CN109146120A - Three-dimensional model identification method for construction task progress state of power transmission and transformation project - Google Patents

Three-dimensional model identification method for construction task progress state of power transmission and transformation project Download PDF

Info

Publication number
CN109146120A
CN109146120A CN201810659161.XA CN201810659161A CN109146120A CN 109146120 A CN109146120 A CN 109146120A CN 201810659161 A CN201810659161 A CN 201810659161A CN 109146120 A CN109146120 A CN 109146120A
Authority
CN
China
Prior art keywords
project
transmitting
construction
converting electricity
threedimensional model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810659161.XA
Other languages
Chinese (zh)
Inventor
齐立忠
韩文军
刘海波
张亚平
孙小虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Zhejiang Electric Power Co Ltd
State Grid Economic and Technological Research Institute
Original Assignee
State Grid Zhejiang Electric Power Co Ltd
State Grid Economic and Technological Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Zhejiang Electric Power Co Ltd, State Grid Economic and Technological Research Institute filed Critical State Grid Zhejiang Electric Power Co Ltd
Priority to CN201810659161.XA priority Critical patent/CN109146120A/en
Publication of CN109146120A publication Critical patent/CN109146120A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Geometry (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Game Theory and Decision Science (AREA)
  • Computer Hardware Design (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Computer Graphics (AREA)
  • Primary Health Care (AREA)
  • Educational Administration (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Software Systems (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Health & Medical Sciences (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a three-dimensional model identification method for a construction task progress state of a power transmission and transformation project, which is based on three-dimensional design results, researches a three-dimensional expression mode for simulating construction progress according to construction plan progress arrangement, and shows plan progress, actual progress, and plan progress and actual progress deviation conditions of a construction site. The model is driven to change according to the construction progress data, the construction process from the absence to the existence of the construction site is truly simulated, the visual simulation of the construction progress is realized, and the management and control of the construction progress of the power transmission and transformation project are realized. According to the method, the model is marked with different colors according to the progress of different tasks, and the supervision can check the current task attribute according to the model color, so that the progress management is more visual, and the progress check is more convenient.

