WO2021223573A1 - Construction structure for communication and connection between newly added mined channel and existing station hall layer - Google Patents

Construction structure for communication and connection between newly added mined channel and existing station hall layer Download PDF

Info

Publication number
WO2021223573A1
WO2021223573A1 PCT/CN2021/086346 CN2021086346W WO2021223573A1 WO 2021223573 A1 WO2021223573 A1 WO 2021223573A1 CN 2021086346 W CN2021086346 W CN 2021086346W WO 2021223573 A1 WO2021223573 A1 WO 2021223573A1
Authority
WO
WIPO (PCT)
Prior art keywords
old
new
connection
ring beam
existing station
Prior art date
Application number
PCT/CN2021/086346
Other languages
French (fr)
Chinese (zh)
Inventor
黄欣
张京京
赵静波
冀国栋
陈一夫
岳长城
陈霞飞
彭澍
陈自龙
高飞鹏
Original Assignee
中铁十八局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁十八局集团有限公司 filed Critical 中铁十八局集团有限公司
Publication of WO2021223573A1 publication Critical patent/WO2021223573A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/008Driving transverse tunnels starting from existing tunnels

Definitions

  • connection connection interface structure for shallow-buried urban underground space, in particular to a connection connection interface structure form of newly-added digging channels in shallow-buried urban underground space and existing station hall floors, belonging to urban rail transit connections Technical field.
  • Chinese patent 201710115981.8 discloses a block for constructing a guide wall and a construction method for the block to construct a guide wall, which belongs to the field of construction of a guide wall for buildings.
  • the block has a rectangular strip structure, including an upper connecting surface and The lower bonding surface and the left and right sides, the upper connecting surface has a curved surface structure, and the block is provided with vertical through holes along its axial direction.
  • prefabricated blocks are used, which eliminates the tedious steps of on-site construction.
  • the site only needs to be bonded and fixed to complete the guide wall process, which saves time and effort, and the use of prefabricated guide walls avoids the on-site During the construction, the guide wall and the wall are cracked due to the guide wall not being completely dry, which affects the beauty and moisture-proof and waterproof problems.
  • the present invention relates to the removal of the connection structure of the existing station hall layer, so as to realize the connection and connection with the newly-added underground excavation channel, and the removal of the existing station hall layer wall structure, thereby realizing the connection and connection with the newly-added underground excavation channel (tunnel). change.
  • the technical solution adopted by the present invention is to add a new underground excavation channel to the existing station hall floor to connect and connect the construction structure.
  • the details are as follows: a reinforced ring beam 21 and a new
  • the added surface layer 107 is connected to the existing station hall layer 1.
  • the structure of the connecting joint includes the planting bar 103, the interface between the new and the old structure 104, the rebar lap 105 between the old and the new structure, and the anchor bar 106.
  • the anchor bars are arranged in a plum blossom shape on one side horizontally, and the other side is used as a plant bar to be implanted in the existing station hall floor 1 breaking opening.
  • a reinforced structural stirrup 110 is added to the newly added surface layer 107, and the two outermost rows are welded to the main reinforcement in the existing station hall floor 1 to form a new and old structural reinforcement overlap 105; the middle two rows of reinforced structural stirrups 110 extend the planting Enter the existing station hall floor 1, as the planting bar 103 of the old structure.
  • the main reinforcement 108 of the buried channel is extended and buried in the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102.
  • the main reinforcement structure 109 and the reinforcement structure stirrup 110 are arranged; the old structure side of the new and old structure interface 104 is smeared with an interface agent to enhance the bonding performance with the new structure.
  • the concrete for strengthening the ring beam 21 and the concrete for the newly added surface layer 107 are poured to complete the connection structure construction.
  • the welding length of the overlap 105 of the new and old structural steel bars is not less than 120 mm.
  • the interface agent adopts materials such as polymer-modified cement mortar sand, epoxy mortar or 1:1 cement mortar.
  • connection form of the docking structure involved in the present invention adopts a symmetrical form up and down, and the structural connection is stable and beautiful; at the same time, the new and old docking structures are effectively connected to ensure the consistency between the new and the old structures.
  • the newly-added reinforced ring beam and the newly-added surface layer effectively and firmly connect the barge interface to ensure that there will be no bumps or water seepage in the subsequent practical process.
  • the structure between the newly-added structure and the existing structure is effectively used, and the integrated structure of the invention is added. form.
  • Figure 1 is a flow chart of the implementation of the present invention.
  • Figure 2 is a schematic diagram of the connection side wall structure connecting the newly built transfer hall and the existing tunnel.
  • (a), (b), (c) are the schematic diagrams of the connection implementation process respectively.
  • Figure 3 is a schematic diagram of a flow chart of broken grouting.
  • Figure 4 is a schematic diagram I of the connection structure.
  • Figure 5 is a schematic diagram of the connection structure II.
  • the roof reinforcement ring beam 101 is set at the vault interface of the newly-added concealed tunnel, the size is 450mm*800mm, the upper two rows of main reinforcement 8C22, waist reinforcement 2C22, stirrup A12@ 150. Between the new and old structures, 150mm*300mm plum blossoms are arranged with 850mm long C20 anchor bars 106, which are anchored into the existing station hall floor 1 by 400mm.
  • the top surface layer 107 is 500mm*150mm in size, C40 self-compacting concrete is poured, the bottom is equipped with reinforced structural main reinforcement 1095C22, and the reinforced structural stirrup 110C12@100/200 is newly added, and the reinforced structural stirrup 110 is used as a planting bar to be embedded in the existing station hall Layer 1, the anchorage length is not less than 250mm;
  • the size is 450*1100mm, the main reinforcement, waist reinforcement C22, stirrup A12@150; horizontal arrangement length 850mm C20 anchor reinforcement between the existing station hall floor 1 106, 150mm*300mm plum blossom layout, anchored into the existing station hall floor 1 length not less than 400mm.
  • the size of the new surface layer 107 at the bottom is 500*150mm, C40 self-compacting concrete is poured, the top is equipped with C20 main reinforcement, and the reinforcement structure stirrup 110C12@100/200 is added to pass through the interface 104 of the new and old structure, and is buried in the existing station hall layer 1.
  • a construction method for connecting new underground tunnels with the existing station hall layer is used to construct the new underground tunnel without affecting the normal operation of the existing station hall floor 1.
  • Dig channel 2, and the connection steps are as follows:
  • the first step use deep hole grouting to penetrate the newly-added undercut channel. Deep-hole grouting is carried out on the grouting range 3 of the undercut channel 2 from the ground, and the connecting connection is pre-reinforced to protect the surrounding structure of the station connection from damage and improve the safety of connection construction.
