CN109973115A - A kind of construction method of karst area tunnel vault draining - Google Patents

A kind of construction method of karst area tunnel vault draining Download PDF

Info

Publication number
CN109973115A
CN109973115A CN201910268363.6A CN201910268363A CN109973115A CN 109973115 A CN109973115 A CN 109973115A CN 201910268363 A CN201910268363 A CN 201910268363A CN 109973115 A CN109973115 A CN 109973115A
Authority
CN
China
Prior art keywords
tunnel
conduit
vault
slip casting
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910268363.6A
Other languages
Chinese (zh)
Other versions
CN109973115B (en
Inventor
金玲玲
李军
刘传敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201910268363.6A priority Critical patent/CN109973115B/en
Publication of CN109973115A publication Critical patent/CN109973115A/en
Application granted granted Critical
Publication of CN109973115B publication Critical patent/CN109973115B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/155Laggings made of strips, slats, slabs or sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention is a kind of construction method of karst area tunnel vault draining, belong to the construction method in tunnel, it is characterized in that in the construction in tunnel, conduit is simultaneously squeezed into the first drill straight hole in the rock stratum of the tunnel vault excavated, this conduit is quincuncial arrangement, compartment of terrain slip casting or not slip casting in conduit adjacent two-by-two, the conduit of slip casting has the function of firm wall, the conduit of not slip casting has the function of that the later period excludes water in country rock, after fixing country rock, just continues tunneling;After squeezing into conduit on the vault of tunnel wall, the center line of the corresponding arc-shaped vault for being located at tunnel each side cuts the groove of rectangular ∩ shape on 15 degree of position in tunnel wall after shotcrete layer, it is corresponding in this groove to be embedded in cuboid and uniform circular hole steel plate, this steel plate is cut in the rock stratum of vault, the part water of Karst Water System can be discharged, the later period is effectively prevented from because of the stress concentration caused by a large amount of water, tunnel is avoided to generate serious quality, safety problem.

