CN110107304A - A kind of shield launching receives well borehole wall part FRP tendons method for protecting support - Google Patents

A kind of shield launching receives well borehole wall part FRP tendons method for protecting support Download PDF

Info

Publication number
CN110107304A
CN110107304A CN201910417946.0A CN201910417946A CN110107304A CN 110107304 A CN110107304 A CN 110107304A CN 201910417946 A CN201910417946 A CN 201910417946A CN 110107304 A CN110107304 A CN 110107304A
Authority
CN
China
Prior art keywords
reinforcing bar
borehole wall
excavation
fpr
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910417946.0A
Other languages
Chinese (zh)
Inventor
张会芝
刘纪峰
崔秀琴
连跃宗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanming University
Original Assignee
Sanming University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanming University filed Critical Sanming University
Priority to CN201910417946.0A priority Critical patent/CN110107304A/en
Publication of CN110107304A publication Critical patent/CN110107304A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to borehole wall support technology fields, and it discloses shield launching or receives well borehole wall part FRP tendons method for protecting support, pass through earth excavation, modify side slope, reinforcement placing net, fill gap, gunite concrete and etc. realize launching shaft and receive the borehole wall supporting of well, wherein steel mesh is mixed with FPR reinforcing bar for common HRB335 reinforcing bar and is built, steel mesh main body is built using HRB335 reinforcing bar, FPR reinforcing bar is changed at tunnel excavation mouth to build with the dislocation of HRB335 reinforcing bar, steel mesh is HRB335 reinforcing bar and FPR bar splicing using mechanical connection or welding manner, and length is built not less than 35d, it is high using FPR Steel Bar Tensile Strength, it is light-weight, processing carrying and installation easy to cut, and it is easy to twist when resisting torque and change at the features such as disconnected tunnel excavation mouth For FPR reinforcing bar, realize that part replaces, to realize construction safety, shield cutter, which can be tunneled directly, carries out opening operation, and shield directly tunnels the borehole wall of starting well or received well, working security height, short time limit, low cost.

Description

A kind of shield launching receives well borehole wall part FRP tendons method for protecting support
Technical field
The present invention relates to borehole wall support technology field, specially a kind of shield launching or receive well borehole wall part FRP tendons branch Maintaining method.
Background technique
Shield launching well construction is one of master operation of shield tunnel, and shield method is that one of shallow mining method is complete Mechanized construction method, it is to promote Shield-type machinery in ground, and supporting surrounding country rock by shield shell and section of jurisdiction prevents from sending out The raw collapsing in tunnel, while soil excavation is carried out with cutting apparatus in front of excavation face, by being unearthed, machinery is transported outside hole, By jack in rear pressurization jacking, and assembled precast concrete section of jurisdiction, form a kind of mechanized construction method of tunnel structure. Wherein shield machine appearance has nearly 200 years history so far, starts from Britain, is developed in Japan, Germany, more than 40 years, passes through To key technology earth pressure balanced, in slurry type shield machine, such as effective sealing of shield machine, it is ensured that the stabilization of excavation face, control It surface uplift processed and is collapsed upon within prescribed limit, cutting-tool's used life and the cutter changing under air-proof condition, to one It the explorations of processing technique of some severe for example high hydraulic conditions of geology etc. and researchs and solves, shield machine is made to have cracking development Basic functional principle is exactly that the steel component an of cylindrical body excavates soil when pushing ahead along canal axes.The cylinder Shell, that is, shield of body component, it plays a part of temporary support to the also unlined Tunnel Section excavated, and bears surrounding soil The pressure of layer, sometimes outside also subject to ground water pressure and by underground water gear.The operations such as excavation, casting, lining cutting are in shield Shielding is lower to be carried out.Shield launching passes through starting well and reaches the work progress for drilling through received well, is the main wind of shield tunnel Dangerous, control is bad, be easy to cause accident.It originates and reaches and pass through one of difficult point of supporting construction and be shield cutter to common Reinforced concrete shaft lining in reinforcing bar be difficult to twist disconnected, usually using the method for artificial broken chisel, not only operating environment is arduous, and It is very easy to the landslide of borehole wall water burst in work progress, leads to settlement of stratum, jeopardizes surrounding building and underground utilities etc..If with Shield cutter directly tunnels and carries out opening operation, then reinforcing bar is easy winding, abrasion cutterhead and cutter, causes mechanical breakdown.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the present invention provides a kind of shield launching or receive the FRP tendons supporting of well borehole wall part Method has the advantages that borehole wall that can directly tunnel starting well or received well with shield, solves and directly dug with shield cutter Into opening operation is carried out, reinforcing bar is easy the problem of winding, wearing cutterhead and cutter, cause mechanical breakdown.
(2) technical solution
To achieve the above object, the invention provides the following technical scheme: a kind of shield launching or receiving well borehole wall part FRP Muscle method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: according to borehole wall chamfered shape reinforcement placing bracket.
(4) it fills gap: filling broken spoil between the borehole wall and Steel bar rack.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil.
Preferably, after the earth excavation should supporting immediately, exposure duration be no more than 48h, not can be carried out and once scrape out Payment form of construction work is carried out again.
Preferably, concrete ejection processing first is carried out to borehole wall inside before the reinforcement placing net and is formed with concrete Protective layer.
Preferably, the steel mesh is mixed with FPR reinforcing bar for common HRB335 reinforcing bar and is built, and steel mesh main body uses HRB335 reinforcing bar is built, and FPR reinforcing bar is changed at tunnel excavation mouth and is built with the dislocation of HRB335 reinforcing bar, HRB335 reinforcing bar and FPR Bar splicing builds length not less than 35d using mechanical connection or welding manner.
Preferably, the spoil partial size is chosen for the spoil no more than 100mm.
Preferably, in the step (5) shotcrete layer thickness in 100mm between 300mm.
(3) beneficial effect
Compared with prior art, the present invention provides a kind of shield launching or receive well borehole wall part FRP tendons method for protecting support, Have it is following the utility model has the advantages that
The shield launching receives well borehole wall part FRP tendons method for protecting support, by changing common steel mesh to steel mesh It mixes and builds with FPR reinforcing bar for HRB335 reinforcing bar, steel mesh main body is built using HRB335 reinforcing bar, at tunnel excavation mouth It is changed to FPR reinforcing bar to build with the dislocation of HRB335 reinforcing bar, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection or welding side Formula, and build length not less than 35d, solves directly tunnel with shield cutter and carries out opening operation, and reinforcing bar is easy winding, wears Cutterhead and cutter, tunnel shield cutter directly and carry out opening operation the problem of causing mechanical breakdown, improve construction peace Quan Xinggao, it shortens the duration, reduce cost.
Specific embodiment
Below in conjunction with the embodiment of the present invention, technical solution in the embodiment of the present invention is clearly and completely retouched It states, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the present invention In embodiment, every other implementation obtained by those of ordinary skill in the art without making creative efforts Example, shall fall within the protection scope of the present invention.
Domestic basalt fibre (BFRP) muscle or glass fibre (GFRP) muscle (external common carbon fibre bar CFRP and virtue Synthetic fibre fiber bar AFRP cost is higher) it is tensile strength high (ultimate tensile strength be HRB335 reinforcing bar 1.5-3.0 times), light-weight (density is the 1/5~1/4 of HRB335 reinforcing bar) is easy to be easy to twist (springform of breaking when cutting processing and carrying and installation, resistance torque Amount is 0.22-0.23 times of HRB335 reinforcing bar, and elongation is 0.13-0.14 times of HRB335 reinforcing bar), it is good with concrete binding Characteristics such as (reaching 4.5~6.5MPa with the adhesive tensile resistance strength degree value of C40 concrete), basalt fiber tendons (BFRP) be with Basalt fibre is reinforcing material and synthetic resin (unsaturated polyester (UP), epoxy resin, vinylite etc.) and filler, curing agent Equal matrixes combine, through a kind of molding advanced composite material (ACM) of pultrude process.Unlike reinforcing bar, basalt fiber tendons density It is 1.9~2.1g/cm3, about 1/4 (reinforcing bar density be 7.8~7.9) of reinforcing bar;The tensile yield strength of basalt fiber tendons It is 2~3 times of reinforcing bar, thermal expansion coefficient is close with concrete, it is ensured that concrete deformation synchronous with muscle material.Basalt is fine Tie up muscle be a kind of rustless electrical insulator, have it is non magnetic, especially: have high acid resistance and alkali resistance.To cement Moisture concentration and carbon dioxide in mortar are impregnated with and spread permission with higher, can prevent the coagulation under harsh environment The corrosion of native structures, to have the function that the durability for improving building, in launching shaft or the shield of the received well borehole wall Structure tunnel range in, glass fiber-reinforced polymer is called glass-fiber reinforcement material, is commonly called as glass muscle or fiber bar, be by high-performance fiber with synthesize Resin matrix, curing agent are formed by material using moulding process appropriate;High-performance fiber is reinforcing material, and synthetic resin is Basis material fiber has very high tensile strength, is the main provider of fibre reinforced composites intensity, with FRP tendons office Portion replaces reinforcing bar, and the borehole wall of starting well or received well can be directly tunneled with shield, has working security height, short time limit, makes The features such as valence is low.
Embodiment one:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing use welding manner, and the lap of splice is 35d, and side length of element is 200 millimeters, is used Welding manner can reduce cost.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 150mm.
Embodiment two:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing use welding manner, and the lap of splice is 35d, and side length of element is 300 millimeters, is used Welding manner and compared with embodiment one increase side length of element more reduce cost, can be used in the not high situation of intensity requirement.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 150mm.
Embodiment three:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection, and the lap of splice is 35d, and side length of element is 250 millimeters, is used Although being mechanically connected increase cost but easy for construction, the reinforcing bar only change of generation in shape, physical property not change, increasing Add the stability of steel mesh.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 150mm.
Example IV:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection, and the lap of splice is 35d, and side length of element is 300 millimeters, is used Although being mechanically connected increase cost but easy for construction, the reinforcing bar only change of generation in shape, physical property not change, increasing Add the stability of steel mesh.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 150mm.
Embodiment five:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing use welding manner, and the lap of splice is 35d, and side length of element is 200 millimeters, is used Welding manner can reduce cost.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 250mm.
Embodiment six:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing use welding manner, and the lap of splice is 35d, and side length of element is 300 millimeters, is used Welding manner and compared with embodiment five increase side length of element more reduce cost, can be used in the not high situation of intensity requirement.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 250mm.
Embodiment seven:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection, and the lap of splice is 35d, and side length of element is 250 millimeters, is used Although being mechanically connected increase cost but easy for construction, the reinforcing bar only change of generation in shape, physical property not change, increasing Add the stability of steel mesh.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 250mm.
Embodiment eight:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection, and the lap of splice is 35d, and side length of element is 300 millimeters, is used Although being mechanically connected increase cost but easy for construction, the reinforcing bar only change of generation in shape, physical property not change, increasing Add the stability of steel mesh.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 250mm.
Embodiment nine:
A kind of shield launching receives well borehole wall part FRP tendons method for protecting support, comprising the following steps:
1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting, should prop up immediately after earth excavation Shield, exposure duration are no more than 48h, not can be carried out primary scrape out and carry out payment form of construction work again.
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and slope leveling degree is permitted Perhaps deviation is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil.
(3) reinforcement placing net: concrete ejection processing is carried out to borehole wall inside first and is formed with concrete shield root According to borehole wall chamfered shape reinforcement placing bracket, used steel mesh be common HRB335 reinforcing bar mixed with FPR reinforcing bar build and At steel mesh main body is built using HRB335 reinforcing bar, and FPR reinforcing bar is changed at tunnel excavation mouth and is taken with the dislocation of HRB335 reinforcing bar It builds, HRB335 reinforcing bar and FPR bar splicing are using mechanical connection, and the lap of splice is 35d, and side length of element is 300 millimeters, is used Although being mechanically connected increase cost but easy for construction, the reinforcing bar only change of generation in shape, physical property not change, increasing Add the stability of steel mesh.
(4) gap: the spoil of filled stone partial size 100mm between the borehole wall and Steel bar rack is filled.
(5) gunite concrete: mixed towards the side injection in well in spoil layer after steel mesh and gap filling completion Solidifying soil, concrete layer is with a thickness of 300mm.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (7)

1. a kind of shield launching receives well borehole wall part FRP tendons method for protecting support, which comprises the following steps:
(1) earth excavation: earth excavation follows stage excavation, the method for being layered supporting;
(2) modify side slope: excavation of foundation pit is in mechanical excavation and then carries out manual amendment slope surface, and the permission of slope leveling degree is inclined Difference is ± 20mm, before slope surface carries out supporting, first carries out the removing of slope surface loosened soil;
(3) reinforcement placing net: according to borehole wall chamfered shape reinforcement placing bracket;
(4) it fills gap: filling broken spoil between the borehole wall and Steel bar rack;
(5) gunite concrete: after steel mesh and gap filling completion, coagulation is sprayed towards the side in well in spoil layer Soil.
2. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: after step (1) earth excavation should supporting immediately, exposure duration is no more than 48h, not can be carried out and once scrape out and propped up Pay form of construction work.
3. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: concrete ejection processing is carried out to borehole wall inside first before the step (3) and is formed with concrete shield.
4. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: steel mesh used in the step (3) is mixed with FPR reinforcing bar for common HRB335 reinforcing bar and is built, steel mesh main body It is built using HRB335 reinforcing bar, FPR reinforcing bar is changed at tunnel excavation mouth and is built with the dislocation of HRB335 reinforcing bar.
5. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: steel mesh used in the step (3) is that HRB335 reinforcing bar and FPR bar splicing use mechanical connection or welding manner, And building length is 30d to 40d.
6. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: spoil partial size is 50mm to 100mm in the step (4).
7. a kind of shield launching according to claim 1 receives well borehole wall part FRP tendons method for protecting support, feature exists In: shotcrete layer thickness is in 100mm between 300mm in the step (5).
CN201910417946.0A 2019-05-20 2019-05-20 A kind of shield launching receives well borehole wall part FRP tendons method for protecting support Pending CN110107304A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910417946.0A CN110107304A (en) 2019-05-20 2019-05-20 A kind of shield launching receives well borehole wall part FRP tendons method for protecting support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910417946.0A CN110107304A (en) 2019-05-20 2019-05-20 A kind of shield launching receives well borehole wall part FRP tendons method for protecting support

Publications (1)

Publication Number Publication Date
CN110107304A true CN110107304A (en) 2019-08-09

Family

ID=67491060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910417946.0A Pending CN110107304A (en) 2019-05-20 2019-05-20 A kind of shield launching receives well borehole wall part FRP tendons method for protecting support

Country Status (1)

Country Link
CN (1) CN110107304A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01315586A (en) * 1988-03-24 1989-12-20 Ing Giovanni Rodio & C Impresa Costruzioni Speciali Spa Method and device for expanding diameter of tunnel
CN101614126A (en) * 2008-06-27 2009-12-30 深圳市海川实业股份有限公司 A kind of job practices of directly cutting guard post for tunnel end well by shield machine
CN102022119A (en) * 2010-12-15 2011-04-20 广东华隧建设股份有限公司 Shield machine balance originating method
CN102561358A (en) * 2010-12-22 2012-07-11 中国建筑第七工程局有限公司 Construction method of ahead mini type composite soil nail wall support
CN105201513A (en) * 2015-09-11 2015-12-30 重庆工程职业技术学院 Shaft construction method for rail transit
CN105909253A (en) * 2016-04-07 2016-08-31 中建交通建设集团有限公司 Quick receiving method for shield receiving vertical shaft without lining structure
CN109736354A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Tunnel open excavation section main structure construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01315586A (en) * 1988-03-24 1989-12-20 Ing Giovanni Rodio & C Impresa Costruzioni Speciali Spa Method and device for expanding diameter of tunnel
CN101614126A (en) * 2008-06-27 2009-12-30 深圳市海川实业股份有限公司 A kind of job practices of directly cutting guard post for tunnel end well by shield machine
CN102022119A (en) * 2010-12-15 2011-04-20 广东华隧建设股份有限公司 Shield machine balance originating method
CN102561358A (en) * 2010-12-22 2012-07-11 中国建筑第七工程局有限公司 Construction method of ahead mini type composite soil nail wall support
CN105201513A (en) * 2015-09-11 2015-12-30 重庆工程职业技术学院 Shaft construction method for rail transit
CN105909253A (en) * 2016-04-07 2016-08-31 中建交通建设集团有限公司 Quick receiving method for shield receiving vertical shaft without lining structure
CN109736354A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Tunnel open excavation section main structure construction method

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
KR100771904B1 (en) Earth Reinforcement System by Using Bamboo Reinforcement
CN102493821B (en) Support method for high stress roadway coal-rock mass
CN102094650A (en) Construction method for shield holing under complicated working conditions
CN105736003B (en) A kind of structure of shield launching portal and the construction method of shield launching
CN107503767B (en) A kind of precast concrete-FRP corrugated plating tunnel bottom construction method for supporting
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN111119935A (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN110905538A (en) Construction method for TBM (Tunnel boring machine) of unfavorable geological section
CN203488189U (en) Tunnel structure for emptying renovation
CN107575246A (en) A kind of construction method of pre-manufactured steel-FRP complex wave card tunnel bottom supporting construction
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN110284885A (en) Shield inspection-pit construction method
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN112177623A (en) TBM (Tunnel boring machine) grading construction method for stratum tunnels with different water-rich crushing degrees
CN103573280A (en) Method for supporting porous ooze invasion compound roof roadway
CN108915702A (en) It is a kind of circle narrow-bore tunnel in shield method of reseptance
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN104453915A (en) Large-section vertical shaft pre-grouting reinforcement quick excavation method
CN104389619A (en) Shield excess hole construction method
CN110107304A (en) A kind of shield launching receives well borehole wall part FRP tendons method for protecting support
CN114165269B (en) Composite support system based on reinforced concrete combined support and spraying arch and construction process thereof
CN204663550U (en) Grid is gone along with sb. to guard him in the interval engineering glass fiber-reinforced polymer construction of the shield structure that starts in hole
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190809