  • the earthwork of the newly-increased tunnel 2 is excavated by the CRD method. During the earthwork excavation, a step distance of 1.5 times the diameter of each pilot hole shall be maintained. When the earthwork is excavated, enough core soil shall be left as a stable support to keep the newly added The soil in the tunnel is balanced. Go through No. 1 cavern 4, No. 2 cavern 5, No. 3 cavern 6, and No. 4 cavern 7 of the newly-added underground tunnel 2 in sequence, and then spray the first branch 14 of the underground tunnel inside the newly-added underground tunnel.
  • Step 2 Destroy the temporary middle wall and temporary invert of the newly-added digging tunnel, and erect a full house.
  • the temporary intermediate wall 9 and the temporary invert 8 between the new tunnels of No. 1 cavern 4, No. 2 cavern 5, No. 3 cavern 6 and No. 4 cavern 7 are removed by segmentation, and synchronized Set up full red scaffolding 10 to ensure the stability of the internal structure of the newly-added concealed tunnel 2.
  • the third step implement waterproofing, secondary lining and steel joints for newly-added digging channels.
  • Step 4 Dismantle the 1.2m range of the scaffolding on the 1 side of the existing station hall floor to provide space for the construction of the connection, that is, the opening range17.
  • the opening range 17 is broken to correspond to the side walls of the newly-added undercut passage and the surface of the first branch 14 of the undercut passage and the first branch 15 of the existing station hall floor, and the surface of the first branch 14 of the undercut passage and the first branch 15 of the existing station hall floor.
  • Do waterproof lap joints Adopt double-sided butyl adhesive tape to bond the waterproof 11 of the digging channel and the waterproof 16 of the existing station hall.
  • Step 5 Destroy the concrete structure of the opening area 17 section by section, and penetrate through the existing station hall floor 1 and the newly-added underground excavation channel 2.
  • the cutting method of stripping and block breaking adopts the wire saw cutting method.
  • the support of the opening area 17 and the cutting and breaking are carried out at the same time, and the preliminary breaking of the connection port is completed.
  • Step 6 Chiseling the top and bottom of the connection port completed in Step 5, planting ribs 20 and pouring the reinforced ring beam 21.
  • Figure 3 is a schematic diagram of a flow chart of broken grouting.
  • the deep hole grouting process is as follows:
  • the deep hole grouting is carried out in groups, each group has a grouting length of 12m, the overlap between the previous group and the next group is 2m, and the effective reinforcement length is 10m.
  • Grouting holes are arranged at 0.8*0.8m spacing, plum blossom-shaped arrangement, and surface grouting method is adopted.
  • AC slurry cement + water glass + filler
  • cement + water glass + filler cement + water glass + filler
  • the setting time of the slurry is shortened by adjusting the filler to drain and squeeze out the water in the grouting area.
  • AC grout is suitable for geological conditions such as silty clay layer, medium coarse sand layer, silty fine sand layer, etc.
  • Grouting After the injection pipe is set, close the end point and switch the horizontal injection. Apply pressure to the sprayed material to achieve a horizontal penetration effect.
  • the grouting pressure P in the water stop reinforcement range is controlled at 0.8-1.0Mpa, and a new round of grouting is started by controlling the segmented solidification time to control the spray positions of the slurry at different distances in the longitudinal direction.
  • the length of the drawn-back drill pipe (grouting pipe) is controlled within the range of 0.3-0.5m.
  • the main grouting parameters are as follows:
  • Grouting depth depth 0 ⁇ 2m; drilling diameter: 42mm; grout diffusion radius: 0.6m ⁇ 0.8m;
  • the face of the excavation before grouting needs to be double-layered with netting and spray anchors to form a grouting layer and form strength before drilling holes can be drilled and grouted.
  • the thickness of the spray-anchored surface of the grout retaining layer is not less than 300mm.
  • the solidification time of the grout ratio should be flexibly adjusted according to the actual conditions of the site. For example, when the pebble layer on site is poor in pourability, the grout setting time can be appropriately reduced to increase the pourability; when there is a bright water flow, the grout can be adjusted according to the size of the water flow.
  • the appropriate setting time is 6 ⁇ 10s.
  • Figure 4 is a schematic diagram I of the connection structure.
  • Figure 5 is a schematic diagram of the connection structure II.
  • a reinforced ring beam 21 and a new surface layer 107 are installed at the connection port of the newly-added underground excavation hall 2 to connect to the existing station hall floor 1.
  • the structure of the connecting joint includes the planting bar 103, the interface between the new and the old structure 104, the rebar lap 105 between the old and the new structure, and the anchor bar 106.
  • the anchor bars are arranged in a plum blossom shape on one side horizontally, and the other side is used as a plant bar to be implanted in the existing station hall floor 1 breaking opening.
  • a reinforced structural stirrup 110 is added to the newly added surface layer 107, and the two outermost rows are welded to the main reinforcement in the existing station hall floor 1 to form a new and old structural reinforcement overlap 105; the middle two rows of reinforced structural stirrups 110 extend the planting Enter the existing station hall floor 1, as the planting bar 103 of the old structure.
  • the main ribs 108 of the tunnel excavated are extended and embedded in the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102.
  • the main reinforcement structure 109 and the reinforcement structure stirrup 110 are arranged; the old structure side of the new and old structure interface 104 is smeared with an interface agent to enhance the bonding performance with the new structure.
  • the concrete for strengthening the ring beam 21 and the concrete for the newly added surface layer 107 are poured to complete the connection structure construction.
  • the welding length of the new and old structural steel bar overlap 105 is not less than 120mm.
  • the interface agent adopts materials such as polymer modified cement mortar sand, epoxy mortar or 1:1 cement mortar.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Elevator Control (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A construction structure for communication and connection between a newly added mined channel and an existing station hall layer (1). A reinforcing ring beam (21) and a newly added surface layer (107) are provided at a connection port of a newly added mined hall (2), such that the newly added underground hall (2) communicates with and is connected to the existing station hall layer (1). Reinforcing structure main bars (109) and a reinforcing structure stirrup (110) are arranged in the reinforcing ring beam (21) and the newly added surface layer (107). A bonding agent is applied at an old-structure side of a new-old structure interface (104) so as to improve bonding between the old structure and the newly added structure. The connection structures are connected in a horizontally symmetrical manner, such that the connection between the structures is stable and aesthetically pleasing, and the effective connection between the new connection structure and the old connection structure ensures consistency between the new and old structures. The connection port is effectively and stably connected by means of the newly added reinforcing ring beam (21) and the newly added surface layer (107), thereby ensuring that no protrusion or water seepage occurs during subsequent use.

