CN109371767A - 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置 - Google Patents

一种crts-ⅰ型双块式无砟道床混凝土施工养护装置 Download PDF

Info

Publication number
CN109371767A
CN109371767A CN201811335366.9A CN201811335366A CN109371767A CN 109371767 A CN109371767 A CN 109371767A CN 201811335366 A CN201811335366 A CN 201811335366A CN 109371767 A CN109371767 A CN 109371767A
Authority
CN
China
Prior art keywords
railway roadbed
crts
water
water pipe
roadbed concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811335366.9A
Other languages
English (en)
Inventor
吴秀雄
吴江涛
徐凯胜
袁安辉
薛廷贵
张坤
尹晟轩
王勃超
梁明松
漆新郑
李君�
王远彬
韩强
刘君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Fifth Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201811335366.9A priority Critical patent/CN109371767A/zh
Publication of CN109371767A publication Critical patent/CN109371767A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种CRTS‑Ⅰ型双块式无砟道床混凝土施工养护装置,包括道床混凝土上的土工布和塑料薄膜,土工布和塑料薄膜之间设置养护水管(8),养护水管(8)上有一排小孔,养护水管(8)和供水装置连接。自流管铺设完成后,在CRTS‑Ⅰ型双块式无砟道床混凝土面上最终覆盖塑料薄膜。自流管通过流出孔不间断的流水,在塑料薄膜内形成封闭的适用于CRTS‑Ⅰ型双块式无砟道床混凝土养护的潮湿环境,同时达到控制塑料薄膜内混凝土温度的目的。

Description

一种CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置
技术领域
本发明属于施工设备技术领域,具体涉及一种道床混凝土施工养护装置。
背景技术
目前山区多采用CRTS-Ⅰ型双块式无砟轨道***,由于轨枕为C60预制混凝土、道床C40高性能混凝土,另外还有绝缘卡等应力集中点,所以道床开裂已成为CRTS-Ⅰ型双块式双块式无砟轨道结构无法避免的质量通病。
特别是路基段CRTS-Ⅰ型双块式无砟道床由于昼夜温差大,道床混凝土夏季昼夜最大温差可达40度,浇筑无砟道床混凝土后,由于反复热胀冷缩作用,在2个月内,无砟道床混凝土会产生大量的表面裂纹:主要从轨枕边缘开裂;从道床顶面往下开裂,裂纹呈上大、下小的现象。
因此CRTS-Ⅰ型双块式无砟道床施工养护成为防道床混凝土开裂的重要手段,现行通用做法是成立专门养护班组,不停地洒水养护进行保湿、控温,从而减少无砟道床砼裂纹;实践证明,养护做得好,可减少无砟道床80%的裂纹。而人工养护存在喷洒补均匀、时间不稳定的问题。
发明内容
本发明解决的技术问题是:针对目前道床混凝土养护采用人工喷洒的问题,提供了一种自动化的养护装置。
本发明采取的技术方案为:
一种CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,包括道床混凝土上的土工布和塑料薄膜,土工布和塑料薄膜之间设置养护水管,养护水管上有一排小孔,养护水管和供水装置连接。
供水装置抽水机、进水水管、高位储水箱、水箱阀门和铁支架,高位储水箱安装在铁支架上,通过进水水管连接抽水机,通过水箱阀门连接养护水管。
沿线路纵向每间隔25-35m布置一套本养护装置,安装在两条线路之间,每个高位储水箱连接两根养护水管。
高位储水箱底部距离地面1.6-2米。
护水管上每隔20-30cm设置一个出水孔,护水管一端封堵,一端连接水箱阀门。
本发明的有益效果:将喷淋管夹在土工布和塑料薄膜之间,可以使水分扩散得更块更均匀,通过供水装置可以实现持续稳定的供水,保持混凝土湿度,有效提高了道床板混凝土的抗裂性能。
附图说明
图1为本发明装置的示意图;
图1中,1-高位储水箱,2-进水水管,3-水箱阀门,4-右线已浇筑段无砟道床外边线,5-左线线路中线,6-铁支架,7-右线线路中线,8-养护水管,9-左线未浇筑段无砟道床内边线,10-右线已浇筑段无砟道床内边线,11-抽水机。
具体实施方式
安装及使用步骤
1)安装高位水箱1:采用塑料水箱,容积1m3,水箱底部距地面1.8m,底部安装水箱阀门3,用以控制水流大小,高位水箱1安装在两条线路中间。
2)向高位水箱1中加水:高位水箱1通过进水水管2连接抽水机,于水源处启动抽水机11向高位水箱1中供水,加满水箱。
3)铺土工布覆盖已浇筑的无砟道床:无砟道床混凝土终凝后,拆除模板,无砟道床混凝土覆盖土工布包裹。
4)在土工布上铺养护水管8:沿无砟道床面横向标高最高处铺养护水管8,沿养护水管8每间隔25cm在自流管上设置3mm的流出孔,并高出混凝土面,自流喷淋管一端封堵,另一端连到水箱阀门3。
5)铺塑料薄膜覆盖:在土工布及自流喷淋管上铺塑料薄膜覆盖,塑料薄膜厚0.2mm;塑料薄膜侧面用夹子夹住,底部多留出一定宽度的塑料薄膜用小沙袋压住,防止风吹开薄膜。
6)自流管自喷流养护:养护水管8与高位水箱1底部水箱阀门3相接,打开水箱阀门3,使水通过流出孔自由喷流而出,保持砼面潮湿,养护14天以上;通过调整水流大小(供水阀门)及流水孔的孔径来调整滴管两侧的有效养护面,直至水流覆盖到所有的混凝土表面。沿线路纵向每间隔30m设置一个养护单元,养护过程中,派专人巡视,发现水流不畅或水箱无水的情况,应及时排除;如果发现混凝土局部表面有干燥的现象不要紧张,此时还需看看薄膜上是否有雾水的存在,因为雾水的存在已经证明了薄膜内部已经具有足够的湿度,并且大于95%;定期检查养护薄膜下的养护环境,如果发现有缺水现象,及时给水箱加水;薄膜如果有被风吹开的现象,重新覆盖固定即可。
7)重复步骤1)-6),直至完成整个无砟道床施工。

Claims (5)

1.一种CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,包括道床混凝土上的土工布和塑料薄膜,其特征在于:土工布和塑料薄膜之间设置养护水管(8),养护水管(8)上有一排小孔,养护水管(8)和供水装置连接。
2.根据权利要求1所述的CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,其特征在于:供水装置抽水机(11)、进水水管(2)、高位储水箱(1)、水箱阀门(3)和铁支架(6),高位储水箱(1)安装在铁支架(6)上,通过进水水管(2)连接抽水机(11),通过水箱阀门(3)连接养护水管(8)。
3.根据权利要求2所述的CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,其特征在于:沿线路纵向每间隔25-35m布置一套本养护装置,安装在两条线路之间,每个高位储水箱(1)连接两根养护水管(8)。
4.根据权利要求2所述的CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,其特征在于:高位储水箱(1)底部距离地面1.6-2米。
5.根据权利要求2所述的CRTS-Ⅰ型双块式无砟道床混凝土施工养护装置,其特征在于:护水管(8)上每隔20-30cm设置一个出水孔,护水管(8)一端封堵,一端连接水箱阀门(3)。
CN201811335366.9A 2018-11-10 2018-11-10 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置 Pending CN109371767A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811335366.9A CN109371767A (zh) 2018-11-10 2018-11-10 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811335366.9A CN109371767A (zh) 2018-11-10 2018-11-10 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置

Publications (1)

Publication Number Publication Date
CN109371767A true CN109371767A (zh) 2019-02-22

Family

ID=65384332

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811335366.9A Pending CN109371767A (zh) 2018-11-10 2018-11-10 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置

Country Status (1)

Country Link
CN (1) CN109371767A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258207A (zh) * 2019-07-01 2019-09-20 中铁七局集团有限公司 一种用于双块式无砟轨道道床板的养护设备

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413236A (zh) * 2008-09-26 2009-04-22 中铁十二局集团第二工程有限公司 Crtsⅱ型双块式无砟轨道道床板施工方法
WO2012128411A1 (ko) * 2011-03-23 2012-09-27 Kang Nam-Hun 3차원 입체형상을 갖는 조립식 직결궤도의 제조방법 및 이 방법에 의해 제조된 조립식 직결궤도를 이용한 콘크리트 직결궤도 부설방법
CN104762850A (zh) * 2015-03-12 2015-07-08 中交一航局第四工程有限公司 Crtsⅰ型双块式无砟轨道道床板混凝土优化方法
CN107151954A (zh) * 2017-06-24 2017-09-12 中铁十局集团第二工程有限公司 一种crtsⅲ型无砟轨道底座板滴增压灌养护装置及灌养方法
CN108149526A (zh) * 2017-11-06 2018-06-12 武汉三源特种建材有限责任公司 一种crtsⅰ型双块式无砟轨道道床板抗裂构筑方法
CN209602883U (zh) * 2018-11-10 2019-11-08 中铁五局集团有限公司 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413236A (zh) * 2008-09-26 2009-04-22 中铁十二局集团第二工程有限公司 Crtsⅱ型双块式无砟轨道道床板施工方法
WO2012128411A1 (ko) * 2011-03-23 2012-09-27 Kang Nam-Hun 3차원 입체형상을 갖는 조립식 직결궤도의 제조방법 및 이 방법에 의해 제조된 조립식 직결궤도를 이용한 콘크리트 직결궤도 부설방법
CN104762850A (zh) * 2015-03-12 2015-07-08 中交一航局第四工程有限公司 Crtsⅰ型双块式无砟轨道道床板混凝土优化方法
CN107151954A (zh) * 2017-06-24 2017-09-12 中铁十局集团第二工程有限公司 一种crtsⅲ型无砟轨道底座板滴增压灌养护装置及灌养方法
CN108149526A (zh) * 2017-11-06 2018-06-12 武汉三源特种建材有限责任公司 一种crtsⅰ型双块式无砟轨道道床板抗裂构筑方法
CN209602883U (zh) * 2018-11-10 2019-11-08 中铁五局集团有限公司 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258207A (zh) * 2019-07-01 2019-09-20 中铁七局集团有限公司 一种用于双块式无砟轨道道床板的养护设备

Similar Documents

Publication Publication Date Title
CN205261226U (zh) 一种简约多功能不间断供气的大型调压装置
CN209602883U (zh) 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置
CN109371767A (zh) 一种crts-ⅰ型双块式无砟道床混凝土施工养护装置
CN203340578U (zh) 城市公路绿化带自动灌溉管理***
CN102330634A (zh) 高原高山管道引水至低处发电用水及减少管道流水摩擦阻力的新装置及新方法
CN206308584U (zh) 城市道路排水***
CN203105240U (zh) 一种立交桥上绿化自动灌溉***
CN210969332U (zh) 一种桥梁施工用喷淋养护***
CN109636246B (zh) 一种分布式地表水供水水源***
CN204626238U (zh) 一种便于施工和检修的输水管桥结构
CN103485387B (zh) 渠灌区管道输水灌溉***
CN206128021U (zh) 一种现代农田的排灌***
CN106836175B (zh) 一种适用于雨季期间丛式井平台的施工方法
CN107151954A (zh) 一种crtsⅲ型无砟轨道底座板滴增压灌养护装置及灌养方法
CN205404576U (zh) 一种沿海地区氯盐渍土路基病害处理模拟***
CN205922295U (zh) 一种便于安装的高架桥绿化灌溉排水装置
CN205775702U (zh) 用于海绵城市透水人行道的过水缘石
CN207512520U (zh) 一种可长距离输水的高速铁路
CN205546790U (zh) 基于雨水收集的节水灌溉***
CN206902537U (zh) 一种兼输水和交通功能的桥梁
CN201787264U (zh) 一种农田低压管道浮球定额给水栓
CN107119507A (zh) 一种可长距离输水的高速铁路
CN201358967Y (zh) 多头虹吸管
CN109707001B (zh) 基于流致振动原理的供水高含沙水体取水装置
CN204690894U (zh) 道路排水结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 550003 No. 23, jujube Road, Yunyan District, Guizhou, Guiyang

Applicant after: CHINA RAILWAY NO.5 ENGINEERING GROUP CO., LTD.

Applicant after: The Fifth Engeering Co., Ltd. of China Railway 5th Bureau Group Co., Ltd.

Address before: 550003 Zao Shan Road, Nanming District, Guiyang, Guizhou Province, No. 23

Applicant before: CHINA RAILWAY NO.5 ENGINEERING GROUP CO., LTD.

Applicant before: The Fifth Engeering Co., Ltd. of China Railway 5th Bureau Group Co., Ltd.