CN109296074A - A kind of assembly concrete column beam connecting node - Google Patents

A kind of assembly concrete column beam connecting node Download PDF

Info

Publication number
CN109296074A
CN109296074A CN201811410957.8A CN201811410957A CN109296074A CN 109296074 A CN109296074 A CN 109296074A CN 201811410957 A CN201811410957 A CN 201811410957A CN 109296074 A CN109296074 A CN 109296074A
Authority
CN
China
Prior art keywords
precast concrete
groove
concrete column
installing port
nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201811410957.8A
Other languages
Chinese (zh)
Inventor
张延年
步友滨
王诗哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201811410957.8A priority Critical patent/CN109296074A/en
Publication of CN109296074A publication Critical patent/CN109296074A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to a kind of building energy conservation walls, more particularly to a kind of assembly concrete column beam connecting node.Including precast concrete column, precast concrete beam, bolt A, bolt B, nut, the overhanging muscle of lateral connection, groove is arranged in four direction all around in the middle part of the main unit preform concrete column of the precast concrete column, precast concrete beam is set up on groove, groove top is equipped with sideways, outwardly extending reinforcing bar, the inside of sideways, outwardly extending reinforcing bar insertion precast concrete beam, and fastened by nut, bolt B is inserted into the lower end of groove from precast concrete beam upper end, and upper/lower terminal is installed with nut and fastened;It is an advantage of the invention that connection is reliable, good integrity, reduces resource loss, simplifies construction, largely shortens the construction period;Template is saved, easy for installation, component can be dismantled repeatedly, recycle, and have superior anti-seismic performance, and generalization, standardized production may be implemented, and push China's assembly concrete high residential building industrialized development process.

Description

A kind of assembly concrete column beam connecting node
Technical field
The present invention relates to a kind of building energy conservation walls, more particularly to a kind of assembly concrete column beam connecting node.
Background technique
It is that main passes through site-assembled side that assembly concrete building, which refers to the concrete prefabricated element of the factorial production, The concrete structure class building construction of formula design-build.The assembly method of component pours overlapping layer concrete, steel after generally having scene Sleeve grouting connection, welding, mechanical connection and reserving hole overlap joint can be used in pouring concrete connection etc. after muscle anchoring, reinforcing bar connection The ways such as connection.In the 1980s, in the prefabricated big plate house of China's prevalence, due to structural integrity is poor, leakage, The reasons such as cracks on floor slab, there are many influence structure safety and the hidden danger and defect of normal use, gradually by cast-in-place concrete knot Replaced structure.But it with the application of current emerging prefabricated concrete structure, especially introduces in recent years many external first Into technology, localized prefabricated concrete structure is built new technology and is just gradually formed.
With the quickening of China " building industrialization, housing industrialization " process and constantly subtracting for China's " demographic dividend " The trend of the waste appearance housing industry industrialization of few building trade recruitment is increasingly obvious.The application weight of prefabricated concrete structure Newly become all parts of the country current research hot spot and continues to bring out out the new technology of residential housing prefabricated concrete structure, new model. Precast reinforced concrete structure is one of the important directions of China's building structure development, it is conducive to China's building industrialization Development, raising production efficiency is energy saving, develops Green environmental-protection building, and is conducive to improve and guarantee construction engineering quality. Compared with cast-in-situ construction method, assembled reinforced concrete structure is conducive to green construction, because fabricated construction can more meet green construction Save land, energy conservation, section material, water-saving and environmental protection etc. require, reduce the negative effect to environment, including reduce noise, prevent Fugitive dust reduces environmental pollution, cleans transport, reduce place interference, save resources and the energy such as water, electricity, material, it then follows sustainable The principle of development.Moreover, fabricated construction can continuously complete multiple or whole processes of engineering in order, thus reduce into The engineering machinery type and quantity of field eliminate resting the time for procedure connection, realize interchange operation, reduce construction personnel, To improve work efficiency, reduction supplies consumption, reduce environmental pollution, provided safeguard for green construction.In addition, fabricated construction compared with Building waste (account for about municipal refuse total amount 30% -40%) is reduced in big degree, such as steel scrap muscle, waste iron wire, useless bamboo wood material, is given up Abandon concrete etc..
Assembly concrete building can be divided into full assembly and part assembly two major classes according to assembling degree height.Full assembly Building is generally limited to low layer or the lower tier building of requirements for fortification against earthquake;Part assembly concrete construction main member is general It is connected using prefabricated components, at the scene by cast-in-place concrete, forms the building of cast in place and precast construction.
North America region is mainly main since prefabricated/prestressed concrete association (PCI) studies for a long period of time with America & Canada With popularization pre-cast building, the Specification of precast concrete also improves very much so its assembly concrete Application in Building is non- It is often universal.The pre-cast building of North America mainly includes building prefabrication exterior wall and the big series of structure prefabricated components two, and prefabricated components are total to It is that enlargement and prestressing force combine and can optimize structural reinforcement and connecting structure with feature.Reduce production and installation workload, contracting The short Yi work duration fully demonstrates industrialization, standardization and Technical Economy feature.In 20th century, the pre-cast building of North America is main For the non-antidetonation fortified defence area of low layer.Due to the earthquake effect in California area, antidetonation and on the middle and senior level prefabricated is paid much attention in recent years The engineer application technical research of structure.PCI has published " precast concrete Aseismic Design " book recently, from theory and practice The Aseismic Design problem for analyzing to angle system pre-cast building, the newest section for summarizing many precast construction Aseismic Designs are ground into Fruit has very strong directive significance to instructing precast construction design and engineer application to promote.
Europe is the cradle of pre-cast building, and the road of building industrialization has been begun to early in the 17th century.Second of the world is big After the war, due to human resources shortage, Europe further research and probe building industrialization mode.Either economically developed north Europe, West Europe or Eastern Europe underdeveloped, always all in the design and construction side for actively carrying out prefabrication and assembly construction concrete construction Formula.The design and construction experience for having accumulated many pre-cast buildings forms various special precast building systems and standardized general Pre-manufactured product series, and a series of precast concrete engineering specifications and application manual have been worked out, to promotion precast concrete complete The application in the world plays the role of very important.