Description

新增暗挖通道与既有站厅层连通接驳施工结构Newly-excavated channel is connected with the existing station hall floor to connect the construction structure 技术领域Technical field
本发明涉及一种针对浅埋城市地下空间连通接驳接口结构,特别是一种浅埋城市地下空间中新增暗挖通道与既有站厅层连通接驳接口结构形式,属于城市轨道交通连接技术领域。The invention relates to a connection connection interface structure for shallow-buried urban underground space, in particular to a connection connection interface structure form of newly-added digging channels in shallow-buried urban underground space and existing station hall floors, belonging to urban rail transit connections Technical field.
背景技术Background technique
随着经济的发展、时代形式的变迁,既有地铁运营能力差、既有地下空间拥挤等城市矛盾爆发,开发拓展地下空间是缓解城市发展瓶颈的有效措施,因此引发出既有结构拓建的需求。施工中通常采用的方法是先建新结构,在新老结构衔接处破除老结构侧墙,从而实现搭接。With the development of the economy and the changes of the times, urban contradictions such as the poor operating capacity of existing subways and the congestion of existing underground spaces have erupted. The development and expansion of underground space is an effective measure to alleviate the bottleneck of urban development, which has led to the expansion of existing structures. need. The method usually used in construction is to build a new structure first, and break the side wall of the old structure at the junction of the new and old structure to achieve overlap.
中国专利201710115981.8公开了一种构筑导墙用的砌块及该砌块构筑导墙的施工方法,属于建筑用导墙施工领域,具体的,砌块呈矩形条状结构,包括上接驳面和下粘接面及左、右侧面,所述的上接驳面为曲面结构,砌块沿其轴向设置有竖直的通孔。其设计的接驳结构中,采用预制的砌块,省去在现场施工的繁琐步骤,现场只需要进行粘接固定就完成导墙的工序,省时省力,并且采用预制导墙,避免了现场施工中导墙未干透造成的导墙与墙体开裂,影响美观及防潮防水性的问题。Chinese patent 201710115981.8 discloses a block for constructing a guide wall and a construction method for the block to construct a guide wall, which belongs to the field of construction of a guide wall for buildings. Specifically, the block has a rectangular strip structure, including an upper connecting surface and The lower bonding surface and the left and right sides, the upper connecting surface has a curved surface structure, and the block is provided with vertical through holes along its axial direction. In the design of the connecting structure, prefabricated blocks are used, which eliminates the tedious steps of on-site construction. The site only needs to be bonded and fixed to complete the guide wall process, which saves time and effort, and the use of prefabricated guide walls avoids the on-site During the construction, the guide wall and the wall are cracked due to the guide wall not being completely dry, which affects the beauty and moisture-proof and waterproof problems.
发明内容Summary of the invention
本发明涉及破除既有站厅层的连通结构,从而实现与新增暗挖通道连通接驳,破除既有站厅层墙体结构,从而实现与新增暗挖通道(隧道)连通接驳一体化。The present invention relates to the removal of the connection structure of the existing station hall layer, so as to realize the connection and connection with the newly-added underground excavation channel, and the removal of the existing station hall layer wall structure, thereby realizing the connection and connection with the newly-added underground excavation channel (tunnel). change.
为了实现上述目的,本发明采用的技术方案为新增暗挖通道与既有站厅层连通接驳施工结构,具体如下,在新增暗挖厅2接驳口处设置加强环梁21和新增面层107,与既有站厅层1进行连通接驳。连通接驳处的结构包括植筋103、新旧结构交界面104、新旧结构钢筋搭接105和锚筋106。在顶板加强环梁101、底板加强环梁102中水平向一侧采用梅花形布置锚筋,另一侧作为植筋植入既有站厅层1破除口。在新增面层107中新增加强结构箍筋110,最外侧两排与既有站厅层1中的主筋进行焊接,形成新旧结构钢筋搭接105;中间两排加强结构箍筋110延长植入既有站厅层1中,作为老结构的植筋103。暗挖通道主筋108延 长埋入顶板加强环梁101和底板加强环梁102中。在加强环梁21和新增面层107中布置加强结构主筋109、加强结构箍筋110;新旧结构交界面104的旧结构一侧涂抹界面剂,增强与新增结构的粘接性能。浇筑加强环梁21的混凝土和新增面层107的混凝土,完成接驳口结构施工。In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is to add a new underground excavation channel to the existing station hall floor to connect and connect the construction structure. The details are as follows: a reinforced ring beam 21 and a new The added surface layer 107 is connected to the existing station hall layer 1. The structure of the connecting joint includes the planting bar 103, the interface between the new and the old structure 104, the rebar lap 105 between the old and the new structure, and the anchor bar 106. In the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102, the anchor bars are arranged in a plum blossom shape on one side horizontally, and the other side is used as a plant bar to be implanted in the existing station hall floor 1 breaking opening. A reinforced structural stirrup 110 is added to the newly added surface layer 107, and the two outermost rows are welded to the main reinforcement in the existing station hall floor 1 to form a new and old structural reinforcement overlap 105; the middle two rows of reinforced structural stirrups 110 extend the planting Enter the existing station hall floor 1, as the planting bar 103 of the old structure. The main reinforcement 108 of the buried channel is extended and buried in the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102. In the reinforced ring beam 21 and the newly added surface layer 107, the main reinforcement structure 109 and the reinforcement structure stirrup 110 are arranged; the old structure side of the new and old structure interface 104 is smeared with an interface agent to enhance the bonding performance with the new structure. The concrete for strengthening the ring beam 21 and the concrete for the newly added surface layer 107 are poured to complete the connection structure construction.
进一步地,新旧结构钢筋搭接105的焊接长度不小于120mm。Further, the welding length of the overlap 105 of the new and old structural steel bars is not less than 120 mm.
进一步地,界面剂采用聚合物改性水泥浆沙、环氧砂浆或1:1水泥砂浆等材料。Further, the interface agent adopts materials such as polymer-modified cement mortar sand, epoxy mortar or 1:1 cement mortar.
与现有技术相比较,本发明涉及的驳接结构连接形式采用上下对称的形式,结构连接稳定、美观;同时对新旧驳接结构进行有效连接,保证了新旧结构之间的一致。新增的加强环梁和新增面层对驳接口进行了有效稳固连接,保证后续实用过程中不出现凸起、渗水,新增结构与既有结构之间结构有效利用,增加了发明的一体化结构形式。Compared with the prior art, the connection form of the docking structure involved in the present invention adopts a symmetrical form up and down, and the structural connection is stable and beautiful; at the same time, the new and old docking structures are effectively connected to ensure the consistency between the new and the old structures. The newly-added reinforced ring beam and the newly-added surface layer effectively and firmly connect the barge interface to ensure that there will be no bumps or water seepage in the subsequent practical process. The structure between the newly-added structure and the existing structure is effectively used, and the integrated structure of the invention is added. form.
附图说明Description of the drawings
图1是本发明的实施流程图。Figure 1 is a flow chart of the implementation of the present invention.
图2是新建换乘厅与既有隧道连通的接驳侧墙结构示意图,(a)、(b)、(c)分别为接驳实施流程示意图。Figure 2 is a schematic diagram of the connection side wall structure connecting the newly built transfer hall and the existing tunnel. (a), (b), (c) are the schematic diagrams of the connection implementation process respectively.
图3是破注浆流程图示意图。Figure 3 is a schematic diagram of a flow chart of broken grouting.
图4是接驳结构示意图I。Figure 4 is a schematic diagram I of the connection structure.
图5是接驳结构示意图II。Figure 5 is a schematic diagram of the connection structure II.
具体实施方式Detailed ways
下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明的实施例,而不能理解为对本发明的限制。The embodiments of the present invention are described in detail below. Examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals indicate the same or similar elements or elements with the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary, and are intended to explain the embodiments of the present invention, but should not be construed as limiting the present invention.
以下结合附图和实施例对本发明进行详细说明。The present invention will be described in detail below with reference to the drawings and embodiments.
以某市地铁十字交叉换乘线路的结构为例,在新增暗挖通道拱顶接口处设置顶板加强环梁101,尺寸450mm*800mm,上部两排主筋8C22,腰筋2C22,箍筋A12@150,新老结构之间150mm*300mm梅花型布置850mm长C20锚筋106,锚入既有站厅层1中400mm。Take the structure of a subway cross-transfer line in a city as an example, the roof reinforcement ring beam 101 is set at the vault interface of the newly-added concealed tunnel, the size is 450mm*800mm, the upper two rows of main reinforcement 8C22, waist reinforcement 2C22, stirrup A12@ 150. Between the new and old structures, 150mm*300mm plum blossoms are arranged with 850mm long C20 anchor bars 106, which are anchored into the existing station hall floor 1 by 400mm.
顶部新增面层107尺寸500mm*150mm,浇筑C40自密实混凝土,底部配置加强结构主筋1095C22,新增加强结构箍筋110C12@100/200,加强结构箍筋110作为植筋埋入既有站厅层1,锚固长度不小于250mm;The top surface layer 107 is 500mm*150mm in size, C40 self-compacting concrete is poured, the bottom is equipped with reinforced structural main reinforcement 1095C22, and the reinforced structural stirrup 110C12@100/200 is newly added, and the reinforced structural stirrup 110 is used as a planting bar to be embedded in the existing station hall Layer 1, the anchorage length is not less than 250mm;
在新增暗挖通道仰拱接口处设置底板加强环梁102,尺寸450*1100mm,主筋、腰筋C22,箍筋A12@150;与既有站厅层1之间水平向布置长度850mmC20锚筋106,150mm*300mm梅花布置,锚入既有站厅层1长度不少于400mm。Set up the bottom plate reinforcement ring beam 102 at the invert interface of the newly-added concealed tunnel, the size is 450*1100mm, the main reinforcement, waist reinforcement C22, stirrup A12@150; horizontal arrangement length 850mm C20 anchor reinforcement between the existing station hall floor 1 106, 150mm*300mm plum blossom layout, anchored into the existing station hall floor 1 length not less than 400mm.
底部新增面层107尺寸500*150mm,浇筑C40自密实混凝土,顶部配置C20主筋,增设加强结构箍筋110C12@100/200穿过新旧结构交界面104,埋入既有站厅层1。The size of the new surface layer 107 at the bottom is 500*150mm, C40 self-compacting concrete is poured, the top is equipped with C20 main reinforcement, and the reinforcement structure stirrup 110C12@100/200 is added to pass through the interface 104 of the new and old structure, and is buried in the existing station hall layer 1.
如图1-2所示,一种新增暗挖通道与既有站厅层连通接驳施工方法,在不影响既有站厅层1正常运营的条件下采用暗挖法施做新增暗挖通道2,连通接驳步骤如下:As shown in Figure 1-2, a construction method for connecting new underground tunnels with the existing station hall layer is used to construct the new underground tunnel without affecting the normal operation of the existing station hall floor 1. Dig channel 2, and the connection steps are as follows:
第一步:采用深孔注浆、贯通新增暗挖通道。从地面对暗挖通道2的注浆范围3进行深孔注浆,对连通接驳口进行预加固,保护车站驳接口周边结构不受破坏,提高接驳施工作业安全性。新增暗挖通道2的土方采用CRD法开挖,土方开挖过程中的各导洞间保持步距为1.5倍的洞径,土方开挖时要留够核心土作为稳固支撑,保持新增暗挖通道内的土体平衡。依次贯通新增暗挖通道2的1号洞室4、2号洞室5、3号洞室6、4号洞室7,然后在新增暗挖通道的内部喷射暗挖通道初支14。The first step: use deep hole grouting to penetrate the newly-added undercut channel. Deep-hole grouting is carried out on the grouting range 3 of the undercut channel 2 from the ground, and the connecting connection is pre-reinforced to protect the surrounding structure of the station connection from damage and improve the safety of connection construction. The earthwork of the newly-increased tunnel 2 is excavated by the CRD method. During the earthwork excavation, a step distance of 1.5 times the diameter of each pilot hole shall be maintained. When the earthwork is excavated, enough core soil shall be left as a stable support to keep the newly added The soil in the tunnel is balanced. Go through No. 1 cavern 4, No. 2 cavern 5, No. 3 cavern 6, and No. 4 cavern 7 of the newly-added underground tunnel 2 in sequence, and then spray the first branch 14 of the underground tunnel inside the newly-added underground tunnel.
第二步:破除新增暗挖通道的临时中隔壁、临时仰拱,并架设满堂红。采用分段分部破除新增暗挖通道的1号洞室4、2号洞室5、3号洞室6和4号洞室7之间的临时中隔壁9和临时仰拱8,并同步设置满堂红脚手架10,以保障新增暗挖通道2内部结构稳定。Step 2: Destroy the temporary middle wall and temporary invert of the newly-added digging tunnel, and erect a full house. The temporary intermediate wall 9 and the temporary invert 8 between the new tunnels of No. 1 cavern 4, No. 2 cavern 5, No. 3 cavern 6 and No. 4 cavern 7 are removed by segmentation, and synchronized Set up full red scaffolding 10 to ensure the stability of the internal structure of the newly-added concealed tunnel 2.
第三步:施做新增暗挖通道的防水、二衬、钢筋接头。在满堂红脚手架10的支撑作用下,施做暗挖通道防水11、暗挖通道二衬12,暗挖通道防水11预留防水接头,暗挖通道二衬12预留钢筋接驳器13,用作接驳口的防水和二衬新老结构连接。The third step: implement waterproofing, secondary lining and steel joints for newly-added digging channels. Under the support of the full house red scaffolding 10, the underground tunnel waterproofing 11, the second tunnel lining 12, the tunnel waterproofing 11 reserved waterproof joints, the buried tunnel second lining 12 reserved steel connector 13 for The waterproof connection of the connection port is connected with the new and old structure of the two linings.
第四步:拆除既有站厅层1侧处1.2m范围的脚手架,为接驳的施工作业提供空间即开洞范围17。破除开洞范围17对应新增暗挖通道的侧墙以及暗挖通道 初支14和既有站厅层初支15,并在暗挖通道初支14和既有站厅层初支15的表面施做防水搭接。采用双面丁基胶粘带对暗挖通道防水11和既有站厅防水16进行粘接。Step 4: Dismantle the 1.2m range of the scaffolding on the 1 side of the existing station hall floor to provide space for the construction of the connection, that is, the opening range17. The opening range 17 is broken to correspond to the side walls of the newly-added undercut passage and the surface of the first branch 14 of the undercut passage and the first branch 15 of the existing station hall floor, and the surface of the first branch 14 of the undercut passage and the first branch 15 of the existing station hall floor. Do waterproof lap joints. Adopt double-sided butyl adhesive tape to bond the waterproof 11 of the digging channel and the waterproof 16 of the existing station hall.
第五步:分条分块破除开洞范围17的混凝土结构,贯通既有站厅层1和新增暗挖通道2。分条分块破除的切割方法采用绳锯切割法,开洞范围17的支护与切割破除同时进行,完成接驳口的初步破除。Step 5: Destroy the concrete structure of the opening area 17 section by section, and penetrate through the existing station hall floor 1 and the newly-added underground excavation channel 2. The cutting method of stripping and block breaking adopts the wire saw cutting method. The support of the opening area 17 and the cutting and breaking are carried out at the same time, and the preliminary breaking of the connection port is completed.
第六步:对第五步施作完成的接驳口顶部和底部进行凿毛植筋20以及浇筑加强环梁21。Step 6: Chiseling the top and bottom of the connection port completed in Step 5, planting ribs 20 and pouring the reinforced ring beam 21.
图3是破注浆流程图示意图。深孔注浆工艺如下::Figure 3 is a schematic diagram of a flow chart of broken grouting. The deep hole grouting process is as follows:
深孔注浆采用分组进行,每组注浆长度12m,上一组与下一组之间的搭接2m,有效加固长度10m。注浆孔布置间距0.8*0.8m,梅花形布置,采用地表注浆方式。The deep hole grouting is carried out in groups, each group has a grouting length of 12m, the overlap between the previous group and the next group is 2m, and the effective reinforcement length is 10m. Grouting holes are arranged at 0.8*0.8m spacing, plum blossom-shaped arrangement, and surface grouting method is adopted.
采用钻机引流钻孔,后退式注浆,以压注WSS无收缩双液浆为主;均匀布孔,纵向钻孔,易控制,浆液扩散分布比较均匀,在卵石层加固效果好。Use drilling rig drainage to drill, retreat grouting, mainly injecting WSS non-shrinking double-liquid grout; evenly arranged holes, longitudinal drilling, easy to control, relatively uniform grout spreading and distribution, and good reinforcement effect on the pebble layer.
(1)浆材分类(1) Pulp classification
采用AC浆液(水泥+水玻璃+填加剂),当加固土体区域有明流水时则通过调整填加剂缩短浆液凝固时间达到注浆区域内沥干和挤出水份。AC浆液适用于粉质黏土层、中粗砂层、粉细砂层等地质条件。AC slurry (cement + water glass + filler) is used. When there is clear water in the reinforced soil area, the setting time of the slurry is shortened by adjusting the filler to drain and squeeze out the water in the grouting area. AC grout is suitable for geological conditions such as silty clay layer, medium coarse sand layer, silty fine sand layer, etc.
(2)施工工序流程(2) Construction process flow
1)布孔:利用既有站厅层初支做为注浆止浆墙,采用深孔注浆加固区域内梅花形布孔,由测量人员在通道内放出的注浆区域轮廓线,按设计要求进行注浆加固,编号后由专人做孔位预检记录。1) Hole distribution: use the initial support of the existing station hall floor as the grouting stop wall, and adopt deep hole grouting to reinforce the plum blossom-shaped hole in the area. The contour line of the grouting area released by the surveyor in the channel is designed according to the design Grouting reinforcement is required, and the hole position pre-inspection record will be done by a dedicated person after numbering.
2)成孔:孔径42mm,每次纵向水平深度为2m(以现场技术交底为准),当孔位遇隔栅主筋时应在3~5cm范围内调整,使注浆孔位避开钢筋。2) Hole formation: The hole diameter is 42mm, and the vertical horizontal depth is 2m each time (subject to the on-site technical report). When the hole position meets the main reinforcement of the grille, it should be adjusted within the range of 3~5cm, so that the grouting hole position avoids the reinforcement.
3)配浆:浆液必须严格按配比调配,搅拌必须有足够的时间以保证浆液浓度均匀。3) Slurry preparation: The slurry must be prepared strictly according to the ratio, and there must be enough time for stirring to ensure uniform slurry concentration.
4)注浆:喷入管设置完毕后,将端点进行关闭而进行横喷射切换。将喷入材料施加压力,实现水平渗透效果。止水加固范围内注浆压力P值控制在0.8~1.0Mpa,通过控制分段凝固时间来控制纵向不同距离的浆液喷射位置而开始新一 轮注浆。回抽钻杆(注浆管)长度控制在0.3~0.5m范围内。4) Grouting: After the injection pipe is set, close the end point and switch the horizontal injection. Apply pressure to the sprayed material to achieve a horizontal penetration effect. The grouting pressure P in the water stop reinforcement range is controlled at 0.8-1.0Mpa, and a new round of grouting is started by controlling the segmented solidification time to control the spray positions of the slurry at different distances in the longitudinal direction. The length of the drawn-back drill pipe (grouting pipe) is controlled within the range of 0.3-0.5m.
5)结束:当所有布置的注浆孔位注浆完毕且探孔确定无明水后,则注浆结束。5) End: When all the arranged grouting hole positions are grouted and there is no clear water in the exploration hole, the grouting ends.
主要注浆参数如下:The main grouting parameters are as follows:
注浆深度:纵深0~2m;钻孔直径:42mm;浆液扩散半径:0.6m~0.8m;Grouting depth: depth 0~2m; drilling diameter: 42mm; grout diffusion radius: 0.6m~0.8m;
浆液凝结时间:8s~20s;注浆压力0.3~0.5Mpa。Slurry setting time: 8s~20s; grouting pressure 0.3~0.5Mpa.
注浆加固注意事项如下:The precautions for grouting reinforcement are as follows:
1)如果在导洞开挖过程中遇明流水需深孔注浆加固时,注浆前开挖掌子面需双层挂网喷锚形成挡浆层并形成强度后方可布孔钻孔注浆;挡浆层喷锚面厚度不小于300mm。1) If deep-hole grouting is required for deep-hole grouting reinforcement during the excavation of the pilot tunnel, the face of the excavation before grouting needs to be double-layered with netting and spray anchors to form a grouting layer and form strength before drilling holes can be drilled and grouted. ; The thickness of the spray-anchored surface of the grout retaining layer is not less than 300mm.
2)浆液配比凝固时间应根据现场实际条件灵活调整,如现场卵石层可灌性较差时,可适当降低浆液凝固时间,增加可灌性;当遇明水流时,可根据水流大小,浆液凝固时间以6~10s为宜。2) The solidification time of the grout ratio should be flexibly adjusted according to the actual conditions of the site. For example, when the pebble layer on site is poor in pourability, the grout setting time can be appropriately reduced to increase the pourability; when there is a bright water flow, the grout can be adjusted according to the size of the water flow. The appropriate setting time is 6~10s.
3)地下实际岩土层标高和水位条件会因汛期及枯水期而与勘探报告有出入,施工时要依据实际水文地质条件灵活调整灌浆材料,加大注浆量,保证注浆加固效果。3) The actual underground rock and soil layer elevation and water level conditions may differ from the exploration report due to flood seasons and dry seasons. During construction, grouting materials must be flexibly adjusted according to actual hydrogeological conditions to increase the amount of grouting to ensure the effect of grouting reinforcement.
4)注浆加固过程中,定时排查地下管线的地面检查井;及时监测监控点的标高变化,注浆地面抬升控制在允许的安全范围内。严禁跑浆冒浆发生;对既有管线管沟在注浆范围及接近注浆范围的区域,应适当调整钻杆角度,保证钻杆离既有管线管沟有足够的安全距离,采取减小注浆压力、浆液配比延长凝固时间和减小注浆量等综合措施减小注浆对既有管线管沟的扰动。4) During the grouting reinforcement process, regularly check the ground inspection wells of the underground pipelines; monitor the elevation changes of the monitoring points in time, and control the grouting ground uplift within the allowable safety range. It is strictly forbidden to run mortar and mortar; for the existing pipeline trenches in the grouting range and the area close to the grouting range, the angle of the drill pipe should be adjusted appropriately to ensure that the drill pipe has a sufficient safety distance from the existing pipeline trench, and reduce it Comprehensive measures such as grouting pressure and slurry ratio to extend the solidification time and reduce the amount of grouting reduce the disturbance of grouting to existing pipeline trenches.
图4是接驳结构示意图I。Figure 4 is a schematic diagram I of the connection structure.
图5是接驳结构示意图II。Figure 5 is a schematic diagram of the connection structure II.
在新增暗挖厅2接驳口处设置加强环梁21和新增面层107,与既有站厅层1进行连通接驳。连通接驳处的结构包括植筋103、新旧结构交界面104、新旧结构钢筋搭接105和锚筋106。在顶板加强环梁101、底板加强环梁102中水平向一侧采用梅花形布置锚筋,另一侧作为植筋植入既有站厅层1破除口。在新增面层107中新增加强结构箍筋110,最外侧两排与既有站厅层1中的主筋进行焊接,形成新旧结构钢筋搭接105;中间两排加强结构箍筋110延长植入既有站厅层1 中,作为老结构的植筋103。暗挖通道主筋108延长埋入顶板加强环梁101和底板加强环梁102中。在加强环梁21和新增面层107中布置加强结构主筋109、加强结构箍筋110;新旧结构交界面104的旧结构一侧涂抹界面剂,增强与新增结构的粘接性能。浇筑加强环梁21的混凝土和新增面层107的混凝土,完成接驳口结构施工。A reinforced ring beam 21 and a new surface layer 107 are installed at the connection port of the newly-added underground excavation hall 2 to connect to the existing station hall floor 1. The structure of the connecting joint includes the planting bar 103, the interface between the new and the old structure 104, the rebar lap 105 between the old and the new structure, and the anchor bar 106. In the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102, the anchor bars are arranged in a plum blossom shape on one side horizontally, and the other side is used as a plant bar to be implanted in the existing station hall floor 1 breaking opening. A reinforced structural stirrup 110 is added to the newly added surface layer 107, and the two outermost rows are welded to the main reinforcement in the existing station hall floor 1 to form a new and old structural reinforcement overlap 105; the middle two rows of reinforced structural stirrups 110 extend the planting Enter the existing station hall floor 1, as the planting bar 103 of the old structure. The main ribs 108 of the tunnel excavated are extended and embedded in the top plate reinforced ring beam 101 and the bottom plate reinforced ring beam 102. In the reinforced ring beam 21 and the newly added surface layer 107, the main reinforcement structure 109 and the reinforcement structure stirrup 110 are arranged; the old structure side of the new and old structure interface 104 is smeared with an interface agent to enhance the bonding performance with the new structure. The concrete for strengthening the ring beam 21 and the concrete for the newly added surface layer 107 are poured to complete the connection structure construction.
新旧结构钢筋搭接105的焊接长度不小于120mm。The welding length of the new and old structural steel bar overlap 105 is not less than 120mm.
界面剂采用聚合物改性水泥浆沙、环氧砂浆或1:1水泥砂浆等材料。The interface agent adopts materials such as polymer modified cement mortar sand, epoxy mortar or 1:1 cement mortar.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only the preferred embodiments of the present invention and are not intended to limit the present invention. Any modification, equivalent replacement and improvement made within the spirit and principle of the present invention shall be included in the protection of the present invention. Within range.

Claims (3)

  1. 新增暗挖通道与既有站厅层连通接驳施工结构,其特征在于:在新增暗挖厅(2)接驳口处设置加强环梁(21)和新增面层(107),与既有站厅层(1)进行连通接驳;连通接驳处的结构包括植筋(103)、新旧结构交界面(104)、新旧结构钢筋搭接(105)和锚筋(106);在顶板加强环梁(101)、底板加强环梁(102)中水平向一侧采用梅花形布置锚筋,另一侧作为植筋植入既有站厅层(1)破除口;在新增面层(107)中新增加强结构箍筋(110),最外侧两排加强结构箍筋(110)与既有站厅层(1)中的主筋进行焊接,形成新旧结构钢筋搭接(105);中间两排加强结构箍筋(110)延长植入既有站厅层(1)中,作为旧结构的植筋(103);暗挖通道主筋(108)延长埋入顶板加强环梁(101)和底板加强环梁(102)中;在加强环梁(21)和新增面层(107)中布置加强结构主筋(109)、加强结构箍筋(110);新旧结构交界面(104)的旧结构一侧涂抹界面剂,增强与新增结构的粘接性能;浇筑加强环梁(21)的混凝土和新增面层(107)的混凝土。The newly-added underground excavation channel is connected with the existing station hall floor to connect the construction structure, which is characterized in that: a reinforced ring beam (21) and a new surface layer (107) are set at the connection port of the newly-added underground excavation hall (2), Connect with the existing station hall floor (1); the structure of the connection point includes the planting bar (103), the interface between the new and the old structure (104), the old and new structure rebar overlap (105) and the anchor bar (106); In the top plate reinforced ring beam (101) and bottom plate reinforced ring beam (102), the anchor bars are arranged in a plum blossom shape on one side horizontally, and the other side is used as a plant bar to be implanted into the existing station hall floor (1) breaking opening; The reinforced structural stirrups (110) are added to the surface layer (107), and the two outermost rows of reinforced structural stirrups (110) are welded to the main reinforcements in the existing station hall floor (1) to form a new and old structural reinforcement lap (105). ); the middle two rows of reinforced structural stirrups (110) are extended and implanted in the existing station hall floor (1) as the planting reinforcement (103) of the old structure; the main reinforcement (108) of the buried channel is extended and embedded into the roof reinforcement ring beam ( 101) and the floor reinforced ring beam (102); the reinforced ring beam (21) and the newly added surface layer (107) are arranged in the reinforced structure main bar (109) and the reinforced structure stirrup (110); the new and old structure interface (104) ) Is coated with an interface agent on one side of the old structure to enhance the bonding performance with the new structure; the concrete for strengthening the ring beam (21) and the concrete for the new surface layer (107) are poured.
  2. 根据权利要求1所述的新增暗挖通道与既有站厅层连通接驳施工结构,其特征在于:新旧结构钢筋搭接(105)的焊接长度不小于120mm。According to claim 1, the newly-built underground excavated channel and the existing station hall floor are connected to the construction structure, characterized in that the welding length of the new and old structure steel bar overlap (105) is not less than 120mm.
  3. 根据权利要求1所述的新增暗挖通道与既有站厅层连通接驳施工结构,其特征在于:界面剂采用聚合物改性水泥浆沙、环氧砂浆或1:1水泥砂浆材料。The construction structure for connecting the newly-added digging channel and the existing station hall layer according to claim 1, characterized in that the interface agent adopts polymer-modified cement mortar sand, epoxy mortar or 1:1 cement mortar material.
PCT/CN2021/086346 2020-05-07 2021-04-12 Construction structure for communication and connection between newly added mined channel and existing station hall layer WO2021223573A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010378233.0 2020-05-07
CN202010378233.0A CN111594181B (en) 2020-05-07 2020-05-07 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer

Publications (1)

Publication Number Publication Date
WO2021223573A1 true WO2021223573A1 (en) 2021-11-11

Family

ID=72183890

Family Applications (2)

Application Number Title Priority Date Filing Date
PCT/CN2021/086346 WO2021223573A1 (en) 2020-05-07 2021-04-12 Construction structure for communication and connection between newly added mined channel and existing station hall layer
PCT/CN2021/086344 WO2021223571A1 (en) 2020-05-07 2021-04-12 One-way circulation rapid transfer structure for intersecting subway lines

Family Applications After (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/086344 WO2021223571A1 (en) 2020-05-07 2021-04-12 One-way circulation rapid transfer structure for intersecting subway lines

Country Status (2)

Country Link
CN (1) CN111594181B (en)
WO (2) WO2021223573A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114108617A (en) * 2021-11-12 2022-03-01 山西机械化建设集团有限公司 Method for removing groove and planting bar for foundation pit supporting pile by using down-the-hole drill
CN114263215A (en) * 2021-12-21 2022-04-01 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-adding joint of subway station by combining open excavation and underground excavation
CN114320378A (en) * 2021-12-16 2022-04-12 中铁十局集团第三建设有限公司 Broken belt supporting tunnel top-lifting rapid construction device and method
CN115404871A (en) * 2022-10-11 2022-11-29 中建八局第一建设有限公司 Construction method for connecting existing underground structure in close proximity of deep foundation pit
CN117948150A (en) * 2024-03-27 2024-04-30 北京城建道桥建设集团有限公司 Subway station air duct combined excavation construction method capable of saving materials and working hours

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111706351B (en) * 2020-05-07 2022-03-11 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN111594181B (en) * 2020-05-07 2021-12-10 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN112483094B (en) * 2020-12-09 2023-03-31 中国铁路设计集团有限公司 Construction method for reinforcing U-shaped structure of old tunnel
CN112855213B (en) * 2021-01-26 2022-05-27 中建八局轨道交通建设有限公司 Construction method of primary support structure of transfer passage at existing station
CN114624039B (en) * 2022-01-21 2023-10-20 石家庄铁道大学 Model test method and device for simulating opening fracture of underground engineering structure
CN115027507B (en) * 2022-06-07 2024-05-28 中铁二院工程集团有限责任公司 Railway line structure additionally arranged in boundary of existing railway land and train running method
CN115233733B (en) * 2022-09-01 2023-06-06 广州珠江建设发展有限公司 Underground structure connection method for crossing thick underground connecting wall in narrow space
CN116838382B (en) * 2023-09-01 2023-12-05 中国铁路设计集团有限公司 Connection type and construction method of underground excavation subway station main body and auxiliary structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109854253A (en) * 2019-03-20 2019-06-07 中国铁路设计集团有限公司 A kind of existing Metro folds the enlargement method of island transfer station
JP2019157502A (en) * 2018-03-13 2019-09-19 ▲濱▼新 正博 Roadbed construction method
CN210013697U (en) * 2019-05-21 2020-02-04 中铁十一局集团城市轨道工程有限公司 Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
CN111594181A (en) * 2020-05-07 2020-08-28 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN111706351A (en) * 2020-05-07 2020-09-25 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN213063578U (en) * 2020-05-07 2021-04-27 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101709573A (en) * 2009-12-15 2010-05-19 田耕 Ladder-shaped platform of island type station of parallel elevated road
CN206841421U (en) * 2016-11-17 2018-01-05 长安大学 The urban track traffic transfer stop of separate type subway concourse
CN106640121B (en) * 2017-01-11 2023-06-27 中铁第六勘察设计院集团有限公司 Supporting structure for six-pilot tunnel large-section subway station to pass through existing line
KR101772362B1 (en) * 2017-03-14 2017-09-05 홍순례 A Great deep metro station structure
CN208039306U (en) * 2018-02-22 2018-11-02 中铁第一勘察设计院集团有限公司 A kind of construction unicom system at new subway line station and building up station
CN209290386U (en) * 2018-09-28 2019-08-23 广州地铁设计研究院股份有限公司 A kind of transfer structure of subway station
CN111688724B (en) * 2020-05-07 2021-11-05 中铁十八局集团有限公司 Subway crossline one-way circulation quick transfer structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019157502A (en) * 2018-03-13 2019-09-19 ▲濱▼新 正博 Roadbed construction method
CN109854253A (en) * 2019-03-20 2019-06-07 中国铁路设计集团有限公司 A kind of existing Metro folds the enlargement method of island transfer station
CN210013697U (en) * 2019-05-21 2020-02-04 中铁十一局集团城市轨道工程有限公司 Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
CN111594181A (en) * 2020-05-07 2020-08-28 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN111706351A (en) * 2020-05-07 2020-09-25 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN213063578U (en) * 2020-05-07 2021-04-27 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114108617A (en) * 2021-11-12 2022-03-01 山西机械化建设集团有限公司 Method for removing groove and planting bar for foundation pit supporting pile by using down-the-hole drill
CN114320378A (en) * 2021-12-16 2022-04-12 中铁十局集团第三建设有限公司 Broken belt supporting tunnel top-lifting rapid construction device and method
CN114263215A (en) * 2021-12-21 2022-04-01 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-adding joint of subway station by combining open excavation and underground excavation
CN114263215B (en) * 2021-12-21 2023-05-02 中铁十四局集团隧道工程有限公司 Construction method for building waterproof structure at storey-added connection part of subway station by combined excavation and excavation
CN115404871A (en) * 2022-10-11 2022-11-29 中建八局第一建设有限公司 Construction method for connecting existing underground structure in close proximity of deep foundation pit
CN115404871B (en) * 2022-10-11 2023-07-25 中建八局第一建设有限公司 Construction method for connecting existing underground structure of deep foundation pit
CN117948150A (en) * 2024-03-27 2024-04-30 北京城建道桥建设集团有限公司 Subway station air duct combined excavation construction method capable of saving materials and working hours

Also Published As

Publication number Publication date
CN111594181A (en) 2020-08-28
CN111594181B (en) 2021-12-10
WO2021223571A1 (en) 2021-11-11

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN210013697U (en) Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN205742213U (en) Foundation pit supporting construction
CN110067563A (en) Close on the station entrance-exit main structure construction method of urban architecture and road
CN104389610B (en) A kind of ultrashort step construction method of traversing operation freeway tunnel
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN101280568A (en) Station pit construction method forming protection for neighboring operated subway interval tunnel
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
WO2022100346A1 (en) Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method
CN213063578U (en) Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN111455977A (en) Underground continuous wall construction method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN103437779A (en) Construction method for renovating tunnel lining water seeping damage

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21800378

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21800378

Country of ref document: EP

Kind code of ref document: A1