CN109146120A - Three-dimensional model identification method for construction task progress state of power transmission and transformation project - Google Patents
Three-dimensional model identification method for construction task progress state of power transmission and transformation project Download PDFInfo
- Publication number
- CN109146120A CN109146120A CN201810659161.XA CN201810659161A CN109146120A CN 109146120 A CN109146120 A CN 109146120A CN 201810659161 A CN201810659161 A CN 201810659161A CN 109146120 A CN109146120 A CN 109146120A
- Authority
- CN
- China
- Prior art keywords
- project
- transmitting
- construction
- converting electricity
- threedimensional model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 113
- 238000000034 method Methods 0.000 title claims abstract description 33
- 230000009466 transformation Effects 0.000 title claims abstract 4
- 230000005540 biological transmission Effects 0.000 title abstract 3
- 238000013461 design Methods 0.000 claims abstract description 42
- 239000003086 colorant Substances 0.000 claims abstract description 3
- 230000005611 electricity Effects 0.000 claims description 67
- 238000001914 filtration Methods 0.000 claims description 29
- 238000005457 optimization Methods 0.000 claims description 16
- 238000005070 sampling Methods 0.000 claims description 14
- 238000004422 calculation algorithm Methods 0.000 claims description 10
- 239000000284 extract Substances 0.000 claims description 4
- 238000001514 detection method Methods 0.000 claims description 2
- 239000000203 mixture Substances 0.000 claims description 2
- 238000009877 rendering Methods 0.000 claims description 2
- 238000004870 electrical engineering Methods 0.000 claims 1
- 238000004088 simulation Methods 0.000 abstract description 4
- 230000000007 visual effect Effects 0.000 abstract 2
- 238000011160 research Methods 0.000 abstract 1
- 238000004364 calculation method Methods 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 6
- 238000007726 management method Methods 0.000 description 4
- 238000013459 approach Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 239000004744 fabric Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000035800 maturation Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Geometry (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Game Theory and Decision Science (AREA)
- Computer Hardware Design (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- Computer Graphics (AREA)
- Primary Health Care (AREA)
- Educational Administration (AREA)
- Biodiversity & Conservation Biology (AREA)
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Software Systems (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- General Health & Medical Sciences (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a three-dimensional model identification method for a construction task progress state of a power transmission and transformation project, which is based on three-dimensional design results, researches a three-dimensional expression mode for simulating construction progress according to construction plan progress arrangement, and shows plan progress, actual progress, and plan progress and actual progress deviation conditions of a construction site. The model is driven to change according to the construction progress data, the construction process from the absence to the existence of the construction site is truly simulated, the visual simulation of the construction progress is realized, and the management and control of the construction progress of the power transmission and transformation project are realized. According to the method, the model is marked with different colors according to the progress of different tasks, and the supervision can check the current task attribute according to the model color, so that the progress management is more visual, and the progress check is more convenient.
Description
Technical field
The present invention relates to converting electricity fields, more particularly, to the three of a kind of project of transmitting and converting electricity construction task progress status
Dimension module identification method.
Background technique
Country's three-dimensional visualization is applied at present and the construction project time management of engineering project is applied gradually in terms of architectural engineering
Maturation, in the prior art, although these methods are for a certain specific there is also some construction project time management methods
The solution of architectural engineering customization, it is also fewer in the application of electricity transmitting and converting construction engineering, especially to project of transmitting and converting electricity
The construction speed simulation control aspect of work progress.
Summary of the invention
For existing defect or deficiency, the present invention provides a kind of three-dimensionals of project of transmitting and converting electricity construction task progress status
Model identification method, for carrying out three-dimensional display and management control to project of transmitting and converting electricity construction task progress status, comprising:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model are associated with construction schedule, shape
At project of transmitting and converting electricity construction speed threedimensional model;
Step 5, actual progress is compared, to described by the actual progress of typing engineering construction with construction schedule
Project of transmitting and converting electricity construction task in project of transmitting and converting electricity construction speed threedimensional model carries out colour code according to the color identifier table
Know, be associated with and reflect current construction speed state, to distinguish that displaying is completed or carried out according to plan and exist with plan
The task of schedule variance.
The beneficial effects of the present invention are firstly, being directed to current status, we are based on construction speed emulation and three-dimensional visible
Change technology construction simulation progress can send out three-dimensional artificial feature well.It, can be in the mode of 3 D stereo again by system demonstration
Under to entire work progress carry out Schedule monitoring.Secondly, drawing can be illustrated not complete, size marking contradiction etc. by unit in charge of construction
The problem of can not constructing caused by factor, is resolved, it is ensured that accomplish in construction rational technology, material are qualified, operation is correct,
Securely and reliably.Finally, for the generation of threedimensional model, levels of precision depends on constructing the quality of the sample set of the model, multiple
Miscellaneous project of transmitting and converting electricity design problem, Modeling Calculation be it is very time-consuming, search for optimal design parameters when, it is either traditional
Optimization algorithm or heuritic approach based on gradient information will carry out multiple iterative calculation.And the present invention is before modeling
Element filtering optimization has been carried out in advance, and the element after selection filtering optimization is modeled, so that Modeling Calculation amount is small, again maximum
The model that can guarantee precision of prediction in degree, to replace the numerical value of time-consuming actual physical amount during Modeling and Design, with
Improve design efficiency.Especially, characteristic point filtering and Eigenvector filtering proposed by the present invention, very well satisfy following two
A characteristic: first, space filling properties: all sample points are full of entire design space as much as possible, to capture as far as possible
More information about model;And second, projection property: in lower dimensional space, the projection of sample point uniformly divides as much as possible
Cloth avoids the occurrence of overlapping.
Detailed description of the invention
Method flow frame Fig. 1 proposed by the invention.
Specific embodiment
For a better understanding of the present invention, with reference to the description of the embodiment of the accompanying drawings, method of the invention is carried out
Further instruction.
In order to fully understand the present invention, numerous details are referred in the following detailed description.But art technology
Personnel are it should be understood that the present invention may not need these details and realize.In embodiment, it is not described in detail well known side
Method, process, component, in order to avoid unnecessarily make embodiment cumbersome.
It is shown in Figure 1, a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status of the invention,
For carrying out three-dimensional display and management control to project of transmitting and converting electricity construction task progress status, it is characterised in that:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model are associated with construction schedule, shape
At project of transmitting and converting electricity construction speed threedimensional model;
Step 5, actual progress is compared, to described by the actual progress of typing engineering construction with construction schedule
Project of transmitting and converting electricity construction task in project of transmitting and converting electricity construction speed threedimensional model carries out colour code according to the color identifier table
Know, be associated with and reflect current construction speed state, to distinguish that displaying is completed or carried out according to plan and exist with plan
The task of schedule variance.
Wherein, the project of transmitting and converting electricity construction task in the project of transmitting and converting electricity construction speed threedimensional model is according to institute
It states color identifier table and carries out colored indicator, specifically include: being with construction schedule beginning and ending time and practical beginning and ending time respectively
Foundation, mark is completed task, does not complete and appoint respectively in different colors on the project of transmitting and converting electricity construction speed threedimensional model
Business, ongoing task.
Wherein, the project of transmitting and converting electricity construction speed threedimensional model further includes progress back track function, and the progress backtracking is used
In the construction task progress for checking any date.
Wherein, the two-dimentional construction drawing of step 3, foundation establishes project of transmitting and converting electricity threedimensional model, specifically using modeling technique
Include:
Step 3-1: from gathering project element on the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing;
Step 3-3: the engineering factor after choosing filtering optimization generates project of transmitting and converting electricity construction three by 3 d modeling software
Tie up initial model;
Step 3-4: carrying out collision detection to the three-dimensional initial model of project of transmitting and converting electricity construction and three-dimensional drawing school be careful, and
Image rendering is carried out, final project of transmitting and converting electricity threedimensional model is obtained;
Wherein, the engineering factor includes characteristic point, Eigenvector, project of transmitting and converting electricity construction plan, sectional view, engineering
Height etc..
Wherein, step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing, including to feature
The filtering optimization of point, and the filtering of Eigenvector is optimized.
Wherein, the filtering optimization to characteristic point specifically includes:
Step 3-2-1 extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, carry out
Feature point sampling;
Step 3-2-2 obtains the closure that existing characteristic point is constituted on each dimension direction in characteristic point sampling process
Space, it is desirable that new characteristic point cannot be fallen into these closed spaces;The form of closed space is varied, art technology
Personnel can design according to actual needs.For example, it may be certain length is that the sphere of radius is empty using characteristic point as the centre of sphere
Between, it is also possible to centered on characteristic point, certain length is the cubic space of side length, and certain length can be according to feature
Number or sparse requirement or model granularity requirements etc. is put to determine.The Eigenvector that closed space expression newly samples cannot be fallen
Enter meaning therein.
Feature point set C is added in existing characteristic point by step 3-2-3P;
Step 3-2-4, by original design SPACE V0Subtract existing characteristic point structure on each dimension direction in feature point set
At closed space, obtain filtered free time design space V1;
Step 3-2-5, idle design space V after filtration1It is middle to generate a large amount of random point;
These are located at free time design space V by step 3-2-61On random point be mapped to original design SPACE V0;
Step 3-2-7 calculates the space length between random point and existing characteristic point, selects the filling of certain amount space special
The optimal random point of property is as random character point set CPR;
Step 3-2-8 identifies random character point set CPRIn area of feasible solutions where each random point, in these areas of feasible solutions
It is scanned for along search boundary line, obtains a series of alternative features points, for each random point, selection does not fall within wherein existing
Feature point set C is added as new characteristic point in the optimal solution for the closed space that characteristic point is constitutedP;
Step 3-2-9, checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 to 2- is repeated
9。
Wherein, the termination condition of the algorithm is the granularity requirements of scheduled characteristic point number or threedimensional model.
Wherein, the filtering to Eigenvector optimizes, and specifically includes:
Step 3-2-1 ' extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, into
The sampling of row Eigenvector;
Step 3-2-2 ' obtains existing Eigenvector and is made of in the plane it in Eigenvector sampling process
Closure plane, it is desirable that new Eigenvector cannot fall into these closure planes in;The characteristic curve that closure plane expression newly samples
Duan Buneng falls into meaning therein.
Eigenvector collection C is added in existing Eigenvector by step 3-2-3 'L;
Step 3-2-4 ', judging characteristic line-segment sets CLIn the closure plane that is constituted of existing Eigenvector whether may make up
Closed space, if it is not, then continue Eigenvector sampling;It is closed if it is, obtaining by what existing closure plane was constituted
Close space;The requirement for the closed space that whether may make up is varied, and those skilled in the art can set according to actual needs
Meter.For example, can require just to may be constructed a specific closure when six intersecting planes for having cube as building
Space may also require that the space of composition is not necessarily cube, for example can have the two of mutual relative tilt out of square
A face, if require the intersection of multiple planes to may make up enclosure space, be considered as reaching wanting for the closed space that may make up
It asks.The Eigenvector that closed space expression newly samples cannot fall into meaning therein.
Step 3-2-5 ', by original design SPACE V0The closed space that existing closure plane is constituted is subtracted, after obtaining filtering
Idle design space V2;
Step 3-2-6 ', idle design space V after filtration2It is middle to generate a large amount of random line segment;
These are located at free time design space V by step 3-2-7 '2On random line segment be mapped to original design SPACE V0, obtain
The plane where these random line segments is taken, if the plane where the random line segment and original design SPACE V0In any institute
It states existing closure plane to be overlapped, then deletes the random line segment, obtain the random line segment after filtering optimizes, addition and more new feature
Line-segment sets CL;
Step 3-2-8 ', checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 ' is repeated extremely
2-8’。
Wherein, the termination condition of the algorithm is the granularity requirements of scheduled Eigenvector number or threedimensional model.
The beneficial effects of the present invention are firstly, being directed to current status, we are based on construction speed emulation and three-dimensional visible
Change technology construction simulation progress can send out three-dimensional artificial feature well.It, can be in the mode of 3 D stereo again by system demonstration
Under to entire work progress carry out Schedule monitoring.Secondly, drawing can be illustrated not complete, size marking contradiction etc. by unit in charge of construction
The problem of can not constructing caused by factor, is resolved, it is ensured that accomplish in construction rational technology, material are qualified, operation is correct,
Securely and reliably.Finally, for the generation of threedimensional model, levels of precision depends on constructing the quality of the sample set of the model, multiple
Miscellaneous project of transmitting and converting electricity design problem, Modeling Calculation be it is very time-consuming, search for optimal design parameters when, it is either traditional
Optimization algorithm or heuritic approach based on gradient information will carry out multiple iterative calculation.And the present invention is before modeling
Element filtering optimization has been carried out in advance, and the element after selection filtering optimization is modeled, so that Modeling Calculation amount is small, again maximum
The model that can guarantee precision of prediction in degree, to replace the numerical value of time-consuming actual physical amount during Modeling and Design, with
Improve design efficiency.Especially, characteristic point filtering and Eigenvector filtering proposed by the present invention, very well satisfy following two
A characteristic: first, space filling properties: all sample points are full of entire design space as much as possible, to capture as far as possible
More information about model;And second, projection property: in lower dimensional space, the projection of sample point uniformly divides as much as possible
Cloth avoids the occurrence of overlapping.
Here the preferred embodiment of the present invention is only illustrated, but its meaning is not intended to limit the scope of the invention, applicability and is matched
It sets.On the contrary, detailed explanation of the embodiments can be implemented by those skilled in the art.It will be understood that without departing from appended power
In the case of the spirit and scope of the invention that sharp claim determines, changes and modifications may be made to details.
Claims (10)
1. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status, for appointing to project of transmitting and converting electricity construction
Business progress status carries out three-dimensional display and management control, it is characterised in that:
Step 1, according to project of transmitting and converting electricity construction task, establish the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 2, according to project of transmitting and converting electricity construction task, work out project of transmitting and converting electricity construction task progress color identifier table;
Step 3 establishes project of transmitting and converting electricity threedimensional model using modeling technique according to two-dimentional construction drawing;
Step 4, establishment construction schedule, the project of transmitting and converting electricity threedimensional model is associated with construction schedule, is formed defeated
Power transformation engineering construction speed threedimensional model;
Step 5, actual progress is compared by the actual progress of typing engineering construction with construction schedule, to the defeated change
Project of transmitting and converting electricity construction task in electrical engineering construction speed threedimensional model carries out colored indicator according to the color identifier table, closes
Join and reflect current construction speed state, shows completing or carry out according to plan and that there are progresses is inclined with plan to distinguish
The task of difference.
2. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1,
In, the project of transmitting and converting electricity construction task in the project of transmitting and converting electricity construction speed threedimensional model is according to the color identifier
Table carries out colored indicator, specifically includes: respectively using construction schedule beginning and ending time and practical beginning and ending time as foundation, described
Mark is completed task, does not complete task, carrying out respectively in different colors on project of transmitting and converting electricity construction speed threedimensional model
Task.
3. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1,
In, the project of transmitting and converting electricity construction speed threedimensional model further includes progress back track function, and the progress backtracking is any for checking
The construction task progress on date.
4. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 1,
In, step 3 is established project of transmitting and converting electricity threedimensional model, is specifically included according to two-dimentional construction drawing using modeling technique:
Step 3-1: from gathering project element on the two-dimentional construction drawing of project of transmitting and converting electricity construction task;
Step 3-2: element filtering optimization is carried out to the engineering factor of the two-dimentional construction drawing;
Step 3-3: it is three-dimensional just to generate project of transmitting and converting electricity construction by 3 d modeling software for the engineering factor after choosing filtering optimization
Beginning model;
Step 3-4: collision detection is carried out to the three-dimensional initial model of project of transmitting and converting electricity construction and three-dimensional drawing school is careful, and is carried out
Image rendering obtains final project of transmitting and converting electricity threedimensional model.
5. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 4,
In, the engineering factor includes characteristic point, Eigenvector, project of transmitting and converting electricity construction plan, sectional view, engineering height etc..
6. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 5,
In, step 3-2: carrying out element filtering optimization to the engineering factor of the two-dimentional construction drawing, excellent including the filtering to characteristic point
Change, and the filtering of Eigenvector is optimized.
7. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 6,
In, the filtering optimization to characteristic point specifically includes:
Step 3-2-1 extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, feature is carried out
Point sampling;
It is empty to obtain the closure that existing characteristic point is constituted on each dimension direction in characteristic point sampling process by step 3-2-2
Between, it is desirable that new characteristic point cannot be fallen into these closed spaces;
Feature point set C is added in existing characteristic point by step 3-2-3P;
Step 3-2-4, by original design SPACE V0Subtract that existing characteristic point in feature point set constitutes on each dimension direction closes
Space is closed, filtered free time design space V is obtained1;
Step 3-2-5, idle design space V after filtration1It is middle to generate a large amount of random point;
These are located at free time design space V by step 3-2-61On random point be mapped to original design SPACE V0;
Step 3-2-7 calculates the space length between random point and existing characteristic point, selects certain amount space filling properties most
Excellent random point is as random character point set CPR;
Step 3-2-8 identifies random character point set CPRIn area of feasible solutions where each random point, along searching in these areas of feasible solutions
Rope boundary line scans for, and obtains a series of alternative features points, and for each random point, selection does not fall within existing characteristic point wherein
Feature point set C is added as new characteristic point in the optimal solution of the closed space of compositionP;
Step 3-2-9, checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 to 2-9 is repeated.
8. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 7,
In, the termination condition of the algorithm is the granularity requirements of scheduled characteristic point number or threedimensional model.
9. a kind of threedimensional model mark side of project of transmitting and converting electricity construction task progress status according to one of claim 6-8
Method, wherein the filtering to Eigenvector optimizes, and specifically includes:
Step 3-2-1 ' extracts the original design SPACE V of two-dimentional construction drawing0, in original design SPACE V0In range, carry out special
Levy line segment sampling;
Step 3-2-2 ' obtains existing Eigenvector and is closed by what it was constituted in the plane in Eigenvector sampling process
Close plane, it is desirable that new Eigenvector cannot be fallen into these closure planes;
Eigenvector collection C is added in existing Eigenvector by step 3-2-3 'L;
Step 3-2-4 ', judging characteristic line-segment sets CLIn closing of whether may make up of the closure plane that is constituted of existing Eigenvector
Space is closed, if it is not, then continuing Eigenvector sampling;If it is, it is empty to obtain the closure being made of existing closure plane
Between;
Step 3-2-5 ', by original design SPACE V0The closed space that existing closure plane is constituted is subtracted, the filtered free time is obtained
Design space V2;
Step 3-2-6 ', idle design space V after filtration2It is middle to generate a large amount of random line segment;
These are located at free time design space V by step 3-2-7 '2On random line segment be mapped to original design SPACE V0, obtain this
Plane where a little random line segments, if plane and original design SPACE V where the random line segment0In it is any described existing
It is closed plane to be overlapped, then deletes the random line segment, the random line segment after obtaining filtering optimization is added and updates Eigenvector collection
CL;
Step 3-2-8 ', checks whether algorithm reaches termination condition, if so, sampling terminates;Otherwise, step 2-4 ' to 2- is repeated
8’。
10. a kind of threedimensional model identification method of project of transmitting and converting electricity construction task progress status according to claim 9,
In, the termination condition of the algorithm is the granularity requirements of scheduled Eigenvector number or threedimensional model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810659161.XA CN109146120A (en) | 2018-06-25 | 2018-06-25 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810659161.XA CN109146120A (en) | 2018-06-25 | 2018-06-25 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109146120A true CN109146120A (en) | 2019-01-04 |
Family
ID=64802254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810659161.XA Pending CN109146120A (en) | 2018-06-25 | 2018-06-25 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109146120A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110704705A (en) * | 2019-10-15 | 2020-01-17 | 中国电力企业联合会电力建设技术经济咨询中心 | Method and system for displaying project progress in real time |
CN111930027A (en) * | 2020-10-10 | 2020-11-13 | 上海交大智邦科技有限公司 | Electromechanical and hydraulic combined simulation virtual debugging method and device |
CN113961281A (en) * | 2021-08-13 | 2022-01-21 | 叮联信息技术有限公司 | Internet-based task progress display method and device |
CN115526739A (en) * | 2022-09-16 | 2022-12-27 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN115878872A (en) * | 2023-02-08 | 2023-03-31 | 一智科技(成都)有限公司 | Construction progress visualization method and system |
CN117592949A (en) * | 2024-01-18 | 2024-02-23 | 一智科技(成都)有限公司 | Construction task management method, system and storage medium |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5901252A (en) * | 1991-12-11 | 1999-05-04 | Fujitsu Limited | Process and apparatus for extracting and recognizing figure elements using division into receptive fields, polar transformation, application of one-dimensional filter, and correlation between plurality of images |
CN103207936A (en) * | 2013-04-13 | 2013-07-17 | 大连理工大学 | Sequence sampling algorithm based on space reduction strategy |
CN103853867A (en) * | 2013-06-08 | 2014-06-11 | 成都希盟泰克科技发展有限公司 | Hydropower engineering full information MBD (model based definition) and mold building method thereof |
CN104166892A (en) * | 2014-06-19 | 2014-11-26 | 国家电网公司 | Engineering management and control method and system based on three-dimensional design system |
CN106934487A (en) * | 2017-02-04 | 2017-07-07 | 国网电力科学研究院武汉南瑞有限责任公司 | A kind of three dimensions of a plurality of cable lays method for optimizing route |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN107679310A (en) * | 2017-09-26 | 2018-02-09 | 华北电力大学 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
-
2018
- 2018-06-25 CN CN201810659161.XA patent/CN109146120A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5901252A (en) * | 1991-12-11 | 1999-05-04 | Fujitsu Limited | Process and apparatus for extracting and recognizing figure elements using division into receptive fields, polar transformation, application of one-dimensional filter, and correlation between plurality of images |
CN103207936A (en) * | 2013-04-13 | 2013-07-17 | 大连理工大学 | Sequence sampling algorithm based on space reduction strategy |
CN103853867A (en) * | 2013-06-08 | 2014-06-11 | 成都希盟泰克科技发展有限公司 | Hydropower engineering full information MBD (model based definition) and mold building method thereof |
CN104166892A (en) * | 2014-06-19 | 2014-11-26 | 国家电网公司 | Engineering management and control method and system based on three-dimensional design system |
CN106934487A (en) * | 2017-02-04 | 2017-07-07 | 国网电力科学研究院武汉南瑞有限责任公司 | A kind of three dimensions of a plurality of cable lays method for optimizing route |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN107679310A (en) * | 2017-09-26 | 2018-02-09 | 华北电力大学 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
Non-Patent Citations (3)
Title |
---|
GÉZA ÓDOR 等: "Heterogeneity effects in power grid network models", 《PHYSICS SUBJECT HEADINGS》, pages 1 - 10 * |
LIU, JQ 等: "Study on a Computing Technique Suitable for True 3D Modeling of Complex Geologic Bodies", 《JOURNAL OF THE GEOLOGICAL SOCIETY OF INDIA》, pages 570 - 574 * |
李东亮 等: "电网工程设计三维地理信息***应用探讨", 《能源技术经济》, vol. 22, no. 3, pages 40 - 44 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110704705A (en) * | 2019-10-15 | 2020-01-17 | 中国电力企业联合会电力建设技术经济咨询中心 | Method and system for displaying project progress in real time |
CN111930027A (en) * | 2020-10-10 | 2020-11-13 | 上海交大智邦科技有限公司 | Electromechanical and hydraulic combined simulation virtual debugging method and device |
CN113961281A (en) * | 2021-08-13 | 2022-01-21 | 叮联信息技术有限公司 | Internet-based task progress display method and device |
CN115526739A (en) * | 2022-09-16 | 2022-12-27 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN115526739B (en) * | 2022-09-16 | 2023-06-30 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN115878872A (en) * | 2023-02-08 | 2023-03-31 | 一智科技(成都)有限公司 | Construction progress visualization method and system |
CN117592949A (en) * | 2024-01-18 | 2024-02-23 | 一智科技(成都)有限公司 | Construction task management method, system and storage medium |
CN117592949B (en) * | 2024-01-18 | 2024-06-11 | 一智科技(成都)有限公司 | Construction task management method, system and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109146120A (en) | Three-dimensional model identification method for construction task progress state of power transmission and transformation project | |
CN112651059A (en) | Multi-scheme generation method for urban design of control and regulation land based on artificial intelligence | |
CN112085840B (en) | Semantic segmentation method, semantic segmentation device, semantic segmentation equipment and computer readable storage medium | |
Sofia et al. | Mobile mapping, machine learning and digital twin for road infrastructure monitoring and maintenance: Case study of mohammed VI bridge in Morocco | |
CN110517487B (en) | Urban area traffic resource regulation and control method and system based on thermodynamic diagram change identification | |
Liu | Three-dimensional visualized urban landscape planning and design based on virtual reality technology | |
CN111553963B (en) | Meta-grid generation method and device based on geographic information | |
CN107679310A (en) | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology | |
CN110322564B (en) | Three-dimensional model construction method suitable for VR/AR transformer substation operation environment | |
CN105718643A (en) | Optimization view angle based ship production design drawing-inspection device implementation method | |
CN107464064A (en) | Project Management System platform based on BIM network technologies | |
CN113449355A (en) | Building house type graph automatic generation method based on artificial intelligence | |
CN110990919A (en) | Three-dimensional GIS route selection design analysis method for urban rail transit | |
CN113722797A (en) | Lightweight BIM prefabricated part full life cycle comprehensive information management system | |
CN113269875A (en) | Building design scheme evaluation method and system based on virtual-real fusion of real scene and simulation three-dimensional model and storage medium | |
CN109034736A (en) | Project management system and operating platform based on BIM | |
CN112256815A (en) | Three-dimensional planning auxiliary examination and approval system and method | |
CN115757604A (en) | GDP (generalized projection) space-time evolution analysis method based on noctilucent image data | |
Francis | The chronographical approach for construction project modelling | |
CN109712241A (en) | A kind of method for building up of the three-dimensional mine physical model comprising goaf | |
CN109493425A (en) | A kind of method for building up of mine three-dimensional goaf physical model | |
CN113971721A (en) | Lightweight characterization method for digital twins of substation equipment | |
CN116341064B (en) | Modeling system and method of intelligent substation cloud system based on 3DMax modeling | |
CN113177086B (en) | Three-dimensional visualization method applied to intelligent operation and maintenance system of transformer substation | |
Nagrodzka-Godycka et al. | Method of selective fading as a educational tool to study the behaviour of prestressed concrete elements under excess loading |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |