CN109653534A CN201910120036.6A CN201910120036A CN109653534A CN 109653534 A CN109653534 A CN 109653534A CN 201910120036 A CN201910120036 A CN 201910120036A CN 109653534 A CN109653534 A CN 109653534A
Authority
CN
China
Prior art keywords
straining beam
bottom plate
building
club
existing building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910120036.6A
Other languages
Chinese (zh)
Inventor
习朝位
史永健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Architectural Design Research Institute LLC
Original Assignee
Hebei Architectural Design Research Institute LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Architectural Design Research Institute LLC filed Critical Hebei Architectural Design Research Institute LLC
Priority to CN201910120036.6A priority Critical patent/CN109653534A/en
Publication of CN109653534A publication Critical patent/CN109653534A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The present invention provides a kind of set building club-footed pile strip footing straining beam and set buildings, belong to set and builds building foundation technical field, including straining beam bottom plate and basic straining beam, the ratcheting connection in straining beam bottom plate side and existing building basis, the opposite other side extends outwardly beyond the outer edge of the cushion cap below frame column, and straining beam bottom plate is equipped with two-way steel mesh;Basic straining beam is set to the upper surface of described straining beam bottom plate, it is connected between two adjacent cushion caps, by stirrup together with straining beam bottom plate hoop, the width of basic straining beam is less than the width of cushion cap, and the center line of basic straining beam is overlapped with the line of centres of two adjacent cushion caps.Set provided by the invention builds club-footed pile strip footing straining beam, pass through the ratcheting connection of strip footing straining beam and existing building basis, it is combination stressed, transmit set building column bottom internal force effectively, set builds building foundation and only undertakes structure vertical force, the spacing that set is built between building foundation and existing building basis can be reduced, economize the land resource utilization.

Description

Set building club-footed pile strip footing straining beam and set building
Technical field
It is to be related to a kind of set building club-footed pile item more specifically the invention belongs to cover to build building foundation technical field Shape basis straining beam and set building.
Background technique
With the rapid development of our country's economy, the paces of urbanization are quickly grown, and skyscraper rises sheer from level ground like the mushrooms after rain And rise, cause the soil of downtown urban land fewer and fewer.And in Old City Reconstruction, generally take changing for " tearing open build in large scale greatly " Method is made, Old building bring building waste is removed and nowhere discharges, Land Environment is caused seriously to pollute.
And build the normal life for influencing people in large scale in order to avoid tearing open greatly, one, which is built, in the outer cover of an existing building creates Building is a kind of good processing mode.Set building is generally skyscraper, and foundation bearing force request is high, and basis is general to be used The form of pile foundation, buried depth are greater than existent building, and newly-built set build the spacing between building foundation and existing building basis compared with It is small, it cannot guarantee that set builds the stress of building pile foundation using usual manner.
Summary of the invention
The purpose of the present invention is to provide a kind of sets to build club-footed pile strip footing straining beam, to solve to cover building laterally The technical issues of basic straining beam can not be arranged in large span direction.
To achieve the above object, the technical solution adopted by the present invention is that: a kind of set building club-footed pile strip footing is provided Straining beam is set to the outside on existing building basis, comprising:
Straining beam bottom plate, the ratcheting connection in side and existing building basis, the opposite other side extends outwardly beyond frame The outer edge of cushion cap below column, straining beam bottom plate are equipped with two-way steel mesh;
Basic straining beam is set to the upper surface of described straining beam bottom plate, is connected between two adjacent cushion caps, by hoop Muscle is together with the straining beam bottom plate hoop, and the width of the basis straining beam is less than the width of the cushion cap, the basis straining beam Center line is overlapped with the line of centres of two adjacent cushion caps.
Further, the structure of the ratcheting connection are as follows: the straining beam bottom plate connect with the existing building basis one The section configuration of side, for the tooth-shape structure that matches with the existing building foundation outline, the two-way steel mesh is laid with to leaning on The nearly existing building is basic, and after formed by integrally casting, straining beam bottom plate is closely connect with the existing building basis.
Further, the elevation of bottom of the straining beam bottom plate is equal to or higher than the grey earth foundation on the existing building basis Absolute altitude, elevation of top are high not higher than the top mark that the brick of the existing building ash earth foundation puts foot.
Further, the straining beam bottom plate lower section be laid with concrete cushion, the concrete cushion side be laid with to The grey earth foundation on the existing building basis connects, and the other side is laid with the outer edge beyond the straining beam bottom plate outward.
Further, the elevation of bottom of the concrete cushion is higher than the bottom mark of the grey earth foundation of the existing building Height, and lower than the elevation of top of the grey earth foundation.
Further, the lower section of the frame column is coaxial with the frame column and is deep into the club-footed pile in ground, institute The upper end that cushion cap is set to the club-footed pile is stated, the lower end of the club-footed pile is equipped with the base expanding and base expanding portion for increasing bearing capacity.
Further, grey earth foundation of the maximum outer edge in the base expanding and base expanding portion on the existing building basis is formed by just In drop shadow spread.
Further, the maximum outer edge in the base expanding and base expanding portion exceeds the outer edge of the straining beam bottom plate.
Another object of the present invention is to provide a kind of set building, based on the strip footing straining beam.
The beneficial effect of set building club-footed pile strip footing straining beam provided by the invention is: compared with prior art, Set of the present invention builds club-footed pile strip footing straining beam, passes through the ratcheting connection of strip footing straining beam and existing building basis, group Stress is closed, the horizontal shear and column bottom moment of flexure at the top of club-footed pile are effectively undertaken, transmits set building column bottom internal force effectively, set is built Building foundation only undertakes structure vertical force, can reduce the spacing that set is built between building foundation and existing building basis, reduce soil Ground occupies, and economize the land resource utilization.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention some Embodiment for those of ordinary skill in the art without creative efforts, can also be attached according to these Figure obtains other attached drawings.
Fig. 1 is the planar structure schematic diagram that set provided in an embodiment of the present invention builds club-footed pile strip footing straining beam;
Fig. 2 is the schematic cross-sectional view of the line A-A along Fig. 1;
Fig. 3 is the schematic view of facade structure that set provided in an embodiment of the present invention builds club-footed pile and strip footing straining beam.
Wherein, marked in the figure:
1- frame column;The basis 2- straining beam;3- straining beam bottom plate;4- club-footed pile;41- base expanding and base expanding portion;42- cushion cap;5- existing building Basis;51- ash earth foundation;52- brick puts foot;6- stirrup;7- two-way steel mesh;8- concrete cushion.
Specific embodiment
In order to which technical problems, technical solutions and advantages to be solved are more clearly understood, tie below Accompanying drawings and embodiments are closed, the present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only To explain the present invention, it is not intended to limit the present invention.
Also referring to Fig. 1 and Fig. 2, now set provided by the invention building 4 strip footing straining beam of club-footed pile is said It is bright.The set builds 4 strip footing straining beam of club-footed pile, is set to the outside on existing building basis 5, including 3 He of straining beam bottom plate Basic straining beam 2,3 side of straining beam bottom plate and the basic 5 ratcheting connections of the existing building, the opposite other side extends outwardly beyond frame The outer edge of the cushion cap 42 of 1 lower section of trestle, straining beam bottom plate 3 are equipped with two-way steel mesh 7;Basic straining beam 2 is set to straining beam bottom plate 3 The upper surface of, it is connected between the cushion cap 42 of adjacent two, is bound round together by stirrup 6 and the straining beam bottom plate 3, the base The width of plinth straining beam 2 is less than the width of the cushion cap 42, the center line and two adjacent cushion caps 42 of the basis straining beam 2 The line of centres be overlapped.
Set building 4 strip footing straining beam of club-footed pile provided by the invention is drawn by strip footing compared with prior art The ratcheting connection of beam and existing building basis 5, it is combination stressed, the horizontal shear and column bottom moment of flexure at 4 top of club-footed pile are effectively undertaken, Transmit set building column bottom internal force effectively, set builds building foundation and only undertakes structure vertical force, can reduce set and build building foundation With the spacing between existing building basis 5, land seizure is reduced, economize the land resource utilization.
Wherein, the spacing for the steel mesh being laid in the straining beam bottom plate 3 of basic 2 two sides of straining beam is greater than in basic straining beam 2 Reinforcing bar spacing, economize on resources.
Referring to Fig. 2, a kind of specific embodiment party as set provided by the invention building 4 strip footing straining beam of club-footed pile Formula, the structure of the ratcheting connection are as follows: the section configuration for the side that the straining beam bottom plate 3 is connect with the existing building basis 5, For the tooth-shape structure matched with basic 5 shapes of the existing building, the two-way steel mesh 7 is laid with to close to described and existing builds Basis 5 is built, after formed by integrally casting, straining beam bottom plate 3 is closely connect with the existing building basic 5.Wherein, existing basis includes dirt Basis 51 and brick put foot 52, wherein the width of grey earth foundation 51 is greater than the width that brick puts foot 52, therefore, grey earth foundation 51 and brick One step of formation between foot 52 is put, a tooth form can be also formed, be put for shape with the brick of step on grey earth foundation 51 Foot 52, each step that brick puts foot 52 can form a tooth form, after strip footing straining beam pours, the side of straining beam bottom plate 3 Face can form the tooth-shape structure tightly engaged with existing building basis 5, and so after combination, strip footing straining beam can undertake water Straight snips power and column bottom moment of flexure, namely share set and build the part internal force of building foundation, and improve set building total bearing capacity;Separately Outside, by the way of ratcheting connection, existing building can also be shortened and set builds the distance between building foundation, soil is reduced and account for With effectively improving the utilization rate of space.
Referring to Fig. 2, a kind of specific embodiment party as set provided by the invention building 4 strip footing straining beam of club-footed pile Formula, the elevation of bottom of the straining beam bottom plate 3 are equal to or higher than the absolute altitude of the grey earth foundation 51 on the existing building basis 5, top Portion's absolute altitude is high not higher than the top mark that the brick of the existing building ash earth foundation puts foot 52.
Referring to Fig. 2, a kind of specific embodiment party as set provided by the invention building 4 strip footing straining beam of club-footed pile Formula, the lower section of the straining beam bottom plate 3 are laid with concrete cushion 8,8 side of concrete cushion be laid with to the existing building The grey earth foundation 51 on basis 5 connects, and the other side is laid with the outer edge beyond the straining beam bottom plate 3 outward.
Referring to Fig. 2, a kind of specific embodiment party as set provided by the invention building 4 strip footing straining beam of club-footed pile Formula, the elevation of bottom of the concrete cushion 8 are higher than the elevation of bottom of the grey earth foundation 51 of the existing building, and lower than described The elevation of top of grey earth foundation 51.Referring to fig. 2, wherein the height of straining beam bottom plate 3 is H1, and the height of straining beam entirety is H2, coagulation The height of soil padding 8 is H3, and basic straining beam 2 to the outer peripheral distance of straining beam bottom plate 3 is A2, and basic straining beam 2 arrives existing building base The shortest distance of the grey earth foundation 51 of plinth 5 is A1, wherein A1 and A2 can be equal, and concrete cushion 8 is beyond outside straining beam bottom plate 3 The width at edge is the distance of A3, above-mentioned each parameter and frame column 1 to basic 5 centers of existing building, according to engineering design requirements Depending on.
Refering to fig. 1 and Fig. 3, a kind of specific reality as set provided by the invention building 4 strip footing straining beam of club-footed pile Mode is applied, the lower section of the frame column 1 is club-footed pile 4 that is coaxial with the frame column 1 and being deep into ground, the cushion cap 42 Set on the upper end of the club-footed pile 4, the lower end of the club-footed pile 4 is equipped with the base expanding and base expanding portion 41 for increasing bearing capacity.Pass through base expanding and base expanding Stake 4 increases the bearing capacity of frame column 1, meanwhile, using club-footed pile 4, the distance between existing building can also be shortened.
Fig. 1 and Fig. 3 is please referred to, one kind as set provided by the invention building 4 strip footing straining beam of club-footed pile is specific Embodiment, grey earth foundation 51 of the maximum outer edge in the base expanding and base expanding portion 41 on the existing building basis 5 are formed by positive throwing Within the scope of shadow.Wherein, partly overlapping for base expanding and base expanding portion 41 and existing building basis 5 is utilized, reduces the occupancy to surrounding ground.
Referring to Fig. 1, a kind of specific embodiment party as set provided by the invention building 4 strip footing straining beam of club-footed pile Formula, the maximum outer edge in the base expanding and base expanding portion 41 exceed the outer edge of the straining beam bottom plate 3.By base expanding and base expanding portion 41, bored concrete pile is improved Foundation bearing capacity, further increase the stability of monolithic architecture.
Another object of the present invention is to provide a kind of set building, based on the strip footing straining beam.
Set building provided by the invention, due to passing through the ratcheting connection of strip footing straining beam and existing building basis 5, group Stress is closed, the horizontal shear and column bottom moment of flexure at 4 top of club-footed pile are effectively undertaken, set building column bottom internal force is transmitted effectively, covers It builds building foundation and only undertakes structure vertical force, the spacing that set is built between building foundation and existing building basis 5 can be reduced, reduce Land seizure, economize the land resource utilization.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (9)

1. set building club-footed pile strip footing straining beam, is set to the outside on existing building basis characterized by comprising
Straining beam bottom plate, the ratcheting connection in side and existing building basis, the opposite other side extends outwardly beyond under frame column The outer edge of the cushion cap of side, the straining beam bottom plate are equipped with two-way steel mesh;And
Basic straining beam is set to the upper surface of described straining beam bottom plate, is connected between two adjacent cushion caps, by stirrup with Together, the width of the basis straining beam is less than the width of the cushion cap, the center of the basis straining beam to the straining beam bottom plate hoop Line is overlapped with the line of centres of two adjacent cushion caps.
2. set building club-footed pile strip footing straining beam as described in claim 1, which is characterized in that the knot of the ratcheting connection Structure are as follows: the section configuration for the side that the straining beam bottom plate is connect with the existing building basis is basic with the existing building The tooth-shape structure that shape matches, the two-way steel mesh are laid with to behind existing building basis, formed by integrally casting, straining beam Bottom plate is closely connect with the existing building basis.
3. set building club-footed pile strip footing straining beam as described in claim 1, which is characterized in that the bottom of the straining beam bottom plate Portion's absolute altitude is equal to or higher than the absolute altitude of the grey earth foundation on the existing building basis, and elevation of top is not higher than the existing building The top mark that the brick of grey earth foundation puts foot is high.
4. set building club-footed pile strip footing straining beam as described in claim 1, which is characterized in that under the straining beam bottom plate Side is laid with concrete cushion, and the concrete cushion side, which is laid with to the grey earth foundation on the existing building basis, to connect, separately Side is laid with the outer edge beyond the straining beam bottom plate outward.
5. set building club-footed pile strip footing straining beam as claimed in claim 4, which is characterized in that the concrete cushion Elevation of bottom is higher than the elevation of bottom of the grey earth foundation of the existing building, and lower than the elevation of top of the grey earth foundation.
6. set building club-footed pile strip footing straining beam as described in claim 1, which is characterized in that the lower section of the frame column Be it is coaxial with the frame column and be deep into the club-footed pile in ground, the cushion cap is set to the upper end of the club-footed pile, the expansion The lower end of bottom stake is equipped with the base expanding and base expanding portion for increasing bearing capacity.
7. set building club-footed pile strip footing straining beam as claimed in claim 6, which is characterized in that the maximum in the base expanding and base expanding portion Grey earth foundation of the outer edge on the existing building basis is formed by within the scope of orthographic projection.
8. set building club-footed pile strip footing straining beam as claimed in claim 6, which is characterized in that the maximum in the base expanding and base expanding portion Outer edge exceeds the outer edge of the straining beam bottom plate.
9. set building, which is characterized in that based on such as the described in any item strip footing straining beams of claim 1-8.
CN201910120036.6A 2019-02-18 2019-02-18 Set building club-footed pile strip footing straining beam and set building Pending CN109653534A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910120036.6A CN109653534A (en) 2019-02-18 2019-02-18 Set building club-footed pile strip footing straining beam and set building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910120036.6A CN109653534A (en) 2019-02-18 2019-02-18 Set building club-footed pile strip footing straining beam and set building

Publications (1)

Publication Number Publication Date
CN109653534A true CN109653534A (en) 2019-04-19

Family

ID=66122977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910120036.6A Pending CN109653534A (en) 2019-02-18 2019-02-18 Set building club-footed pile strip footing straining beam and set building

Country Status (1)

Country Link
CN (1) CN109653534A (en)

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113290A (en) * 1997-06-19 1999-01-19 Shimizu Corp Base isolation implementating method for existing building
JP2000265574A (en) * 1999-03-18 2000-09-26 For You Planning Consultant:Kk High floor type steel frame footing beam method
CN1730849A (en) * 2005-09-07 2006-02-08 贵阳铝镁设计研究院 Existing one-storied factory continuation end foundation construction method
CN101806040A (en) * 2010-03-25 2010-08-18 徐国彬 Underpinning device and method for bridge and building
CN202706332U (en) * 2012-08-31 2013-01-30 中国建筑第五工程局有限公司 Steel reinforced concrete composite structure post bracket
CN105649100A (en) * 2016-01-07 2016-06-08 浙江理工大学 Seismic retrofit method for existing pile foundation buildings
CN106065595A (en) * 2016-08-05 2016-11-02 青岛建集团有限公司 Motor train unit body bump test platform-specific fender pile
CN107700474A (en) * 2017-10-27 2018-02-16 西安建筑科技大学 A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN107916798A (en) * 2017-12-22 2018-04-17 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set
CN108005399A (en) * 2017-10-31 2018-05-08 上海市政工程设计研究总院(集团)有限公司 Add the construction method for building multi-layer underground space under a kind of existing building group
CN108086343A (en) * 2017-12-12 2018-05-29 上海建工建集团有限公司 Overhanging type unilateral side wall mixed reinforcement and replacing structure and its construction method
CN207597914U (en) * 2017-10-31 2018-07-10 上海市政工程设计研究总院(集团)有限公司 Add the construction stress structure for building multi-layer underground space under a kind of existing building group
CN207672592U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Sinking space basis structure in skyscraper room
CN207672595U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Set builds foundation structure of building
CN207672594U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Large-span space structure foundation pile
CN207728018U (en) * 2017-12-22 2018-08-14 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set
CN109339087A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of foundation structure system of low-rise building
CN209723695U (en) * 2019-02-18 2019-12-03 河北建筑设计研究院有限责任公司 Set building club-footed pile strip footing straining beam and set building

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113290A (en) * 1997-06-19 1999-01-19 Shimizu Corp Base isolation implementating method for existing building
JP2000265574A (en) * 1999-03-18 2000-09-26 For You Planning Consultant:Kk High floor type steel frame footing beam method
CN1730849A (en) * 2005-09-07 2006-02-08 贵阳铝镁设计研究院 Existing one-storied factory continuation end foundation construction method
CN101806040A (en) * 2010-03-25 2010-08-18 徐国彬 Underpinning device and method for bridge and building
CN202706332U (en) * 2012-08-31 2013-01-30 中国建筑第五工程局有限公司 Steel reinforced concrete composite structure post bracket
CN105649100A (en) * 2016-01-07 2016-06-08 浙江理工大学 Seismic retrofit method for existing pile foundation buildings
CN106065595A (en) * 2016-08-05 2016-11-02 青岛建集团有限公司 Motor train unit body bump test platform-specific fender pile
CN107700474A (en) * 2017-10-27 2018-02-16 西安建筑科技大学 A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN207597914U (en) * 2017-10-31 2018-07-10 上海市政工程设计研究总院(集团)有限公司 Add the construction stress structure for building multi-layer underground space under a kind of existing building group
CN108005399A (en) * 2017-10-31 2018-05-08 上海市政工程设计研究总院(集团)有限公司 Add the construction method for building multi-layer underground space under a kind of existing building group
CN108086343A (en) * 2017-12-12 2018-05-29 上海建工建集团有限公司 Overhanging type unilateral side wall mixed reinforcement and replacing structure and its construction method
CN107916798A (en) * 2017-12-22 2018-04-17 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set
CN207672592U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Sinking space basis structure in skyscraper room
CN207672595U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Set builds foundation structure of building
CN207672594U (en) * 2017-12-22 2018-07-31 河北建筑设计研究院有限责任公司 Large-span space structure foundation pile
CN207728018U (en) * 2017-12-22 2018-08-14 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set
CN109339087A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of foundation structure system of low-rise building
CN209723695U (en) * 2019-02-18 2019-12-03 河北建筑设计研究院有限责任公司 Set building club-footed pile strip footing straining beam and set building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘金砺: "工民建专业毕业设计手册", 中国建筑工业出版社, pages: 196 - 200 *

Similar Documents

Publication Publication Date Title
CN105625261B (en) Quick-assembling green plant growth barricade precast concrete block and system and construction method
CN203939288U (en) Anti-wind net structure
CN211036998U (en) Novel foundation pit support structure
CN202519697U (en) Steel hoop truss high pile-cap tower crane basic structure
CN209723695U (en) Set building club-footed pile strip footing straining beam and set building
CN102359118A (en) Annular foundation of underground continuous wall and construction method thereof
CN201981547U (en) Above-water bearing platform structure combined precasting installation with cast-in-place
CN203924703U (en) Chamfered edge important actor hat cone plate
CN210684718U (en) Combined foundation pit supporting structure
CN112031003A (en) Support device with combined action of pile and soil and construction method thereof
CN109653534A (en) Set building club-footed pile strip footing straining beam and set building
CN207728018U (en) The building structure of skyscraper is built suitable for tier building set
CN207017169U (en) A kind of high-filled subgrade culvert off-loading structure
CN109653191A (en) Prefabricated PC continuous underground wall structure and its construction method
CN206267169U (en) A kind of split blade type prestressing force anchor slab
CN107916798A (en) The building structure of skyscraper is built suitable for tier building set
CN108487303B (en) Combined retaining wall of supporting pile and counterfort retaining wall and construction method
CN208136828U (en) Narrow river Retaining Wall Reinforcement device
CN202298641U (en) Tower foundation structure of high pile cap
CN205742292U (en) A kind of to the protection structure of existing tunnel below newly-built underground engineering
CN205804278U (en) A kind of assembled long piled wharf superstructure system
CN206143548U (en) Expressway subgrade based on concrete placement
CN110318367A (en) A kind of novel revetment structure
CN218597183U (en) Building foundation fertilizer groove backfill system close to subway
CN108951618A (en) A kind of pile-anchor retaining device and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination