CN109914259A - The limited steel truss of hoisting platform encircles hanging method - Google Patents

The limited steel truss of hoisting platform encircles hanging method Download PDF

Info

Publication number
CN109914259A
CN109914259A CN201910281895.3A CN201910281895A CN109914259A CN 109914259 A CN109914259 A CN 109914259A CN 201910281895 A CN201910281895 A CN 201910281895A CN 109914259 A CN109914259 A CN 109914259A
Authority
CN
China
Prior art keywords
steel truss
arch
shoulder pole
pole girder
cable crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910281895.3A
Other languages
Chinese (zh)
Inventor
于长彬
张敏
贺常松
田波
孙立强
田鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201910281895.3A priority Critical patent/CN109914259A/en
Publication of CN109914259A publication Critical patent/CN109914259A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the steel truss that a kind of hoisting platform is limited to encircle hanging method, coordinate to complete with installation from steel truss arch, main chord, shoulder pole girder, suspender belt, platform sling, hoisting platform, cable crane suspension hook, main rope, cable crane suspension hook and main rope spacing are wider than assembled good steel truss arch span degree, shoulder pole girder is hung on cable crane suspension hook, suspender belt is arranged according to steel truss arch bar part spacing on shoulder pole girder, steel truss arch main chord is suspended on shoulder pole girder suspender belt;Hoisting platform is located at steel truss and encircles at 1/4 projection, is encircleed by already installed steel truss cover completely;Cable crane main hook is outer in steel truss arch when lifting, plays shoulder pole girder from arch is lower and enters lifting place, steel truss arch main chord is then hung up properly on shoulder pole girder;Cable crane suspension hook is installed, leaves ground to main chord rod piece, already installed steel truss arch range is walked out in shoulder pole girder translation, and cable crane is hooked up to institute position to be mounted.The present invention solves the problems, such as that span centre setting lifting point is difficult, reduces subaqueous work steel platform security risk, save the cost.

Description

The limited steel truss of hoisting platform encircles hanging method
Technical field
The present invention relates to large-span steel braced arch lift field, especially a kind of hoisting platform can not extend to closure mouth or across In the limited steel truss of hoisting platform encircle hanging method.
Background technique
Chord member is lifted in Arch Bridge Construction at present and mainly uses the whole segment lifting of cable crane or single rib, single member erection.Cable Rope is hung in hoisting process, and as hung segment extends to span centre, lifting place is generally located on span centre.Institute's cross a river stream has navigation The steel truss arched bridge beam column part transport of condition uses waterway transportation, and lifting point is just arranged on river surface ship.And it is logical for not having The river of boat condition is general using steel platform of constructing in water when hoisting platform is arranged in span centre.For playing the heavier bridge of hanging object Beam is very high to the force request of steel platform.Mountainous region arch bridge, narrow terrain, institute does not have navigation condition again across rivers and water flow is rapid Anxious, it is difficult greatly that lifting point is arranged in span centre, and span centre setting hoisting platform cost is too high, exists simultaneously very big security risk.
Summary of the invention
The technical problem to be solved in the present invention is to provide the steel truss that a kind of hoisting platform is limited to encircle hanging method, solves Existing difficulty when subaqueous work steel platform, eliminates security risk existing for subaqueous work, while also largely saving Cost.
In order to solve the above technical problems, the technical solution adopted by the present invention is that:
A kind of steel truss arch hanging method that hoisting platform is limited, passes through steel truss arch, main chord, shoulder pole girder, suspender belt, platform sling, lifting Platform, cable crane suspension hook, main rope are coordinated installation cooperation and are completed, and cable crane suspension hook and main rope spacing are wider than assembled good steel truss arch span Degree, hangs shoulder pole girder on cable crane suspension hook, arranges suspender belt according to steel truss arch bar part spacing on shoulder pole girder, steel truss encircles main chord suspention In on shoulder pole girder suspender belt;Hoisting platform is located at steel truss and encircles at 1/4 projection, is encircleed by already installed steel truss cover completely;Lifting When cable crane main hook it is outer in steel truss arch, play shoulder pole girder from arch is lower and enter lifting place, steel truss arch is then hung up properly on shoulder pole girder Main chord;Cable crane suspension hook is installed, leaves ground to main chord rod piece, already installed steel truss arch model is walked out in shoulder pole girder translation It encloses, cable crane is hooked up to institute position to be mounted.
The present invention by adopting the above technical scheme, compared with prior art, the beneficial effect is that:
The steel truss arched bridge beam of hoisting platform cannot be set for span centre, how the emphasis that reasonable hoisting platform is lifting is set. This method is wider than the shoulder pole girder, cable crane and main rope of steel truss arch span degree by design, so that cable crane suspension hook can outside steel truss arch To slide laterally to steel truss arch projection 1/4;Encircleed using cable crane with already installed steel truss is worn under shoulder pole girder, is solved The difficulty of hoisting platform cannot be arranged in span centre, reduce subaqueous work and restrict to lifting bring, reduce steel platform in water and apply Work bring security risk, while also saving construction cost.This method is played flat by the cable crane main hook outside steel truss is encircleed Spreader beam is pierced into from arch is lower into lifting place, hangs main chord, leaves ground to main chord rod piece, shoulder pole girder translation is walked out Mounted steel truss encircles range, and cable crane is hooked up to designated position, solves the problems, such as that span centre does not set hoisting platform.
Further optimal technical scheme is as follows:
When each two suspension hooks of cable crane upstream and downstream are on the outside of steel truss arch, moved freely above hoisting platform.
Two shoulder pole girders are hung on cable band four suspension hooks of upstream and downstream by suspender belt or platform sling direction across bridge, shoulder pole girder setting Removable saddle, suspender belt are hung on saddle to hang main chord.
Shoulder pole girder encircles from already installed steel truss arch abutment subordinate, and arching upward from the lower steel truss entered at 1/4 of arch, it is flat to hang Platform.
Arch ring main chord spacing is adjusted by removable saddle, and the elevation angle is adjusted by shoulder pole girder height.
Detailed description of the invention
Fig. 1 is the schematic elevation view of the embodiment of the present invention;
Fig. 2 is the side view of Fig. 1;
In figure: 1, steel truss is encircleed;2, cable crane main rope;3, cable crane main hook;4, shoulder pole girder;5, annular suspender belt;6, platform sling or suspender belt; 7, saddle is moved;8, main chord;9, hoisting platform.
Specific embodiment
With reference to the accompanying drawings and embodiments, the present invention is further illustrated.
Referring to Fig. 1, Fig. 2, a kind of steel truss arch hanging method that hoisting platform is limited, mainly by cable crane main rope 2, cable crane The cooperations such as main hook 3, shoulder pole girder 4, suspender belt 5, suspender belt or platform sling 6, main chord 8, removable saddle 7 are completed.Present invention lifting Front hook process is related to two groups of cable crane main ropes of upstream and downstream, 2, four cable crane main hooks 3, and cable crane main hook 3 is by suspender belt or hangs Plate 6 suspends shoulder pole girder 4 in midair;Removable saddle 7 is set on shoulder pole girder 6, and 5 sets of annular suspender belt are hung down on removable saddle 7 to hang Main chord 8;Make shoulder pole girder 4 be lower than the steel truss being installed arch 1 by 3 off the hook of cable crane main hook, then passes through cable crane main hook 3 9 top of hoisting platform is moved to reach, 3 off the hook of cable crane main hook to hoisting platform 9 simultaneously hangs up properly main chord 8.
Hoisting process is as follows:
It is hooked up by cable crane main hook 3, shoulder pole girder 4 drives after main chord 8 leaves place, and cable crane main hook 3 is to being installed Steel truss encircles the movement of 1 front end, and after shoulder pole girder 4 moves out the steel truss being installed arch 1, cable crane is hooked up, so that main chord 8 reaches Designated position adjusts the contraposition of 8 elevation angle of main chord by adjusting 4 height of shoulder pole girder.
The above is only specific embodiments of the present invention, but protection of the invention is without being limited thereto, the skill of any the art Art personnel the thinkable variation or substitution being equal with the technical program technical characteristic, all cover in protection scope of the present invention Within.

Claims (5)

1. a kind of limited steel truss of hoisting platform encircles hanging method, by steel truss arch, main chord, shoulder pole girder, suspender belt, platform sling, rise It hangs platform, cable crane suspension hook, main rope and coordinates installation cooperation completion, it is characterised in that: cable crane suspension hook and main rope spacing are wider than spelling The steel truss arch span degree installed, hangs shoulder pole girder on cable crane suspension hook, arranges suspender belt, steel according to steel truss arch bar part spacing on shoulder pole girder Braced arch main chord is suspended on shoulder pole girder suspender belt;Hoisting platform is located at steel truss and encircles at 1/4 projection, completely by already installed steel Braced arch covering;Cable crane main hook is outer in steel truss arch when lifting, plays shoulder pole girder from arch is lower and enters lifting place, then in shoulder pole girder On hang up properly steel truss arch main chord;Cable crane suspension hook is installed, leaves ground to main chord rod piece, shoulder pole girder translation, which is walked out, has installed Good steel truss encircles range, and cable crane is hooked up to institute position to be mounted.
2. the limited steel truss of hoisting platform according to claim 1 encircles hanging method, it is characterised in that: cable crane upstream and downstream When each two suspension hooks are on the outside of steel truss arch, moved freely above hoisting platform.
3. the limited steel truss of hoisting platform according to claim 1 encircles hanging method, it is characterised in that: two shoulder pole girders are logical It crosses suspender belt or platform sling direction across bridge is hung on cable band four suspension hooks of upstream and downstream, removable saddle is arranged in shoulder pole girder, and suspender belt is hung over To hang main chord on saddle.
4. the limited steel truss of hoisting platform according to claim 1 encircles hanging method, it is characterised in that: shoulder pole girder is from Mounted steel truss arch abutment subordinate arch encircles hoisting platform from the lower steel truss entered at 1/4 of arch.
5. the limited steel truss of hoisting platform according to claim 1 encircles hanging method, it is characterised in that: between arch ring main chord Away from being adjusted by removable saddle, the elevation angle is just adjusted by shoulder pole girder.
CN201910281895.3A 2019-04-09 2019-04-09 The limited steel truss of hoisting platform encircles hanging method Withdrawn CN109914259A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910281895.3A CN109914259A (en) 2019-04-09 2019-04-09 The limited steel truss of hoisting platform encircles hanging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910281895.3A CN109914259A (en) 2019-04-09 2019-04-09 The limited steel truss of hoisting platform encircles hanging method

Publications (1)

Publication Number Publication Date
CN109914259A true CN109914259A (en) 2019-06-21

Family

ID=66969172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910281895.3A Withdrawn CN109914259A (en) 2019-04-09 2019-04-09 The limited steel truss of hoisting platform encircles hanging method

Country Status (1)

Country Link
CN (1) CN109914259A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668391A (en) * 2021-08-03 2021-11-19 中交路桥建设有限公司 Double-width arch rib synchronous installation method of half-through steel box basket arch bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09209312A (en) * 1996-02-05 1997-08-12 Mitsubishi Heavy Ind Ltd Bridge erecting device
CN101445208A (en) * 2008-12-29 2009-06-03 中铁二局股份有限公司 Hanger for lifting construction of bridge cable
CN101525865A (en) * 2008-12-30 2009-09-09 中铁二局股份有限公司 Extroversive posture adjusting method for steel box arch rib section
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
CN104790300A (en) * 2015-05-19 2015-07-22 中铁大桥局集团有限公司 Flexible pier-side girder erecting platform and construction method thereof
CN207003260U (en) * 2017-07-01 2018-02-13 中铁十八局集团第二工程有限公司 Adjustable shoulder pole girder for cable crane lifting

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09209312A (en) * 1996-02-05 1997-08-12 Mitsubishi Heavy Ind Ltd Bridge erecting device
CN101445208A (en) * 2008-12-29 2009-06-03 中铁二局股份有限公司 Hanger for lifting construction of bridge cable
CN101525865A (en) * 2008-12-30 2009-09-09 中铁二局股份有限公司 Extroversive posture adjusting method for steel box arch rib section
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
CN104790300A (en) * 2015-05-19 2015-07-22 中铁大桥局集团有限公司 Flexible pier-side girder erecting platform and construction method thereof
CN207003260U (en) * 2017-07-01 2018-02-13 中铁十八局集团第二工程有限公司 Adjustable shoulder pole girder for cable crane lifting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668391A (en) * 2021-08-03 2021-11-19 中交路桥建设有限公司 Double-width arch rib synchronous installation method of half-through steel box basket arch bridge

Similar Documents

Publication Publication Date Title
CN101117795A (en) Mounting method for steel case basket arch single-frame segment
CN108374347A (en) A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method
CN207919363U (en) A kind of Filled Steel Tubular Arch Bridge low level assembly lifting system
CN102912730A (en) Hoisting construction method for single-rib closure rope of large-span reinforced concrete arch bridge
CN107119567A (en) Suspension bridge steel box-girder deck erection gantry and spreading hoist cable swing shifting construction method
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN209685155U (en) A kind of combined type lifting system
CN107089584A (en) A kind of jacket lifts technology for binding
CN109914259A (en) The limited steel truss of hoisting platform encircles hanging method
CN110499702A (en) A kind of cable saddle positioning reinforcing device of Cable-stayed Bridge Pylon
CN109518590A (en) A kind of suspension cross a river pontoon bridge
CN205367454U (en) Large -size formwork hoisting machine constructs
CN205576744U (en) Special jack -up hoist is erect to cable -stay bridge cordless district large -tonnage steel case girder segment section
CN202031029U (en) Cross-arch rib gantry crane
CN103708360A (en) Swing arm tower crane, standard knot introduction system thereof and standard knot introduction method
CN104878139B (en) Blast furnace Y-type three way type installation method of formula down-comer integral hoisting
CN205474862U (en) Wet seam template operation platform of portable case roof beam
CN208071235U (en) A kind of bearing and lifting system of steel truss frame integral hoisting
CN207435902U (en) Pier shaft hanging flower basket mounting platform
CN209635724U (en) Platform is lifted for the more rod piece closures in four purlins
CN205576743U (en) A mechanism that is used for suspension bridge catwalk main rope to put cable
CN110080083A (en) The method for installing basket type steel truss arch main chord
CN205932925U (en) Electric precipitation removes anode plate hoist device
CN208748525U (en) Swing shifting specific purpose tool
CN209323393U (en) A kind of drag-line bridge king-tower side plane repairing nacelle construction structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20190621

WW01 Invention patent application withdrawn after publication