CN108921443A - Power grid early warning scheduling system, method and device and server - Google Patents
Power grid early warning scheduling system, method and device and server Download PDFInfo
- Publication number
- CN108921443A CN108921443A CN201810762392.3A CN201810762392A CN108921443A CN 108921443 A CN108921443 A CN 108921443A CN 201810762392 A CN201810762392 A CN 201810762392A CN 108921443 A CN108921443 A CN 108921443A
- Authority
- CN
- China
- Prior art keywords
- information
- emergency
- fuzzy
- early warning
- parameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 37
- 238000013210 evaluation model Methods 0.000 claims abstract description 32
- 239000000463 material Substances 0.000 claims abstract description 14
- 230000005611 electricity Effects 0.000 claims description 67
- 230000006870 function Effects 0.000 claims description 19
- 238000004891 communication Methods 0.000 claims description 8
- 238000004590 computer program Methods 0.000 claims description 6
- 230000010354 integration Effects 0.000 claims description 2
- 239000000203 mixture Substances 0.000 abstract description 6
- 230000002159 abnormal effect Effects 0.000 abstract description 5
- 238000009472 formulation Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 3
- 241000196324 Embryophyta Species 0.000 description 19
- 230000005540 biological transmission Effects 0.000 description 5
- 238000011156 evaluation Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 5
- 238000012544 monitoring process Methods 0.000 description 4
- 201000004569 Blindness Diseases 0.000 description 3
- 230000008859 change Effects 0.000 description 3
- 238000006243 chemical reaction Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000007726 management method Methods 0.000 description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000034303 cell budding Effects 0.000 description 1
- 238000007405 data analysis Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000007935 neutral effect Effects 0.000 description 1
- 230000010355 oscillation Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a power grid early warning scheduling system, a method, a device and a server, wherein the system comprises: the system comprises an information acquisition device, an early warning center, a provincial and local dispatching integrated platform and a dispatching center; firstly, arranging an information acquisition device in a plant station to be monitored to acquire abnormal power information; secondly, enabling the early warning center to generate emergency demand grading information according to the power abnormity information and a preset fuzzy evaluation model; then, sending the emergency demand grading information to a dispatching center according to a preset interface and a preset protocol through a provincial dispatching integrated platform; finally, the dispatching center generates an emergency plan according to the emergency demand grading information, and dispatches emergency materials according to the emergency plan, so that the technical problems that the collection of power abnormity information is difficult, and the grading of the emergency demand and the formulation of the emergency plan lack scientific methods for guidance are solved, the accurate and rapid collection of the power abnormity information is achieved, the information can be sent to the dispatching center through a stable and efficient channel, and the technical effect that a commander carries out overall planning is facilitated.
Description
Technical field
The present invention relates to emergency scheduling technical field, more particularly, to a kind of power grid early warning scheduling system, method, apparatus and
Server.
Background technique
Currently, such as the severe operation against rules of great construction accident, public emergency event, property, earthquake, flood, pole
Easily cause massive blackout accident even electric network from collapsing, large-scale power outage and seriously affects social stability and people's life wealth
Produce safety.When electricity exception occurs, the data that the formulation of emergency preplan is often depending on the emergency exception information being collected into are
It is no accurate, comprehensive and timely;But during electricity exception, actual conditions one second of power failure may occur earth-shaking
Change, the collection work of electricity exception information is difficult to execute in time, and the classification of emergency demand and the formulation of emergency preplan are often main
By the experience and subjective judgement of contingency management personnel and emergency expert, there is certain randomness and blindness in scheduling,
The stage division for lacking science coaches.
Summary of the invention
In view of this, the purpose of the present invention is to provide a kind of power grid early warning scheduling system, method, apparatus and server,
To alleviate, there is certain randomness and blindness in current emergency scheduling, lack the skill that the stage division of science coaches
Art problem.
In a first aspect, the embodiment of the invention provides a kind of power grid early warning to dispatch system, including:It is information collecting device, pre-
Alert center saves ground tune unified platform and control centre;
The information collecting device is set in plant stand to be monitored, for acquiring the electricity exception information of plant stand to be monitored;
The warning center is used to generate emergency demand point according to the electricity exception information and default fuzzy evaluation model
Grade information;
Adjust to the province unified platform for sending out the emergency demand rating information by preset interface and preset protocol
Give the control centre;
The control centre is used to be generated and the emergency demand rating information pair according to the emergency demand rating information
The emergency preplan answered, and emergency materials are dispatched by the emergency preplan.
With reference to first aspect, the embodiment of the invention provides the first possible embodiments of first aspect, wherein institute
Stating power grid early warning scheduling system further includes:Communication device;
The communication device is used to the electricity exception information being sent to the warning center.
Second aspect, the embodiment of the present invention also provide a kind of power grid early warning dispatching method, are applied to warning center, including:
Receive the electricity exception information of information collecting device acquisition;
Emergency demand rating information is generated according to the electricity exception information and default fuzzy evaluation model;
By saving unified platform is adjusted to be sent to control centre the emergency demand rating information.
In conjunction with second aspect, the embodiment of the invention provides the first possible embodiments of second aspect, wherein institute
It states and emergency demand rating information is generated according to the electricity exception information and default fuzzy evaluation model, including:
The input parameter, the input ginseng are determined by the corresponding relationship for presetting the electricity exception information and input parameter
Number is the input of fuzzy evaluation model;
In the fuzzy evaluation model, the input parameter is subjected to blurring, controlling fuzzy parameter is calculated;
It is fuzzy that emergency demand levels are carried out by the corresponding relationship for presetting the controlling fuzzy parameter and emergency demand levels influence
Reasoning from logic obtains fuzzy reasoning parameter;
In the fuzzy evaluation model, emergency demand point is calculated in fuzzy reasoning parameter progress de-fuzzy
Grade information.
In conjunction with second aspect, the embodiment of the invention provides second of possible embodiments of second aspect, wherein institute
It states in the fuzzy evaluation model, the input parameter is subjected to blurring, controlling fuzzy parameter is calculated, including:
The first subordinating degree function is determined by the default corresponding relationship of the input parameter and the first subordinating degree function;
The calculating for receiving user's input inputs operation, and the input parameter fuzzy is obtained controlling fuzzy parameter.
In conjunction with second aspect, the embodiment of the invention provides the third possible embodiments of second aspect, wherein
In the fuzzy evaluation model, emergency demand rating information is calculated in fuzzy reasoning parameter progress de-fuzzy, is wrapped
It includes:
The second subordinating degree function is determined by the default corresponding relationship of the fuzzy reasoning parameter and output subordinating degree function;
The calculating for receiving user's input exports operation, and the fuzzy reasoning parameter de-fuzzy is generated the classification of emergency demand
Information.
The third aspect, the embodiment of the present invention also provide a kind of power grid early warning dispatching method, are applied to control centre, including:
Receive the emergency demand rating information that warning center is sent;
By the corresponding relationship of default emergency preplan and the emergency demand rating information, institute is generated in the control centre
State the corresponding emergency preplan of emergency demand rating information;
Emergency materials are dispatched by the emergency preplan.
In conjunction with the third aspect, the embodiment of the invention provides the first possible embodiments of the third aspect, wherein institute
It states and dispatches emergency materials by the emergency preplan, including:
The power plant and substation's information for the generation electricity exception situation that warning center is sent is received, the power plant and substation's information includes plant stand geography
Position;
According to the plant stand geographical location, it is different that the corresponding emergency materials of the emergency preplan are dispatched to the generation electric power
The plant stand of reason condition.
Second aspect, the embodiment of the present invention also provide a kind of power grid early warning dispatching device, are applied to warning center, including:
First receiving module, for receiving the electricity exception information of information collecting device acquisition;
First generation module, for generating emergency demand point according to the electricity exception information and default fuzzy evaluation model
Grade information;
First sending module, for by saving unified platform being adjusted to be sent to scheduling the emergency demand rating information
Center.
A kind of server, including memory, processor, be stored in the memory to run on the processor
Computer program, the processor realize above-mentioned second aspect and the third aspect either side institute when executing the computer program
The step of method stated.
The embodiment of the present invention brings following beneficial effect:The embodiment of the present invention is by providing a kind of power grid early warning scheduling system
System, method, apparatus and server, the system comprises:Information collecting device, warning center save ground tune unified platform and tune
Degree center;The information collecting device is set in plant stand to be monitored first, for acquiring the electricity exception of plant stand to be monitored
Information;Secondly, the warning center is enabled to generate emergency demand point according to the electricity exception information and default fuzzy evaluation model
Grade information;Then, adjust unified platform by the emergency demand rating information by preset interface and default association by the province
View is sent to the control centre;Finally, the control centre generates and the emergency according to the emergency demand rating information
The corresponding emergency preplan of demand rating information, and emergency materials are dispatched by the emergency preplan.
The embodiment of the present invention realizes the automatic collection to electricity exception information by setting information acquisition device, by setting
It adjusts integral intelligent platform the electricity exception information can be sent to control centre in real time with setting province, realizes accurate quick
Collection electricity exception information and control centre can be sent information to by the channel of stability and high efficiency, so as to cammander progress
Global planning.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification
It obtains it is clear that understand through the implementation of the invention.The objectives and other advantages of the invention are in specification, claims
And specifically noted structure is achieved and obtained in attached drawing.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment is cited below particularly, and cooperate
Appended attached drawing, is described in detail below.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art
Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below
Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor
It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is that system composition schematic diagram is dispatched in a kind of power grid early warning provided in an embodiment of the present invention;
Fig. 2 is a kind of power grid early warning dispatching method flow chart applied to warning center provided in an embodiment of the present invention;
Fig. 3 is the method flow schematic diagram that step S2 includes;
Fig. 4 is a kind of power grid early warning dispatching method flow chart applied to control centre provided in an embodiment of the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with attached drawing to the present invention
Technical solution be clearly and completely described, it is clear that described embodiments are some of the embodiments of the present invention, rather than
Whole embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creative work premise
Under every other embodiment obtained, shall fall within the protection scope of the present invention.
Currently, such as the severe operation against rules of great construction accident, public emergency event, property, earthquake, flood, pole
Easily cause massive blackout accident even electric network from collapsing, large-scale power outage and seriously affects social stability and people's life wealth
Produce safety.When electricity exception occurs, the data that the formulation of emergency preplan is often depending on the emergency exception information being collected into are
It is no accurate, comprehensive and timely;But during electricity exception, actual conditions one second of power failure may occur earth-shaking
Change, the collection work of electricity exception information is difficult to execute in time, and the classification of emergency demand and the formulation of emergency preplan are often main
By the experience and subjective judgement of contingency management personnel and emergency expert, there is certain randomness and blindness in scheduling,
The stage division for lacking science coaches, and is based on this, and it is fast that exception information is dispatched during a kind of emergency provided in an embodiment of the present invention
Speed reports and submits method, apparatus and system, and the automatic collection to electricity exception information can be realized by setting information acquisition device,
It adjusts integral intelligent platform the electricity exception information can be sent to control centre in real time with saving by setting, realizes standard
It really quickly collects electricity exception information and control centre can be sent information to by the channel of stability and high efficiency, to command
Person carries out global planning.
It is to be dispatched to a kind of power grid early warning disclosed in the embodiment of the present invention first convenient for understanding the present embodiment
System describes in detail, as shown in Figure 1, power grid early warning scheduling system includes:Information collecting device 1, saves warning center 2
Ground tune unified platform 3 and control centre 4;
The information collecting device 1 is set in plant stand to be monitored, for acquiring the electricity exception information of plant stand to be monitored;
In embodiments of the present invention, the information collecting device 1 can refer to intelligent electric power monitor table, with intelligence interface
Low-voltage circuit breaker and the intellectual monitorings instrument such as direct current cabinet;The plant stand can refer to that power plant and substation, power plant are used to send out
Electricity, the substation are the hinges of the voltage for converting, and the conversion of the height of voltage may be implemented.Substantially, by power plant
The electricity issued require by line transmission to substation through substation conversion voltage after again by line transmission to purpose
Ground.It can be seen that the plant stand occupies extremely important position in the power system, once electric power occurs for power plant or substation
Abnormal failure often causes disintegrating for power grid, and then the power failure phenomenon of occurrence of large-area, seriously affects people's lives and wealth
Produce safety.Therefore in embodiments of the present invention, for the power information situation of each plant stand of real-time monitoring, can distinguish in each plant stand
The electricity exception information that setting information acquisition device 1 is used to acquire plant stand can be sent out through the embodiment of the present invention in electricity exception
Raw initial stage can monitor exception information in time, facilitate staff that can find electricity exception situation in time, arrange early
Except failure, realizes to a certain extent and power abnormal failure was just excluded and is solved in the budding stage, avoid large-area power-cuts
The generation of event.
The warning center 2 is used to generate emergency demand point according to the electricity exception information and default fuzzy evaluation model
Grade information;
In embodiments of the present invention, the warning center 2 may include server, and the electricity exception information can refer to electricity
Pressure, the deviation of frequency are more than permissible range, and certain equipment are overloaded, overcurrent, and list does not occur neutral point for solidly grounded system
It is mutually grounded, the abnormal conditions information such as oscillation occur for system;In embodiments of the present invention, the fuzzy evaluation model can refer to including
The preset evaluation model that Indistinct Input operation, fuzzy logic inference and fuzzy output calculate.The emergency demand classification
Information can refer to the different brackets divided according to the influence that different electricity exception situations may cause, illustratively, can incite somebody to action
Electricity exception situation divides I grade (superfine demand) by urgency level, by II grade (urgent need) III grade (compared with being badly in need of asking) IV grade (one
As demand).Corresponding evaluation of estimate can be set for different grades, it is big that I grade of corresponding evaluation of estimate, which illustratively can be set,
Be less than or equal to 10 in being equal to 8, II grade of corresponding evaluation of estimate is to be less than or equal to 7 more than or equal to 5, III grade of corresponding evaluation of estimate be greater than
It is less than or equal to 4 equal to 2, IV grade of corresponding evaluation of estimate is to be less than or equal to 1 more than or equal to 0.
Adjust to the province unified platform 3 for sending out the emergency demand rating information by preset interface and preset protocol
Give the control centre 4;
In embodiments of the present invention, adjust to the province unified platform 3 that can refer to adjusts end and ground to adjust the intelligence at end including saving
Service platform saves and end is adjusted the key hardwares such as server, computer and display equipment to can be set and including such as platform
The software systems of software, operating system, database and application software etc.;Ground tune end then may include some monitoring service modules,
End is adjusted to pass through detailed monitoring information to save.
In embodiments of the present invention, with can the referring to province integrated webServices interface of the preset interface, it is described pre-
If agreement can refer to webServices agreement;In embodiments of the present invention, province's tune end and described adjust end that can pass through province
The integrated webServices interface in ground carries out the transmission of electricity exception information data using webServices agreement, described
Electricity exception information data can be encoded using utf-8 coded format, can also will be after coding for the safety of transmission
Message using base64 encrypt, save adjust end and ground adjust end according to include in encrypted message unique identifier carry out data
Interaction.
The control centre 4 is used to be generated and the emergency demand rating information pair according to the emergency demand rating information
The emergency preplan answered, and emergency materials are dispatched by the emergency preplan.
In embodiments of the present invention, the emergency preplan, which can refer to, is directed to electric power according to what emergency demand rating information generated
The emergency measure and scheme that abnormal conditions are made.
The embodiment of the present invention realizes the automatic collection to electricity exception information by setting information acquisition device 1, passes through
Setting saves ground and integral intelligent platform is adjusted the electricity exception information can be sent to control centre 4 in real time, and it is accurate to realize
It quickly collects electricity exception information and control centre 4 can be sent information to by the channel of stability and high efficiency, to command
Person carries out global planning.
In another embodiment of the present invention, the power grid early warning scheduling system further includes:Communication device;
The communication device is used to the electricity exception information being sent to the warning center 2.
In embodiments of the present invention, the communication device can refer between information collecting device 1 and warning center 2 into
The PORT COM or device of row communication interaction.
In another embodiment of the present invention, as shown in Fig. 2, also providing a kind of power grid early warning dispatching method, it is applied to pre-
Alert center 2, includes the next steps:
Step S1, for receiving the electricity exception information of the acquisition of information collecting device 1;
Step S2, for generating emergency demand classification letter according to the electricity exception information and default fuzzy evaluation model
Breath;
Step S3, for by saving unified platform 3 being adjusted to be sent to control centre the emergency demand rating information
4。
In embodiments of the present invention, the warning center 2 can be with real-time reception electricity exception information, and can be according to reception
To electricity exception information calculate emergency demand rating information, finally will emergency demand rating information by save ground adjust integration
Platform 3 is timely transmitted to control centre 4.
In another embodiment of the present invention, as shown in figure 3, step S2 can also include the following steps:
Step S21, for determining that the input is joined by the corresponding relationship for presetting the electricity exception information and input parameter
Number, the input parameter are the input of fuzzy evaluation model;
In embodiments of the present invention, the input parameter and the electricity exception information are corresponding, and the input parameter is by institute
The decision of electricity exception information is stated, different electricity exception information corresponds to different input parameters.It illustratively, can be by the electricity
Power exception information corresponds to different input parameters in terms of importance, timeliness and notch degree three.It is fixed by natural language
The different electricity exception situation of justice corresponds to different importance, timeliness and notch degree, may be implemented through the embodiment of the present invention
Real data, that is, electricity exception information is converted into mathematical data, in order to what how can be constructed in advance by the mathematical data
Analysis and operation are carried out in fuzzy evaluation model.
Step S22, in the fuzzy evaluation model, the input parameter be blurred be calculated it is fuzzy
Change parameter;
In embodiments of the present invention, blurring calculating process can have been pre-defined in the fuzzy evaluation model.
The blurring, which calculates, can refer to the numerical value that input parameter is transformed into default domain in the proper ratio, utilize mouth
Language variable come describe measurement physical quantity process, the colloquial style variable be referred to as fuzzy subset conjunction, the default domain can
Think a kind of bounded theory of real numbers domain with mathematical form predetermined.
Step S23, for meeting an urgent need by the corresponding relationship for presetting the controlling fuzzy parameter and emergency demand levels influence
Demand levels fuzzy logic inference obtains fuzzy reasoning parameter;
In embodiments of the present invention, the fuzzy logic inference can refer to pre-establishes according in the fuzzy evaluation model
Knowledge base, carry out inference with fuzzy logic and fuzzy deduction method and obtain fuzzy control signal;In embodiments of the present invention, institute
Stating knowledge base may include database and rule base two parts, and the correlation that the database can provide processing fuzzy data is fixed
Justice, the rule base, which can refer to, has gathered some Linguistic control laws and description control target and strategy, the rule base description
The combined influence of the corresponding anxious demand levels of the input variable of various combination, illustratively, the rule base can be by different groups
The combined influence of the corresponding anxious demand levels of the input variable of conjunction is described by natural language, mostly uses " the IF- of fuzzy statement
THEN " rule." IF-THEN " rule can be divided into two parts:The part IF is the premise that can be compared with input parameter;
The part THEN is then the result obtained under the premise of this.
Step S24, in the fuzzy evaluation model, fuzzy reasoning parameter progress de-fuzzy to be calculated
To emergency demand rating information.
In embodiments of the present invention, the de-fuzzy calculating can refer to the fuzzy reasoning that will be obtained through fuzzy logic inference
Parameter Switch is the calculating process of specific emergency demand rating information data;The emergency demand rating information can be used as mould
Paste the output of evaluation model.
In another embodiment of the present invention, step S22 can also include:
The first subordinating degree function is determined by the default corresponding relationship of the input parameter and the first subordinating degree function;
The calculating for receiving user's input inputs operation, and the input parameter fuzzy is obtained controlling fuzzy parameter.
In embodiments of the present invention, can refer to will be described according to membership predetermined for first subordinating degree function
Parameter sets are inputted into the function of fuzzy set.It illustratively, can be using trapezoidal function as subordinating degree function.
In another embodiment of the present invention, step S24 can also include:
The second subordinating degree function is determined by the default corresponding relationship of the fuzzy reasoning parameter and output subordinating degree function;
The calculating for receiving user's input exports operation, and the fuzzy reasoning parameter de-fuzzy is generated the classification of emergency demand
Information.
In embodiments of the present invention, can refer to will be described according to membership predetermined for second subordinating degree function
Fuzzy reasoning Parameter Switch at fuzzy set function.
In another embodiment of the present invention, as shown in figure 4, also providing a kind of power grid early warning dispatching method, it is applied to adjust
Degree center 4, may comprise steps of:
Step S101, for receiving the emergency demand rating information of the transmission of warning center 2;
Step S102, for the corresponding relationship by default emergency preplan and the emergency demand rating information, in the tune
The corresponding emergency preplan of the emergency demand rating information is generated in degree center 4;
Step S103, for dispatching emergency materials by the emergency preplan.
Power grid early warning dispatching method provided in an embodiment of the present invention dispatches system with power grid early warning provided by the above embodiment
Technical characteristic having the same reaches identical technical effect so also can solve identical technical problem, to briefly describe,
Part of the embodiment of the present invention does not refer to place, can refer to corresponding contents in aforementioned power grid early warning scheduling system embodiment.
In another embodiment of the present invention, step S103 may include:
The power plant and substation's information for the generation electricity exception situation that warning center 2 is sent is received, the power plant and substation's information includes plant stand
Manage position;
According to the plant stand geographical location, it is different that the corresponding emergency materials of the emergency preplan are dispatched to the generation electric power
The plant stand of reason condition.
In embodiments of the present invention, the plant stand geographical location information can refer to the actual geographic position letter of the plant stand
Breath.Through the embodiment of the present invention, it may be implemented fast and accurately to be dispatched emergency materials according to the geographical location information
It goes, solves the problems, such as electricity exception in time.
In another embodiment of the present invention, a kind of power grid early warning dispatching device is also provided, is applied to warning center 2, packet
It includes:
First receiving module, for receiving the electricity exception information of the acquisition of information collecting device 1;
First generation module, for generating emergency demand point according to the electricity exception information and default fuzzy evaluation model
Grade information;
First sending module, for by saving unified platform 3 being adjusted to be sent to tune the emergency demand rating information
Degree center 4.
Power grid early warning dispatching device provided in an embodiment of the present invention is applied to warning center 2 with provided by the above embodiment
Power grid early warning dispatching method technical characteristic having the same reach identical skill so also can solve identical technical problem
Art effect.
In another embodiment of the present invention, a kind of server, including memory, processor, the memory are also provided
In be stored with the computer program that can be run on the processor, the processor is realized when executing the computer program
The step of stating either the method for the intrinsic control centre 4 of methods and applications applied to warning center 2 method.
It is apparent to those skilled in the art that for convenience and simplicity of description, the system of foregoing description
It with the specific work process of device, can refer to corresponding processes in the foregoing method embodiment, details are not described herein.
In addition, in the description of the embodiment of the present invention unless specifically defined or limited otherwise, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary
Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition
Concrete meaning in invention.
It, can be with if the function is realized in the form of SFU software functional unit and when sold or used as an independent product
It is stored in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially in other words
The part of the part that contributes to existing technology or the technical solution can be embodied in the form of software products, the meter
Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be a
People's computer, server or network equipment etc.) it performs all or part of the steps of the method described in the various embodiments of the present invention.
And storage medium above-mentioned includes:USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited
The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic or disk.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical",
The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to
Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation,
It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ",
" third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
Finally it should be noted that:Embodiment described above, only a specific embodiment of the invention, to illustrate the present invention
Technical solution, rather than its limitations, scope of protection of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair
It is bright to be described in detail, those skilled in the art should understand that:Anyone skilled in the art
In the technical scope disclosed by the present invention, it can still modify to technical solution documented by previous embodiment or can be light
It is readily conceivable that variation or equivalent replacement of some of the technical features;And these modifications, variation or replacement, do not make
The essence of corresponding technical solution is detached from the spirit and scope of technical solution of the embodiment of the present invention, should all cover in protection of the invention
Within the scope of.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (10)
1. system is dispatched in a kind of power grid early warning, which is characterized in that including:Information collecting device, warning center save ground tune integration
Platform and control centre;
The information collecting device is set in plant stand to be monitored, for acquiring the electricity exception information of plant stand to be monitored;
The warning center is used to generate emergency demand classification letter according to the electricity exception information and default fuzzy evaluation model
Breath;
Adjust to the province unified platform for the emergency demand rating information to be sent to by preset interface and preset protocol
The control centre;
The control centre is used to be generated according to the emergency demand rating information corresponding with the emergency demand rating information
Emergency preplan, and emergency materials are dispatched by the emergency preplan.
2. system is dispatched in power grid early warning according to claim 1, which is characterized in that further include:Communication device;
The communication device is used to the electricity exception information being sent to the warning center.
3. a kind of power grid early warning dispatching method, which is characterized in that it is applied to warning center, including:
Receive the electricity exception information of information collecting device acquisition;
Emergency demand rating information is generated according to the electricity exception information and default fuzzy evaluation model;
By saving unified platform is adjusted to be sent to control centre the emergency demand rating information.
4. power grid early warning dispatching method according to claim 3, which is characterized in that described according to the electricity exception information
Emergency demand rating information is generated with default fuzzy evaluation model, including:
Determine that the input parameter, the input parameter are by the corresponding relationship for presetting the electricity exception information and input parameter
The input of fuzzy evaluation model;
In the fuzzy evaluation model, the input parameter is subjected to blurring, controlling fuzzy parameter is calculated;
Emergency demand levels fuzzy logic is carried out by the corresponding relationship for presetting the controlling fuzzy parameter and emergency demand levels influence
Reasoning obtains fuzzy reasoning parameter;
In the fuzzy evaluation model, emergency demand classification letter is calculated in fuzzy reasoning parameter progress de-fuzzy
Breath.
5. power grid early warning dispatching method according to claim 4, which is characterized in that described in the fuzzy evaluation model
In, the input parameter is subjected to blurring, controlling fuzzy parameter is calculated, including:
The first subordinating degree function is determined by the default corresponding relationship of the input parameter and the first subordinating degree function;
The calculating for receiving user's input inputs operation, and the input parameter fuzzy is obtained controlling fuzzy parameter.
6. power grid early warning dispatching method according to claim 4, which is characterized in that, will in the fuzzy evaluation model
The fuzzy reasoning parameter carries out de-fuzzy and emergency demand rating information is calculated, including:
The second subordinating degree function is determined by the default corresponding relationship of the fuzzy reasoning parameter and output subordinating degree function;
The calculating for receiving user's input exports operation, and the fuzzy reasoning parameter de-fuzzy is generated emergency demand classification letter
Breath.
7. a kind of power grid early warning dispatching method, which is characterized in that it is applied to control centre, including:
Receive the emergency demand rating information that warning center is sent;
By the corresponding relationship of default emergency preplan and the emergency demand rating information, answered described in generation in the control centre
Urgent need seeks the corresponding emergency preplan of rating information;
Emergency materials are dispatched by the emergency preplan.
8. power grid early warning dispatching method according to claim 7, which is characterized in that described to be answered by emergency preplan scheduling
Anxious goods and materials, including:
The power plant and substation's information for the generation electricity exception situation that warning center is sent is received, the power plant and substation's information includes plant stand geography position
It sets;
According to the plant stand geographical location, the corresponding emergency materials of the emergency preplan are dispatched to the generation electricity exception feelings
The plant stand of condition.
9. a kind of power grid early warning dispatching device, which is characterized in that it is applied to warning center, including:
First receiving module, for receiving the electricity exception information of information collecting device acquisition;
First generation module, for generating emergency demand classification letter according to the electricity exception information and default fuzzy evaluation model
Breath;
First sending module, for by saving unified platform being adjusted to be sent in scheduling the emergency demand rating information
The heart.
10. a kind of server, including memory, processor, be stored in the memory to run on the processor
Computer program, which is characterized in that the processor realizes that the claims 3 to 8 are any when executing the computer program
The step of method described in item.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810762392.3A CN108921443A (en) | 2018-07-11 | 2018-07-11 | Power grid early warning scheduling system, method and device and server |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810762392.3A CN108921443A (en) | 2018-07-11 | 2018-07-11 | Power grid early warning scheduling system, method and device and server |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108921443A true CN108921443A (en) | 2018-11-30 |
Family
ID=64412034
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810762392.3A Pending CN108921443A (en) | 2018-07-11 | 2018-07-11 | Power grid early warning scheduling system, method and device and server |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108921443A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110991799A (en) * | 2019-10-30 | 2020-04-10 | 广西电网有限责任公司电力科学研究院 | Comprehensive early warning method for power distribution network production |
CN111833561A (en) * | 2019-11-20 | 2020-10-27 | 杭州四方博瑞科技股份有限公司 | Method and system for judging abnormal conditions of perimeter of enclosing wall |
CN112348327A (en) * | 2020-10-26 | 2021-02-09 | 易显智能科技有限责任公司 | Supervision system of evaluation management system |
CN117768246A (en) * | 2024-02-22 | 2024-03-26 | 广东电网有限责任公司中山供电局 | Control method of district monitoring terminal and control device of district monitoring terminal |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102074956A (en) * | 2011-02-11 | 2011-05-25 | 华北电网有限公司 | Power grid risk management method and system |
CN104346701A (en) * | 2014-11-11 | 2015-02-11 | 国家电网公司 | Condition-based maintenance and evaluation decision making system for grid information communication equipment |
CN105303285A (en) * | 2014-09-04 | 2016-02-03 | 国网山东省电力公司应急管理中心 | Intelligent allocation method for power emergency disposal materials |
-
2018
- 2018-07-11 CN CN201810762392.3A patent/CN108921443A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102074956A (en) * | 2011-02-11 | 2011-05-25 | 华北电网有限公司 | Power grid risk management method and system |
CN105303285A (en) * | 2014-09-04 | 2016-02-03 | 国网山东省电力公司应急管理中心 | Intelligent allocation method for power emergency disposal materials |
CN104346701A (en) * | 2014-11-11 | 2015-02-11 | 国家电网公司 | Condition-based maintenance and evaluation decision making system for grid information communication equipment |
Non-Patent Citations (1)
Title |
---|
张向东 等: "基于模糊综合评判的智能变电站告警***研究", 《电网与清洁能源》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110991799A (en) * | 2019-10-30 | 2020-04-10 | 广西电网有限责任公司电力科学研究院 | Comprehensive early warning method for power distribution network production |
CN111833561A (en) * | 2019-11-20 | 2020-10-27 | 杭州四方博瑞科技股份有限公司 | Method and system for judging abnormal conditions of perimeter of enclosing wall |
CN111833561B (en) * | 2019-11-20 | 2021-11-09 | 杭州四方博瑞科技股份有限公司 | Method and system for judging abnormal conditions of perimeter of enclosing wall |
CN112348327A (en) * | 2020-10-26 | 2021-02-09 | 易显智能科技有限责任公司 | Supervision system of evaluation management system |
CN117768246A (en) * | 2024-02-22 | 2024-03-26 | 广东电网有限责任公司中山供电局 | Control method of district monitoring terminal and control device of district monitoring terminal |
CN117768246B (en) * | 2024-02-22 | 2024-06-11 | 广东电网有限责任公司中山供电局 | Control method of district monitoring terminal and control device of district monitoring terminal |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108921443A (en) | Power grid early warning scheduling system, method and device and server | |
CN110134094B (en) | Industrial enterprise energy consumption monitoring and management system | |
CN103633739B (en) | Microgrid energy management system and method | |
CN110429714B (en) | Cloud platform intelligent power distribution system based on big data | |
Lin et al. | Situation awareness of active distribution network: Roadmap, technologies, and bottlenecks | |
CN102737287B (en) | Regional power grid on-line power supply risk assessment system | |
CN105678467A (en) | Regulation and control integrated data analysis and aid decision making system and method under ultrahigh-voltage alternating current and direct current networking | |
CN107798395A (en) | A kind of power grid accident signal automatic diagnosis method and system | |
CN109636113A (en) | Power grid risk analysis method based on deploying node | |
CN105787606A (en) | Power dispatching online trend early warning system based on ultra short term load prediction | |
CN105372534A (en) | Multi-sensor multi-parameter information intelligent integration system | |
CN102436226A (en) | Online monitoring and condition maintenance management system | |
CN105184490B (en) | Forming Electrical Dispatching Command Tickets process risk assists Pre-control System | |
CN113595090B (en) | Multi-element load data processing method and system crossing safety zone | |
CN109767063A (en) | Stability control device operation information system and online power grid risk assessment method thereof | |
CN102254241A (en) | On-line estimating method for power demand balanced capability based on full network topology | |
CN113837423A (en) | Power grid operation situation prediction method based on energy internet electric power big data | |
CN105811588A (en) | Electric power grid safety running monitoring and communication system | |
CN109787242A (en) | A kind of power grid low-frequency voltage off-load method and system | |
Zhang et al. | Risk assessment for substation operation based on triangular fuzzy number AHP and cloud model | |
CN104979903B (en) | A kind of centralized control center patrols dimension analysis method and device | |
CN107390592A (en) | A kind of business electrical monitoring information and mobile phone interaction communication system | |
CN108288122B (en) | Assessment method and device of multi-region interconnection system | |
CN113919528A (en) | Power distribution network maintenance method under flood disaster | |
CN105914888A (en) | Power grid operation state monitoring and communication system and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181130 |