Description

A kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status
Technical field
The present invention relates to converting electricity fields, more particularly, to the three of a kind of project of transmitting and converting electricity construction task progress status Dimension module identification method.
Background technique
Country's three-dimensional visualization is applied at present and the construction project time management of engineering project is applied gradually in terms of architectural engineering Maturation, in the prior art, although these methods are for a certain specific there is also some construction project time management methods The solution of architectural engineering customization, it is also fewer in the application of electricity transmitting and converting construction engineering, especially to project of transmitting and converting electricity The construction speed simulation control aspect of work progress.
Summary of the invention
For existing defect or deficiency, the present invention provides a kind of three-dimensionals of project of transmitting and converting electricity construction task progress status Model identification method, for carrying out three-dimensional display and management control to project of transmitting and converting electricity construction task progress status, comprising:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model are associated with construction schedule, shape At project of transmitting and converting electricity construction speed threedimensional model;
Step 5, actual progress is compared, to described by the actual progress of typing engineering construction with construction schedule Project of transmitting and converting electricity construction task in project of transmitting and converting electricity construction speed threedimensional model carries out colour code according to the color identifier table Know, be associated with and reflect current construction speed state, to distinguish that displaying is completed or carried out according to plan and exist with plan The task of schedule variance.
The beneficial effects of the present invention are firstly, being directed to current status, we are based on construction speed emulation and three-dimensional visible Change technology construction simulation progress can send out three-dimensional artificial feature well.It, can be in the mode of 3 D stereo again by system demonstration Under to entire work progress carry out Schedule monitoring.Secondly, drawing can be illustrated not complete, size marking contradiction etc. by unit in charge of construction The problem of can not constructing caused by factor, is resolved, it is ensured that accomplish in construction rational technology, material are qualified, operation is correct, Securely and reliably.Finally, for the generation of threedimensional model, levels of precision depends on constructing the quality of the sample set of the model, multiple Miscellaneous project of transmitting and converting electricity design problem, Modeling Calculation be it is very time-consuming, search for optimal design parameters when, it is either traditional Optimization algorithm or heuritic approach based on gradient information will carry out multiple iterative calculation.And the present invention is before modeling Element filtering optimization has been carried out in advance, and the element after selection filtering optimization is modeled, so that Modeling Calculation amount is small, again maximum The model that can guarantee precision of prediction in degree, to replace the numerical value of time-consuming actual physical amount during Modeling and Design, with Improve design efficiency.Especially, characteristic point filtering and Eigenvector filtering proposed by the present invention, very well satisfy following two A characteristic: first, space filling properties: all sample points are full of entire design space as much as possible, to capture as far as possible More information about model;And second, projection property: in lower dimensional space, the projection of sample point uniformly divides as much as possible Cloth avoids the occurrence of overlapping.
Detailed description of the invention
Method flow frame Fig. 1 proposed by the invention.
Specific embodiment
For a better understanding of the present invention, with reference to the description of the embodiment of the accompanying drawings, method of the invention is carried out Further instruction.
In order to fully understand the present invention, numerous details are referred in the following detailed description.But art technology Personnel are it should be understood that the present invention may not need these details and realize.In embodiment, it is not described in detail well known side Method, process, component, in order to avoid unnecessarily make embodiment cumbersome.
It is shown in Figure 1, a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status of the invention, For carrying out three-dimensional display and management control to project of transmitting and converting electricity construction task progress status, it is characterised in that:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model are associated with construction schedule, shape At project of transmitting and converting electricity construction speed threedimensional model;
Step 5, actual progress is compared, to described by the actual progress of typing engineering construction with construction schedule Project of transmitting and converting electricity construction task in project of transmitting and converting electricity construction speed threedimensional model carries out colour code according to the color identifier table Know, be associated with and reflect current construction speed state, to distinguish that displaying is completed or carried out according to plan and exist with plan The task of schedule variance.
Wherein, the project of transmitting and converting electricity construction task in the project of transmitting and converting electricity construction speed threedimensional model is according to institute It states color identifier table and carries out colored indicator, specifically include: being with construction schedule beginning and ending time and practical beginning and ending time respectively Foundation, mark is completed task, does not complete and appoint respectively in different colors on the project of transmitting and converting electricity construction speed threedimensional model Business, ongoing task.
Wherein, the project of transmitting and converting electricity construction speed threedimensional model further includes progress back track function, and the progress backtracking is used In the construction task progress for checking any date.
Wherein, the two-dimentional construction drawing of step 3, foundation establishes project of transmitting and converting electricity threedimensional model, specifically using modeling technique Include:
Step 3-1: from gathering project element on the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing;
Step 3-3: the engineering factor after choosing filtering optimization generates project of transmitting and converting electricity construction three by 3 d modeling software Tie up initial model;
Step 3-4: carrying out collision detection to the three-dimensional initial model of project of transmitting and converting electricity construction and three-dimensional drawing school be careful, and Image rendering is carried out, final project of transmitting and converting electricity threedimensional model is obtained;
