Slot in, reinforced after being completed with split bolt.When one group of concrete precast block after processing is completed removes mold, then
Installation next group of concrete precast block of production.The production mold can satisfy the basic production demand of prefabricated section when in use, so
And remain the defect and deficiency of some aspects in actual use: the installation of 1. the method and demolishing process are cumbersome, time-consuming
Long, low efficiency must re-start mold processing and prepare after a period of use due to mold breakage;2. in one group of concrete
Prefabricated section, which completes the process, removes mold when re-assemblying, and the concrete being bonded on baffle and partition is not easily cleaned, especially baffle
The concrete cleaning being bonded in slot is got up more troublesome;3. being led due to being assembled mold if reinforcing and loosely will cause mold distortion
Concrete precast block deformation is caused, due to that need to be beaten with iron hammer when removing, the dismounting time is longer, generally in concreting
It is dismountable to complete 24 hours rears, when dismounting is beaten with iron hammer be easy to cause concrete precast block losing fangle, influences concrete
The presentation quality of prefabricated section.
Summary of the invention
In order to solve the prior art summarize concrete precast block production mould when in use process cross be it is cumbersome, cleaning compared with
For the not high problem of troublesome and prefabricated section production quality, it is pre- that the utility model provides a kind of construction site small-size concrete
Clamp dog producing device.
To achieve the above object, the utility model provides the following technical solutions:
A kind of construction site small-size concrete prefabricated section producing device, including die ontology, the both ends of the die ontology
It is provided with a handle, the inside of the die ontology includes that two longitudinal baffles being parallel to each other and two are parallel to each other
Transverse baffle is disposed with partition between two transverse baffles.
Preferably, two handles are fixed on the both ends of die ontology by welding.
Preferably, it is connected between the longitudinal baffle and transverse baffle for integral type.
Preferably, to be vertically arranged between the partition and transverse baffle, the partition is fixed on by welding
Between two transverse baffles.
Preferably, it is covered on the inner wall of the die ontology and is connected to release agent.
Preferably, the longitudinal baffle, transverse baffle and partition are prepared by the steel plate of 5mm.
Preferably, the lower end of the die ontology is without bed die.
Positive beneficial effect: the utility model provides a kind of construction site small-size concrete prefabricated section producing device, tool
For following the utility model has the advantages that 1, the utility model is by setting die ontology, handle, longitudinal baffle, transverse baffle and partition, originally
Longitudinal baffle, transverse baffle and partition in utility model are welded by the steel plate of 5mm, spell installation and dismantling without recycling
It removes, mold is produced once, and is used for a long time, and is prepared without recycling, and mold rapidoprint and labour cost are saved, and spending reduces, has
Good use space and use.2, the utility model by setting die ontology, handle, longitudinal baffle, transverse baffle and
Partition, the steel plate of the present apparatus are welding fabrication, the concrete ratio that mold is not needed to re-assembly, therefore is bonded on baffle and partition
It is easier to clear up, baffle plate groove is not present, solve the problems, such as baffle plate groove inner concrete cleaning trouble.3, the utility model is by setting
Set die ontology, handle, longitudinal baffle, transverse baffle and partition, longitudinal baffle, transverse baffle in the utility model and
Partition is welded by steel plate, and without recycling assembled and removing, there is no mold reinforcings loosely mold distortion to be caused to cause
The case where concrete precast block deforms holds mould ambilateral handle when demoulding, mold is gently lifted, therefore does not need
Mold is beaten, the time is removed and relatively holds, shorten the dismounting time of mold, simultaneously because do not need to beat in prefabricated section demoulding,
Therefore the case where avoiding due to beaing and damaging prefabricated section quality, does not have losing fangle phenomenon, ensure that concrete precast block
Quality, therefore the presentation quality of concrete precast block can guarantee, the concrete prefabricated block size of production is correct, upright, see
Feel.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the top view of the utility model;
Fig. 3 is the side view of the utility model;
Fig. 4 is the sectional view of the utility model die ontology.
In figure are as follows: die ontology 1, handle 2, longitudinal baffle 3, transverse baffle 4, partition 5, release agent 6.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
As shown in Figs 1-4, a kind of a kind of embodiment provided by the utility model: construction site small-size concrete prefabricated section system
Make device, including die ontology 1, the both ends of die ontology 1 are provided with a handle 2, and two handles 2 pass through welding
Mode be fixed on the both ends of die ontology 1, ensure that the fastness of two handles 2, and the inside of die ontology 1 includes two
The longitudinal baffle 3 being parallel to each other and two transverse baffles 4 being parallel to each other are integral type between longitudinal baffle 3 and transverse baffle 4
Connection, two longitudinal baffles 3 and two transverse baffles 4 are staggered in the surrounding of die ontology 1, and die ontology 1 is in square
Shape is arranged, and is disposed with partition 5 between two transverse baffles 4, is vertically arranged between partition 5 and transverse baffle 4, and every
Plate 5 is fixed on by welding between two transverse baffles 4, and longitudinal baffle 3, transverse baffle 4 and partition 5 by
The steel plate of 5mm is prepared, and ensure that the precision of longitudinal baffle 3, transverse baffle 4 and partition 5, and when use is more handy, together
When die ontology 1 inner wall on cover and be connected to release agent 6, facilitate the demoulding of concrete precast block, and the lower end of die ontology 1 is bottomless
Mould.
When in use, die ontology 1 need to be placed on smooth place, after the inner surface of die ontology 1 is cleaned out
One layer of release agent 6 is brushed, concrete is then poured into die ontology 1 progress vibration compacting, when demoulding, holds mold sheet
The handle 2 of 1 two sides of body, die ontology 1 is gently lifted, it should be noted that after the completion of one group of prefabricated section concreting,
The demoulding time of concrete need to be grasped, too early, concrete is be easy to cause to collapse according to slump and the temperature height of concrete
Deformation be easy to cause demoulding difficult, is learnt according to site operation experience too late, demoulding time when summer makes under normal circumstances
It is carried out between 1~1.5 hour after the completion of concreting, demoulding time is 2 after the completion of concreting when spring and autumn makes
It is carried out between~2.5 hours.
Embodiment
Using 3mm thick steel plate according to the specification size of concrete precast block carry out mold be welded, the mold by surrounding baffle,
Intermediate bulkhead and handle composition, no bed die.When making concrete precast block using the present invention, mold need to be only placed on smooth
On place, one layer of release agent is brushed after steel mold inner surface is cleaned out, then concrete is poured into steel die and is carried out
Vibration compacting when demoulding, holds the ambilateral handle of mould, mold is gently lifted.It should be noted that when one group it is prefabricated
After the completion of block concrete pours, the demoulding time of concrete, mistake need to be grasped according to slump and the temperature height of concrete
It is early, it is be easy to cause concrete Collapse Deformation, too late, be easy to cause demoulding difficult.It is learnt according to site operation experience, ordinary circumstance
Demoulding time carries out between 1~1.5 hour after the completion of concreting when lower summer will make, demoulding time when spring and autumn makes
It is carried out between 2~2.5 hours after the completion of concreting.
The concrete precast block of 120 × 300 × 200mm is such as made, welded steel plate mold is as shown in Figs 1-4,
It can to sum up obtain, the utility model passes through setting die ontology 1, handle 2, longitudinal baffle 3, transverse baffle 4, partition 5
And release agent 6, solve concrete precast block production mould at this stage when in use process cross be it is cumbersome, cleaning is more numb
The not high problem of tired and prefabricated section production quality;Small-size concrete prefabricated section producing device in construction site of the present invention
Simple processing, it is practical, it can be widely used, have the advantages that in the construction process
(1) mold uses welded steel plate, and indeformable, the concrete prefabricated block size of production is correct, upright, and perception is good.
(2) mold is produced once, and is used for a long time, and is prepared without recycling, and mold rapidoprint and labour cost are saved.
(3) unitary mould, without recycling assembled and removing, and demoulding time is short, highly shortened prefabricated section production week
Phase, effect are high.It is compared according to scene, concrete precast block is made using the present invention, effect can be improved 300% or more.
(4) gently mold is lifted when demoulding, without beaing, concrete precast block corner angle are clearly demarcated, existing without losing fangle
As impression quality is good.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (7)
1. a kind of construction site small-size concrete prefabricated section producing device, including die ontology (1), it is characterised in that: the mould
The both ends of tool ontology (1) are provided with a handle (2), the inside of the die ontology (1) include two be parallel to each other it is vertical
The transverse baffle (4) being parallel to each other to baffle (3) and two is disposed with partition between two transverse baffles (4)
(5).
2. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: two
The handle (2) is fixed on the both ends of die ontology (1) by welding.
3. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: described
It is connect between longitudinal baffle (3) and transverse baffle (4) for integral type.
4. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: described
To be vertically arranged between partition (5) and transverse baffle (4), the partition (5) is fixed on two transverse gears by welding
Between plate (4).
5. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: described
It is covered on the inner wall of die ontology (1) and is connected to release agent (6).
6. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: described
Longitudinal baffle (3), transverse baffle (4) and partition (5) are prepared by the steel plate of 5mm.
7. a kind of construction site small-size concrete prefabricated section producing device according to claim 1, it is characterised in that: described
The lower end of die ontology (1) is without bed die.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821458405.XU CN209350490U (en) | 2018-09-06 | 2018-09-06 | A kind of construction site small-size concrete prefabricated section producing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821458405.XU CN209350490U (en) | 2018-09-06 | 2018-09-06 | A kind of construction site small-size concrete prefabricated section producing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209350490U true CN209350490U (en) | 2019-09-06 |
Family
ID=67779603
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821458405.XU Active CN209350490U (en) | 2018-09-06 | 2018-09-06 | A kind of construction site small-size concrete prefabricated section producing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209350490U (en) |
-
2018
- 2018-09-06 CN CN201821458405.XU patent/CN209350490U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106113230B (en) | The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need | |
CN105484421A (en) | Ring beam formwork bricks and building secondary structure filler wall ring beam construction method | |
CN209350490U (en) | A kind of construction site small-size concrete prefabricated section producing device | |
CN104805960A (en) | Mould-stripping-free concrete beam and construction method thereof | |
CN102773918B (en) | Manufacturing method of concrete precast pile | |
CN101748893B (en) | Method for manufacturing high-rise building balcony boards | |
CN109252879A (en) | A kind of vcehicular tunnel gutter liner tool-typed formwork and construction method | |
CN110281347A (en) | A kind of construction site small-size concrete prefabricated section production method | |
CN111075101A (en) | BM interlocking building block U-shaped block lintel, ring beam and horizontal tie beam and construction method thereof | |
CN207469596U (en) | A kind of beam column outer rim is exempted to tear concrete mold open | |
CN205928992U (en) | Prefabricated machine of mortar hollow brick | |
CN212897009U (en) | Take assembled shear wall structure of corner | |
CN212562647U (en) | Can have enough to meet need modularization secondary structure wall body and build system construction model | |
CN202689278U (en) | Superimposed hollow slab | |
CN210552005U (en) | Wallboard type assembled side form structure | |
CN210562389U (en) | Plastic module assembly for collecting and storing rainwater and water storage tank with same | |
CN207290398U (en) | A kind of building structural post molding machine | |
CN107190652B (en) | A kind of collection bundled tube intersects long cantilever class stayed-cable bridge structure system and construction method | |
CN206941628U (en) | A kind of construction site enclosing prefabricated foundation | |
CN101298792A (en) | High efficiency construction method of cast-in-situ hollow core floor slab | |
CN205651493U (en) | Umbrella -type skeleton supports assembled mandrel | |
CN216276374U (en) | Ribbed concrete laminated slab | |
CN211421375U (en) | Assembly type building structure | |
CN101372133A (en) | Method for manufacturing reverse T shaped plate | |
CN221212200U (en) | Road cement board mould |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |