CN109763508A - A kind of domatic isolated footing structure - Google Patents

A kind of domatic isolated footing structure Download PDF

Info

Publication number
CN109763508A
CN109763508A CN201910076290.0A CN201910076290A CN109763508A CN 109763508 A CN109763508 A CN 109763508A CN 201910076290 A CN201910076290 A CN 201910076290A CN 109763508 A CN109763508 A CN 109763508A
Authority
CN
China
Prior art keywords
domatic
isolated footing
prefabricated framework
prefabricated
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910076290.0A
Other languages
Chinese (zh)
Inventor
郭鹏涛
李由
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal Construction Engineering Co Ltd
Original Assignee
China Coal Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Coal Construction Engineering Co Ltd filed Critical China Coal Construction Engineering Co Ltd
Priority to CN201910076290.0A priority Critical patent/CN109763508A/en
Publication of CN109763508A publication Critical patent/CN109763508A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

The present invention relates to a kind of domatic isolated footing structures comprising prefabricated framework, cast-in-place body and column muscle;Prefabricated framework includes four cycle side plates, substrate steel mesh and intermediate lacing wire;There are bed course, the spacer bar rod that setting end face is inclined outwardly on bed course under prefabricated framework;Pre-buried baffle reinforcing bar is to connect slope surface template on the side plate of prefabricated framework.The present invention, which has, simplifies working procedure, improves construction efficiency, saves the effect of construction time.

Description

A kind of domatic isolated footing structure
Technical field
The present invention relates to the technical fields of foundation engineering, more particularly, to a kind of domatic isolated footing structure.
Background technique
Isolated footing is as important one of type of foundation at present, because its structure is simple, of less demanding to geology, various It is generally used in structure type, stepped foundation, domatic basis and cup-shaped foundation can be divided into.Wherein, cast-in-place domatic basis Construction process is: excavation of foundation pit and reserved construction width --- pouring blinding concrete --- the binding substrate steel mesh on bed course --- installation template --- pours base concrete --- form removal after concrete initial set --- foundation pit to return and vertical posts muscle It fills out.(column muscle refers to foundation bolt or vertical dowel pre-buried in basis) due to needed in work progress install, disassembly template, But also concrete set time is needed to wait for, so there are process complexity, duration longer problem for entire construction.
Summary of the invention
Simple, high construction efficiency a kind of domatic isolated footing structure that the object of the present invention is to provide a kind of processes.
Foregoing invention purpose of the invention has the technical scheme that including prefabricated framework, cast-in-place body With column muscle;Prefabricated framework includes four cycle side plates, substrate steel mesh and intermediate lacing wire;Substrate steel mesh is horizontally disposed, and four sides are pre- It is embedded in four cycle side plates, close to the position of bottom, substrate steel mesh includes the more transverse steels and longitudinal reinforcement of arranged crosswise; The both ends of intermediate lacing wire are embedded in four cycle side plates of prefabricated framework, after column muscle and intermediate lacing wire binding or welding, realize position It is fixed.
By using above-mentioned technical proposal, domatic isolated footing eliminates existing in such a way that prefabrication cast-in-place combines The installation and removal of template in technology can directly be poured after framework positioning, simplify construction procedure.Pacify in prefabricated framework Backfilling of earthwork can be carried out after dress is in place, the available relatively flat working face after backfilling of earthwork connects down for construction personnel The operation that pours come provides convenience, saves the time for waiting concrete setting in the prior art, shortens the construction period.Substrate steel The setting of muscle not only can satisfy substrate bending resistance, but also resistance to plucking can be prevented with column muscle drawknot, while intermediate lacing wire is played column muscle and determined Position and fixed effect keep column muscle crooked in process of vibrating, improve installation accuracy.
The present invention is further arranged to: multiple tracks is vertically arranged in the intermediate lacing wire.
By using above-mentioned technical proposal, lacing wire among multiple tracks is arranged can be fixed along the elongated direction of column muscle, make column Muscle accurate positioning, it is more stable under the instant impact for starting to pour.
The present invention is further arranged to: further including bed course.
By using above-mentioned technical proposal, horizontal placed side is provided for prefabricated framework, moreover it is possible to it is horizontal to save adjustment framework Construction procedure.
The present invention is further arranged to: the mat surface insertion constitutes the spacer bar rod that prefabricated framework card puts position.
By using above-mentioned technical proposal, the position that hangs of prefabricated framework, precise positioning are quickly positioned.
The present invention is further arranged to: the spacer bar rod is arranged at least two in the periphery of every block of side plate.
By using above-mentioned technical proposal, when spacer bar rod setting quantity is more, it is ensured that framework is in placement process In axial rotation does not occur.
The present invention is further arranged to: spacer bar rod top is inclined outwardly.
By using above-mentioned technical proposal, spacer bar rod slant setting can play guidance to hanging for prefabricated framework Effect, can also reduce the friction on spacer bar rod top Yu prefabricated frame side plate, avoid damaging prefabricated framework.
The present invention is further arranged to: further including the pre- baffle reinforcing bar for being embedded in the fixed slope surface template in side plate top surface.
By using above-mentioned technical proposal, when the slope surface gradient on domatic basis is larger needs to install slope surface template, baffle Reinforcing bar can limit slope surface template movement.
In conclusion advantageous effects of the invention are as follows:
1. domatic isolated footing, in such a way that prefabrication cast-in-place combines, prefabricated frame body by integral forming eliminates in the prior art The installation and removal of template, simplify construction procedure;
2. without mounting and dismounting template, when excavation pit can not the excessive construction width of indwelling, the installation of prefabricated framework just Backfilling of earthwork can be carried out behind position, the available relatively flat working face after backfilling of earthwork is that construction personnel is next It pours operation and great convenience is provided, save the time for waiting concrete setting in the prior art, shorten the construction period;
3. the setting of substrate reinforcing bar not only can satisfy substrate bending resistance inside prefabricated frame body, resistance to plucking also is prevented with column muscle drawknot, together When among lacing wire play the role of positioning and fixation to column muscle, keep column muscle crooked in process of vibrating, improve basis with Installation accuracy between column;
4. hoisting process can be made to settle at one go by the prefabricated framework of spacer bar rod precise positioning, avoid waste of manpower and when Between.
5. the pre-buried baffle reinforcing bar that can connect slope surface template, makes the easier for installation of slope surface template.
Detailed description of the invention
Fig. 1 is the attachment structure schematic diagram of domatic isolated footing;
Fig. 2 is the structural schematic diagram of prefabricated framework;
Fig. 3 is the structural schematic diagram that spacer bar rod is arranged on bed course;
Fig. 4 is the partial enlargement diagram of Fig. 1 mesoslope face die plate part.
In figure, 1, bed course;11, spacer bar rod;2, prefabricated framework;21, four cycle side plate;22, substrate steel mesh;23, in Between lacing wire;3, cast-in-place body;4, column muscle;51, slope surface template;52, fixed steel bars;53, baffle reinforcing bar.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
It referring to Fig.1, is a kind of domatic isolated footing structure disclosed by the invention, including bed course 1, prefabricated framework 2, cast-in-place body 3 and column muscle 4.Prefabricated framework 2 includes four cycle side plates 21, substrate steel mesh 22 and intermediate lacing wire 23.22 level of substrate steel mesh is set It sets, four sides are embedded in four cycle side plates 21, close to the position of bottom, and substrate steel mesh 22 includes more transverse directions of arranged crosswise Reinforcing bar and longitudinal reinforcement.The both ends of intermediate lacing wire 23 are embedded in four cycle side plates 21 of prefabricated framework 2, column muscle 4 and intermediate lacing wire After 23 bindings or welding, realize that position is fixed;Intermediate lacing wire 23 is in the settable multiple tracks of vertical direction.
When construction, the prefabricated framework 2 being made of four cycle side plates 21 is made in factory, while by substrate steel mesh 22 in Between lacing wire 23 be embedded in prefabricated framework 2, prefabricated framework 2 is then transported to construction site.It is reserved when cast in situs bed course 1 prefabricated Pre-buried substrate steel mesh 22 and the intermediate binding of lacing wire 23 or welding in the placement location of framework 2, column muscle 4 and prefabricated framework 2, Gu It is set to one, prefabricated framework 2 is hung in the foundation pit of excavation, starts to carry out backfilling of earthwork, the finishing operations after being backfilled Behind face, start to be poured.
In such a way that prefabrication cast-in-place combines, prefabricated framework 2 is integrally formed for domatic isolated footing, eliminates the prior art The installation and removal of middle template, simplify construction procedure.When excavation pit can not the excessive construction width of indwelling, in prefabricated frame Body 2 can carry out backfilling of earthwork after installing in place, the available relatively flat working face after backfilling of earthwork, be construction personnel It is next that operation offer great convenience is provided, the time for waiting concrete setting in the prior art is saved, construction is shortened Duration.The setting of prefabricated 2 interior substrate reinforcing bar of framework not only can satisfy substrate bending resistance, but also can prevent resistance to plucking with 4 drawknot of column muscle, Intermediate lacing wire 23 plays the role of positioning and fixation to column muscle 4 simultaneously, keeps column muscle 4 crooked in process of vibrating, improves Installation accuracy.
Further, in order to when placing prefabricated framework 2 once positioning, more smoothly, as shown in figure 3, prefabricated framework 2 is put Spacer bar rod 11 is arranged in the surrounding of seated position, and the card for reserving basis puts position.
When pouring with a thickness of the bed course 1 of 10cm, setting-out work is carried out, determines position of the prefabricated framework 2 on bed course 1, padded Before 1 initial set of layer, it is inserted into spacer bar rod 11 in the surrounding of prefabricated 2 placement location of framework, steel rod is inclined outwardly, the card of formation base Put position.It is finished to column muscle 4 and the embedded bar binding in prefabricated framework 2, prefabricated framework 2 is hung into 11 structure of spacer bar rod At card put in position.
The setting of spacer bar rod 11 can quickly position the position that hangs of prefabricated framework 2, and the inclination of spacer bar rod 11 is put Guidance can be played the role of to prefabricated hanging for framework 2 by setting, and can also be reduced the friction of steel rod Yu prefabricated 2 side plate of framework, be kept away Exempt to damage prefabricated framework 2.
Further, when the slope surface gradient on domatic basis is larger, in order to make to pour smoothly, need to install slope surface template 51.As best shown in figs. 1 and 4, baffle reinforcing bar 53, baffle reinforcing bar 53 is arranged close to the position of inner wall in the side plate top surface of prefabricated framework 2 One end embedment side plate in, one end is exposed;One end of slope surface template 51 rides over the side plate top surface of prefabricated framework 2, while and baffle Reinforcing bar 53 abuts, and the other end of slope surface template 51 contacts fixation with column muscle 4.Setting fixed steel bars 52 consolidate slope surface template 51 Fixed, fixed steel bars 52 are located at the top of slope surface template 51, and both ends are connected with baffle reinforcing bar 53 and column muscle 4 respectively.Fixed steel bars 52 Setting slope surface template 51 can be prevented to heave deformation when casting concrete, control ramp slope.
The implementation principle of the present embodiment are as follows: the prefabricated framework 2 of prefabrication is transported to scene, through substrate steel mesh 22 in Between lacing wire 23 bound with column muscle 4, if the slope surface gradient is larger, need to install inclined-plane template, then hang to bed course 1 card put Position is fixed.Backfilling of earthwork is carried out, starts to pour cast-in-place body 3 after obtaining preferable working face.The structure type of the present embodiment can To reduce complicated construction operation in the construction process, without construction personnel's installation, disassembly foundation forms, by embedded ribs to column Muscle 4 is positioned and is fixed, and makes to pour, saving working procedure smooth with process of vibrating, while also substantially reducing the construction period.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (7)