Wherein, the engineering factor includes characteristic point, Eigenvector, project of transmitting and converting electricity construction plan, sectional view, engineering Height etc..
Wherein, step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing, including to feature The filtering optimization of point, and the filtering of Eigenvector is optimized.
Wherein, the filtering optimization to characteristic point specifically includes:
Step 3-2-1 extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, carry out Feature point sampling;
Step 3-2-2 obtains the closure that existing characteristic point is constituted on each dimension direction in characteristic point sampling process Space, it is desirable that new characteristic point cannot be fallen into these closed spaces;The form of closed space is varied, art technology Personnel can design according to actual needs.For example, it may be certain length is that the sphere of radius is empty using characteristic point as the centre of sphere Between, it is also possible to centered on characteristic point, certain length is the cubic space of side length, and certain length can be according to feature Number or sparse requirement or model granularity requirements etc. is put to determine.The Eigenvector that closed space expression newly samples cannot be fallen Enter meaning therein.
Feature point set C is added in existing characteristic point by step 3-2-3P
Step 3-2-4, by original design SPACE V0Subtract existing characteristic point structure on each dimension direction in feature point set At closed space, obtain filtered free time design space V1
Step 3-2-5, idle design space V after filtration1It is middle to generate a large amount of random point;
These are located at free time design space V by step 3-2-61On random point be mapped to original design SPACE V0
Step 3-2-7 calculates the space length between random point and existing characteristic point, selects the filling of certain amount space special The optimal random point of property is as random character point set CPR
Step 3-2-8 identifies random character point set CPRIn area of feasible solutions where each random point, in these areas of feasible solutions It is scanned for along search boundary line, obtains a series of alternative features points, for each random point, selection does not fall within wherein existing Feature point set C is added as new characteristic point in the optimal solution for the closed space that characteristic point is constitutedP
Step 3-2-9, checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 to 2- is repeated 9。
Wherein, the termination condition of the algorithm is the granularity requirements of scheduled characteristic point number or threedimensional model.
Wherein, the filtering to Eigenvector optimizes, and specifically includes:
Step 3-2-1 ' extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, into The sampling of row Eigenvector;
Step 3-2-2 ' obtains existing Eigenvector and is made of in the plane it in Eigenvector sampling process Closure plane, it is desirable that new Eigenvector cannot fall into these closure planes in;The characteristic curve that closure plane expression newly samples Duan Buneng falls into meaning therein.
Eigenvector collection C is added in existing Eigenvector by step 3-2-3 'L
Step 3-2-4 ', judging characteristic line-segment sets CLIn the closure plane that is constituted of existing Eigenvector whether may make up Closed space, if it is not, then continue Eigenvector sampling;It is closed if it is, obtaining by what existing closure plane was constituted Close space;The requirement for the closed space that whether may make up is varied, and those skilled in the art can set according to actual needs Meter.For example, can require just to may be constructed a specific closure when six intersecting planes for having cube as building Space may also require that the space of composition is not necessarily cube, for example can have the two of mutual relative tilt out of square A face, if require the intersection of multiple planes to may make up enclosure space, be considered as reaching wanting for the closed space that may make up It asks.The Eigenvector that closed space expression newly samples cannot fall into meaning therein.
Step 3-2-5 ', by original design SPACE V0The closed space that existing closure plane is constituted is subtracted, after obtaining filtering Idle design space V2
Step 3-2-6 ', idle design space V after filtration2It is middle to generate a large amount of random line segment;
These are located at free time design space V by step 3-2-7 '2On random line segment be mapped to original design SPACE V0, obtain The plane where these random line segments is taken, if the plane where the random line segment and original design SPACE V0In any institute It states existing closure plane to be overlapped, then deletes the random line segment, obtain the random line segment after filtering optimizes, addition and more new feature Line-segment sets CL
Step 3-2-8 ', checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 ' is repeated extremely 2-8’。
Wherein, the termination condition of the algorithm is the granularity requirements of scheduled Eigenvector number or threedimensional model.
The beneficial effects of the present invention are firstly, being directed to current status, we are based on construction speed emulation and three-dimensional visible Change technology construction simulation progress can send out three-dimensional artificial feature well.It, can be in the mode of 3 D stereo again by system demonstration Under to entire work progress carry out Schedule monitoring.Secondly, drawing can be illustrated not complete, size marking contradiction etc. by unit in charge of construction The problem of can not constructing caused by factor, is resolved, it is ensured that accomplish in construction rational technology, material are qualified, operation is correct, Securely and reliably.Finally, for the generation of threedimensional model, levels of precision depends on constructing the quality of the sample set of the model, multiple Miscellaneous project of transmitting and converting electricity design problem, Modeling Calculation be it is very time-consuming, search for optimal design parameters when, it is either traditional Optimization algorithm or heuritic approach based on gradient information will carry out multiple iterative calculation.And the present invention is before modeling Element filtering optimization has been carried out in advance, and the element after selection filtering optimization is modeled, so that Modeling Calculation amount is small, again maximum The model that can guarantee precision of prediction in degree, to replace the numerical value of time-consuming actual physical amount during Modeling and Design, with Improve design efficiency.Especially, characteristic point filtering and Eigenvector filtering proposed by the present invention, very well satisfy following two A characteristic: first, space filling properties: all sample points are full of entire design space as much as possible, to capture as far as possible More information about model;And second, projection property: in lower dimensional space, the projection of sample point uniformly divides as much as possible Cloth avoids the occurrence of overlapping.
Here the preferred embodiment of the present invention is only illustrated, but its meaning is not intended to limit the scope of the invention, applicability and is matched It sets.On the contrary, detailed explanation of the embodiments can be implemented by those skilled in the art.It will be understood that without departing from appended power In the case of the spirit and scope of the invention that sharp claim determines, changes and modifications may be made to details.

Claims (10)

1. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status, for appointing to project of transmitting and converting electricity construction Business progress status carries out three-dimensional display and management control, it is characterised in that:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model is associated with construction schedule, is formed defeated Power transformation engineering construction speed threedimensional model;
Step 5, actual progress is compared by the actual progress of typing engineering construction with construction schedule, to the defeated change Project of transmitting and converting electricity construction task in electrical engineering construction speed threedimensional model carries out colored indicator according to the color identifier table, closes Join and reflect current construction speed state, shows completing or carry out according to plan and that there are progresses is inclined with plan to distinguish The task of difference.
2. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1, In, the project of transmitting and converting electricity construction task in the project of transmitting and converting electricity construction speed threedimensional model is according to the color identifier Table carries out colored indicator, specifically includes: respectively using construction schedule beginning and ending time and practical beginning and ending time as foundation, described Mark is completed task, does not complete task, carrying out respectively in different colors on project of transmitting and converting electricity construction speed threedimensional model Task.
3. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1, In, the project of transmitting and converting electricity construction speed threedimensional model further includes progress back track function, and the progress backtracking is any for checking The construction task progress on date.
4. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1, In, step 3 is established project of transmitting and converting electricity threedimensional model, is specifically included according to two-dimentional construction drawing using modeling technique:
Step 3-1: from gathering project element on the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing;
Step 3-3: it is three-dimensional just to generate project of transmitting and converting electricity construction by 3 d modeling software for the engineering factor after choosing filtering optimization Beginning model;
Step 3-4: collision detection is carried out to the three-dimensional initial model of project of transmitting and converting electricity construction and three-dimensional drawing school is careful, and is carried out Image rendering obtains final project of transmitting and converting electricity threedimensional model.
5. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 4, In, the engineering factor includes characteristic point, Eigenvector, project of transmitting and converting electricity construction plan, sectional view, engineering height etc..
6. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 5, In, step 3-2: carrying out element filtering optimization to the engineering factor of the two-dimentional construction drawing, excellent including the filtering to characteristic point Change, and the filtering of Eigenvector is optimized.
7. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 6, In, the filtering optimization to characteristic point specifically includes:
Step 3-2-1 extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, feature is carried out Point sampling;
It is empty to obtain the closure that existing characteristic point is constituted on each dimension direction in characteristic point sampling process by step 3-2-2 Between, it is desirable that new characteristic point cannot be fallen into these closed spaces;
Feature point set C is added in existing characteristic point by step 3-2-3P
Step 3-2-4, by original design SPACE V0Subtract that existing characteristic point in feature point set constitutes on each dimension direction closes Space is closed, filtered free time design space V is obtained1
Step 3-2-5, idle design space V after filtration1It is middle to generate a large amount of random point;
These are located at free time design space V by step 3-2-61On random point be mapped to original design SPACE V0
Step 3-2-7 calculates the space length between random point and existing characteristic point, selects certain amount space filling properties most Excellent random point is as random character point set CPR
Step 3-2-8 identifies random character point set CPRIn area of feasible solutions where each random point, along searching in these areas of feasible solutions Rope boundary line scans for, and obtains a series of alternative features points, and for each random point, selection does not fall within existing characteristic point wherein Feature point set C is added as new characteristic point in the optimal solution of the closed space of compositionP
Step 3-2-9, checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 to 2-9 is repeated.
8. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 7, In, the termination condition of the algorithm is the granularity requirements of scheduled characteristic point number or threedimensional model.
9. a kind of threedimensional model mark side of project of transmitting and converting electricity construction task progress status according to one of claim 6-8 Method, wherein the filtering to Eigenvector optimizes, and specifically includes:
Step 3-2-1 ' extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, carry out special Levy line segment sampling;
Step 3-2-2 ' obtains existing Eigenvector and is closed by what it was constituted in the plane in Eigenvector sampling process Close plane, it is desirable that new Eigenvector cannot be fallen into these closure planes;
Eigenvector collection C is added in existing Eigenvector by step 3-2-3 'L
Step 3-2-4 ', judging characteristic line-segment sets CLIn closing of whether may make up of the closure plane that is constituted of existing Eigenvector Space is closed, if it is not, then continuing Eigenvector sampling;If it is, it is empty to obtain the closure being made of existing closure plane Between;
Step 3-2-5 ', by original design SPACE V0The closed space that existing closure plane is constituted is subtracted, the filtered free time is obtained Design space V2
Step 3-2-6 ', idle design space V after filtration2It is middle to generate a large amount of random line segment;
These are located at free time design space V by step 3-2-7 '2On random line segment be mapped to original design SPACE V0, obtain this Plane where a little random line segments, if plane and original design SPACE V where the random line segment0In it is any described existing It is closed plane to be overlapped, then deletes the random line segment, the random line segment after obtaining filtering optimization is added and updates Eigenvector collection CL
Step 3-2-8 ', checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 ' to 2- is repeated 8’。
10. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 9, In, the termination condition of the algorithm is the granularity requirements of scheduled Eigenvector number or threedimensional model.
CN201810659161.XA 2018-06-25 2018-06-25 Three-dimensional model identification method for construction task progress state of power transmission and transformation project Pending CN109146120A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810659161.XA CN109146120A (en) 2018-06-25 2018-06-25 Three-dimensional model identification method for construction task progress state of power transmission and transformation project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810659161.XA CN109146120A (en) 2018-06-25 2018-06-25 Three-dimensional model identification method for construction task progress state of power transmission and transformation project

Publications (1)

Publication Number Publication Date
CN109146120A true CN109146120A (en) 2019-01-04

Family

ID=64802254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810659161.XA Pending CN109146120A (en) 2018-06-25 2018-06-25 Three-dimensional model identification method for construction task progress state of power transmission and transformation project

Country Status (1)

Country Link
CN (1) CN109146120A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110704705A (en) * 2019-10-15 2020-01-17 中国电力企业联合会电力建设技术经济咨询中心 Method and system for displaying project progress in real time
CN111930027A (en) * 2020-10-10 2020-11-13 上海交大智邦科技有限公司 Electromechanical and hydraulic combined simulation virtual debugging method and device
CN113961281A (en) * 2021-08-13 2022-01-21 叮联信息技术有限公司 Internet-based task progress display method and device
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN117592949A (en) * 2024-01-18 2024-02-23 一智科技(成都)有限公司 Construction task management method, system and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5901252A (en) * 1991-12-11 1999-05-04 Fujitsu Limited Process and apparatus for extracting and recognizing figure elements using division into receptive fields, polar transformation, application of one-dimensional filter, and correlation between plurality of images
CN103207936A (en) * 2013-04-13 2013-07-17 大连理工大学 Sequence sampling algorithm based on space reduction strategy
CN103853867A (en) * 2013-06-08 2014-06-11 成都希盟泰克科技发展有限公司 Hydropower engineering full information MBD (model based definition) and mold building method thereof
CN104166892A (en) * 2014-06-19 2014-11-26 国家电网公司 Engineering management and control method and system based on three-dimensional design system
CN106934487A (en) * 2017-02-04 2017-07-07 国网电力科学研究院武汉南瑞有限责任公司 A kind of three dimensions of a plurality of cable lays method for optimizing route
CN107516161A (en) * 2017-08-03 2017-12-26 中国建筑第五工程局有限公司 A kind of project progress management-control method based on BIM
CN107679310A (en) * 2017-09-26 2018-02-09 华北电力大学 The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5901252A (en) * 1991-12-11 1999-05-04 Fujitsu Limited Process and apparatus for extracting and recognizing figure elements using division into receptive fields, polar transformation, application of one-dimensional filter, and correlation between plurality of images
CN103207936A (en) * 2013-04-13 2013-07-17 大连理工大学 Sequence sampling algorithm based on space reduction strategy
CN103853867A (en) * 2013-06-08 2014-06-11 成都希盟泰克科技发展有限公司 Hydropower engineering full information MBD (model based definition) and mold building method thereof
CN104166892A (en) * 2014-06-19 2014-11-26 国家电网公司 Engineering management and control method and system based on three-dimensional design system
CN106934487A (en) * 2017-02-04 2017-07-07 国网电力科学研究院武汉南瑞有限责任公司 A kind of three dimensions of a plurality of cable lays method for optimizing route
CN107516161A (en) * 2017-08-03 2017-12-26 中国建筑第五工程局有限公司 A kind of project progress management-control method based on BIM
CN107679310A (en) * 2017-09-26 2018-02-09 华北电力大学 The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
GÉZA ÓDOR 等: "Heterogeneity effects in power grid network models", 《PHYSICS SUBJECT HEADINGS》, pages 1 - 10 *
LIU, JQ 等: "Study on a Computing Technique Suitable for True 3D Modeling of Complex Geologic Bodies", 《JOURNAL OF THE GEOLOGICAL SOCIETY OF INDIA》, pages 570 - 574 *
李东亮 等: "电网工程设计三维地理信息***应用探讨", 《能源技术经济》, vol. 22, no. 3, pages 40 - 44 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110704705A (en) * 2019-10-15 2020-01-17 中国电力企业联合会电力建设技术经济咨询中心 Method and system for displaying project progress in real time
CN111930027A (en) * 2020-10-10 2020-11-13 上海交大智邦科技有限公司 Electromechanical and hydraulic combined simulation virtual debugging method and device
CN113961281A (en) * 2021-08-13 2022-01-21 叮联信息技术有限公司 Internet-based task progress display method and device
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN115526739B (en) * 2022-09-16 2023-06-30 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN117592949A (en) * 2024-01-18 2024-02-23 一智科技(成都)有限公司 Construction task management method, system and storage medium
CN117592949B (en) * 2024-01-18 2024-06-11 一智科技(成都)有限公司 Construction task management method, system and storage medium

Similar Documents

Publication Publication Date Title
CN109146120A (en) Three-dimensional model identification method for construction task progress state of power transmission and transformation project
CN112651059A (en) Multi-scheme generation method for urban design of control and regulation land based on artificial intelligence
CN112085840B (en) Semantic segmentation method, semantic segmentation device, semantic segmentation equipment and computer readable storage medium
Sofia et al. Mobile mapping, machine learning and digital twin for road infrastructure monitoring and maintenance: Case study of mohammed VI bridge in Morocco
CN110517487B (en) Urban area traffic resource regulation and control method and system based on thermodynamic diagram change identification
Liu Three-dimensional visualized urban landscape planning and design based on virtual reality technology
CN111553963B (en) Meta-grid generation method and device based on geographic information
CN107679310A (en) The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology
CN110322564B (en) Three-dimensional model construction method suitable for VR/AR transformer substation operation environment
CN105718643A (en) Optimization view angle based ship production design drawing-inspection device implementation method
CN107464064A (en) Project Management System platform based on BIM network technologies
CN113449355A (en) Building house type graph automatic generation method based on artificial intelligence
CN110990919A (en) Three-dimensional GIS route selection design analysis method for urban rail transit
CN113722797A (en) Lightweight BIM prefabricated part full life cycle comprehensive information management system
CN113269875A (en) Building design scheme evaluation method and system based on virtual-real fusion of real scene and simulation three-dimensional model and storage medium
CN109034736A (en) Project management system and operating platform based on BIM
CN112256815A (en) Three-dimensional planning auxiliary examination and approval system and method
CN115757604A (en) GDP (generalized projection) space-time evolution analysis method based on noctilucent image data
Francis The chronographical approach for construction project modelling
CN109712241A (en) A kind of method for building up of the three-dimensional mine physical model comprising goaf
CN109493425A (en) A kind of method for building up of mine three-dimensional goaf physical model
CN113971721A (en) Lightweight characterization method for digital twins of substation equipment
CN116341064B (en) Modeling system and method of intelligent substation cloud system based on 3DMax modeling
CN113177086B (en) Three-dimensional visualization method applied to intelligent operation and maintenance system of transformer substation
Nagrodzka-Godycka et al. Method of selective fading as a educational tool to study the behaviour of prestressed concrete elements under excess loading

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination