CN109989346A - Bridge major diameter precast concrete tubular column basis and its construction method - Google Patents

Bridge major diameter precast concrete tubular column basis and its construction method Download PDF

Info

Publication number
CN109989346A
CN109989346A CN201910021408.XA CN201910021408A CN109989346A CN 109989346 A CN109989346 A CN 109989346A CN 201910021408 A CN201910021408 A CN 201910021408A CN 109989346 A CN109989346 A CN 109989346A
Authority
CN
China
Prior art keywords
tubing string
section
tubular column
construction
major diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910021408.XA
Other languages
Chinese (zh)
Other versions
CN109989346B (en
Inventor
翟世鸿
吴启和
柯杰
韩鹏鹏
徐杰
邱敏
万猛
张磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201910021408.XA priority Critical patent/CN109989346B/en
Publication of CN109989346A publication Critical patent/CN109989346A/en
Application granted granted Critical
Publication of CN109989346B publication Critical patent/CN109989346B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)

Abstract

The invention discloses bridge major diameter precast concrete tubular column bases, it include: tubular column main body, it includes sequentially connected tubing string bottom section, more standard tubing string section and tubing string top section from bottom to up, the tubular column main body is the tube-in-tube structure of inner hollow and is vertically positioned in soil layer that the tubular column main body bottom is sealed by bottom concrete;Linkage section is located on soil layer and is solid construction, and the linkage section lower end connecting tube capital section, upper end are directly connected to pier stud.The invention also discloses the construction methods on bridge major diameter precast concrete tubular column basis, and by prefabricated major diameter tubing string, scene cooperates the fabricated construction of small-sized strand suction dredging plant completion bridge tube caisson foudations using static pressure method.Cushion cap is not needed after the completion of tube caisson foudations construction of the present invention, cost is reduced, shortens the construction period, prefabrication and assembly construction degree is high, is with a wide range of applications.

Description

Bridge major diameter precast concrete tubular column basis and its construction method
Technical field
The present invention relates to bridge foundation construction technical field of structures.More specifically, the invention relates to using for land bridges Major diameter precast concrete tubular column basis and its construction method.
Background technique
With China's rapid economic development, Urban Transportation demand is increased rapidly, and municipal bridge is due to can be significantly Traffic ability is improved, urban congestion is alleviated, using more extensively in urban construction.The substructure of municipal bridge generallys use The structure type of " cast-in-situ bored pile+cushion cap+pier stud ", bored concrete pile has mechanization of operation, easy for construction;Steel reinforcement cage and concrete Can concentrated processing, dispatching, operation is convenient;The advantages that speed of application is fast, technical maturity, work progress is safe and reliable, at present in bridge Beam is widely used in basis.
Currently, there are mainly two types of the common construction technologies of bored concrete pile.First method is mud off method, is set by drilling machine Standby (impact drill, abrasion drill, churning driven etc.) pore-forming concrete perfusion and pile on the spot.It is protected for the hole that prevents from collapsing with mud when drilling Wall.It is recycled by mud and excludes boring mud soil bits, borehole cleaning is after reaching projected depth with round bottom sediment.Its work progress includes smooth Place, slurrying, embedded casing, rigging up and position, drilling and forming hole, borehole cleaning and inspection hole, installation steel reinforcement cage, pour it is underwater Concrete.Large diameter bored pile is mostly used this construction technology in the heavy constructions such as skyscraper and bridge at present, and stake diameter is more In 2.5m or less.Second method is full-sleeve construction method, is mainly characterized by using full-sleeve retaining wall, work progress is not necessarily to mud Slurry and borehole cleaning, reduce the frictional resistance between steel sleeve and soil layer using the shake of agitating device, are pressed into when shaking, utilize simultaneously Punching grab bucket, which is excavated, takes soil.General work progress is: smooth location, rigging up, set pipe construction, drilling and forming hole, installation steel reinforcement cage, Casting concrete, checks pile quality at drawing casing.
But the structure type of Urban Bridge substructure " cast-in-situ bored pile+cushion cap+pier stud ", stratum deformation adaptability Difference, appearance effects are serious after roadbed subsidence, passage space under the big influence bridge of suspended deck structure size, and basis is existed using bored concrete pile The problems such as structure construction consumption of materials is big, and speed of fulfiling hole is slow, and the construction period is long, and construction quality control is difficult;Cast-in-situ bored pile There is also certain defect, construction slurry and boring mud vegetation soil, surface water and groundwaters to surrounding to cause seriously for construction technology It pollutes, there are larger construction noise in construction, underwater concreting quality is difficult to ensure, prefabrication and assembly construction degree is low etc..
Summary of the invention
It is an object of the present invention to provide bridge major diameter precast concrete tubular column basis and its construction methods, by pre- Major diameter tubing string processed, scene cooperate small-sized strand suction dredging plant to complete the fabricated construction of bridge foundation, apply using static pressure method Cushion cap is not needed after work, reduces cost, shortens the construction period, and prefabrication and assembly construction degree is high, is with a wide range of applications.
In order to realize these purposes and other advantages according to the present invention, bridge major diameter precast concrete tubular column is provided Basis, comprising: tubular column main body comprising sequentially connected tubing string bottom section, more standard tubing string section and tubing string top section from bottom to up, The tubular column main body is the tube-in-tube structure of inner hollow and is vertically positioned in soil layer that the tubular column main body bottom passes through back cover coagulation Soil sealing;Linkage section is located on soil layer and is solid construction, and the linkage section lower end connecting tube capital section, upper end directly connect Connect pier stud.
Preferably, the diameter of the tubular column main body is 2~4m, and wall thickness is 25~35cm, the bottom concrete height For 2~5m.
Preferably, tubing string bottom section inside is provided with the blade foot with blade foot tyre tread, the blade foot outer cladding blade foot steel Plate.
Preferably, the connection between the tubing string bottom section, more standard tubing string section and tubing string top section is using welding, flange It is bolted or mechanical splice connects.
Preferably, the tubular column main body is concrete structure and the double-deck stiffener is arranged in inside concrete.
The present invention also provides a kind of construction methods on bridge major diameter precast concrete tubular column basis, include the following steps:
S1: using non-drainage subsidence technique combination static pressure method sinking tubing string bottom section;
S2: first segment standard pipe shell of column is connect with tubing string bottom section, equally uses non-drainage subsidence technique combination static pressure method Sinking first segment standard pipe shell of column;
S3: the quasi- tubing string section of the second feast-brand mark is successively connected on first segment standard pipe shell of column and uses non-drainage subsidence technique knot The static pressure method sinking quasi- tubing string section of the second feast-brand mark is closed, the quasi- tubing string section of third feast-brand mark is connected in the quasi- tubing string section of the second feast-brand mark and using not The quasi- tubing string section ... of drainage sink technique combination static pressure method sinking third feast-brand mark connects N in the quasi- tubing string section of N-1 feast-brand mark The quasi- tubing string section of feast-brand mark simultaneously uses the non-drainage subsidence technique combination static pressure method sinking quasi- tubing string section of N feast-brand mark;
S4: sunk in the quasi- tubing string section upper connector capital section of N feast-brand mark and using non-drainage subsidence technique combination static pressure method Tubing string top section;
S5: at tubing string bottom, section carries out the construction of bottom concrete;
S6: construction linkage section.
Preferably, before step S1, merogenesis first is carried out to the tubular column main body constructed of needs, then precast plant to point Tubing string bottom section, more standard tubing string section and tubing string top section progress of section are prefabricated, finally transport to construction site.
Preferably, non-drainage subsidence technique is to be constructed by twisting suction dredging plant;Static pressure method is on tubing string Surface applies static pressure load;Only apply static pressure load under soft layer;Under horizon d, UHPC sections are connected on tubing string, are led to It crosses weight and hammers UHPC sections of auxiliary tubing strings sinkings.
Preferably, step S6 construction linkage section method particularly includes: install end template in the section of tubing string top and bind connection Section reinforcing bar, then installs linkage section template, is finally attached a section cast-in-place construction.
Preferably, in non-drainage subsidence technique, scum pipe is vertically positioned at the center of tube caisson foudations, the scum pipe lower end It is provided with mechanism of dredging comprising:
Fixed ring, inner ring is connected on scum pipe by more connecting rods and the lucky horizontal snap of the fixed ring is in sword In card slot on the inside of foot;
Rotational sleeve is located at below fixed ring and is sheathed on outside scum pipe, and the rotational sleeve is driven by driving mechanism The dynamic central axes around scum pipe rotate;
Outer drill bit of dredging, is arranged for multiple and circumferential uniform intervals along scum pipe, and the outer drill bit of dredging passes through water The flat support rod connection for being fixed on rotational sleeve top, the center that the outer drill bit of dredging is downwardly away from scum pipe are obliquely installed;
Inside dredge drill bit, be arranged for multiple and circumferential uniform intervals along scum pipe, it is described in dredge drill bit pass through it is solid Lantern ring due to rotational sleeve lower part connects, and the center that the interior drill bit of dredging also is downwardly away from scum pipe is obliquely installed.
The present invention is include at least the following beneficial effects:
(1) major diameter precast concrete pipe column structure is directly connect with pier stud using no cushion cap form, is become to stratum settlement Shape is adaptable, and passage space is big under bridge;
(2) precast concrete tubular column basis diameter is big, increase side frictional resistance forced area, can give full play to side friction and End resistance promotes basic vertical bearing capacity load, while increasing the stability of tube caisson foudations;
(3) large diameter pipe column foundation arranges double steel bar, improves concrete strength, horizontal bearing capacity is big, and anti-bending strength is strong;
(4) tubing string use prefabrication, tubing string quality is secure, and after foundation construction during on-site construction without maintenance when Between, the completion time of project can be shortened, prefabrication and assembly construction degree is high;
(5) tubing string static pressure sinking watching kind is by the intuitive controllable of loading blocks weight, thus by construction static pressure load with Piling coefficient, can tentatively judge tube caisson foudations Vertical Bearing Capacity, and tube caisson foudations construction quality and load-carrying properties are secure;
(6) precast concrete tubular column work progress is not necessarily to mud off, and noise is low, and work progress is environmentally protective;
(7) precast concrete tubular column uses hollow thin-wall structure, saves steel and cement, and cost is lower, economic benefit and Social benefit is obvious, is with a wide range of applications.
Further advantage, target and feature of the invention will be partially reflected by the following instructions, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of tube caisson foudations of the present invention;
Fig. 2 is section sinking construction figure in tubing string bottom of the present invention;
Fig. 3 is standard pipe shell of column sinking construction figure of the present invention;
Fig. 4 is section sinking construction figure in tubing string top of the present invention;
Fig. 5 is bottom concrete construction drawing of the present invention;
Fig. 6 is linkage section construction drawing of the present invention,
Fig. 7 is the structural schematic diagram of mechanism of the invention of dredging.
Description of symbols:
1, tubing string bottom section, 2, standard pipe shell of column, 3, tubing string top section, 4, blade foot steel plate, 5, bottom concrete, 6, linkage section, 7, pier stud, 8, bent cap, 9, horizon d, 10, sandy soils, 11, Soft Soil Layer, 12, mechanism of dredging, 13, scum pipe, 121, fixed ring, 122, support rod, 123, drill bit of dredging outside, 124, interior drill bit of dredging.
Specific embodiment
Present invention will be described in further detail below with reference to the accompanying drawings, to enable those skilled in the art referring to specification text Word can be implemented accordingly.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained;In the description of the present invention, term " transverse direction ", " vertical To ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", the instructions such as "outside" side Position or positional relationship are to be based on the orientation or positional relationship shown in the drawings, and are merely for convenience of description of the present invention and simplification of the description, It is not that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, because This is not considered as limiting the invention.
As shown in Figure 1, the present invention provides a kind of bridge major diameter precast concrete tubular column basis, comprising: tubular column main body, It is inside including sequentially connected tubing string bottom section 1, more standard tubing string section 2 and tubing string top section 3, the tubular column main body from bottom to up It hollow tube-in-tube structure and is vertically positioned in soil layer, the tubular column main body bottom is sealed by bottom concrete 5;Linkage section 6, It on soil layer and is solid construction, 6 lower end connecting tube capital of the linkage section section 3, upper end are directly connected to pier stud 7.
In the above-mentioned technical solutions, existing tube caisson foudations are grouped piles cap structure, and more concrete cast-in-situ bored concrete piles need Pier stud 7 is connected by cushion cap, pier stud 7 reconnects bent cap 8, and in addition existing cast-in-situ concrete poured column diameter is generally in 2.5m Hereinafter, being unable to reach the performance for needing to carry in certain constructions, therefore grouped piles cap structure needs cushion cap as connection.And this Invention passes through the structure type of major diameter precast concrete tubular column, and tubular column main body is divided into multi-segmental, tubing string bottom section 1, more standard Tubing string section 2 and tubing string top 3 prefabricated in advance, assembled in situ of section, can not only reach fabricated construction, improve the efficiency of site operation, It is also able to achieve and is directly connected to pier stud 7, using no cushion cap form, expand the passage space under bridge floor, in addition tubular column main body is using empty Steel and cement consumption are greatly saved in heart thin-wall construction, and cost reduces, and economic benefit is obvious.Linkage section 6 is solid cast-in-place mixed Xtah Crude Clay structure, using UHPC structure, for connecting the pier stud 7 of tubular column main body and top.
In another technical solution, the diameter of the tubular column main body is 2~4m, and wall thickness is 25~35cm, the back cover 5 height of concrete is 2~5m.According to requirement for bearing capacity come the diameter and wall thickness of reasonable set tubular column main body, according further to specific Soil property situation reasonable arrangement bottom concrete 5 height.
In another technical solution, section 1 inside in the tubing string bottom is provided with the blade foot with blade foot tyre tread, outside the blade foot Coat blade foot steel plate 4.Blade foot is arranged in tubing string bottom section 1, and it is blade foot tyre tread that blade foot, which divides into horizontal support surface, and the above are swords for blade foot tyre tread Foot inclined-plane is each provided at prefabricated 1 inside of tubing string bottom section, while reinforcing blade foot using blade foot steel plate 4 to prevent blade foot thread damages.
Connection in another technical solution, between the tubing string bottom section 1, more standard tubing string section 2 and tubing string top section 3 Using welding, flange bolt connection or mechanical splice connection.The connection structure of use must guarantee pile quality, it is ensured that structure is whole Property and shear behavior etc. meet design requirement.In addition mechanical splice can be engaging type connector, Snap-in joint, grout sleeve Connector, nipple, I-shaped type joint etc..
In another technical solution, the tubular column main body is concrete structure and the double-deck reinforcement steel of inside concrete setting Muscle.Tubular column main body two stage cultivation in prefabricated processing factory is prefabricated, and each segment inside concrete is respectively provided with double steel bar, improves mixed Solidifying soil intensity, the horizontal bearing capacity and bending strength of tubing string segment.
As shown in Fig. 2 to 6, the construction method on bridge major diameter precast concrete tubular column basis includes the following steps:
S1: using non-drainage subsidence technique combination static pressure method sinking tubing string bottom section 1;Tubing string bottom section 1 uses non-drainage subsidence Technique mainly passes through load static pressure in soft layer, and cooperation twists suction dredging plant, it is ensured that tubing string bottom 1 sinking watching of section is steady, It is balanced;It is dredged adjustment when tubing string sinking watching glances off by twisting suction equipment;Water level in digging process tubing string is controlled, is kept Inside and outside water level meets design requirement;When section 1 sinking in tubular pole bottom is obstructed, reinforces management of dredging in stake according to the actual situation, adjust simultaneously Water-head inside and outside whole stake, after tubular pole bottom section 1 sinks to specified absolute altitude, removal static pressure load;
S2: first segment standard pipe shell of column 2 is connect with tubing string bottom section 1, equally uses non-drainage subsidence technique combination static pressure Method sinking first segment standard pipe shell of column 2;When tubing string bottom section 1 sinks to design height, on-site hoisting first segment standard pipe shell of column 2, Structure connection is carried out with tubing string bottom section 1;After the completion of tubing string segment connects height, continue to load static pressure on first segment standard pipe shell of column 2;
S3: the quasi- tubing string section 2 of the second feast-brand mark is successively connected on first segment standard pipe shell of column 2 and uses non-drainage subsidence technique In conjunction with the static pressure method sinking quasi- tubing string section 2 of the second feast-brand mark, the quasi- tubing string section 2 of third feast-brand mark is connected simultaneously in the quasi- tubing string section 2 of the second feast-brand mark Using the quasi- tubing string section 2...... of non-drainage subsidence technique combination static pressure method sinking third feast-brand mark in the quasi- tubing string section 2 of N-1 feast-brand mark Connect the quasi- tubing string section 2 of N feast-brand mark and using the non-drainage subsidence technique combination static pressure method sinking quasi- tubing string section 2 of N feast-brand mark;
S4: under quasi- 2 upper connector capital of the tubing string section section 3 of N feast-brand mark and using non-drainage subsidence technique combination static pressure method Immersed tube capital section 3;More standard tubing string section 2, the connection of tubing string top section 3 are consistent with 1 sinking of section of tubing string bottom with subsidence process, mainly Using suction dredging plant is twisted, the local sand for excavating tube caisson foudations leading portion reduces tubing string sinking side friction and end resistance, leads to Tubing string self weight and static pressure load are crossed to ensure the steady sinking of tubing string segment, sandy soils 10 as shown in Figures 2 and 3 and Soft Soil Layer 11;After tubing string bottom section 1 enters lithosphere, in horizon d 9 as shown in Figure 4, injection auxiliary is carried out using weight and is sunk, it is ensured that is met Designed elevation and pile penetration requirement;To prevent from being destroyed at the top of tubing string by hammering, dedicated UHPC sections of the connection on tubing string top, tubular pole is complete At rear dismounting;
S5: at tubing string bottom, section 1 carries out the construction of bottom concrete 5;As shown in figure 5, tubing string bottom absolute altitude meets design requirement Afterwards, the strand suction device at tubing string bottom is removed;Concreting conduit is installed, tube caisson foudations bottom concrete 5 is poured, improves tubing string The end resistance on basis.
S6: construction linkage section 6, as shown in fig. 6, installing end template in tubing string top section 3 and binding 6 reinforcing bar of linkage section, so 6 template of linkage section is installed afterwards, is finally attached 6 cast-in-place construction of section;Pass through the linkage section of pre-embedded bolt installation foundation and pier stud 7 End template under 6, end template arrange molding according to design requirement without recycling, by the reinforcing bar of the linkage section 6 in tubing string top section 3, Bind the reinforcing bar of linkage section 6;6 template of linkage section is installed, the concrete of 7 linkage section 6 of tubular column main body and pier stud is poured;Tubular column main body After the completion of the construction of 7 linkage section 6 of pier stud, construct into bridge pier column 7 and bent cap 8.
In the above-mentioned technical solutions, the location and installation of the first section tubing string bottom section 1 of precast concrete tubular column, tubing string are carried out first It after bottom section 1 is sunk in place, then carries out the connection of standard pipe shell of column 2 installation and sinks, prefabricated pipe stake top section 3 of finally constructing, tubing string is each The sinking construction of segment can be used static pressure technique, and cooperation twists suction and dredges technology, as necessary by installing dedicated UHPC tubing string section Cooperation is sunk using hammering method auxiliary.Construction method of the present invention, large diameter pile foundation use hollow cylinder structure, can give full play to The side friction and end resistance force characteristic of large diameter pile foundation;The prefabricated tubing string of major diameter uses fabricated construction technique, convenient, function of constructing Effect is high;Formation of pile is not necessarily to mud off, and noise is low, has short construction period, time saving material-saving, operating efficiency height, construction environmental protection The advantages that.Construction method of the present invention is suitable for the construction of Urban Bridge large diameter pipe column foundation.
In another technical solution, before step S1, merogenesis first is carried out to the tubular column main body that needs are constructed, is then existed Precast plant is prefabricated to the tubing string bottom section 1, more standard tubing string section 2 and 3 progress of tubing string top section of merogenesis, and finally transport is existing to constructing ?.
In the above-mentioned technical solutions, by checking each segmental length of structure bending resistance classifying rationally tubular column main body, each section is avoided Section junction is not moment of flexure maximum point.Prefabricated each segment is carried out in prefabricated processing factory, then transports to construction site and carries out Fabricated construction.Before construction, levelling of the land is carried out to tube caisson foudations construction area, surveying setting-out determines that prefabricated tubing string is accurate Position.After the completion of tubing string bottom section 1 is prefabricated, transport to scene is lifted to design position by equipment, measures precise positioning, it is ensured that The plan-position of tubing string and verticality meet design requirement.Installation twists suction dredging plant, twists suction dredging plant and is installed on pipe Column bottom 1 lower part of section, excavates prefabricated tubing string column subsoil earth, reduces tubing string end resistance, stake subdrilling slag is by twisting suction equipment tap Outside.
In another technical solution, non-drainage subsidence technique is to be constructed by twisting suction dredging plant;Static pressure method To apply static pressure load in tubing string upper surface;Only apply static pressure load under soft layer such as sandy soils 10 and Soft Soil Layer 11;? Under horizon d 9, UHPC sections are connected on tubing string, and UHPC sections of auxiliary tubing strings are hammered by weight and are sunk.
In another technical solution, as shown in fig. 7, scum pipe 13 is vertically positioned at tubing string base in non-drainage subsidence technique The center of plinth, 13 lower end of scum pipe are provided with mechanism 12 of dredging comprising: fixed ring 121, inner ring pass through more connections Bar is connected on scum pipe 13 and the lucky horizontal snap of the fixed ring 121 is in the card slot on the inside of the blade foot;Rotational sleeve, position It in 121 lower section of fixed ring and is sheathed on outside scum pipe 13, the rotational sleeve is driven in scum pipe 13 by driving mechanism Axis rotation;Outer drill bit 123 of dredging, is arranged for multiple and circumferential uniform intervals along scum pipe 13, the outer drill bit of dredging 123 are connected by the support rod 122 that level is fixed on rotational sleeve top, and the outer drill bit 123 of dredging is downwardly away from scum pipe 13 center is obliquely installed;Inside dredge drill bit 124, be arranged for multiple and circumferential uniform intervals along scum pipe 13, it is described in Drill bit 124 of dredging is connected by being fixed on the lantern ring of rotational sleeve lower part, and the interior drill bit 124 of dredging also is downwardly away from scum pipe 13 center is obliquely installed.
In the above-mentioned technical solutions, by that will dredge mechanism 12 and scum pipe 13 combines, equipment optimizes integration. Fixed ring 121 can be sticked in the included interior side bayonet slot of blade foot, realize the stabilization of 13 position of scum pipe, facilitated and stablized the row of dredging Slag, fixed ring 121 can be set as needed two or more;Rotational sleeve is connected by the driving mechanism on the ground of construction site The rotation of powered rotatable sleeve to drive outer dredge drill bit 123 and the interior rotation of drill bit 124 of dredging, and then is realized and is dredged;Outer digging Abundant, raising dredging efficiency, in addition, interior drill bit 124 of dredging of dredging is realized in the combination of mud drill bit 123 and interior drill bit 124 of dredging Be less than the acute rake angle of dredge outside drill bit 123 and vertical direction with the acute rake angle of vertical direction, inside dredge drill bit 124 mainly to Under dig into, and drill bit 123 of dredging outside is expanded outward and is dug into.
In conjunction with the municipal viaduct foundation design condition in Wuhan, tube caisson foudations of the invention are held with what cast-in-plase pile reached When the overall performances such as load power are the same, concrete amount comparison is as shown in the table:
Under the conditions of general geology, the overall performances one such as bearing capacity that tube caisson foudations of the invention and cast-in-plase pile reach When sample, single earthwork is caused to increase although prefabricated tube caisson foudations of the invention are relatively large in diameter, site operation is without carrying out Basis pours and maintenance construction, and construction efficiency is substantially improved.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and legend shown and described herein.

Claims (10)

1. bridge major diameter precast concrete tubular column basis characterized by comprising
Tubular column main body comprising sequentially connected tubing string bottom section, more standard tubing string section and tubing string top section from bottom to up, the pipe Column ontology is the tube-in-tube structure of inner hollow and is vertically positioned in soil layer that the tubular column main body bottom is close by bottom concrete Envelope;
Linkage section is located on soil layer and is solid construction, and the linkage section lower end connecting tube capital section, upper end are directly connected to pier Column.
2. bridge major diameter precast concrete tubular column basis as described in claim 1, which is characterized in that the tubular column main body Diameter is 2~4m, and wall thickness is 25~35cm, and the bottom concrete height is 2~5m.
3. bridge major diameter precast concrete tubular column basis as described in claim 1, which is characterized in that in the tubing string bottom section Side is provided with the blade foot with blade foot tyre tread, the blade foot outer cladding blade foot steel plate.
4. bridge major diameter precast concrete tubular column basis as described in claim 1, which is characterized in that the tubing string bottom section, Connection between more standard tubing string section and tubing string top section is using welding, flange bolt connection or mechanical splice connection.
5. bridge major diameter precast concrete tubular column as described in claim 1 basis, which is characterized in that the tubular column main body is The double-deck stiffener is arranged in concrete structure and inside concrete.
6. the construction method on bridge major diameter precast concrete tubular column basis, which comprises the steps of:
S1: using non-drainage subsidence technique combination static pressure method sinking tubing string bottom section;
S2: first segment standard pipe shell of column is connect with tubing string bottom section, is equally sunk using non-drainage subsidence technique combination static pressure method First segment standard pipe shell of column;
S3: successively connecting the quasi- tubing string section of the second feast-brand mark on first segment standard pipe shell of column and is combined using non-drainage subsidence technique quiet The platen press sinking quasi- tubing string section of the second feast-brand mark, connects the quasi- tubing string section of third feast-brand mark in the quasi- tubing string section of the second feast-brand mark and use does not drain The quasi- tubing string section ... of subsidence process combination static pressure method sinking third feast-brand mark connects N feast-brand mark in the quasi- tubing string section of N-1 feast-brand mark Quasi- tubing string section simultaneously uses the non-drainage subsidence technique combination static pressure method sinking quasi- tubing string section of N feast-brand mark;
S4: in the quasi- tubing string section upper connector capital section of N feast-brand mark and non-drainage subsidence technique combination static pressure method sinking tubing string is used Push up section;
S5: at tubing string bottom, section carries out the construction of bottom concrete;
S6: construction linkage section.
7. the construction method on bridge major diameter precast concrete tubular column as claimed in claim 6 basis, which is characterized in that in step Before rapid S1, merogenesis first is carried out to the tubular column main body that needs are constructed, then in precast plant to the tubing string bottom section of merogenesis, more standard Tubing string section and the section progress of tubing string top are prefabricated, finally transport to construction site.
8. the construction method on bridge major diameter precast concrete tubular column as claimed in claim 6 basis, which is characterized in that do not arrange Water subsidence process is to be constructed by twisting suction dredging plant;Static pressure method is to apply static pressure load in tubing string upper surface;Soft Lower application static pressure load of weak soil layer;Under horizon d, UHPC sections are connected on tubing string, and UHPC sections of auxiliary tubes are hammered by weight Column sinks.
9. the construction method on bridge major diameter precast concrete tubular column as claimed in claim 6 basis, which is characterized in that step S6 construction linkage section method particularly includes: install end template in the section of tubing string top and bind linkage section reinforcing bar, then install linkage section Template is finally attached a section cast-in-place construction.
10. the construction method on bridge major diameter precast concrete tubular column as claimed in claim 6 basis, which is characterized in that no In drainage sink technique, scum pipe is vertically positioned at the center of tube caisson foudations, and the scum pipe lower end is provided with mechanism of dredging, packet It includes:
Fixed ring, inner ring is connected on scum pipe by more connecting rods and the lucky horizontal snap of the fixed ring is in blade foot In the card slot of side;
Rotational sleeve, be located at fixed ring below and be sheathed on outside scum pipe, the rotational sleeve by driving mechanism driving around The central axes of scum pipe rotate;
Outer drill bit of dredging, is arranged for multiple and circumferential uniform intervals along scum pipe, and the outer drill bit of dredging is solid by level Support rod due to rotational sleeve top connects, and the center that the outer drill bit of dredging is downwardly away from scum pipe is obliquely installed;
Inside dredge drill bit, be arranged for multiple and circumferential uniform intervals along scum pipe, it is described in dredge drill bit by being fixed on The lantern ring of rotational sleeve lower part connects, and the center that the interior drill bit of dredging also is downwardly away from scum pipe is obliquely installed.
CN201910021408.XA 2019-01-10 2019-01-10 Bridge large-diameter precast concrete tubular column foundation and construction method thereof Active CN109989346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910021408.XA CN109989346B (en) 2019-01-10 2019-01-10 Bridge large-diameter precast concrete tubular column foundation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910021408.XA CN109989346B (en) 2019-01-10 2019-01-10 Bridge large-diameter precast concrete tubular column foundation and construction method thereof

Publications (2)

Publication Number Publication Date
CN109989346A true CN109989346A (en) 2019-07-09
CN109989346B CN109989346B (en) 2023-11-10

Family

ID=67129230

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910021408.XA Active CN109989346B (en) 2019-01-10 2019-01-10 Bridge large-diameter precast concrete tubular column foundation and construction method thereof

Country Status (1)

Country Link
CN (1) CN109989346B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453722A (en) * 2019-08-27 2019-11-15 天津大学 A kind of mechanical auxiliary sink device reducing the resistance that breaks ground
CN112012109A (en) * 2020-08-25 2020-12-01 华恒建设集团有限公司 Construction process of ultra-small-spacing double-limb pier stud

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040098872A (en) * 2003-05-16 2004-11-26 진성토건 주식회사 Construction method and the structure for assembling segments pier
CN101831875A (en) * 2010-06-09 2010-09-15 中交第一公路勘察设计研究院有限公司 Precast assembly process of prestressed concrete cylindrical hollow pier
CN101892632A (en) * 2009-05-19 2010-11-24 上海市基础工程公司 Construction method of structural system of river under no-cutoff working condition
CN102767189A (en) * 2012-07-31 2012-11-07 中铁第五勘察设计院集团有限公司 Set bearing platform foundations and construction method thereof
CN103590415A (en) * 2013-11-26 2014-02-19 中铁大桥勘测设计院集团有限公司 Prefabricated bearing platform suitable for large-diameter tubular column foundation of sea bridge and construction method thereof
CN204849569U (en) * 2015-08-10 2015-12-09 江苏建筑职业技术学院 Steel pipe concrete stem stem prefabricated unit construction bridge pier stud of putting more energy into
CN105239594A (en) * 2015-10-30 2016-01-13 江苏中大建设集团有限公司 Prestressed pipe pile upright
CN106049259A (en) * 2016-06-16 2016-10-26 安徽省交通规划设计研究总院股份有限公司 Bridge integrally-assembled pier and construction method
CN205875193U (en) * 2016-06-02 2017-01-11 青岛理工大学 Assembled stake integral structure
CN107354862A (en) * 2017-06-30 2017-11-17 东北大学 Prefabricated interlayer steel tube concrete and hollow steel bar concrete assembly bridge pier
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN108914931A (en) * 2018-07-13 2018-11-30 北京工业大学 A kind of ring-like foundation pile of the vertical shield of assembled and construction method
CN209584855U (en) * 2019-01-10 2019-11-05 中交第二航务工程局有限公司 Bridge major diameter precast concrete tubular column basis

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040098872A (en) * 2003-05-16 2004-11-26 진성토건 주식회사 Construction method and the structure for assembling segments pier
CN101892632A (en) * 2009-05-19 2010-11-24 上海市基础工程公司 Construction method of structural system of river under no-cutoff working condition
CN101831875A (en) * 2010-06-09 2010-09-15 中交第一公路勘察设计研究院有限公司 Precast assembly process of prestressed concrete cylindrical hollow pier
CN102767189A (en) * 2012-07-31 2012-11-07 中铁第五勘察设计院集团有限公司 Set bearing platform foundations and construction method thereof
CN103590415A (en) * 2013-11-26 2014-02-19 中铁大桥勘测设计院集团有限公司 Prefabricated bearing platform suitable for large-diameter tubular column foundation of sea bridge and construction method thereof
CN204849569U (en) * 2015-08-10 2015-12-09 江苏建筑职业技术学院 Steel pipe concrete stem stem prefabricated unit construction bridge pier stud of putting more energy into
CN105239594A (en) * 2015-10-30 2016-01-13 江苏中大建设集团有限公司 Prestressed pipe pile upright
CN205875193U (en) * 2016-06-02 2017-01-11 青岛理工大学 Assembled stake integral structure
CN106049259A (en) * 2016-06-16 2016-10-26 安徽省交通规划设计研究总院股份有限公司 Bridge integrally-assembled pier and construction method
CN107354862A (en) * 2017-06-30 2017-11-17 东北大学 Prefabricated interlayer steel tube concrete and hollow steel bar concrete assembly bridge pier
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN108914931A (en) * 2018-07-13 2018-11-30 北京工业大学 A kind of ring-like foundation pile of the vertical shield of assembled and construction method
CN209584855U (en) * 2019-01-10 2019-11-05 中交第二航务工程局有限公司 Bridge major diameter precast concrete tubular column basis

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453722A (en) * 2019-08-27 2019-11-15 天津大学 A kind of mechanical auxiliary sink device reducing the resistance that breaks ground
CN112012109A (en) * 2020-08-25 2020-12-01 华恒建设集团有限公司 Construction process of ultra-small-spacing double-limb pier stud

Also Published As

Publication number Publication date
CN109989346B (en) 2023-11-10

Similar Documents

Publication Publication Date Title
CN108360972A (en) A kind of rotary drilling rig is combined with percussive drill carries out bored pile construction method
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
EP3118374A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN109083182A (en) Collapsible loess super long large diameter pile foundation churning driven dry method construction method
CN103669365A (en) External diagonal-pulling and internal diagonal-bracing herringbone foundation pit supporting pile and construction method thereof
CN109235426A (en) A kind of construction process for bored pile
CN109630127A (en) A kind of construction method of rich water soft stratum ultra-deep shield vertical shaft
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN110735432A (en) Method for clearing pile foundation and controlling parameters in shield tunneling machine over-invasion limit tunnel range
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
Gil-Martín et al. Developments in excavation bracing systems
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN105926592A (en) Construction method of hole drilling pile
CN106930274B (en) A kind of a full set of cylinder rotatory boring castinplace pile construction method that reinforcing bar cage location is fixed
CN109083181A (en) Collapsible loess super long large diameter pile foundation churning driven half bore mud wet process pore-forming technique
CN209584855U (en) Bridge major diameter precast concrete tubular column basis
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN213625605U (en) Dig deep basal pit structure of stake anchor and hanging net injection concrete soon

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210901

Address after: No.430011, Jinyinhu Road, Wuhan, Hubei Province

Applicant after: CCCC SECOND HARBOR ENGINEERING Co.,Ltd.

Applicant after: CCCC HIGHWAY BRIDGES NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 430048 No. 11 Jinyinhu Road, Dongxihu District, Wuhan City, Hubei Province

Applicant before: CCCC SECOND HARBOR ENGINEERING Co.,Ltd.

GR01 Patent grant
GR01 Patent grant