Japan and South Korea have used for reference American-European successful experience, on the basis of exploring the standardized designs construction of pre-cast building. In conjunction with oneself requirement.Breakthrough is achieved in terms of precast construction system globality antidetonation and shock design.With representative Property achievement two 58 floor for being Japan 2008 and being built up using prefabrication and assembly construction frame structure Tokyo Tower.Meanwhile it is Japanese pre- Concrete construction System Design processed, production and the standard criterion of construction are also very perfect, and prefabricated specification used at present has " prefabricated mixed Solidifying geotechnique's journey } (JASSl0) and " concrete curtain wall) (JASSl4).
China from five sixties of 20th century begin one's study assembly concrete build design and construction technology, form one Serial assembly concrete building system, more typical building system have assembled single storey industry workshop building system, assembly Formula multistory frame building system, assembled large panel building system etc..The application built to assembly concrete the 1980s Reach the period of full bloom, many places in the whole nation all form the integrated assembly concrete industry of design, production and construction and installation Change architectural mode assembly concrete building and two kinds of most important building bodies are become using the masonry building of prefabricated hollow floor System, application popularization rate is up to 70% or more.Since there are many limitations and deficiency, China for the function and physical property of assembled architecture Assembly concrete architectural design and construction technology R & D Level do not catch up with also social demand and Building technology development variation, To mid-term the 1990s, assembly concrete building is gradually replaced by full cast-in-place concrete building system, at present except dress With formula single storey industry workshop building system using wide outer.The engineer application of other prefabrication systems is few.In advance The globality of earthquake-resistant structure processed and the specialized research of management in design and operation are inadequate, cause its Technical Economy poor.It is to cause The basic reason that precast construction stagnates for a long time.
Summary of the invention
In order to solve the above-mentioned technical problems, the present invention provides a kind of assembly concrete column beam connecting nodes, main to solve The certainly overall coordination performance of assembly concrete wall improves energy-efficient performance, significantly improves anti-seismic performance, and connection is greatly reduced Number of packages amount simplifies construction.
The technical solution adopted by the invention is as follows:
A kind of assembly concrete column beam connecting node of the present invention, including precast concrete column, precast concrete beam, bolt A, spiral shell The overhanging muscle of bolt B, nut, lateral connection, in the middle part of the main unit preform concrete column of the precast concrete column all around Groove is arranged in four direction, and precast concrete beam is set up on groove, and groove top is equipped with sideways, outwardly extending reinforcing bar, sideways, outwardly extending reinforcing bar It is inserted into the inside of precast concrete beam, and is fastened by nut, bolt B is inserted under groove from precast concrete beam upper end End, upper/lower terminal are installed with nut and are fastened;The precast concrete column includes precast concrete cylinder, groove, lateral connection Frame, laterally elongated dowel vertically connect installing port;The precast concrete cylinder and groove are one-piece casting, prefabricated mixed Solidifying earth pillar body is connected with inside grooves using laterally elongated dowel, and lateral connection frame, lateral connection frame is arranged in inside grooves The vertical connection installing port of lower part setting;Precast concrete beam includes precast concrete beam body, T-type section, lateral connection steel plate, cross It is prefabricated to connection installing port A, lateral connection installing port B, vertical junction steel plate A, vertical junction steel plate B, the lateral elongated muscle of beam body Beams of concrete end is T-type section, using beam body laterally elongated muscle connection between T-type section and precast concrete beam body, in T-type Vertical junction steel plate A is arranged in section end, three lateral connection installing port A is arranged on vertical junction steel plate A, for installing transverse direction Lateral connection installing port B is arranged on vertical junction steel plate B for protruding bar;The top in T-type section rides over the recessed of precast concrete column The lower part on the top of slot, T-type section is put into inside groove port;In the sideways, outwardly extending reinforcing bar insertion vertical junction steel plate in T-type section, and It is fastened using nut, when fastening, nut is installed in lateral connection installing port A and fastened;Using bolt A by precast concrete column It is connected with precast concrete beam, lateral connection frame connects in one end of bolt A and the groove of concrete column, the other end and concrete Vertical junction steel plate connection, nut install fastening in the lateral connection installing port B of precast concrete beam inside beam;Using bolt B Precast concrete beam and precast concrete column are vertically connected, one end of bolt B and the T-type section top of precast concrete beam are perpendicular It is connected to junction steel plate, the other end connect with precast concrete column bottom portion of groove lateral connection frame, and when fastening, nut is mixed prefabricated Open tightening is installed in the vertical connection of solidifying earth pillar.
Further, the lateral connection frame includes side connection board, horizontal force dowel, horizontal connecting hole, if One end of dry horizontal force dowel is welded with side connection board respectively, and horizontal force dowel is preferentially uniformly distributed, it is horizontal by Power dowel is located on the middle line of side connection board, in two adjacent horizontal force dowels and side connection board solder joint Between have horizontal connecting hole.
Further, the vertical connection installing port is projected as isosceles trapezoid in the plane of precast concrete column, Out-of-plane plane is projected as arc.
Further, the lateral connection installing port A is projected as isosceles trapezoid in the plane of precast concrete beam, Out-of-plane plane is projected as arc.
Further, the lateral connection installing port B is projected as isosceles trapezoid in the plane of precast concrete beam, Out-of-plane plane is projected as arc.
Beneficial effects of the present invention:
The advantages of the present invention are energy conservation and environmental protections, reduce resource loss;Simplify construction, largely shortens the construction period;It saves Template, easy for installation, component can be dismantled repeatedly, recycle;Connection is reliable, and good integrity, rigidity is obviously improved, and has superior Anti-seismic performance, and reduce connector quantity, be obviously improved its and industrialize efficiency, and generalization may be implemented, standardize, push China's assembly concrete high residential building industrialized development process.
Detailed description of the invention
Fig. 1 is a kind of side schematic view of assembly concrete column beam connecting node.
Fig. 2 is a kind of front schematic view of assembly concrete column beam connecting node.
Fig. 3 is a kind of top view of assembly concrete column beam connecting node.
Fig. 4 is precast concrete column elevational schematic view.
Fig. 5 is precast concrete beam elevation.
Fig. 6 is the right elevation of precast concrete column.
Fig. 7 is the left elevation of precast concrete beam.
Fig. 8 is lateral connection frame elevational schematic view.
Fig. 9 is side connection board elevation.
In figure, 1 is precast concrete column;2 be precast concrete beam;3 be bolt A;4 be bolt B;5 be nut;6 be cross To the overhanging muscle of connection;1-1 is precast concrete cylinder;1-2 is groove;1-3 is lateral connection frame;1-4 is laterally elongated connection Muscle;1-5 is vertical connection installing port;1-3-1 is side connection board;1-3-2 is horizontal force dowel;1-3-3 is horizontal connects Connect hole;2-1 is precast concrete beam body;2-2 is beam-ends T-type section;2-3 is lateral connection steel plate;2-4 is lateral connection installation Mouth A;2-5 is lateral connection installing port B;2-6 is the vertical junction steel plate in T-type section;2-7 is the vertical junction steel plate of beam body;2-8 is The lateral elongated muscle of beam body.
Specific embodiment
In order to further illustrate the present invention, the present invention is described in detail with reference to the accompanying drawings and embodiments, but not They can be interpreted as limiting the scope of the present invention.
Embodiment: as shown in Fig. 1 ~ 9, a kind of assembly concrete column beam connecting node of the present invention, including precast concrete The overhanging muscle 6 of column 1, precast concrete beam 2, bolt A3, bolt B 4, nut 5, lateral connection, the master of the precast concrete column 1 Groove 1-2 is arranged in four direction all around in the middle part of body precast concrete cylinder 1-1, sets up precast concrete on groove 1-2 Beam 2, the top groove 1-2 are equipped with sideways, outwardly extending reinforcing bar 6, and sideways, outwardly extending reinforcing bar 6 is inserted into the inside of precast concrete beam 2, and passes through Nut 5 fastens, and bolt B 4 is inserted into the lower end of groove 1-2 from 2 upper end of precast concrete beam, and upper/lower terminal nut 5 is installed tightly Gu;The precast concrete column 1 includes precast concrete cylinder 1-1, groove 1-2, lateral connection frame 1-3, laterally elongated company Meet muscle 1-4, vertical connection installing port 1-5;The precast concrete cylinder 1-1 and groove 1-2 is one-piece casting, concrete Earth pillar body 1-1 is connected with inside groove 1-2 using laterally elongated dowel 1-4, and lateral connection frame 1- is arranged inside groove 1-2 3, the vertical connection installing port 1-5 of the lateral connection lower part frame 1-3 setting;Precast concrete beam 2 includes precast concrete beam body 2-1, T Type section 2-2, lateral connection steel plate 2-3, lateral connection installing port A2-4, lateral connection installing port B2-5, vertical junction steel plate Laterally elongated muscle 2-8,2 end of precast concrete beam are T-type section 2-2, T-type section for A2-6, vertical junction steel plate B2-7, beam body Beam body laterally elongated muscle 2-8 connection is used between 2-2 and precast concrete beam body 2-1, setting is vertical in the T-type section end 2-2 Three lateral connection installing port A2-4 are set on junction steel plate A2-6, vertical junction steel plate A2-6, for installing sideways, outwardly extending steel Lateral connection installing port B2-5 is arranged on vertical junction steel plate B2-7 for muscle 6;The top of T-type section 2-2 rides over precast concrete The lower part on the top of the groove 1-2 of column 1, T-type section 2-2 is put into inside groove port 1-2;Sideways, outwardly extending reinforcing bar 6 is inserted into T-type section It in the vertical junction steel plate 2-6 of 2-2, and is fastened using nut 5, when fastening, nut 5 is installed in lateral connection installing port A2-4 Fastening;Precast concrete column 1 and precast concrete beam 2 are connected using bolt A3, one end of bolt A3 is recessed with concrete column 1 Lateral connection frame 1-3 connection in slot 1-2, the vertical junction steel plate 2-7 in 2 inside of the other end and beams of concrete are connect, when fastening, nut 5 install fastening in the lateral connection installing port B2-5 of precast concrete beam;Using bolt B 4 by precast concrete beam 2 and prefabricated mixed The solidifying vertically connection of earth pillar 1, one end of bolt B 4 and the T-type section 2-2 upper lateral junction steel plate 2-3 of precast concrete beam 2 connect It connecing, the other end is connect with the bottom groove 1-2 transverse direction connection frame 1-3, when fastening, vertical connection of the nut 5 in precast concrete column Installing port 1-5 fastening.
The lateral connection frame 1-3 includes side connection board 1-3-1, horizontal force dowel 1-3-2, horizontal connecting hole 1-3-3, one end of several horizontal force dowel 1-3-2 are welded with side connection board 1-3-1 respectively, horizontal force dowel 1- 3-2 is preferentially uniformly distributed, and horizontal force dowel 1-3-2 is located on the middle line of side connection board 1-3-1, in two adjacent water There is horizontal connecting hole 1-3-3 in the centre of flat stress dowel 1-3-2 and side connection board 1-3-1 solder joint.
The vertical connection installing port 1-5 is projected as isosceles trapezoid in the plane of precast concrete column 1, outside plane Plane be projected as arc;Lateral connection installing port A2-4 is projected as isosceles trapezoid in the plane of precast concrete beam 2, Out-of-plane plane is projected as arc;Lateral connection installing port B2-5 is projected as isosceles in the plane of precast concrete beam 2 It is trapezoidal, arc is projected as in out-of-plane plane.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (5)

1. a kind of assembly concrete column beam connecting node, including precast concrete column (1), precast concrete beam (2), bolt A (3), bolt B (4), nut (5), the overhanging muscle of lateral connection (6), it is characterised in that: the main body of the precast concrete column (1) Groove (1-2) is arranged in four direction all around in the middle part of precast concrete cylinder (1-1), sets up on groove (1-2) prefabricated mixed Solidifying Tu Liang (2), the groove top (1-2) are equipped with sideways, outwardly extending reinforcing bar (6), and sideways, outwardly extending reinforcing bar (6) is inserted into precast concrete beam (2) Inside, and fastened by nut (5), bolt B (4) is inserted into the lower end of groove (1-2) from precast concrete beam (2) upper end, Upper/lower terminal is installed with nut (5) and is fastened;The precast concrete column (1) includes precast concrete cylinder (1-1), groove (1-2), lateral connection frame (1-3), laterally elongated dowel (1-4) vertically connect installing port (1-5);The concrete Earth pillar body (1-1) and groove (1-2) are one-piece casting, are led to inside precast concrete cylinder (1-1) and groove (1-2) using lateral Long dowel (1-4) is connected, and lateral connection frame (1-3) is arranged inside groove (1-2), the setting of the lateral connection frame lower part (1-3) Vertical connection installing port (1-5);Precast concrete beam (2) includes precast concrete beam body (2-1), T-type section (2-2), transverse direction Junction steel plate (2-3), lateral connection installing port A(2-4), lateral connection installing port B(2-5), vertical junction steel plate A(2-6), it is perpendicular To junction steel plate B(2-7), beam body, laterally elongated muscle (2-8), precast concrete beam (2) end are T-type section (2-2), and T-type is cut Using beam body, laterally elongated muscle (2-8) is connect between face (2-2) and precast concrete beam body (2-1), is held at T-type section (2-2) Vertical junction steel plate A(2-6 is arranged in portion), three lateral connection installing port A (2-4) are set on vertical junction steel plate A (2-6), are used In installing sideways, outwardly extending reinforcing bar (6), lateral connection installing port B (2-5) is set on vertical junction steel plate B (2-7);T-type section (2- 2) top rides over the top of the groove (1-2) of precast concrete column (1), and the lower part of T-type section (2-2) is put into groove port (1- 2) internal;In the sideways, outwardly extending vertical junction steel plate (2-6) of reinforcing bar (6) insertion T-type section (2-2), and it is using nut (5) that it is tight Gu nut (5) is installed in lateral connection installing port A (2-4) and is fastened;Using bolt A(3) by precast concrete column (1) and prefabricated Beams of concrete (2) connection, bolt A(3) one end connect with the interior lateral connection frame (1-3) of the groove (1-2) of concrete column (1), The internal vertical junction steel plate B(2-7 of the other end and beams of concrete (2)) it connect, when fastening, nut (5) is in precast concrete beam Lateral connection installing port B(2-5) installation fastening;It is using bolt B (4) that precast concrete beam (2) and precast concrete column (1) is perpendicular To connection, one end of bolt B (4) and T-type section (2-2) the upper lateral junction steel plate (2-3) of precast concrete beam (2) connect It connects, the other end is connect with precast concrete column (1) groove (1-2) bottom transverse direction connection frame (1-3), and when fastening, nut (5) is pre- The vertical connection installing port (1-5) of concrete column processed fastens.
2. a kind of assembly concrete column beam connecting node according to claim 1, it is characterised in that: the transverse direction connects Connecing frame (1-3) includes side connection board (1-3-1), horizontal force dowel (1-3-2), horizontal connecting hole (1-3-3), if solid carbon dioxide One end of flat stress dowel (1-3-2) is welded with side connection board (1-3-1) respectively, and horizontal force dowel (1-3-2) is excellent It is first uniformly distributed, horizontal force dowel (1-3-2) is located on the middle line of side connection board (1-3-1), in two adjacent water The centre of flat stress dowel (1-3-2) and side connection board (1-3-1) solder joint has horizontal connecting hole (1-3-3).
3. a kind of assembly concrete column beam connecting node according to claim 1, it is characterised in that: described vertically connects It connects installing port (1-5) and is projected as isosceles trapezoid in the plane of precast concrete column (1), be projected as arc in out-of-plane plane Shape.
4. a kind of assembly concrete column beam connecting node according to claim 1, it is characterised in that: the transverse direction connects It meets installing port A (2-4) and is projected as isosceles trapezoid in the plane of precast concrete beam (2), in being projected as out-of-plane plane Arc.
5. a kind of assembly concrete column beam connecting node according to claim 1, it is characterised in that: the transverse direction connects Meet installing port B(2-5) it is projected as isosceles trapezoid in the plane of precast concrete beam (2), in being projected as out-of-plane plane Arc.
CN201811410957.8A 2018-11-24 2018-11-24 A kind of assembly concrete column beam connecting node Withdrawn CN109296074A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811410957.8A CN109296074A (en) 2018-11-24 2018-11-24 A kind of assembly concrete column beam connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811410957.8A CN109296074A (en) 2018-11-24 2018-11-24 A kind of assembly concrete column beam connecting node

Publications (1)

Publication Number Publication Date
CN109296074A true CN109296074A (en) 2019-02-01

Family

ID=65143908

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811410957.8A Withdrawn CN109296074A (en) 2018-11-24 2018-11-24 A kind of assembly concrete column beam connecting node

Country Status (1)

Country Link
CN (1) CN109296074A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528950A (en) * 2019-08-30 2019-12-03 绍兴文理学院 A kind of assembled hidden bracket type beam column node connection device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528950A (en) * 2019-08-30 2019-12-03 绍兴文理学院 A kind of assembled hidden bracket type beam column node connection device

Similar Documents

Publication Publication Date Title
CN106121107B (en) Assemble type concrete slab and its plate dry type connection method
CN106149937B (en) Assembly concrete beam and its dry type connection method
CN109322386A (en) Assembly concrete beam column dry type connector
CN209468856U (en) A kind of assembly concrete column beam connecting node
CN106320601B (en) Assembly concrete is whole without heat bridge board wall and its vertical connection method
CN107747378A (en) The body composite board processing method of Fast Installation heat insulation decorative load-bearing one
CN109296074A (en) A kind of assembly concrete column beam connecting node
CN206016002U (en) Assembly concrete beam
CN103541435B (en) With the cross node of full assembling of steel plate concrete Cantilever Beams
CN106284681B (en) Assembly concrete is whole without heat bridge board wall and the connection method of running-on floor
CN206016048U (en) Assemble type concrete slab
CN106223532B (en) Assembly concrete is whole without heat bridge wallboard
CN106638956A (en) Concrete wallboard and ribbed slab dry type connection node
CN206408743U (en) A kind of assembly concrete node
CN207597635U (en) One body composite board L-shaped wall of Fast Installation heat insulation decorative load-bearing
CN206034685U (en) Integrated system is gone along with sb. to guard him to structure of wide post husked kaoliang of dry -type link pack formula concrete
CN207812740U (en) One body composite board linear type wall of Fast Installation heat insulation decorative load-bearing
CN207597695U (en) One body composite board of Fast Installation heat insulation decorative load-bearing
CN206616695U (en) A kind of concrete panel and girt strip floor dry type connecting node
CN207892081U (en) One body composite board T shape walls of Fast Installation heat insulation decorative load-bearing
CN106284739B (en) Assembly concrete is whole without heat bridge gusset
CN109296067A (en) Assembly concrete girder and secondary beam dry type connecting node
CN106245806B (en) The whole hook bolt connection without heat bridge board wall of assembly concrete
CN209260898U (en) Assembly concrete girder and secondary beam dry type connecting node
CN108678259A (en) Dry construction bilayer core plate thermal insulation concrete roof boarding

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190201