CN205474862U - Wet seam template operation platform of portable case roof beam - Google Patents
Wet seam template operation platform of portable case roof beam Download PDFInfo
- Publication number
- CN205474862U CN205474862U CN201620224055.5U CN201620224055U CN205474862U CN 205474862 U CN205474862 U CN 205474862U CN 201620224055 U CN201620224055 U CN 201620224055U CN 205474862 U CN205474862 U CN 205474862U
- Authority
- CN
- China
- Prior art keywords
- walking
- suspension
- platform
- operation platform
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a wet seam template operation platform of portable case roof beam belongs to superstructure construction equipment, including walking and braced system, suspension and construction platform, walking and braced system include frame construction and the shaft mechanism of fixing with frame construction, the suspension is ability direction of rotation's gallows structure, and suspension one end is rotated with walking and braced system and is connected, and the other end and construction platform are fixed, construction platform includes the frame and spreads the panel layer on the frame. The utility model provides a defect that reliable operation platform is not had down in the tradition construction is overcome to difficulties such as the wet seam form setting of adverse circumstances nowel roof beam is influenced greatly by the wind speed, effective activity duration is short, the form setting degree of difficulty is big, the destabilizing factor is more, improves construction efficiency, reduces safe risk.
Description
Technical field
This utility model belongs to bridge superstructure constructing device, is particularly suited for the construction of the wet seam of box beam under adverse circumstances.
Background technology
1) box beam wet seam construction under tradition adverse circumstances:
Prefabricated case beam installs, and needs the wet seam of cast in situs, the erector of the tradition wet joint template of box beam between box beam and box beam
Skill, uses suspension method to be sling by wet joint template, is mounted between two Pin prefabricated case beams.Marine environment and rivers environment
Under, without wet joint template mounting platform, generally individually wet joint template is positioned over above canoe, sails to canoe need to install
Immediately below at the wet joint template of box beam, template is sling to install and has been fixed hoisting die construction by use hoist engine.
2) limitation of traditional construction technique
Under the adverse circumstances such as Conventional marine and rivers, wet joint template is installed, and uses the platform that canoe has enough to meet the need as masterplate, it is impossible to carry
For stable, safe and reliable operation construction environment;Rising under ebb and Lidar Equation in ocean, effective time every day is relatively
Few;Marine environment median year wind-force more than 4 grades, template is relatively big, in hoisting process by windage when ship platform lifts by crane
Easily shake, be not easy to install and fix, be easily generated security incident;When constructing in Gao Dun district, template sling height is relatively big,
Installation operation easier increases, and workmen is difficult to obtain safely guarantee, and it is serious that construction is affected situation by adverse circumstances.Wet seam
Model sheetinstallat device should possess the features such as simple structure, easy construction, efficiency height, reusable edible from construction angle, and
Economically should be reasonable, safety should be relatively strong, in traditional construction technique, wet joint template can be made to install without a kind of device
The most more economically, safe, in hgher efficiency.The construction of traditional handicraft wet seam has bigger office in adverse circumstances
Sex-limited.
Utility model content
The purpose of this utility model is: solves the wet joint template of box beam under adverse circumstances and installs by air speed influence greatly, effectively makees
The difficulties such as the industry time is short, model sheetinstallat difficulty is big, unstable factor is more, overcome under traditional construction without reliable operation platform
Defect, improves construction efficiency, reduces security risk.
The purpose of this utility model is realized by following technical proposals:
A kind of portable box beam wet joint template operating platform, including walking and support system, suspension and operation platform;
Walking and support system include frame structure and the axle mechanism fixing with frame structure;Suspension is can direction of rotation
Hanger structure, suspension one end is rotationally connected with walking and support system, and the other end and operation platform are fixed;Operation platform
Including framework and the panel layer that is laid on framework.
As selection, walking and support system, suspension and operation platform are monolithically fabricated a nearly I-shaped structure.
As selection, the frame structure of walking and support system includes framework, and the multiple tracks horizontal stroke arranged along the long cross direction of framework
To, skewed horizontal load, frame structure combines two groups of axle mechanism as walking and support system.
As selection, suspension includes the parallel pressure bearing fixing with walking and support system, and holding as rotating shaft
Heavy Derrick, load-bearing suspension rod end face is provided with and turns to hole and alignment pin thereof, location for what suspension turned to location, suspension with
Some braces it are also associated with between operation platform.
As selection, the panel layer of operation platform is bar-mat reinforcement, and operation platform surrounding is additionally provided with the connection rope for connecting box beam.
Aforementioned this utility model main formula case and each further selection scheme thereof can be this with independent assortment to form multiple schemes
Utility model can use and claimed scheme: such as this utility model, each selection can select combination in any with other, this
Skilled person can understand there is multiple combination according to prior art and common knowledge after understanding the present invention program, is this reality
By novel claimed technical scheme, do not do exhaustive at this.
Workflow of the present utility model: during construction, walking and support system be positioned at the position, median strip on box beam top, its
Axle mechanism is across this median strip, and wheel is walked along this median strip on box beam top;By suspension rotating band
Dynamic operation platform rotate to direction across bridge direction (long limit is prolonged bridge direction across bridge direction and is placed) and with connect rope connect fixed platform with
Box beam, wet joint template also can be placed directly on operation platform, and owing to operation platform lateral separation is longer, operator can
Directly on this operation platform, carry out a plurality of wet joint template handling, vertical location etc..With across interior walking time, can directly release
Connect rope fixing, use hoist engine or other power-equipments to pull walking and support system to move ahead, to next construction location.
When crossing spanning walk, it is fixing that releasing connects rope, by the most vertical for operation platform rotation bridge to direction (long limit is prolonged bridge longitudinal direction and placed),
Run to again adjacent across, rotate operation platform and to direction across bridge direction and fix, carry out next process construction.
The beneficial effects of the utility model: use patent device carry out wet joint template installation, can be prevented effectively from strong wind,
The conventional construction method drawbacks such as billow, Gao Dun, activity duration are short, can preferably adapt to wet joint template in adverse circumstances and install
Institute's yarn part, relatively traditional construction safety are more preferable, and work efficiency is higher, and does not increase more input (such as ship etc.), construction party
Just, can be recycled.
Accompanying drawing explanation
Fig. 1 is the operating platform of this utility model embodiment view when constructing;
Fig. 2 is the A-A view of Fig. 1;
Fig. 3 be the operating platform of this utility model embodiment walked across time view;
Fig. 4 is the B-B view of Fig. 3;
Fig. 5 is the C-C view of Fig. 3;
In figure, 1 is walking and support system, and 11 is frame structure, and 12 is axle mechanism, and 2 is suspension, and 21 is flat
Row pressure bearing, 22 is load-bearing suspension rod, and 23 for turning to hole, location and alignment pin thereof, and 24 is brace, and 25 for connecting support,
3 is operation platform, and 31 is platform framework, and 4 is box beam, and 5 for connecting rope, and 6 is walking steel wire rope, and 7 is median strip.
Detailed description of the invention
Below in conjunction with specific embodiments and the drawings, this utility model is further described.
Referring to figs. 1 to shown in 5, a kind of portable box beam wet joint template operating platform, including walking and support system 1, outstanding
Extension system 2 and operation platform 3;Walking and support system 1 include frame structure 11 and the wheel shaft fixed with frame structure 11
Mechanism 12;Suspension 2 is the hanger structure of energy direction of rotation, and suspension 2 one end rotates with walking and support system 1
Connecting, the other end and operation platform 3 are fixed;Operation platform 3 includes platform framework 31 and is laid on platform framework 31
Panel layer.
As selection, as shown in this embodiment, walking and support system 1, suspension 2 and operation platform 3 are monolithically fabricated one
Nearly I-shaped structure.The frame structure 11 of walking and support system 1 includes framework, and arranges along the long cross direction of framework
Multiple tracks laterally, skewed horizontal load, frame structure 11 combines two groups of axle mechanism 12 as walking and support system.As showing
Example, uses work 22a shaped steel composition framework, long cross direction respectively set multiple tracks laterally, skewed horizontal load, whole operating platform is conducted oneself with dignity
And construction loads is delivered to axle mechanism 12, and (wheel uses general-utility car to take turns, and two-wheeled Inter cross bar bearing uses Two bors d's oeuveres work 36b
Shaped steel weld), frame structure 11 combine two groups of axle mechanism 12 as walking and support system, fix for operating platform,
Move and turn to.
Suspension 2 includes and walking and the fixing parallel pressure bearing 21 of support system 1, and the load-bearing as rotating shaft is hung
Bar 22, load-bearing suspension rod 22 end face is provided with and turns to turning to of location to position hole and alignment pin 23 thereof for suspension, hangs system
It is also associated with some braces 24 between system 2 and operation platform 3.As example, suspension 2 is rotatable direction suspension bracket
Structure, uses parallel pressure bearing 21 fix steel pipe and be allowed to have spinfunction;Use seamless steel pipe as load-bearing suspension rod 22,
Seamless steel pipe end face sets and turns to hole, location, turns to for platform, prevents from swinging at interpolation alignment pin after turning to;In suspension 2
With use many round steel as the brace 24 of operation platform above operation platform 3 junction, increase whole operation platform stable
Property.Suspension 2 is connected fixing by connecting support 25 with operation platform 3, brace 24 be connected to connection support 25 and
Between operation platform 3.
The panel layer of operation platform 3 is bar-mat reinforcement, and operation platform 3 surrounding is additionally provided with the connection rope 5 for connecting box beam 4.Execute
The long limit of work platform 3 is the box beam wet seam distance that two horizontal spacings are maximum, minor face be across time bridge left and right double width between can
Safety passing distance, can regulate platform size according to on-site actual situations, uses work 10 to be welded into the groined type of the big spacing of the length of side
Framework, then it is encrypted to the length of side closely spaced groined type framework with Φ 50mm steel pipe, platform framework 31 upper berth bar-mat reinforcement is as panel
Layer, operation platform 3 surrounding uses 4 steel wire ropes to be fixed in box beam 4 as connecting rope 5, and this connection rope 5 is positioned at construction
3 four jiaos of platform, is connected with bridge floor embedded bar during construction.It addition, further respectively have steel on 3 liang of length of side limits of operation platform
Cord (walking steel wire rope 6), when walking and support system 1 are walked, is connected with walking and support system 1, it is ensured that OK
Stability when walking.
During construction, walking and support system 1 are positioned at the position, median strip 7 on box beam top, and its axle mechanism 12 is in this
Central median 7, wheel is walked along this median strip 7 on box beam top;Operation platform 3 is rotarily driven by suspension 2
Rotate to direction across bridge direction (long limit is prolonged bridge direction across bridge direction and placed) and with connecting the rope 5 fixing operation platform 3 of connection and case
Beam 4, wet joint template also can be placed directly on operation platform 3, owing to operation platform 3 lateral separation is longer, operator
Directly can carry out a plurality of wet joint template handling, vertical location etc. on this operation platform 3.With across interior walking time, can be direct
Release connection rope 5 to fix, use hoist engine or other power-equipments to pull walking and support system 1 to move ahead, execute to the next one
Station is put.When crossing spanning walk, release and connect rope 5 and fix, operation platform 3 is rotated to vertical bridge (bridge is prolonged on long limit to direction
Longitudinal direction is placed), then run to adjacent across, rotate operation platform 3 to direction across bridge direction and also fix, carry out next process and execute
Work.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, all in this practicality
Any amendment, equivalent and the improvement etc. made within novel spirit and principle, should be included in guarantor of the present utility model
Within the scope of protecting.
Claims (5)
1. a portable box beam wet joint template operating platform, it is characterised in that: include walking and support system, suspension and execute
Work platform;Walking and support system include frame structure and the axle mechanism fixing with frame structure;Suspension is to rotate
The hanger structure in direction, suspension one end is rotationally connected with walking and support system, and the other end and operation platform are fixed;Construction
Platform includes framework and the panel layer being laid on framework.
2. box beam wet joint template operating platform as claimed in claim 1 portable, it is characterised in that: walking and support system, outstanding
Extension system and operation platform are monolithically fabricated a nearly I-shaped structure.
3. portable box beam wet joint template operating platform as claimed in claim 1, it is characterised in that: walking and the frame of support system
Shelf structure includes framework, and the multiple tracks arranged along the long cross direction of framework laterally, skewed horizontal load, frame structure combines two groups of wheel shafts
Mechanism is as walking and support system.
4. portable box beam wet joint template operating platform as claimed in claim 1, it is characterised in that: suspension includes and walking
And the parallel pressure bearing that support system is fixing, and the load-bearing suspension rod as rotating shaft, load-bearing suspension rod end face is provided with for hanging system
System turns to turning to of location to position hole and alignment pin thereof, is also associated with some braces between suspension and operation platform.
5. portable box beam wet joint template operating platform as claimed in claim 1, it is characterised in that: the panel layer of operation platform is
Bar-mat reinforcement, operation platform surrounding is additionally provided with the connection rope for connecting box beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620224055.5U CN205474862U (en) | 2016-03-21 | 2016-03-21 | Wet seam template operation platform of portable case roof beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620224055.5U CN205474862U (en) | 2016-03-21 | 2016-03-21 | Wet seam template operation platform of portable case roof beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205474862U true CN205474862U (en) | 2016-08-17 |
Family
ID=56652040
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620224055.5U Expired - Fee Related CN205474862U (en) | 2016-03-21 | 2016-03-21 | Wet seam template operation platform of portable case roof beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205474862U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108004919A (en) * | 2017-12-05 | 2018-05-08 | 中铁六局集团有限公司 | A kind of wet seam construction crane device of steel box girder bridge panel and its construction method |
CN108589552A (en) * | 2018-06-11 | 2018-09-28 | 交通运输部科学研究院 | A kind of collapsible suspension apparatus |
CN113931071A (en) * | 2021-10-27 | 2022-01-14 | 中交第二航务工程局有限公司 | Prefabricated box girder wet joint adhesion type construction platform and construction method thereof |
-
2016
- 2016-03-21 CN CN201620224055.5U patent/CN205474862U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108004919A (en) * | 2017-12-05 | 2018-05-08 | 中铁六局集团有限公司 | A kind of wet seam construction crane device of steel box girder bridge panel and its construction method |
CN108589552A (en) * | 2018-06-11 | 2018-09-28 | 交通运输部科学研究院 | A kind of collapsible suspension apparatus |
CN108589552B (en) * | 2018-06-11 | 2023-07-21 | 交通运输部科学研究院 | Folding suspension device |
CN113931071A (en) * | 2021-10-27 | 2022-01-14 | 中交第二航务工程局有限公司 | Prefabricated box girder wet joint adhesion type construction platform and construction method thereof |
CN113931071B (en) * | 2021-10-27 | 2024-03-29 | 中交第二航务工程局有限公司 | Prefabricated box girder wet joint attached construction platform and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100476076C (en) | Mobile integral construction platform, construction method thereof and special sling for the same | |
CN101892736B (en) | High altitude moving hanging basket construction method | |
CN106703416A (en) | Lifting method of steel structure roof truss pulling bar in narrow space | |
CN105484162B (en) | Suspension bridge construction stiff girder secondary on the bank swings moving device and method | |
CN205474862U (en) | Wet seam template operation platform of portable case roof beam | |
CN203296361U (en) | Long-span steel structure cross assembling hoisting platform | |
CN108547225A (en) | A kind of assembly moving type security construction of prevention work job platform and construction method and application | |
CN206143719U (en) | Concrete depends on ship components are installed supporting platform | |
CN205934735U (en) | A operation platform for stretch -draw of cantilever bent cap | |
CN209081290U (en) | Bailey truss pylon and distributing earth anchor CABLEWAY ERECTION SYSTEM that can be traversing | |
CN201778479U (en) | Detachable high-altitude working platform | |
CN107816209A (en) | The large-scale Roof Truss construction technology of installation is lifted across outer both sides | |
CN205369229U (en) | But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid | |
CN100560918C (en) | Large steel girder member bar turning device and member bar turning method thereof | |
CN106522097A (en) | Self-adaptive cable cranes for extra large space-cross cable face suspension bridge girder erection | |
CN207209826U (en) | A kind of derrick crane | |
CN208071235U (en) | A kind of bearing and lifting system of steel truss frame integral hoisting | |
CN103848333B (en) | Door frame Lift-on/Lift-off System and using method thereof | |
CN207296361U (en) | A kind of regularization assembled overhanging protection canopy | |
CN203499259U (en) | Tool type cantilevered unloading platform | |
CN206346500U (en) | Compact simplified arm extending type straddle truck | |
CN101967903A (en) | Basic guide rail for helicopter assembly transmission line iron tower leg section | |
CN205955164U (en) | Portable steel truss operation platform | |
CN201647844U (en) | Beam lifting station without abutments | |
CN209816682U (en) | Bridge steel box girder aerial working operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160817 |
|
CF01 | Termination of patent right due to non-payment of annual fee |