Description

A kind of construction method of karst area tunnel vault draining
Technical field
The invention belongs to the construction methods in tunnel, more particularly, to a kind of construction method of karst area tunnel drainage.
Background technique
In the construction of the highway in mountain area, it will usually encounter the construction in tunnel, especially in Guizhou, Yunnan and the Sichuan of China, Since its holds landforms uniquely, underground karst cavity, karst are more, the maintenance runed to the design, construction and later period of Tunnel Engineering Bring bigger difficulty, under normal circumstances, in the work progress in tunnel, when encountering solution cavity, karst, using by all kinds of means, A variety of methods combine, drawn, arranged, around, more, the water in solution cavity is discharged, in addition, after tunnel is built up, some tunnels by , water logging in tunnel the phenomenon that being influenced in by solution cavity and karst water, often will appear Tunnel Water Leakage, will appear in tunnel: 1) No railway roadbed, 2), tunnel floor is squeezed by karst water and destroyed, 3), lining-up craze and transfiguration even destroys, and will jeopardize traffic safety, It even cuts off traffic, therefore, in the work progress in tunnel, how the effective ejectment of water in solution cavity to be gone out, behind tunnel During the operation of phase, how to solve the problems, such as the control and ejectment of tunnel top solution cavity, water flow in karst, be related skill The project that art personnel are probed into.
Summary of the invention
The purpose of the present invention is the above problems present in the construction for lava and solution cavity area tunnel, propose a kind of rock The construction method of molten area tunnel vault draining, can discharge the part water of Karst Water System, be effectively prevented from the later period because of a large amount of water Caused stress is concentrated, and the landslide event that tunnel occurs is effectively prevented from, and the serious quality of tunnel generation, safety is avoided to ask Topic.
The object of the present invention is achieved like this: a kind of construction method of karst area tunnel vault draining, feature Be: in the construction in tunnel, using elder generation excavated tunnel wall (explanation: tunnel be according to design sublevel drive) vault It drill straight hole and is squeezed into conduit (i.e. steel pipe) in the rock stratum (country rock) of portion periphery, this conduit is in quincuncial arrangement, adjacent two-by-two Compartment of terrain slip casting (i.e. injection plain concrete slurry) or not slip casting, the conduit of slip casting have the function of firm wall, do not infuse in conduit The conduit of slurry has the function of that the later period excludes water in country rock, after fixing country rock, just continues tunneling;
In addition, the inner surface after the conduit in tunnel vault portion has been squeezed into, at the top of the tunnel wall of shotcrete layer Upper correspondence be located at the center line of arc-shaped (sector) vault in tunnel each side cut on 15 degree of position front and back to Rectangular ∩ shape groove, it is corresponding in this groove to place (embedded) cuboid and uniform circular hole steel plate, in steel plate and It is stitched agent with rising between groove and is filled.
A kind of construction method of karst area tunnel vault draining proposed by the invention, construction procedure is:
One), general principle is that first branch (support) digs (excavation) afterwards in construction, in constructing tunnel, according to design, first by conduit It is driven into the country rock in the tunnel excavated, conduit is squeezed into, and is to carry out supporting with common temporary support, in tunnel rock The lower surface of (country rock) subdrilling straight hole from lower to upper, the diameter of this straight hole can be 3cm~5cm, depth (length) can be 3m~ Then 5m is squeezed into conduit (i.e. steel pipe) in straight hole, and the lower end of conduit and tunnel arch do not penetrate through, the direction of conduit be perpendicular to Country rock, and the direction range of conduit nozzle is each side 15 degree of the center line of arc-shaped (sector) vault of tunnel arch In the range of (totally 30 degree), the direction of conduit is depending on the design of the broken situation of country rock, spacing between adjacent catheter two-by-two Setting: it when Grades of Surrounding Rock is three-level or three-level or more, is constructed using level of confidentiality conduit, two-by-two the center spacing between adjacent catheter For 0.5m, when Grades of Surrounding Rock is three-level hereinafter, the center spacing between adjacent catheter is 1~1.5m two-by-two;
After squeezing into conduit in country rock, each conduit is arranged to the conduit of slip casting and the conduit of not slip casting by compartment of terrain two-by-two, Slip casting is carried out using plain concrete slurry in the conduit of slip casting, slurries can enter the gap of country rock along conduit and solidify, and play steady Gu the purpose of country rock, the conduit of not slip casting is used to exclude the water flow in rock stratum, etc. be further continued for carrying out next section of tunnel after adjoining rock stabilities The excavation in road.
Two) it after, the conduit in tunnel is squeezed into, is supported in tunnel using interim steel arch-shelf, while to tunnel wall Inner surface carries out shotcrete layer, the jet thickness of concrete layer are as follows: just spray is 5cm, and multiple spray is 8~10cm, arch angle 10 ~15cm.
Three) after, concrete layer to be sprayed solidifies the intensity for reaching design, the center line on segment top is located in tunnel wall Each side 15 degree of position cut the groove of sagittal right angle ∩ shape respectively, the depth of the groove can for 15cm, Width can be 10cm, be entirely located in the lower mouth of each conduit should between two grooves in left and right;
Four), (fan-shaped region including vault) is laid with conventional waterproof layer, waterproof layer paving on the concrete layer in tunnel Being set at groove should be firmly bonded;
Five), using conventional method assembling reinforcement, when reinforcing bar binds the top encircleed to tunnel, in the left and right of fan-shaped region (i.e. front and back to) longitudinal in the groove of two sides be embedded in the steel plate of cuboid respectively, the thickness of this steel plate can be for 10cm, highly may be used For 15cm~17cm, agent is stitched with general rising between steel plate and groove and is filled, and this steel plate is embedded into the groove of vault After interior, the bottom surface absolute altitude of steel plate must be consistent with the absolute altitude of top surface that tunnel encircles, and is longitudinally connected using welding between the steel plate of front and back It connects, while uniformly opening up the circular hole of draining on the steel plate, the diameter of the circular hole can be 5cm, which should be embedded in into vault Rock stratum in, then the water of small flow is injected under the inverted arch of tunnel bottom by the back that the circular hole on steel plate is discharged to tunnel arch Drainage system set in addition drain;
Six), installation template trolley carries out the concreting of tunnel arch, the edge on the centre at the top of tunnel arch The longitudinal direction (i.e. front and back to) in tunnel is uniformly distributed, compartment of terrain aperture and installs drainpipe, which can be used pvc pipe and be made, The interior diameter of the drainpipe can be 2cm, this drainpipe installs closing cap in the outlet of each drainpipe perpendicular to vault, according to Draining needs to open or close closing cap, when water flow is big, turns on the outlet of drainpipe, carries out central drainage, to reduce The stress and damaged or destroyed by flood phenomenon of tunnel arch;
(explanation: the quasi- in addition application utility model patent of the closing cap, so its structure is herein without further retouching It states)
After concrete reaches strength of mould stripping, demoulding.
After tunnel IMM algorithm, during the operation in tunnel, is measured by monitoring, Karst geology situation can be monitored The deformation in lower tunnel and drainage situation, once discovery country rock has deformation, slight crack and displacement etc., i.e. temporary enclosed traffic is adopted After being punched with vault, vertical drainpipe is placed, longitudinal direction of the drainpipe along tunnel is equally spacedly arranged, and tunnel vault is logical Water is discharged into fan-shaped region by the conduit for crossing not slip casting, and the circular hole on steel plate that part water passes through dome portions flows into tunnel arch (also known as Two lining concrete) back, be then injected into tunnel arch bottom with inverted arch handover place drainage system in, by tunnel The drainage system of design is drained, and a large amount of water of tunnel vault portion rock stratum can be released from the drainpipe of fan-shaped vault installation Put, using central drainage, so as to discharge rapidly tunnel vault stress and water-based pressure, be effectively prevented from tunnel occur it is big Quality and security risk, after the stabilization for waiting tunnel vaults, then reopen traffic.
The application of technology through the invention, during runing tunnel, the hidden danger of the quality in karst area tunnel is mediated, The application of technology through the invention simultaneously, discharges the stress of tunnel vault effectively, is more advantageous to tunnel vault country rock Stabilization.
A kind of construction method of karst area tunnel vault draining proposed by the invention, can discharge the part of Karst Water System Water is effectively prevented from the later period because of the stress concentration caused by a large amount of water, is effectively prevented from the landslide event that tunnel occurs, avoids Tunnel generates serious quality, safety problem.
Presently in connection with drawings and examples to a kind of construction party of karst area tunnel vault draining proposed by the invention Method is described further.
Detailed description of the invention
Fig. 1 is a kind of use schematic diagram of the construction method of karst area tunnel vault draining proposed by the invention.
In Fig. 1: 1, steel plate 2, drainpipe 3, conduit 4, tunnel encircle 5, inverted arch
Embodiment
A kind of construction method of karst area tunnel vault draining proposed by the invention is undertaking the construction of Guizhou province purple prestige height It is applied in the engineering in speed happiness seat tunnel, the overview of the Tunnel Engineering is as follows:
Liking seat length of tunnel is 4234 meters, and two holes of left and right are in separation arrangement, 2130 meters of left hole overall length, right hole overall length 2104 Rice, is long tunnel, and the Grades of Surrounding Rock of Tunnel Passing is two kinds of level Four, Pyatyi (i.e. IV grade, V grade) country rocks.
Its construction procedure is:
One), conduit 3 is driven into the country rock for having excavated the tunnel of certain drilling depth (drilling depth is depending on design), conduit 3 Squeeze into, be to carry out supporting with common temporary support, in the lower surface of tunnel rock (country rock) subdrilling straight hole from lower to upper, Then conduit 3 is squeezed into straight hole, this conduit 3 is made with overall diameter of 4.2cm, length of the steel pipe of 4m, and the lower end of conduit 3 It 4 is not penetrated through with tunnel arch, the direction of the conduit 3 is perpendicular to country rock, and the direction range of the nozzle of conduit 3 is tunnel arch 4 In the range of each side 15 degree (totally 30 degree) of the center line of arc-shaped (sector) vault, the direction of conduit 3 is according to country rock Broken situation design depending on, two-by-two between adjacent catheter spacing setting: because Grades of Surrounding Rock be level Four, Pyatyi, it is adjacent two-by-two Center spacing between conduit is 1.5m;
After squeezing into conduit 3 in the country rock in tunnel, each conduit 3 is arranged to conduit and the not slip casting of slip casting by compartment of terrain two-by-two Conduit, in the conduit 3 of slip casting using plain concrete slurry carry out slip casting, slurries can along conduit 3 enter country rock gap and Solidification, plays the purpose of firm wall, etc. after adjoining rock stabilities, be further continued for carrying out the excavation in next section of tunnel.
Two) it after, tunnel wall squeezes into conduit, is supported in tunnel using interim steel arch-shelf, while to tunnel wall Inner surface carries out shotcrete layer, the jet thickness of concrete layer are as follows: just spray is 5cm, and multiple spray is 8cm, arch angle 10cm.
Three) after, concrete layer to be sprayed solidifies the intensity for reaching design, the center line on segment top is located in tunnel wall Each side 15 degree of position cut the groove of the sagittal right angle ∩ shape that depth is 15cm, width 10cm respectively, The lower mouth of each conduit 3 is all corresponding to be located between two grooves in left and right;
Four), (fan-shaped region including vault) is laid with conventional waterproof layer, waterproof layer paving on the concrete layer in tunnel Being set at groove should be firmly bonded;
Five), using conventional method assembling reinforcement, when reinforcing bar binds and encircles 4 top to tunnel, in the left and right of fan-shaped region (i.e. front and back to) longitudinal in the groove of two sides be embedded in the steel plate 1 of cuboid respectively, this steel plate 1 with a thickness of 10cm, be highly After 15cm stitches agent with general rising between the steel plate 1 and groove and is filled, and this steel plate 1 is embedded into the groove of vault, steel The bottom surface absolute altitude of plate 1 must be consistent with the absolute altitude of top surface that tunnel encircles 4, longitudinally using being welded to connect between the steel plate of front and back, together When the circular hole of draining is uniformly opened up on steel plate 1, the diameter of the circular hole is 5cm, which should be embedded in the rock stratum into vault Interior, then the water of small flow is injected under the inverted arch 5 of tunnel bottom by the back that the circular hole on steel plate 1 is discharged to tunnel arch 4 Drainage system set in addition is drained;
Six), installation template trolley carries out the concreting of tunnel arch 4, the centre at the top of arch 4 in tunnel On longitudinal direction (i.e. front and back to) along tunnel is uniformly distributed, compartment of terrain aperture and installs drainpipe 2, which uses pvc pipe system At the interior diameter of the drainpipe is 2cm, this drainpipe 2 installs closing cap, root in the outlet of each drainpipe 2 perpendicular to vault It needs to open or close closing cap according to draining, when water flow is big, turns on the outlet of drainpipe 2, central drainage is carried out, to subtract The stress and damaged or destroyed by flood phenomenon of Pollen sterility arch 4, after concrete reaches strength of mould stripping, demoulding.(explanation: formwork jumbo is that one kind can Mobile plate device generallys use this device in constructing tunnel)
After tunnel IMM algorithm, during the operation in tunnel, is measured by monitoring, Karst geology situation can be monitored The deformation in lower tunnel and drainage situation, discharge the stress of tunnel vault effectively, are more advantageous to tunnel vault country rock Stablize, the hidden danger of the quality in karst area tunnel is mediated.

Claims (7)

1. a kind of construction method of karst area tunnel vault draining, it is characterized in that: being opened in the construction in tunnel using elder generation Drill straight hole and conduit (3) i.e. steel pipe is squeezed into rock stratum, that is, country rock of the dome portions periphery of the tunnel wall of digging, this conduit (3) is in plum blossom Shape arrangement, plain concrete slurry or not slip casting, the conduit (3) of slip casting are injected in compartment of terrain slip casting in conduit (3) adjacent two-by-two Have the function of firm wall, the conduit (3) of not slip casting has the function of that the later period excludes water in country rock, after fixed country rock, just after Continuous tunneling;
In addition, after the conduit (3) in tunnel vault portion has been squeezed into, on the inner surface at the top of the tunnel wall of shotcrete layer The center line of the corresponding arc-shaped i.e. fan-shaped vault for being located at tunnel each side cuts on 15 degree of position sagittal The groove of rectangular ∩ shape, it is corresponding in this groove to place cuboid and uniform circular hole steel plate (1), in steel plate (1) and ditch It is stitched agent with rising between slot and is filled;
A kind of construction method of karst area tunnel vault draining proposed by the invention, construction procedure is:
One), general principle is first to support to excavate afterwards in construction, in constructing tunnel, according to design, is first driven into conduit (3) In the country rock in the tunnel of excavation, conduit (3) are squeezed into, and are to carry out supporting with common temporary support, in tunnel rock, that is, country rock Lower surface subdrilling straight hole from lower to upper, conduit (3) i.e. steel pipe, and the lower end of conduit (3) and tunnel are then squeezed into straight hole Road arch does not penetrate through, and the direction of conduit (3) is perpendicular to country rock, and the direction range of conduit nozzle is the circular arc in tunnel arch (4) Shape be the center line of fan-shaped vault each side 15 degree be in the range of totally 30 degree, the direction of conduit (3) is according to country rock Depending on broken situation design, two-by-two between adjacent conduit (3) spacing setting: when Grades of Surrounding Rock is three-level or three-level or more When, using level of confidentiality conduit construct, two-by-two the center spacing between adjacent conduit (3) be 0.5m, when Grades of Surrounding Rock be three-level with Under, the center spacing between adjacent conduit (3) is 1~1.5m two-by-two;
After squeezing into conduit (3) in country rock, each conduit (3) is arranged to the conduit of slip casting and leading for not slip casting by compartment of terrain two-by-two Pipe, the conduit (3) of slip casting is middle to carry out slip casting using plain concrete slurry, and slurries can enter the gap of country rock along conduit (3) and coagulate Gu playing the purpose of firm wall, the conduit (3) of not slip casting is used to exclude the water flow in rock stratum, etc. be further continued for after adjoining rock stabilities Carry out the excavation in next section of tunnel;
Two) it after, the conduit (3) in tunnel is squeezed into, is supported in tunnel using interim steel arch-shelf, while in tunnel wall Surface carries out shotcrete layer, the jet thickness of the concrete layer are as follows: just spray is 5cm, and multiple spray is 8~10cm, arch angle 10 ~15cm.
Three) after, the set strength of concrete layer to be sprayed reaches the intensity of design, the center on segment top is located in tunnel wall Each side 15 degree of the position of line cuts the groove of sagittal right angle ∩ shape respectively, answers the lower mouth of each conduit (3) It is entirely located between two grooves in left and right;
Four), on the concrete layer in tunnel, the fan-shaped region including vault is laid with conventional waterproof layer, and waterproof layer is routed to It should be firmly bonded at groove;
Five), using conventional method assembling reinforcement, when reinforcing bar binds and encircles the top of (4) to tunnel, in the left and right two of fan-shaped region Longitudinally it is the steel plate (1) that front and back is embedded in cuboid to ground respectively in the groove of side, is risen between steel plate (1) and groove with general After seam agent is filled, and this steel plate (1) is embedded into the groove of vault, the bottom surface absolute altitude of steel plate (1) must encircle (4) with tunnel Top surface absolute altitude it is consistent, longitudinally using being welded to connect between front and back steel plate (1), while the uniformly row of opening up on steel plate (1) The circular hole of water, the circular hole position should be embedded in the rock stratum of vault, and the water of small flow is discharged to tunnel by the circular hole on steel plate (1) Encircle the back of (4), then, the drainage system set in addition injected under the inverted arch (5) of tunnel bottom is drained;
Six), installation template trolley carries out the concreting of tunnel arch (4), on the centre at the top of tunnel arch (4) Longitudinal direction along tunnel is front and back to uniformly distributed, compartment of terrain aperture and installs drainpipe (2), this drainpipe (2) perpendicular to vault, Closing cap is installed in the outlet of each drainpipe (2), needs to open or close closing cap by draining, when water flow is big, is just beaten Begin to rehearse the outlets of water pipe (2), carries out central drainage, to reduce the stress and damaged or destroyed by flood phenomenon of tunnel arch (4), to tunnel arch (4) After concrete reaches strength of mould stripping, then demoulding.
2. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that this straight hole Diameter be 3cm~5cm, depth is 3m~5m.
3. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that the groove Depth be 15cm, width 10cm.
4. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that the draining Pipe (2) is made of pvc pipe.
5. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that the draining The interior diameter for managing (2) is 2cm.
6. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that this steel plate (1) with a thickness of 10cm, highly be 15cm~17cm.
7. a kind of construction method of karst area tunnel vault draining according to claim 1, it is characterised in that circular hole Diameter is 5cm.
CN201910268363.6A 2019-04-04 2019-04-04 Construction method for drainage of vault of tunnel in karst area Active CN109973115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910268363.6A CN109973115B (en) 2019-04-04 2019-04-04 Construction method for drainage of vault of tunnel in karst area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910268363.6A CN109973115B (en) 2019-04-04 2019-04-04 Construction method for drainage of vault of tunnel in karst area

Publications (2)

Publication Number Publication Date
CN109973115A true CN109973115A (en) 2019-07-05
CN109973115B CN109973115B (en) 2020-06-05

Family

ID=67082893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910268363.6A Active CN109973115B (en) 2019-04-04 2019-04-04 Construction method for drainage of vault of tunnel in karst area

Country Status (1)

Country Link
CN (1) CN109973115B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985055A (en) * 2019-12-20 2020-04-10 中铁南方投资集团有限公司 Tunnel grouting and drainage synchronous construction method for controlling surface uplift
CN111535829A (en) * 2020-06-09 2020-08-14 中国十七冶集团有限公司 Construction method for treating longitudinal through cracks on side surface of tunnel section hole body
CN116104056A (en) * 2023-03-06 2023-05-12 广东省水利电力勘测设计研究院有限公司 Rock stratum drainage device of underground factory building of pumped storage power station and construction method of rock stratum drainage device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH681475A5 (en) * 1990-04-20 1993-03-31 Peter Ellenberger Water-drainage system for tunnel walls - uses mats made of different layers, an outer sealing layer and filter layer made of cloth and has openings
CN1766289A (en) * 2005-11-29 2006-05-03 长安大学 Centralized water discharge apparatus and method for tunnelling
CN106401600A (en) * 2016-10-28 2017-02-15 招商局重庆交通科研设计院有限公司 Tunnel strengthening treatment method and support structure based on positions of dissolving cavities
CN108590711A (en) * 2018-06-25 2018-09-28 中国电建集团中南勘测设计研究院有限公司 A kind of liner structure of tunnel rock burst hole section
CN109026020A (en) * 2018-08-07 2018-12-18 中电建路桥集团有限公司 A kind of rich water tunnel karst cave treatment and excavation method
CN109519220A (en) * 2018-10-29 2019-03-26 中铁十二局集团有限公司 Karst area diversion tunnel is crushed rich water section grouting treatment method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH681475A5 (en) * 1990-04-20 1993-03-31 Peter Ellenberger Water-drainage system for tunnel walls - uses mats made of different layers, an outer sealing layer and filter layer made of cloth and has openings
CN1766289A (en) * 2005-11-29 2006-05-03 长安大学 Centralized water discharge apparatus and method for tunnelling
CN106401600A (en) * 2016-10-28 2017-02-15 招商局重庆交通科研设计院有限公司 Tunnel strengthening treatment method and support structure based on positions of dissolving cavities
CN108590711A (en) * 2018-06-25 2018-09-28 中国电建集团中南勘测设计研究院有限公司 A kind of liner structure of tunnel rock burst hole section
CN109026020A (en) * 2018-08-07 2018-12-18 中电建路桥集团有限公司 A kind of rich water tunnel karst cave treatment and excavation method
CN109519220A (en) * 2018-10-29 2019-03-26 中铁十二局集团有限公司 Karst area diversion tunnel is crushed rich water section grouting treatment method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985055A (en) * 2019-12-20 2020-04-10 中铁南方投资集团有限公司 Tunnel grouting and drainage synchronous construction method for controlling surface uplift
CN111535829A (en) * 2020-06-09 2020-08-14 中国十七冶集团有限公司 Construction method for treating longitudinal through cracks on side surface of tunnel section hole body
CN116104056A (en) * 2023-03-06 2023-05-12 广东省水利电力勘测设计研究院有限公司 Rock stratum drainage device of underground factory building of pumped storage power station and construction method of rock stratum drainage device

Also Published As

Publication number Publication date
CN109973115B (en) 2020-06-05

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN108194102B (en) The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN105201518B (en) Disassembling method is received in a kind of major diameter slurry balance shield hole
CN107288642A (en) PBA construction technologies
CN108005664A (en) A kind of hole pile construction method of platform structure
CN101864960A (en) Carst region double-arch road tunnel construction method
CN109973115A (en) A kind of construction method of karst area tunnel vault draining
CN108150219B (en) A kind of the ground water drainage system and its construction method of separate type double-hole tunnel
CN109578007B (en) Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN107939415A (en) Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN109736884B (en) Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure
CN109403333A (en) A kind of soft lower hard water rich strata deep basal pit reversed construction method
CN207813651U (en) A kind of ground water drainage system for double-hole tunnel
CN110284885A (en) Shield inspection-pit construction method
KR100877452B1 (en) Construction method of middle wall of three arch excavation tunnel
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN206000553U (en) The shield end soil body reinforcement system in high water head deep and thick sand area
CN108756897B (en) A kind of construction method of breaking surrounding rock people's air defense tunnel cross point
CN117167026B (en) Construction method for reverse roof-picking at intersection of inclined shaft work area of tunnel reconstruction and expansion section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant