CN109505604B - Slope ramp arrangement method applied to stope adopting upward layered filling mining method - Google Patents

Slope ramp arrangement method applied to stope adopting upward layered filling mining method Download PDF

Info

Publication number
CN109505604B
CN109505604B CN201811112241.XA CN201811112241A CN109505604B CN 109505604 B CN109505604 B CN 109505604B CN 201811112241 A CN201811112241 A CN 201811112241A CN 109505604 B CN109505604 B CN 109505604B
Authority
CN
China
Prior art keywords
stope
slope
ramp
layered
horizontal middle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811112241.XA
Other languages
Chinese (zh)
Other versions
CN109505604A (en
Inventor
王志远
焦鹏
佟磊
张文如
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Yin Mao Lead Zinc Mine Co ltd
Original Assignee
Nanjing Yin Mao Lead Zinc Mine Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Yin Mao Lead Zinc Mine Co ltd filed Critical Nanjing Yin Mao Lead Zinc Mine Co ltd
Priority to CN201811112241.XA priority Critical patent/CN109505604B/en
Publication of CN109505604A publication Critical patent/CN109505604A/en
Application granted granted Critical
Publication of CN109505604B publication Critical patent/CN109505604B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/22Methods of underground mining; Layouts therefor for ores, e.g. mining placers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/04Transport of mined material in gravity inclines; in staple or inclined shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Remote Sensing (AREA)
  • Mechanical Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a slope ramp arrangement method applied to an upward layered filling mining method stope, which comprises the following steps: when the mining body is stoped by an upward layered filling mining method, a back-turning type slope way is dug upwards from a lower horizontal middle section roadway on one side of a stope, and the slope way is communicated with each layer of the stope through a short connecting way; constructing the slope ramp section by section along with the rise of the layered stoping of the stope until the slope ramp penetrates through the upper horizontal middle section roadway; the slope way is used as a safety channel and a layer transfer channel of a scraper when the stope is used for layered stoping, and the slope way is used as a main slope way between an upper horizontal middle section roadway and a lower horizontal middle section roadway after the stope is used for layered stoping. The invention reduces the excavation-mining ratio, can realize the nearby filling of the tunneling waste rocks, and has important significance for reducing the production cost and realizing the energy-saving and environment-friendly treatment of the waste rocks.

Description

Slope ramp arrangement method applied to stope adopting upward layered filling mining method
Technical Field
The invention relates to the technical field of underground mining and filling of metal mines, in particular to a slope ramp arrangement method applied to an upward layered filling mining method stope.
Background
In the practical process of the upward stratified filling mining method in the metal mine, along with the application and popularization of the scraper, the mine shoveling operation and the tunneling slag discharging operation efficiency of the stope are greatly improved, and the labor intensity and the operation environment are obviously improved. However, as a large-scale mechanical device, in order to facilitate the entry and exit of a scraper and larger parts into and out of a stope, a slope is generally constructed in stable rocks on one side of the stope to penetrate through an upper horizontal middle roadway and a lower horizontal middle roadway as a main mining-preparation engineering content. And meanwhile, when the layer is changed in the stope, a layer-changing connection channel needs to be constructed again or the waste rocks specially mined are specially piled up in the layer-changing slope way. The typical ramp way arrangement method has the characteristics of large tunneling engineering quantity, high tunneling-mining ratio, complex tunneling and deslagging procedures, high waste rock transferring and filling cost and the like, and when the waste rocks are lifted out of a well, the waste rock conveying and filling method does not accord with the concept of non-waste mining and is not beneficial to controlling the production cost. How to reduce the tunneling engineering amount to the maximum extent, reduce the tunneling-mining ratio and realize the in-situ filling of tunneling waste rocks while meeting the requirements of the scraper on walking and overall mining accuracy is a problem to be solved urgently.
Disclosure of Invention
The invention aims to solve the technical problem of providing a slope ramp arrangement method applied to an upward stratified filling mining method stope, which reduces the project amount of related tunneling projects to the maximum extent through reasonably arranging slope ramps and related connecting road projects, realizes efficient and nearby filling of tunneling waste rocks, avoids excessive mining-standard waste rocks from being lifted out of a well or being transported and filled to other stope dead areas, reduces the production cost, and realizes energy-saving and environment-friendly treatment of the tunneling waste rocks.
In order to achieve the technical purpose, the technical scheme adopted by the invention is as follows:
a slope way arrangement method applied to an upward layered filling mining method stope comprises the following steps:
when the mining body is stoped by an upward layered filling mining method, a back-turning type slope way is dug upwards from a lower horizontal middle section roadway on one side of a stope, and the slope way is communicated with each layer of the stope through a short connecting way;
constructing the slope ramp section by section along with the rise of the layered stoping of the stope until the slope ramp penetrates through the upper horizontal middle section roadway;
the slope way is used as a safety channel and a layer transfer channel of a scraper when the stope is used for layered stoping, and the slope way is used as a main slope way between an upper horizontal middle section roadway and a lower horizontal middle section roadway after the stope is used for layered stoping.
As a further improved technical scheme of the invention, when an upward layered filling mining method is adopted to stope an ore body, a return type slope way is dug upwards from a lower horizontal middle section roadway at a position which is close to the boundary of the ore body or 5-10 meters of the stope boundary on one side of a stope, and the slope of the slope way is less than 20%.
As a further improved technical scheme of the invention, the slope way is constructed section by section along with the rise of the stope layered stope, and the tunneling height of the slope way is always ahead of the height of the stope layered stope of the production stope, rather than penetrating through the upper horizontal middle roadway and the lower horizontal middle roadway at one time; the ramp is turned back between two adjacent stopes, and the ramp is turned back once every 3 layered heights is raised until the ramp penetrates through the upper horizontal middle section roadway.
As a further improved technical scheme of the invention, a manway, an ore pass and a filling return air shaft are arranged in the stope, a slope way is communicated with each layer of stope recovery by a short communication way, and the filling return air shaft in the stope is used as a temporary ventilation shaft for ventilation operation.
As a further improved technical scheme of the invention, the waste rocks during the tunneling of the slope way are transported to the goaf of the layered stope nearby by the scraper, and the transported waste rocks are used for piling a transfer layer connecting road between two adjacent stopes or filling the goaf.
The invention has the beneficial effects that: the invention provides a novel method for arranging a slope way for an upward cut-and-fill stope, which saves larger tunneling engineering amount such as a sublevel drift and the like by arranging the slope way in an area close to an ore body and constructing section by section, can reduce the tunneling-mining ratio and the production cost, can well solve the problem of nearby filling of the waste rocks tunneled by the slope way and an interconnecting road, avoids inefficient transfer and lifting of the waste rocks out of a well, and has important significance for realizing energy-saving and environment-friendly treatment of the tunneling waste rocks. When the slope ramp is used as the content of the stope mining preparation scheme, facilities such as a waste rock chute, a chute yard, related connecting roads, a sectional drift waste rock chute, a yard and a sectional drift temporary air shaft of the slope ramp do not need to be constructed.
Drawings
Fig. 1 is a front view of the present invention.
Fig. 2 is a sectional view in the direction III of fig. 1.
Fig. 3 is a sectional view taken in the direction II of fig. 1.
Detailed Description
The following further describes embodiments of the present invention with reference to fig. 1 to 3:
referring to fig. 1-3, there are 3 stopes in fig. 1. The slope ramp arranging method applied to the stope adopting the upward layered filling mining method provided by the embodiment comprises the following steps of:
(1) when an upward layered filling mining method is adopted to stope an ore body, a return type slope ramp 4 is reversely dug upwards from a lower horizontal middle section roadway 6 at a position, close to the boundary of the ore body or 5-10 meters of the stope boundary, of one side of a stope, wherein the slope of the slope ramp 4 is less than 20%, and the slope ramp is communicated with each layer of the stope through a short communication channel 5; and carrying out slag tapping operation by adopting a scraper.
(2) The slope 4 is constructed section by section along with the rise of the layered stope mining of the stope until the slope penetrates through the upper horizontal middle roadway 7; the slope ramp 4 is used as one of safety channels of the stope and a layer transfer channel of the scraper when the stope is used for layered stope, and the slope ramp 4 is used as a main slope ramp between an upper horizontal middle roadway 7 and a lower horizontal middle roadway 6 after the stope is used for layered stope.
(3) The slope 4 is constructed section by section, and the tunneling height is always ahead of the height of the stoping layer of the production stope, instead of penetrating through the upper horizontal middle roadway 7 and the lower horizontal middle roadway 6 at one time; meanwhile, the ramp 4 is always turned back between two adjacent stopes, and the ramp 4 is turned back once every 3 layered heights rises until the ramp penetrates through the upper horizontal middle section roadway 7.
(4) A man-going well 1, an ore pass 2 and a filling return air well 3 are arranged in a stope, a ramp 4 is communicated with each layer of stope recovery through a short communication channel 5, the filling return air well 3 in the stope is used as a temporary ventilation well for ventilation operation, the temporary ventilation well is not constructed additionally, and a local fan is still needed to be used for local ventilation when the single heading distance of the ramp 4 exceeds a certain range. And the waste rocks generated during the tunneling of the slope 4 are transported to the goaf of the layered stope nearby by the scraper, and the transported waste rocks are used for piling a transfer layer connecting passage between two adjacent stopes or filling the goaf.
(5) Before filling, a stope communicated with the ramp 4 needs to build a filling retaining wall in the short connecting channel 5 close to one side of the ramp 4, isolate the stope (including the short connecting channel 5) from the ramp 4, fill the stope and the short connecting channel 5 synchronously, and permanently reserve the ramp 4 to be used as a subsequent main ramp. As can be seen from fig. 2, the short communication duct 5 of the stope level located below the 5 th level (the level communicated with the short communication duct 5 at B in fig. 2) is filled up at the time of production to the 8 th level (the level communicated with the short communication duct 5 at a in fig. 2), and cannot be seen, and only the single ramp 4 can be seen.
(6) If necessary, anchor rod (net) support or anchor (net) spraying support is carried out in the slope 4 so as to ensure the stability of the top plate and two sides of the slope 4.
The embodiment provides a novel method for arranging the slope ramp 4 for the stope adopting the upward stratified filling mining method, the slope ramp 4 is arranged in the area close to the ore body and is constructed section by section, so that the large tunneling engineering quantity of a subsection roadway and the like is saved, the tunneling and mining ratio and the production cost can be reduced, the problem of nearby filling of the slope ramp 4 and the junction road tunneling waste rocks can be well solved, the inefficient transfer and the lifting and transporting of the waste rocks out of the well are avoided, and the method has important significance for realizing the energy-saving and environment-friendly treatment of the tunneling waste rocks.
The scope of the present invention includes, but is not limited to, the above embodiments, and the present invention is defined by the appended claims, and any alterations, modifications, and improvements that may occur to those skilled in the art are all within the scope of the present invention.

Claims (3)

1. A slope ramp arrangement method applied to an upward cut and fill stope is characterized by comprising the following steps:
when the ore body is stoped by adopting an upward layered filling mining method, a back-turning type slope ramp is dug upwards from a lower horizontal middle section roadway on one side of a stope, and the slope ramp is communicated with each layer of the stope by a short connecting channel;
constructing the slope ramp section by section along with the rise of the layered stoping of the stope until the slope ramp penetrates through the upper horizontal middle section roadway;
the slope way is used as a safety channel of a stope and a layer transfer channel of a scraper when the stope carries out layered stope, and the slope way is used as a main slope way between an upper horizontal middle section roadway and a lower horizontal middle section roadway after the stope carries out layered stope;
when an upward layered filling mining method is adopted to stope an ore body, a return type slope way is dug upwards from a lower horizontal middle section roadway at a position, close to the boundary of the ore body or 5-10 meters of the stope boundary, of one side of a stope, and the slope of the slope way is less than 20%;
constructing the slope ramp section by section along with the rise of the stope layered stope, wherein the tunneling height of the slope ramp is always ahead of the height of the stope layered stope of the production stope, rather than penetrating through the upper horizontal middle roadway and the lower horizontal middle roadway at one time; the ramp is turned back between two adjacent stopes, and the ramp is turned back once every 3 layered heights is raised until the ramp penetrates through the upper horizontal middle section roadway.
2. The method for arranging a slope ramp applied to an upward stratified charge mining stope according to claim 1, wherein a man shaft, an ore pass and a charge return air shaft are arranged in the stope, the slope ramp is communicated with each stratum mined in the stope by a short communication channel, and the charge return air shaft in the stope is used as a temporary air shaft for ventilation.
3. The method for arranging the slope ramp applied to the stope adopting the upward stratified filling mining method as claimed in claim 2, wherein the barren rocks during the tunneling of the slope ramp are transported to the goaf of the stratified stope nearby by a scraper, and the transported barren rocks are used for piling a junction between two adjacent stopes or for filling the goaf.
CN201811112241.XA 2018-09-25 2018-09-25 Slope ramp arrangement method applied to stope adopting upward layered filling mining method Active CN109505604B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811112241.XA CN109505604B (en) 2018-09-25 2018-09-25 Slope ramp arrangement method applied to stope adopting upward layered filling mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811112241.XA CN109505604B (en) 2018-09-25 2018-09-25 Slope ramp arrangement method applied to stope adopting upward layered filling mining method

Publications (2)

Publication Number Publication Date
CN109505604A CN109505604A (en) 2019-03-22
CN109505604B true CN109505604B (en) 2020-07-07

Family

ID=65746008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811112241.XA Active CN109505604B (en) 2018-09-25 2018-09-25 Slope ramp arrangement method applied to stope adopting upward layered filling mining method

Country Status (1)

Country Link
CN (1) CN109505604B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109931063B (en) * 2019-04-25 2020-07-24 安徽马钢矿业资源集团有限公司 Upward step-by-step staggered filling mining method
CN112943292B (en) * 2021-03-03 2022-09-13 中铁四局集团有限公司 Circle shape inclined shaft construction structures suitable for coastal waters downtown area secretly digs subway station

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103557002A (en) * 2013-11-21 2014-02-05 武汉科技大学 Panel mechanized centralized ore-pass upward horizontal cut-and-filling stoping method
CN104060991A (en) * 2014-06-26 2014-09-24 中南大学 Upward cut-and-fill mining method for in-vein slope ramp of gentle dip thin vein
CN104100270A (en) * 2014-06-13 2014-10-15 贵州开磷(集团)有限责任公司 Trackless mining method for gently inclined ore vein
CN105781551A (en) * 2016-04-11 2016-07-20 贵州晨辉达矿业工程设计有限公司 Horizontal strip type mixed filling mining method applicable to three-underground orebody mining
CN105863641A (en) * 2016-04-21 2016-08-17 西北矿冶研究院 Medium-thickness gentle-inclination broken ore body chamber column type upward horizontal layered filling mining method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103557002A (en) * 2013-11-21 2014-02-05 武汉科技大学 Panel mechanized centralized ore-pass upward horizontal cut-and-filling stoping method
CN104100270A (en) * 2014-06-13 2014-10-15 贵州开磷(集团)有限责任公司 Trackless mining method for gently inclined ore vein
CN104060991A (en) * 2014-06-26 2014-09-24 中南大学 Upward cut-and-fill mining method for in-vein slope ramp of gentle dip thin vein
CN105781551A (en) * 2016-04-11 2016-07-20 贵州晨辉达矿业工程设计有限公司 Horizontal strip type mixed filling mining method applicable to three-underground orebody mining
CN105863641A (en) * 2016-04-21 2016-08-17 西北矿冶研究院 Medium-thickness gentle-inclination broken ore body chamber column type upward horizontal layered filling mining method

Also Published As

Publication number Publication date
CN109505604A (en) 2019-03-22

Similar Documents

Publication Publication Date Title
CN104405437B (en) A kind of solid filling with combine the hybrid working face mining method of adopting
CN103742148B (en) The soft coal-mining method covering the descending waste filling of supporting of a kind of half-edge coal seam
CN102996131B (en) Solid-filling coal mining method with two pre-excavating tunnels for advancing
CN107387084B (en) The construction method of top depth is cut in a kind of gob side entry retaining reduction
CN109882239B (en) Open-pit end slope coal-pressing radial filling mining method
CN110593874A (en) Full-filling method for strong and weak full mining of coal mine
CN103967493B (en) A kind of slight slope and thin ore body ore pillar mining codes
CN110424966B (en) Ultrahigh water material filling working face gangue pumping entry retaining non-coal pillar mining method
CN110359914B (en) Safe and low-cost combined sublevel mining method for gently inclined medium-thickness ore body
CN104632220B (en) Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN103615285A (en) Stope route arrangement mode and method beneficial to roof-contacted filling
CN103821558A (en) Coal mine gob filling mining system and gob-side entry retaining filling process
CN111691885B (en) Efficient filling mining method for ultra-thick coal seam
CN102269013B (en) Method for mechanically filling gangue on single support working surface under complex coal seam condition
CN102418527B (en) Method for mining flat dipping ultrathin sedimentary type subterranean iron ore deposit
CN105781551A (en) Horizontal strip type mixed filling mining method applicable to three-underground orebody mining
CN102877848B (en) Method for performing coal mining and gangue cementation stripe filling simultaneously
CN109505604B (en) Slope ramp arrangement method applied to stope adopting upward layered filling mining method
CN102287211A (en) Gob roadway end part hydraulic support frame and gob roadway coal mining method thereof
CN109899070B (en) Slow-inclination medium-thickness ore body solid-waste-free filling mining method based on ellipsoid ore drawing structure
CN105971605A (en) A non-waste mining method for underground mines
CN105971607A (en) Method for gob-side entry retaining of medium-thickness coal seam
CN110644993B (en) Z-shaped strip working face mining method
CN103244121A (en) Track and trackless coupled bottom ore removal system
CN107131805B (en) Mining method for improving ore removal grade of underground caving stope

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant