CN109837102A - The quick method for dismounting of capacity coke oven ontology refractory masonry - Google Patents
The quick method for dismounting of capacity coke oven ontology refractory masonry Download PDFInfo
- Publication number
- CN109837102A CN109837102A CN201910226203.5A CN201910226203A CN109837102A CN 109837102 A CN109837102 A CN 109837102A CN 201910226203 A CN201910226203 A CN 201910226203A CN 109837102 A CN109837102 A CN 109837102A
- Authority
- CN
- China
- Prior art keywords
- coke oven
- coke
- oven
- refractory
- ontology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Coke Industry (AREA)
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
Abstract
A kind of quick method for dismounting of capacity coke oven ontology refractory masonry, characterized by the following steps: a, preparation before the dismounting of coke oven ontology refractory masonry, b, 2 mini-excavators are hung to oven top of coke oven with truck crane, c, high-front shovel is run on coke oven chute position by the slope to be started to oven top of coke oven, carbonization chamber carries out dismounting operation, d, utilize 2 large excavators, it carries out removing chute and regenerative chamber from coke oven machine side both ends to coke side, e, coke oven horizontal flue bottom uses based on manual demolition, f, coke oven furnace bed board is repaired in cleaning, lower jet pipe, clean out the brick slag sundries fallen into seam, the masonry work again of coking furnace shaft refractory brick is carried out after the completion of cleaning.The advantages of present invention is reasonable with removal step design, linking is proper, links closely step by step, is in good order, and projects are safe and reliable, quickly remove refractory masonry, reduces labor intensity, saving construction period and reduction engineering cost.
Description
Technical field
The present invention relates to a kind of refractory masonry method for dismounting, specifically, being that a kind of capacity coke oven ontology refractory masonry is fast
Fast method for dismounting.
Background technique
China has the capacity coke oven that more than 100 seats have been in the middle and later periods in furnace life at present.Over time, coke oven ontology
Masonry will increasingly aging, refractory brick badly broken;Furnace retaining ironware is broken, is poorly sealed with ontology masonry, leads to coke oven ontology
Large area, which is smoldered, in process of production burns with anger, and seriously affects production, environmental requirement is not achieved.And the original coal tower of coke oven, platform,
Coke oven base, resistance wall and furnace end stand are all intact, can continue to use.For save the cost, many coke-oven plants are using reservation institute
There is civil engineering position, remove coke oven ontology masonry, furnace retaining ironware and associated process equipment, then re-starts coke oven ontology masonry block
Furnace retaining ironware and associated process equipment are built and installed, coke oven is allowed to continue to put into production.Therefore it is badly in need of a kind of capacity coke oven sheet in the industry
The quick method for dismounting of body refractory masonry.
Summary of the invention
The purpose of the present invention is that proposing that one kind is safe and reliable removes refractory masonry, effective protection coke oven base platform, supports
The quick method for dismounting of capacity coke oven ontology refractory masonry of equipment under anti-wall, furnace.
To achieve the above object, the technical solution of the invention is as follows:
A kind of quick method for dismounting of capacity coke oven ontology refractory masonry, it is characterised in that the following steps are included:
A, the preparation before coke oven ontology refractory masonry is removed:
(1) coke oven ontology refractory masonry properly protects to coking furnace shaft surrounding before removing, the gap between coke oven ontology and platform
Canopy-protected is carried out using several protection boards;To waste gas valve hole on flue using the wooden springboard canopy-protected, refractory brick is prevented
Fall to coke oven basement;It is blocked at the railing of coke side platform outer using waste and old pallet, prevents the refractory brick tumbled from falling into
On coke-quenching vehicle track;Burlap is filled up out of basement downward jet pipe, prevents brick slag in demolishing process from falling into blocking;
(2) coke oven door is won, coke oven door frame, furnace top equipment pipeline, pusher side and coke side platform, furnace retaining ironware are removed;
B, since oven top structure for coke oven load-bearing is limited, 2 mini-excavators are hung to oven top of coke oven with truck crane, using small-sized digging
Pick machine is removed from oven top of coke oven end stand and platform pusher side between middle coke oven, and oven top of coke oven and carbonization chamber are removed, and
Make a part filling for the useless refractory brick for first removing generation to coke furnace carbonization chamber, another part gives up refractory brick to coke oven machine side direction
It has bad luck, so that useless refractory brick is formed slope in coke oven machine side, after removing 10 hole of coke oven machine side refractory masonry so as to high-front shovel
Climb to operation on coke oven chute position;
C, high-front shovel is run on coke oven chute position by the slope starts to remove oven coke furnace roof, carbonization chamber
Operation, all useless refractory brick are had bad luck to coke oven machine side direction, the waste material dug out through coke oven machine side with being transported to coke oven machine side track
On face, transported to concentrate;
D, it using 2 large excavators, carries out removing coke oven chute and regenerative chamber, waste material from coke oven machine side both ends to coke oven coke side
It is discharged from coke oven machine side, excavating depth reserves subject to coke oven horizontal flue bottom;
E, coke oven horizontal flue bottom uses based on manual demolition, and form of construction work is removed supplemented by machinery, avoids machine in demolishing process
Tool and other tools destroy the screed-coat and both ends resistance wall of coke oven base platform;
F, coke oven furnace bed board, lower jet pipe are repaired in cleaning, the coke oven furnace bed board that partially there is crackle and expansion joint edge are destroyed, clearly
Then the brick slag sundries fallen into the clean seam of reason is reinforced grouting material filling with cement base and is restored, by the burlap in Coke oven lower spray pipe
It after taking down, is dredged with high pressure water, tar, sundries is cleaned out, the weight of coking furnace shaft refractory brick is carried out after the completion of cleaning
It is new to build work.
The quick method for dismounting of capacity coke oven ontology refractory masonry of the invention can also using technical measures below come into
One step is realized.
Method above-mentioned, wherein the protection board is the protection board previously removed.
Method above-mentioned, wherein the wood springboard is with a thickness of >=50mm.
Method above-mentioned, wherein the lifting capacity of the truck crane is >=200t.
After adopting the above technical scheme, the quick method for dismounting of capacity coke oven ontology refractory masonry of the invention is with following excellent
Point:
1, the design of coke oven ontology refractory masonry removal step is rationally, linking is proper, links closely step by step, is in good order;
2, projects are safe and reliable, quickly remove refractory masonry, reduce labor intensity, and save the construction period;
3, equipment under effective protection coke oven base platform, resistance wall, furnace lays the foundation to rebuild, and reduces engineering cost.
Detailed description of the invention
Fig. 1 is the capacity coke oven furnace roof floor map of the embodiment of the present invention;
Fig. 2 is that the capacity coke oven ontology of the embodiment of the present invention removes elevational schematic view.
In figure: 1 resistance wall, 2 end stand, 3 long-armed digging machines, 4 furnace roofs, 5 platforms, 6 carbonization chambers, 7 chutes, 8 regenerative chambers, 9 pusher sides
Ground, 10 Miniature digging machines, 11 useless bricks take off fortune, 12 pusher sides to pusher side ground.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
The quick method for dismounting construction process of capacity coke oven ontology refractory masonry of the invention: coking furnace shaft cool down → remove coke oven shield
Furnace ironware → coke oven coke side, pusher side platform and furnace body opening protection → mini-excavator hang oven top of coke oven end stand, platform → coke
Furnace furnace roof, carbonization chamber pusher side refractory masonry remove 10 holes or so → high-front shovel and remove oven top of coke oven, carbonization chamber refractory masonry
→ coke oven chute, regenerative chamber refractory masonry dismounting → coke oven horizontal flue bottom dismounting → cleaning.
The quick method for dismounting of capacity coke oven ontology refractory masonry of the invention, comprising the following steps:
A, the preparation before coke oven ontology refractory masonry is removed:
(1) coke oven ontology refractory masonry properly protects to coking furnace shaft surrounding before removing, and the gap between furnace body and platform utilizes
The protection board removed carries out canopy-protected, to waste gas valve hole on flue using the thick wooden springboard canopy-protected of 50mm, prevents
Refractory brick falls to basement;It is blocked at the railing of coke side platform outer using waste and old pallet, prevents the refractory brick tumbled from falling
Enter on coke-quenching vehicle track;Burlap is filled up into Coke oven lower spray pipe from basement, prevents brick slag in demolishing process from falling into blocking, it is difficult to
Cleaning;
(2) coke oven door is won, firedoor frame, furnace top equipment pipeline, pusher side, coke side platform, furnace retaining ironware are removed;Fig. 1 is this hair
The capacity coke oven furnace roof floor map of bright embodiment.
B, oven top structure for coke oven load-bearing is limited, and 2 mini-excavators are hung to oven top of coke oven with 200t lifting capacity truck crane,
It is removed using Miniature digging machine from oven top of coke oven end stand and platform pusher side to centre, in end stand 2,5 pusher side of platform to coke oven furnace
Top 4 and carbonization chamber 6 are removed, and the refractory brick a part for first removing generation is first filled to coke furnace carbonization chamber, and another part is useless
Brick is had bad luck toward coke oven machine side direction, and the brick that gives up after removing 10 hole of coke oven machine side forms slope in coke oven machine side, so as to long-armed excavation
Machine 3 is climbed to operation on coke oven chute position.
C, after coke oven machine side forms slope, high-front shovel passes through the useless brick that mini-excavator 10 is excavated at one jiao of pusher side
Slope starts to carry out oven top of coke oven, carbonization chamber dismounting operation to running on coke oven chute position, and all useless bricks are toward coke oven machine
Side direction is had bad luck, and the waste material dug out is transported on pusher side track ground through coke oven machine side, and concentration is transported.
D, using 2 large-scale digging machines, coke oven chute and regenerative chamber remove from coke oven both ends pusher side to coke side, waste material from
Coke oven machine side discharge, excavating depth reserve subject to coke oven horizontal flue bottom.
E, coke oven horizontal flue bottom uses based on manual demolition, form of construction work supplemented by machinery, avoids machinery in demolishing process
And other tools destroy the screed-coat and both ends resistance wall of coke oven base platform;Fig. 2 is the capacity coke oven of the embodiment of the present invention
Ontology removes elevational schematic view.
F, coke oven furnace bed board, the cleaning of lower jet pipe are repaired: the coke oven furnace bed board that partially there is crackle and expansion joint edge are beaten
Fall, clean out the brick slag impurity fallen into seam, then reinforces grouting material filling with cement base and restore, it will be in Coke oven lower spray pipe
It after cloth takes down, is dredged with high pressure water, tar, sundries is cleaned out, coking furnace shaft refractory brick is carried out after the completion of cleaning
Masonry work again.
The present invention has substantive distinguishing features and significant technological progress, and capacity coke oven ontology refractory masonry of the invention is quick
The design of method for dismounting removal step is rationally, linking is proper, it is in good order to link closely step by step, and projects are safe and reliable, quickly remove
Refractory masonry reduces labor intensity, and shortens the construction time, saves operating expenses, remarkable in economical benefits.
The 2 coke oven projects of the quick method for dismounting of capacity coke oven ontology refractory masonry of the invention in Baogang coking Factory
Middle utilization, construction safety is reliable, and the construction time is short, and effect is obvious, receives the affirmative of relevant departments and unit.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (4)
1. a kind of quick method for dismounting of capacity coke oven ontology refractory masonry, it is characterised in that the following steps are included:
A, the preparation before coke oven ontology refractory masonry is removed:
(1) coke oven ontology refractory masonry properly protects to coking furnace shaft surrounding before removing, the gap between coke oven ontology and platform
Canopy-protected is carried out using several protection boards;To waste gas valve hole on flue using the wooden springboard canopy-protected, refractory brick is prevented
Fall to basement;It is blocked at the railing of coke side platform outer using waste and old pallet, prevents the refractory brick tumbled from falling into quenching
On track road;Burlap is filled up out of basement downward jet pipe, prevents brick slag in demolishing process from falling into blocking;
(2) coke oven door is won, firedoor frame, furnace top equipment pipeline, pusher side and coke side platform, furnace retaining ironware are removed;
B, since oven top structure for coke oven load-bearing is limited, 2 mini-excavators are hung to oven top of coke oven with truck crane, using small-sized digging
Pick machine from oven top of coke oven end stand and platform pusher side to coke oven among removed, oven top of coke oven and carbonization chamber are removed, and
Make a part filling for the useless refractory brick for first removing generation to coke furnace carbonization chamber, another part gives up refractory brick to coke oven machine side direction
It has bad luck, after removing 10 hole of coke oven machine side refractory masonry, so that useless refractory brick is formed slope in coke oven machine side, so as to high-front shovel
Climb to operation on coke oven chute position;
C, high-front shovel is run on coke oven chute position by the slope starts to remove oven top of coke oven, carbonization chamber
Operation, all useless refractory brick are had bad luck to coke oven machine side direction, and the waste material dug out is transported on pusher side track ground through coke oven machine side,
It is transported to concentrate;
D, using 2 large excavators, coke oven chute and regenerative chamber remove from coke oven machine side both ends to coke side, waste material is from coke
The discharge of furnace pusher side, excavating depth reserve subject to coke oven horizontal flue bottom;
E, coke oven horizontal flue bottom uses based on manual demolition, and form of construction work is removed supplemented by machinery, avoids machine in demolishing process
Tool and other tools destroy the screed-coat and both ends resistance wall of coke oven base platform;
F, coke oven furnace bed board, lower jet pipe are repaired in cleaning, the coke oven furnace bed board that partially there is crackle and expansion joint edge are destroyed, clearly
Then the brick slag sundries fallen into the clean seam of reason is reinforced grouting material filling with cement base and is restored, by the burlap in Coke oven lower spray pipe
It after taking down, is dredged with high pressure water, tar, sundries is cleaned out, the weight of coking furnace shaft refractory brick is carried out after the completion of cleaning
It is new to build work.
2. the quick method for dismounting of capacity coke oven ontology refractory masonry as described in claim 1, which is characterized in that the protection board
For the protection board previously removed.
3. the quick method for dismounting of capacity coke oven ontology refractory masonry as described in claim 1, which is characterized in that the wood springboard
With a thickness of >=50mm.
4. the quick method for dismounting of capacity coke oven ontology refractory masonry as described in claim 1, which is characterized in that the truck crane
Lifting capacity be >=200t.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910226203.5A CN109837102B (en) | 2019-03-25 | 2019-03-25 | Method for quickly removing refractory masonry of large coke oven body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910226203.5A CN109837102B (en) | 2019-03-25 | 2019-03-25 | Method for quickly removing refractory masonry of large coke oven body |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109837102A true CN109837102A (en) | 2019-06-04 |
CN109837102B CN109837102B (en) | 2020-11-03 |
Family
ID=66886141
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910226203.5A Active CN109837102B (en) | 2019-03-25 | 2019-03-25 | Method for quickly removing refractory masonry of large coke oven body |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109837102B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114874787A (en) * | 2022-04-23 | 2022-08-09 | 中国五冶集团有限公司 | Method for mounting clean heat recovery coke oven door |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101081986A (en) * | 2007-02-13 | 2007-12-05 | 上海五冶冶金建设有限公司 | Coke oven masonry construction method employing upright line rod |
CN101381607A (en) * | 2008-10-06 | 2009-03-11 | 中冶宝钢技术服务有限公司 | Manual repair technique of coking chamber wall |
CN102504837A (en) * | 2011-10-28 | 2012-06-20 | 马钢(集团)控股有限公司 | Synchronous cutting-off and unroofing repair method for coke side oven head of large-scale coke oven machine |
CN106753449A (en) * | 2016-12-09 | 2017-05-31 | 李洪泽 | A kind of method for clearing up coke oven chute |
JP2018039921A (en) * | 2016-09-08 | 2018-03-15 | 新日鐵住金株式会社 | Demolition method of retaining wall of coke oven |
JP2018096072A (en) * | 2016-12-12 | 2018-06-21 | 株式会社奥村組 | System and method for carrying out demolition material of building |
CN109181715A (en) * | 2018-09-21 | 2019-01-11 | 中国冶集团有限公司 | The coke oven protective demolition of resistance to material device and method for dismounting |
-
2019
- 2019-03-25 CN CN201910226203.5A patent/CN109837102B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101081986A (en) * | 2007-02-13 | 2007-12-05 | 上海五冶冶金建设有限公司 | Coke oven masonry construction method employing upright line rod |
CN101381607A (en) * | 2008-10-06 | 2009-03-11 | 中冶宝钢技术服务有限公司 | Manual repair technique of coking chamber wall |
CN102504837A (en) * | 2011-10-28 | 2012-06-20 | 马钢(集团)控股有限公司 | Synchronous cutting-off and unroofing repair method for coke side oven head of large-scale coke oven machine |
JP2018039921A (en) * | 2016-09-08 | 2018-03-15 | 新日鐵住金株式会社 | Demolition method of retaining wall of coke oven |
CN106753449A (en) * | 2016-12-09 | 2017-05-31 | 李洪泽 | A kind of method for clearing up coke oven chute |
JP2018096072A (en) * | 2016-12-12 | 2018-06-21 | 株式会社奥村組 | System and method for carrying out demolition material of building |
CN109181715A (en) * | 2018-09-21 | 2019-01-11 | 中国冶集团有限公司 | The coke oven protective demolition of resistance to material device and method for dismounting |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114874787A (en) * | 2022-04-23 | 2022-08-09 | 中国五冶集团有限公司 | Method for mounting clean heat recovery coke oven door |
Also Published As
Publication number | Publication date |
---|---|
CN109837102B (en) | 2020-11-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113833480A (en) | Shield initial tunneling and arrival construction method | |
CN103603676B (en) | A kind of scraper laneway support method | |
CN110079338B (en) | Coke oven body dismantling and rebuilding method | |
CN112160759A (en) | Method for starting and trial tunneling of tunnel shield crossing river | |
CN110158609A (en) | A kind of mechanization demolition reduction method of reinforced concrete brace in foundation pit | |
CN110685459B (en) | Breaking hammer dismantling construction method for dismantling hoist bent from lower part | |
CN111576106A (en) | Construction method for rapidly pushing and replacing ballastless track structure of passenger special line | |
CN109837102A (en) | The quick method for dismounting of capacity coke oven ontology refractory masonry | |
CN101368447A (en) | Old wall renovation and construction method | |
CN109630131B (en) | Underground chamber construction method | |
JP6971170B2 (en) | How to build an underground structure | |
CN112412467B (en) | Construction method of ventilation vertical shaft (200-600 m) with extra-long highway tunnel by' well reversing method | |
CN110066664B (en) | Maintenance method for smoke emission of small burner of 7.63-meter coke oven | |
CN208594308U (en) | Waste material clears up system in a kind of large blast furnace overhaul furnace | |
CN105605924B (en) | The method for repairing and mending of fixed anode copper metallurgical furnace bottom brick | |
CN113982639B (en) | Tunnel lining full-ring dismantling and replacing construction method in unfavorable geological region | |
CN113999946B (en) | Dismantling method for ball type hot blast stove | |
CN111946351B (en) | Rapid excavation method for contact channel of hard rock stratum of rail transit | |
CN112726434B (en) | Three-span deck reinforced concrete arch bridge dismantling method | |
CN108624730A (en) | Waste material cleaning system and method for cleaning in a kind of large blast furnace overhaul stove | |
CN110725220A (en) | Construction method for dismantling pier | |
CN117345250A (en) | Construction method for removing hole excavation supporting | |
CN105735064B (en) | A kind of train overhaul tunnel sleeper changing construction method | |
CN101307652B (en) | Blast furnace bottom heat resisting foundation pier dismantling method | |
CN216446838U (en) | Device for improving blasting drilling success rate in burning rock stratum |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |