CN107679310A - The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology - Google Patents
The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology Download PDFInfo
- Publication number
- CN107679310A CN107679310A CN201710884562.0A CN201710884562A CN107679310A CN 107679310 A CN107679310 A CN 107679310A CN 201710884562 A CN201710884562 A CN 201710884562A CN 107679310 A CN107679310 A CN 107679310A
- Authority
- CN
- China
- Prior art keywords
- construction
- engineering
- bim
- real
- progress
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Theoretical Computer Science (AREA)
- Mathematical Optimization (AREA)
- Computational Mathematics (AREA)
- Architecture (AREA)
- Mathematical Analysis (AREA)
- Structural Engineering (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Processing Or Creating Images (AREA)
Abstract
The invention discloses a kind of real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology, this method is first with BIM technology, the image collected according to engineering construction figure, project construction schedule and job site, 3 D stereo simulation model is established respectively, then, image that progress model and actual progress model obtain is intended to being laminated conjunction using image congruencing technology, contrasted by different color with layer, the associated schedule parameter such as departure of progress is drawn, realizes the 3 D stereo displaying of the real-time progress of engineering.This method have the advantage that:It is available for projects participant intuitively to obtain real-time 3 D stereo visualization construction speed information in 3D view environments.
Description
Technical field
The invention belongs to the display technique of construction project construction speed, in particular it relates to be based on BIM and image congruencing
The real-time progress 3 D stereo methods of exhibiting of engineering of technology.
Background technology
In existing construction project progress display method, engineering staff is usually to pass through collection with the mode of gunter drawing
Real data shows job site progress, and this methods of exhibiting compares planarization and not directly perceived, and layman also is difficult to quickly
Understand the progress status that gunter drawing is shown, particularly when in face of participate in unit it is more, scope is big, long in time limit, and construction organization process is answered
During miscellaneous large-scale and super-huge construction project, existing methods of exhibiting can not clearly describe construction project progress shape
Condition, it can not also meet the progress control requirement of present large-scale engineering construction project.
BIM is the multidimensional model Technique of Information Integration to grow up in the technical foundation such as CAD (CAD),
It is to architectural engineering physical features and the digitlization carrying of functional characteristic information and Visualization.At present, BIM is because it is visual
The huge advantage that change, harmony, optimization property etc. have, and the building engineering field in the whole world is approved by numerous professionals
And receiving.But existing BIM technology is used for obtaining the three-dimensional three-dimensional real object figure displayings of BIM in the design phase, and its three-dimensional can
Also it is mainly used in that scheme early stage is weighed and interim design sketch shows depending on changing to show, and is not used to build by BIM technology
The Construction of Engineering Projects stage is in the real-time exhibition of construction speed.
The inventive method is adopted first with BIM technology according to engineering construction figure, project construction schedule and job site
The image collected, 3 D stereo simulation model is established respectively, then, using image congruencing technology in original BIM target advances mould
On the basis of type image, the image that actual progress model obtains is placed on overlapping above, is contrasted, come real with layer using different color
The real-time exhibition of existing construction speed image three-dimensional main body.
The content of the invention
The defects of for prior art, it is an object of the invention to establish one to realize that construction project construction is real
The method that Shi Jindu 3 D stereos visualize.This method is by BIM and project scheduling management instrument, method and image congruencing
The means such as technology combine, and so as to reach the real-time progress overall process of engineering construction, round-the-clock, total involvement target, promote China
Construction project progress monitoring develops, and realizes the Effec-tive Function of progress control.
To achieve the above object, the invention provides a kind of real-time progress three of engineering based on BIM and image congruencing technology
Stereo exhibition method is tieed up, is specifically comprised the following steps:
According to the construction drawing of engineering yet to be built, engineering yet to be built is built based on BIM in the construction project design phase for step 1.
3D simulation models, and all components in the model are numbered;
Quantities of the step 2. according to engineering construction tissue, the execution conditions of construction unit and construction drawing to engineering yet to be built
Calculated, and according to quantities, work out construction schedule, it is clear and definite monthly/construction task that should complete day;
Step 3. is imitated according to the construction task that monthly/day completes in construction schedule with reference to 3D constructed in step 1
True mode and respective members numbering, based on BIM by day build construction speed monthly/daily planning 3D simulation models, and by the 3D moulds
Type is stored in database by date;
Step 4. was applied by video monitoring or camera technique to engineering construction scene in the engineering construction stage
Work situation carries out collection in real time and collected, and the job site image to collecting, with reference to 3D simulation models constructed in step 1
And respective members numbering, identify the completed component information in job site;
Step 5. builds time construction speed reality according to completed component information resulting in step 4 based on BIM
When 3D simulation models;
Step 6. is put into database on the 3D simulation models of the same day plan 3D simulation models obtained in real time with stacking
Close, contrasted using different color with layer, draw the associated schedule parameter including schedule variance amount.
Further, for the ease of compartment analysis directly perceived, the line color used in BIM simulation models constructed by each step
And component color is different:Constructed model grey in step 1, the model black built in step 3, build in step 5
Model yellow, if practice of construction progress and target advance have deviation in step 6, the component beyond construction speed is by green
Represent, it should which the component for being accomplished without completing is represented by red.
Further, in step 6, for the result of progress error, related personnel should be forwarded to, analysis discussion is carried out, looks for
Go out the handling suggestion and progress adjustment scheme of feasibility.
Further, to engineering essential information before construction, in construction collection in worksite to video, in pictorial information and construction
All document information etc. all establish corresponding database and carry out classification hierarchical storage management in model and construction.Described information is deposited
Storage form includes numeral, list, picture, word and audio-visual, has both structuring and non-structured information.
Further, for the multi-modal of construction environment, appropriate long-distance transmissions mode is chosen, such as wireless, wired, local
Net and cell phone network etc., realize rear administrative decision department to the remotely-proctored of front job site, commander and management.
Compared with prior art, the beneficial effects of the invention are as follows:According to engineering construction figure, project construction schedule and apply
The picture that work collection in worksite arrives, three-dimensional simulation model is established respectively, and store in a standardized format into database, Ke Yishi
The visualization of existing construction speed, the graphical of management object and management process are intuitively changed, and are the follow-up implementation management of engineering and peace
Complete analysis provides data supporting;Using the BIM models of parametrization as central database, can great convenience to a large amount of real time information
It is managed, it is shared by each participant of project;Progress model and actual progress model are intended to conjunction is laminated, utilizes difference
Color contrasts with layer, realizes the real-time exhibition of construction speed image three-dimensional main body, clear and intuitive easily to understand, and is easy to each participant
Member's exchange, so that constructing aims are effectively ensured.
Brief description of the drawings
Fig. 1 is that the real-time progress of the engineering according to an embodiment of the invention based on BIM and image congruencing technology is three-dimensional vertical
The schematic flow sheet of body display method.
Embodiment
With reference to specific embodiment, the present invention is described in detail.Following examples will be helpful to the technology of this area
Personnel and researcher further understand the present invention, but the invention is not limited in any way.It should be pointed out that it is based on this hair
Bright embodiment, those skilled in the art and researcher obtained on the premise of creative work is not made it is all its
His embodiment, belongs to the scope of protection of the invention.
The embodiments of the invention provide a kind of real-time progress 3 D stereo displaying of engineering based on BIM and image congruencing technology
Method, as shown in figure 1, main processing steps include:
According to the construction drawing of engineering yet to be built, engineering yet to be built is built based on BIM in the construction project design phase for step 1.
3D simulation models, and all components in the model are numbered;
In order that all components obtain unique numbering code, project design and construction stage are to progress after being easy to
, it is necessary to the numbering for assigning each component should have different implications, this means that each composition in code all for analysis
Must have the function that different.In Revit2015 modeling softwares, the component of model mainly include post, beam, wall, stair, floor,
Roof, door, window, curtain wall etc., in order to keep the systematicness of the project and globality, reach code table has preferably with feature code
Uniformity, while also there is the feature of piece code, component code should be on the basis of general coding rule be followed, with reference to building
If the feature in Construction of Engineering Projects stage is encoded.As Z-1F-02-03 represents the post of second row the third line in the first floor
Son, M-B1-12-03 represent the 12nd to ranked third capable door in one layer downstairs.Wherein arrange with from south to northern number consecutively, row with from
Western number consecutively is arrived in east.
Quantities of the step 2. according to engineering construction tissue, the execution conditions of construction unit and construction drawing to engineering yet to be built
Calculated, and according to quantities, work out construction schedule, the clear and definite construction task that monthly (day) should complete;
Step 3. is according to the construction task that monthly (day) completes in construction schedule, with reference to 3D constructed in step 1
Simulation model and respective members numbering, by day building construction speed based on BIM, monthly (day) plans 3D simulation models, and by 3D moulds
Type is stored in database by date;
Step 4. was applied by video monitoring or camera technique to engineering construction scene in the engineering construction stage
Work situation carries out collection in real time and collected, and the job site image to collecting, with reference to 3D simulation models constructed in step 1
And respective members numbering, identify the completed component information in job site;
Step 5. is according to completed component information resulting in step 4, and based on BIM structures, now construction speed is real-time
3D simulation models;
Step 6. is put into database on the 3D simulation models of the same day plan 3D simulation models obtained in real time with stacking
Close, contrasted using different color with layer, draw the associated schedule parameter such as departure of progress.Specifically it is recognized that beam, plate,
The construction volume of post, wall, can draw the difference of progress by subtracting each other, and with difference than the difference ratio that upper whole project obtains,
Now progress accounts for the parameters such as the percentage of aggregate scheduling.
In addition, for the ease of compartment analysis directly perceived, line color used in BIM simulation models constructed by each step and
Component color is different:Constructed model grey in step 1, the model black built in step 3, build in step 5
Model yellow, if the practice of construction progress and target advance in step 6 have deviation, the component beyond construction speed is by green
Represent, it should which the component for being accomplished without completing is represented by red.
In addition, in step 6, for the result of progress error, related personnel should be forwarded to, analysis discussion is carried out, finds out
The handling suggestion and progress adjustment scheme of feasibility.
In addition, will to engineering essential information before construction, in construction collection in worksite to video, mould in pictorial information and construction
The corresponding database of foundation such as all document information carries out classification multi-zone supervision in type and construction.Above- mentioned information storage form bag
Numeral, list, picture, word, audio-visual etc. are included, has both structuring and non-structured information.
In addition, for the multi-modal of construction environment, appropriate long-distance transmissions mode is chosen, such as wireless, wired, LAN
Or cell phone network etc., realize rear administrative decision department to the remotely-proctored of front job site, commander and management.
Claims (5)
- A kind of 1. real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology, it is characterised in that including Following steps:Step 1. is in the construction project design phase, and according to the construction drawing of engineering yet to be built, the 3D that engineering yet to be built is built based on BIM is imitated True mode, and all components in the model are numbered;Step 2. is carried out according to engineering construction tissue, the execution conditions of construction unit and construction drawing to the quantities of engineering yet to be built Calculate, and according to quantities, work out construction schedule, it is clear and definite monthly/construction task that should complete day;Step 3. emulates mould according to the construction task that monthly/day completes in construction schedule with reference to 3D constructed in step 1 Type and respective members numbering, based on BIM by day build construction speed monthly/daily planning 3D simulation models, and the 3D models are pressed In date deposit database;Step 4. is in the engineering construction stage, the construction feelings by video monitoring or camera technique to engineering construction scene Condition carries out collection in real time and collected, and the job site image to collecting, with reference to 3D simulation models and phase constructed in step 1 Answer component to number, identify the completed component information in job site;Step 5. builds the real-time 3D of the time construction speed according to completed component information resulting in step 4 based on BIM Simulation model;Step 6. is put into the 3D simulation models obtained in real time in database on the 3D simulation models of same day plan and closed with stacking, profit Contrasted with different color with layer, draw the associated schedule parameter including schedule variance amount.
- 2. according to the method for claim 1, it is characterised in that constructed model grey in step 1, structure in step 3 The model black built, the model yellow built in step 5, if in step 6 practice of construction progress exist with target advance it is inclined Difference, the component beyond construction speed are represented by green, it should which the component for being accomplished without completing is represented by red.
- 3. according to the method for claim 1, it is characterised in that to engineering essential information before construction, collection in worksite in construction To video, all document information are all established corresponding database and classified in model and construction in pictorial information and construction Hierarchical storage management, described information storage form include numeral, list, picture, word and audio-visual, have both structuring with it is non-structural The information of change.
- 4. according to the method for claim 1, it is characterised in that for the multi-modal of construction environment, choose long-distance transmissions Mode, realize rear administrative decision department to the remotely-proctored of front job site, commander and management.
- 5. according to the method for claim 4, it is characterised in that the long-distance transmissions mode includes wireless, wired, local Net and cell phone network.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710884562.0A CN107679310A (en) | 2017-09-26 | 2017-09-26 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710884562.0A CN107679310A (en) | 2017-09-26 | 2017-09-26 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107679310A true CN107679310A (en) | 2018-02-09 |
Family
ID=61137489
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710884562.0A Pending CN107679310A (en) | 2017-09-26 | 2017-09-26 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107679310A (en) |
Cited By (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108470315A (en) * | 2018-02-11 | 2018-08-31 | 浙江联建工程设计有限公司 | Project progress monitor system based on BIM |
CN108614446A (en) * | 2018-06-22 | 2018-10-02 | 中船第九设计研究院工程有限公司 | A kind of production line digitalized artificial analysis system applied to engineering field |
CN108629310A (en) * | 2018-05-03 | 2018-10-09 | 新奥(中国)燃气投资有限公司 | A kind of engineering management measure of supervision and device |
CN109146120A (en) * | 2018-06-25 | 2019-01-04 | 国网经济技术研究院有限公司 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
CN109446716A (en) * | 2018-11-15 | 2019-03-08 | 中铁第六勘察设计院集团有限公司 | Based on BIM platform shield machine VMT and correction scheme three-dimensional display method |
CN109493006A (en) * | 2018-11-15 | 2019-03-19 | 中铁第六勘察设计院集团有限公司 | The method that project process comparison is shown based on BIM platform |
CN109710990A (en) * | 2018-12-05 | 2019-05-03 | 三峡大学 | Construction of Rolled Concrete Dam progress-cost cooperative control method based on BIM technology |
CN109829693A (en) * | 2019-01-21 | 2019-05-31 | 浙江浙东建设有限公司 | One kind being used for Construction Schedule management system and management method |
CN110008588A (en) * | 2019-04-04 | 2019-07-12 | 南京林业大学 | Multidimensional integrated highway engineering construction progress msg management system and method |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN110460819A (en) * | 2019-09-05 | 2019-11-15 | 河南城建学院 | A kind of Project Management System engineering progress data input method |
CN110704705A (en) * | 2019-10-15 | 2020-01-17 | 中国电力企业联合会电力建设技术经济咨询中心 | Method and system for displaying project progress in real time |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110956032A (en) * | 2019-12-04 | 2020-04-03 | 广联达科技股份有限公司 | Model and model matching method and device, storage medium and electronic equipment |
CN111160838A (en) * | 2018-11-07 | 2020-05-15 | 苏州微缔软件股份有限公司 | 3D visualization building project management system and method based on BIM technology |
CN111242497A (en) * | 2020-01-19 | 2020-06-05 | 深圳云联万企科技有限公司 | Construction cost management system and method based on building information model |
CN111242498A (en) * | 2020-01-19 | 2020-06-05 | 深圳云联万企科技有限公司 | Construction progress management system and management method based on building information model |
CN111260325A (en) * | 2019-07-23 | 2020-06-09 | 上海建工集团股份有限公司 | Bridge construction progress management system based on BIM |
CN111311741A (en) * | 2020-03-23 | 2020-06-19 | 重庆忽米网络科技有限公司 | 5G communication-based interactive indoor space construction device and method |
CN111432197A (en) * | 2020-03-19 | 2020-07-17 | 上海建工四建集团有限公司 | Construction monitoring method and system |
CN111460138A (en) * | 2020-03-02 | 2020-07-28 | 广州高新工程顾问有限公司 | BIM-based digital engineering supervision method and system |
CN111507595A (en) * | 2020-04-08 | 2020-08-07 | 广州高新工程顾问有限公司 | Engineering project intelligent dynamic safety supervision system based on BIM |
CN111524172A (en) * | 2020-03-30 | 2020-08-11 | 平安城市建设科技(深圳)有限公司 | Building construction progress evaluation method and device and storage medium |
CN111932201A (en) * | 2020-07-27 | 2020-11-13 | 上海地矿工程勘察有限公司 | Rail transit construction monitoring method and system, storage medium and intelligent terminal |
CN112581030A (en) * | 2020-12-29 | 2021-03-30 | 基建通(三亚)国际科技有限公司 | Bridge BIM model component level progress display method and device and storage medium |
CN112907211A (en) * | 2021-03-02 | 2021-06-04 | 惠州城际工程咨询有限公司 | BIM-based project progress supervision method, device, equipment and storage medium |
CN114005349A (en) * | 2021-11-26 | 2022-02-01 | 四川建筑职业技术学院 | Construction progress model for building engineering management |
CN115392808A (en) * | 2022-10-31 | 2022-11-25 | 长春龙佳网络科技有限公司 | Building construction prediction progress and allocation system based on deep learning |
CN115526739A (en) * | 2022-09-16 | 2022-12-27 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN116136993A (en) * | 2023-04-18 | 2023-05-19 | 临沂市罗庄区锦汇项目管理有限公司 | Multi-party management system and method for online project data |
CN116502882A (en) * | 2023-06-30 | 2023-07-28 | 杭州新中大科技股份有限公司 | Engineering progress determining method and device based on multi-mode time sequence information fusion |
CN116662439A (en) * | 2023-07-28 | 2023-08-29 | 成都数智创新精益科技有限公司 | Drilling construction progress display method and system based on GIS data |
CN117252328A (en) * | 2023-07-04 | 2023-12-19 | 南通理工学院 | Project integrated management method and system based on BIM |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140200945A1 (en) * | 2013-01-11 | 2014-07-17 | Myongji University Industry And Academia Cooperation Foundation | System and method for creating building information modeling object breakdown structure |
CN104680320A (en) * | 2014-12-03 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM-based project management system and method |
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN106096851A (en) * | 2016-06-21 | 2016-11-09 | 浙江精工钢结构集团有限公司 | A kind of structural steelwork based on BIM technology visualization acceptance method |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
CN106920049A (en) * | 2017-03-28 | 2017-07-04 | 内蒙古科技大学 | A kind of Project Management System platform based on BIM network technologies |
-
2017
- 2017-09-26 CN CN201710884562.0A patent/CN107679310A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140200945A1 (en) * | 2013-01-11 | 2014-07-17 | Myongji University Industry And Academia Cooperation Foundation | System and method for creating building information modeling object breakdown structure |
CN104680320A (en) * | 2014-12-03 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM-based project management system and method |
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN106096851A (en) * | 2016-06-21 | 2016-11-09 | 浙江精工钢结构集团有限公司 | A kind of structural steelwork based on BIM technology visualization acceptance method |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
CN106920049A (en) * | 2017-03-28 | 2017-07-04 | 内蒙古科技大学 | A kind of Project Management System platform based on BIM network technologies |
Cited By (43)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108470315B (en) * | 2018-02-11 | 2020-08-28 | 浙江联建工程设计有限公司 | BIM-based project progress supervision system |
CN108470315A (en) * | 2018-02-11 | 2018-08-31 | 浙江联建工程设计有限公司 | Project progress monitor system based on BIM |
CN108629310A (en) * | 2018-05-03 | 2018-10-09 | 新奥(中国)燃气投资有限公司 | A kind of engineering management measure of supervision and device |
CN108629310B (en) * | 2018-05-03 | 2021-03-23 | 洛阳新奥能源发展有限公司 | Engineering management supervision method and device |
CN108614446A (en) * | 2018-06-22 | 2018-10-02 | 中船第九设计研究院工程有限公司 | A kind of production line digitalized artificial analysis system applied to engineering field |
CN109146120A (en) * | 2018-06-25 | 2019-01-04 | 国网经济技术研究院有限公司 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
CN111160838A (en) * | 2018-11-07 | 2020-05-15 | 苏州微缔软件股份有限公司 | 3D visualization building project management system and method based on BIM technology |
CN109446716A (en) * | 2018-11-15 | 2019-03-08 | 中铁第六勘察设计院集团有限公司 | Based on BIM platform shield machine VMT and correction scheme three-dimensional display method |
CN109493006A (en) * | 2018-11-15 | 2019-03-19 | 中铁第六勘察设计院集团有限公司 | The method that project process comparison is shown based on BIM platform |
CN109710990A (en) * | 2018-12-05 | 2019-05-03 | 三峡大学 | Construction of Rolled Concrete Dam progress-cost cooperative control method based on BIM technology |
CN109710990B (en) * | 2018-12-05 | 2023-02-07 | 三峡大学 | BIM technology-based roller compacted concrete dam construction progress-cost cooperative control method |
CN109829693A (en) * | 2019-01-21 | 2019-05-31 | 浙江浙东建设有限公司 | One kind being used for Construction Schedule management system and management method |
CN110008588A (en) * | 2019-04-04 | 2019-07-12 | 南京林业大学 | Multidimensional integrated highway engineering construction progress msg management system and method |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN111260325A (en) * | 2019-07-23 | 2020-06-09 | 上海建工集团股份有限公司 | Bridge construction progress management system based on BIM |
CN110460819A (en) * | 2019-09-05 | 2019-11-15 | 河南城建学院 | A kind of Project Management System engineering progress data input method |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110704705A (en) * | 2019-10-15 | 2020-01-17 | 中国电力企业联合会电力建设技术经济咨询中心 | Method and system for displaying project progress in real time |
CN110956032B (en) * | 2019-12-04 | 2023-06-27 | 广联达科技股份有限公司 | Model and model pairing method and device, storage medium and electronic equipment |
CN110956032A (en) * | 2019-12-04 | 2020-04-03 | 广联达科技股份有限公司 | Model and model matching method and device, storage medium and electronic equipment |
CN111242498A (en) * | 2020-01-19 | 2020-06-05 | 深圳云联万企科技有限公司 | Construction progress management system and management method based on building information model |
CN111242497A (en) * | 2020-01-19 | 2020-06-05 | 深圳云联万企科技有限公司 | Construction cost management system and method based on building information model |
CN111460138A (en) * | 2020-03-02 | 2020-07-28 | 广州高新工程顾问有限公司 | BIM-based digital engineering supervision method and system |
CN111460138B (en) * | 2020-03-02 | 2021-05-11 | 广州高新工程顾问有限公司 | BIM-based digital engineering supervision method and system |
CN111432197A (en) * | 2020-03-19 | 2020-07-17 | 上海建工四建集团有限公司 | Construction monitoring method and system |
CN111311741A (en) * | 2020-03-23 | 2020-06-19 | 重庆忽米网络科技有限公司 | 5G communication-based interactive indoor space construction device and method |
CN111524172A (en) * | 2020-03-30 | 2020-08-11 | 平安城市建设科技(深圳)有限公司 | Building construction progress evaluation method and device and storage medium |
CN111507595A (en) * | 2020-04-08 | 2020-08-07 | 广州高新工程顾问有限公司 | Engineering project intelligent dynamic safety supervision system based on BIM |
CN111932201A (en) * | 2020-07-27 | 2020-11-13 | 上海地矿工程勘察有限公司 | Rail transit construction monitoring method and system, storage medium and intelligent terminal |
CN112581030A (en) * | 2020-12-29 | 2021-03-30 | 基建通(三亚)国际科技有限公司 | Bridge BIM model component level progress display method and device and storage medium |
CN112907211A (en) * | 2021-03-02 | 2021-06-04 | 惠州城际工程咨询有限公司 | BIM-based project progress supervision method, device, equipment and storage medium |
CN112907211B (en) * | 2021-03-02 | 2024-06-04 | 惠州城际工程咨询有限公司 | BIM-based engineering progress supervision method, device, equipment and storage medium |
CN114005349A (en) * | 2021-11-26 | 2022-02-01 | 四川建筑职业技术学院 | Construction progress model for building engineering management |
CN115526739A (en) * | 2022-09-16 | 2022-12-27 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN115526739B (en) * | 2022-09-16 | 2023-06-30 | 杭州天界数字科技有限公司 | Building engineering progress monitoring method based on BIM and machine vision |
CN115392808B (en) * | 2022-10-31 | 2023-01-13 | 长春龙佳网络科技有限公司 | Building construction prediction progress and allocation system based on deep learning |
CN115392808A (en) * | 2022-10-31 | 2022-11-25 | 长春龙佳网络科技有限公司 | Building construction prediction progress and allocation system based on deep learning |
CN116136993A (en) * | 2023-04-18 | 2023-05-19 | 临沂市罗庄区锦汇项目管理有限公司 | Multi-party management system and method for online project data |
CN116502882A (en) * | 2023-06-30 | 2023-07-28 | 杭州新中大科技股份有限公司 | Engineering progress determining method and device based on multi-mode time sequence information fusion |
CN116502882B (en) * | 2023-06-30 | 2023-10-20 | 杭州新中大科技股份有限公司 | Engineering progress determining method and device based on multi-mode time sequence information fusion |
CN117252328A (en) * | 2023-07-04 | 2023-12-19 | 南通理工学院 | Project integrated management method and system based on BIM |
CN116662439A (en) * | 2023-07-28 | 2023-08-29 | 成都数智创新精益科技有限公司 | Drilling construction progress display method and system based on GIS data |
CN116662439B (en) * | 2023-07-28 | 2023-09-29 | 成都数智创新精益科技有限公司 | Drilling construction progress display method and system based on GIS data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107679310A (en) | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology | |
Ding et al. | A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects | |
Scherer et al. | BIMification: How to create and use BIM for retrofitting | |
Liu | Three-dimensional visualized urban landscape planning and design based on virtual reality technology | |
US20210349476A1 (en) | Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform | |
CN106920049A (en) | A kind of Project Management System platform based on BIM network technologies | |
CN109408907B (en) | Method and device for manufacturing three-dimensional building physical model | |
US20190205484A1 (en) | Systems and methods for construction planning | |
CN109215470A (en) | A kind of goods electronic sand map system and its construction method based on BIM+GIS | |
CN107480370A (en) | A kind of construction speed Forecasting Methodology and system based on BIM models | |
CN109388902A (en) | A kind of Ground arrangement construction method using BIM technology | |
CN106803150A (en) | Municipal Engineering Construction progress msg management method and system based on BIM | |
CN106951583A (en) | Based on method of the BIM technology to job site monitoring camera virtual arrangement | |
CN107516161A (en) | A kind of project progress management-control method based on BIM | |
CN111161417A (en) | Method for constructing three-dimensional data model based on real estate registration result | |
CN113239543A (en) | Digital factory simulation system based on virtual reality technology | |
CN106294918A (en) | A kind of method for designing of virtual transparence office system | |
CN111400800B (en) | Building construction quality control system and method based on BIM and VR technology | |
CN111401726A (en) | Building design method, device, system and storage medium | |
CN112037337A (en) | Market three-dimensional digital emergency plan drilling system and method | |
CN110032804B (en) | Engineering information system based on combination of BIM, MR and 3DP technologies | |
CN112507444B (en) | AI-construction-based digital urban building night scene generation method and system | |
CN109146120A (en) | Three-dimensional model identification method for construction task progress state of power transmission and transformation project | |
Ham et al. | A study on application of bim (building information modeling) to pre-design in construction project | |
KR100683120B1 (en) | A right to enjoy sunshine disturbance analysis system and method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180209 |