1. a kind of domatic isolated footing structure, it is characterised in that: including prefabricated framework (2), cast-in-place body (3) and column muscle (4);It is prefabricated Framework (2) includes four cycle side plates (21), substrate steel mesh (22) and intermediate lacing wire (23);Substrate steel mesh (22) is horizontally disposed, Its four side is embedded in four cycle side plates (21), close to the position of bottom, and substrate steel mesh (22) includes more cross of arranged crosswise To reinforcing bar and longitudinal reinforcement;The both ends of intermediate lacing wire (23) are embedded in four cycle side plates (21) of prefabricated framework (2), column muscle (4) After binding or weld with intermediate lacing wire (23), realize that position is fixed.
2. a kind of domatic isolated footing structure according to claim 1, it is characterised in that: the intermediate lacing wire (23) is perpendicular Set up multiple tracks.
3. a kind of domatic isolated footing structure according to claim 1, it is characterised in that: further include bed course (1).
4. a kind of domatic isolated footing structure according to claim 3, it is characterised in that: bed course (1) the surface insertion Constitute the spacer bar rod (11) that prefabricated framework (2) card puts position.
5. a kind of domatic isolated footing structure according to claim 4, it is characterised in that: the spacer bar rod (11) exists The periphery of every block of side plate is at least arranged two.
6. a kind of domatic isolated footing structure according to claim 4, it is characterised in that: spacer bar rod (11) top End is inclined outwardly.
7. a kind of domatic isolated footing structure according to claim 1, it is characterised in that: further include pre- being embedded in side plate top surface The baffle reinforcing bar (53) of fixed slope surface template (51).
CN201910076290.0A 2019-01-26 2019-01-26 A kind of domatic isolated footing structure Pending CN109763508A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910076290.0A CN109763508A (en) 2019-01-26 2019-01-26 A kind of domatic isolated footing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910076290.0A CN109763508A (en) 2019-01-26 2019-01-26 A kind of domatic isolated footing structure

Publications (1)

Publication Number Publication Date
CN109763508A true CN109763508A (en) 2019-05-17

Family

ID=66455300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910076290.0A Pending CN109763508A (en) 2019-01-26 2019-01-26 A kind of domatic isolated footing structure

Country Status (1)

Country Link
CN (1) CN109763508A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112681363A (en) * 2020-12-25 2021-04-20 中铁二局集团电务工程有限公司 One-time pouring method and device for cup-shaped foundation and support
CN113668588A (en) * 2021-08-20 2021-11-19 中建五局土木工程有限公司 Efficient backfill construction method for large-scale assembled steel plate box factory building foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101289866A (en) * 2007-04-16 2008-10-22 上海市第七建筑有限公司 Construction method for precasting concrete moulding bed in local pit of base pit engineering under soft foundation
CN206844138U (en) * 2017-06-19 2018-01-05 中冶建工集团有限公司 A kind of bar construction of domatic isolated footing
CN207616844U (en) * 2017-12-20 2018-07-17 中国核工业第二二建设有限公司 Foundation platform precast concrete side form and molding machine

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101289866A (en) * 2007-04-16 2008-10-22 上海市第七建筑有限公司 Construction method for precasting concrete moulding bed in local pit of base pit engineering under soft foundation
CN206844138U (en) * 2017-06-19 2018-01-05 中冶建工集团有限公司 A kind of bar construction of domatic isolated footing
CN207616844U (en) * 2017-12-20 2018-07-17 中国核工业第二二建设有限公司 Foundation platform precast concrete side form and molding machine

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112681363A (en) * 2020-12-25 2021-04-20 中铁二局集团电务工程有限公司 One-time pouring method and device for cup-shaped foundation and support
CN113668588A (en) * 2021-08-20 2021-11-19 中建五局土木工程有限公司 Efficient backfill construction method for large-scale assembled steel plate box factory building foundation
CN113668588B (en) * 2021-08-20 2022-10-11 中建五局土木工程有限公司 Efficient backfill construction method for large-scale assembled steel plate box factory building foundation

Similar Documents

Publication Publication Date Title
KR100787178B1 (en) Light weight steel frame foundation flooring material and method for construction
CN109763508A (en) A kind of domatic isolated footing structure
CN109457568B (en) Construction process for prefabricated post-tensioning prestressed assembly pavement of bilateral superposed beam
CN105178358B (en) Vertical supporting system for reverse construction method and construction method of vertical supporting system
CN110499869A (en) Bracket composite beam and its construction method
CN108661169A (en) A kind of assembled marginal frame beam component and design method
RU2082853C1 (en) Method of construction of foundation
CN111456105B (en) Construction method of post-pouring belt of underground garage bottom plate
CN107460886A (en) A kind of lightweight steel construction assembles basis and its construction method of decoration integrated building
CN106567329A (en) Semi-prefabricated reinforced concrete wall type guardrail
CN110439162A (en) The construction technology of cast-in-situ hollow building roof
CN214245823U (en) Advance through structure of new and old structure girder on two sides of mid-partition wall
JPS6410837A (en) Box pulling basket retaining mold of iron pillar fixing part in s building
CN207988637U (en) A kind of prefabricated post connection structure for being fixed temporarily, adjusting height
CN210164241U (en) Prefabricated boundary beam of preset formwork
CN208267093U (en) A kind of Precast Concrete Frame
CN211229721U (en) Prefabricated assembled pond guide wall
CN214363530U (en) Scenic spot landslide stock reinforced structure
CN211498743U (en) Tooth wall composite geomembrane pre-buried construction structure
CN217105550U (en) Reinforced concrete prefabricated integral-cast house structure
CN214993868U (en) Layered pouring device for concrete beam of soft soil foundation pit
JP2624851B2 (en) Circulating water piping construction method
CN217439348U (en) Bracket-free constructional column construction structure
JP2678442B2 (en) Construction method of independent foundation and foundation block used for it
CN209703839U (en) Steel bar clamping device for stirrup

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190517