CN105303285A - Intelligent allocation method for power emergency disposal materials - Google Patents

Intelligent allocation method for power emergency disposal materials Download PDF

Info

Publication number
CN105303285A
CN105303285A CN201410448406.6A CN201410448406A CN105303285A CN 105303285 A CN105303285 A CN 105303285A CN 201410448406 A CN201410448406 A CN 201410448406A CN 105303285 A CN105303285 A CN 105303285A
Authority
CN
China
Prior art keywords
accident
materials
event
goods
emergency
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410448406.6A
Other languages
Chinese (zh)
Other versions
CN105303285B (en
Inventor
蒋斌
孙为民
孙世军
张鹏
李冬
张治取
韩洪
杨啸帅
王波
程中华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Emergency Management Center State Grid Shandong Province Electric Power Co
Original Assignee
Emergency Management Center State Grid Shandong Province Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Emergency Management Center State Grid Shandong Province Electric Power Co filed Critical Emergency Management Center State Grid Shandong Province Electric Power Co
Priority to CN201410448406.6A priority Critical patent/CN105303285B/en
Priority to PCT/CN2015/088917 priority patent/WO2016034142A1/en
Publication of CN105303285A publication Critical patent/CN105303285A/en
Application granted granted Critical
Publication of CN105303285B publication Critical patent/CN105303285B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses an intelligent allocation method for power emergency disposal materials. According to the method, for the problems that in an existing material allocation system, the emergency event allocation is completed manually and the efficiency and accuracy are very low when the quantities of allocation materials and participation units are high, intelligent material allocation improves disposal efficiency of emergency disposal personnel and provides powerful support for emergency disposal of emergency events; and through the reported emergency events, a system automatically determines early-warning ranks of the events according to influence ranges and hazard ratings of the events, the whole process is automatically processed and completed by a program, and the analysis and computation are free of manual intervention, so that the disposal efficiency and accuracy of the emergency events are improved.

Description

Method is alloted in the intellectuality that a kind of power emergency disposes goods and materials
Technical field
Method is alloted in the intellectuality that the present invention relates to a kind of power emergency disposal goods and materials.
Background technology
All trades and professions emerge in an endless stream based on the application system of GIS map in recent years, and these systems are mainly used in the industries such as communications and transportation, power industry, water conservancy industry and communication.GIS map application system is in patterned mode by the data message of computing machine, intuitively, the displaying of diversification, this kind of application system based on GIS map, in service processing function, operates easier and quick, improves the efficiency of decision-making of application system user of service.
Geographic Information System achieved alarming development in nearest 30 years, was widely used in nearly all fields such as resource exploration, environmental assessment, hazard prediction, Territorial management, city planning, post and telecommunications, communications and transportation, military public security, hydraulic and electric engineering, public facility management, agriculture forest and husbandry, statistics, trade financing.Domestic GIS software mainly contains: MAPGIS, GeoStar and SuperMap, on GIS software platform, have developed a series of for city planning, a series of application system such as communication pipe network and distribution, urban water supply, town-gas, comprehensive pipe network, power matching network, cadastral survey manual, clay detailed Investigation, GPS navigation and monitoring, operational commanding, public security warning, environment monitoring, popular geography information making etc.
The intellectuality system of alloting that power emergency disposes goods and materials realizes the intellectuality to delivery of goods and materials in power emergency disposal process.So-called intellectuality is alloted, and study and judge the various incident analysis of electric power exactly, call site disposal scheme, the analysis of personnel's goods and materials adds the analysis of alloting algorithm, what form goods and materials automatically allots scheme, for emergency personnel provides support.
Current existing system delivery of goods and materials be all manually go alloting emergency event.When allocate supplies and participate in Board Lot numerous, can be very low in efficiency and accuracy.
Summary of the invention
The present invention is in order to solve the problem, and method is alloted in the intellectuality proposing a kind of power emergency disposal goods and materials, and the disposal efficiency of emergency personnel that the method is high, the emergency disposal for accident provides strong support.
To achieve these goals, the present invention adopts following technical scheme:
A method is alloted in the intellectuality that power emergency disposes goods and materials, specifically comprises the following steps:
(1) decision event type and grade; According to character, the content of event, event type is divided, according to the event order of severity, divide its concrete grade;
(2) carry out analysis to the time to study and judge; According to event type and grade, in conjunction with topological structure and the spatial geographic information of electrical network, analysis is carried out on the scope of accident impact and the installations and facilities of electrical network and studies and judges;
(3) emergency disposal prediction scheme is called; Emergency disposal prediction scheme is divided into different templates according to the type difference of accident, it is a set of standardized, normalized disposal template, the all corresponding Response project template of each event, call corresponding Response project masterplate according to the type of accident, read the disposal route to accident in prediction scheme masterplate;
(4) personnel's goods and materials are analyzed: the result through step (1)-(3) and call existing material information in material on hand database, determine the goods and materials needing to allot; According to event class, determine the quantity that will allot;
(5) Algorithm Analysis is alloted; According to the geographic position of accident geographic position, material depot, road link and the speed of a motor vehicle, select the preferential vehicle arrived; And consider that material storage deficiency needs the situation of alloting from contiguous material depot, time of arrival and the goods and materials quantity of alloting warehouse are comprehensively analyzed; Evaluate optimal case;
(6) optimum is alloted scheme and actual conditions combine, finely tune, form final plan; Disposal personnel carries out the fine setting of scheme according to the actual conditions of traffic congestion, road construction.
In described step (1), type, the divided rank of event are determined according to " the overall emergency preplan of Utilities Electric Group Co.'s accident "; Event type specifically comprises electric power accident class, power supply service class, public health event class, disaster class, accident class and security incident class, and wherein, electric power accident class comprises electric power accident and large-area power-cuts event; Power supply service class comprises electricity shortage time, important guarantor electricity event and power supply service event; Disaster class comprises bloods and droughts, meteorological disaster, earthquake disaster, geologic hazard, Oceanic disasters and forest fire; Accident class comprises fire, road public transport event, power infrastructures accident, communication system accident and environmental pollution accident; Security incident class comprises the accident of Mass disturbance network and information, casualties event and event concerning foreign affairs.
The concrete grammar of described step (5) is as follows: according to geographic position and the road distribution of accident geographic position, material depot, calculate the path between accident, material depot, the setting speed of a motor vehicle is n, 60km/h≤n≤110km/h, calculates running time T 1i, i=1,2 ..., m, m are the total quantity of material depot, if the allocated supplies quantity of this material depot is inadequate, need to calculate the running time T from other warehouse relaies 2i; Calculate the running time T=T between different material depots and accident successively 1i+ T 2i, obtain T less, then think that scheme is optimum.
A kind of power emergency applying said method disposes goods and materials calling system, comprise: comprise data input/output module, distribution of materials computing module, database and data preprocessing module, wherein, data input/output module connection data storehouse and data preprocessing module, data preprocessing module also communicates with distribution of materials computing module, and database is connected with data preprocessing module, data input/output module and distribution of materials computing module.
Described data input/output module, for the geographic position of the character of the request of typing goods and materials, event, content, accident geographic position, material depot, road link and the speed of a motor vehicle, is connected with processing module with database and data;
Described data preprocessing module, for decision event type, grade with carry out analysis to the scope of accident impact and the installations and facilities of electrical network and study and judge, with data input/output module, distribution of materials computing module and DataBase combining;
Described database, for storing the topological structure of electrical network, spatial geographic information, emergency disposal prediction scheme template and alloting the goods and materials quantity in warehouse;
Described distribution of materials computing module, for calculating running time and assessment optimal case, with data input/output module, data preprocessing module and DataBase combining.
Beneficial effect of the present invention is: intelligentized delivery of goods and materials improves the disposal efficiency of emergency personnel, and the emergency disposal for accident provides strong support; By the emergency event reported, system determines the advanced warning grade of event automatically according to the coverage of event and the extent of injury, then the Response project template of state's net for a certain type is alloted, determine the goods and materials type for this event, call goods and materials data again, draw by the automatic analytical calculation of system the goods and materials that will allot, select for emergency personnel in a recommended manner.Whole process is that program itself has processed automatically, and analytical calculation does not need manual intervention, so the disposal efficiency that improve accident and accuracy.
Accompanying drawing explanation
Fig. 1 is kind of event of the present invention classification schematic diagram;
Fig. 2 is schematic flow sheet of the present invention.
Embodiment:
Below in conjunction with accompanying drawing and embodiment, the invention will be further described.
As shown in Figure 1 and Figure 2, method is alloted in the intellectuality that a kind of power emergency disposes goods and materials, specifically comprises the following steps:
(1) decision event type and grade; According to character, the content of event, event type is divided, according to the event order of severity, divide its concrete grade.
(2) carry out analysis to the time to study and judge; According to event type and grade, in conjunction with topological structure and the spatial geographic information of electrical network, analysis is carried out on the scope of accident impact and the installations and facilities of electrical network and studies and judges;
(3) site disposal scheme is called; Site disposal scheme is divided into different templates according to the type difference of accident, is a set of standardized, normalized disposal template, calls corresponding site disposal scheme according to the type of accident;
(4) personnel's goods and materials are analyzed: the result through step (1)-(3) and call existing material information in material on hand database, determine the goods and materials needing to allot;
(5) Algorithm Analysis is alloted; According to the geographic position of accident geographic position, material depot, road link and the speed of a motor vehicle, and consider that material storage deficiency needs the situation of alloting from contiguous material depot, comprehensively analyze;
(6) scheme is alloted in formation, and by the analytical calculation of step (5), what evaluate optimum allots scheme;
(7) optimum is alloted scheme and actual conditions combine, finely tune, form final plan.
Attack Binzhou for severe snow in 2013 below, what the intellectuality carrying out power emergency disposal goods and materials was alloted illustrates:
1) decision event type and grade;
Type according to electrical network accident is divided, and this belongs to is the severe snow event of disaster class, and according to the scope of severe snow weather effect and the extent of damage of electrical network, event class is decided to be three grades.
2) decision event type and grade;
According to the scope of severe snow, in conjunction with the spatial geographic information of GIS, call the topological structure of electrical network, analysis is carried out to the installations and facilities of the electrical network of current severe snow weather effect and scope and studies and judges.
3) site disposal scheme is called
Through analysis to event type, after the type determining event and grade, remove the three grades of severe snow weather site disposal plan template calling state's net.
4) personnel's goods and materials are analyzed
According to the site disposal scheme called, the goods and materials needing to allot are analyzed with the personnel sent; Determine the concrete commit resources of emergency disaster relief goods and materials (cotton-padded overcoat, tent, automobile anti-skid chain etc.), emergency first-aid repair Work tool (gin wheel, hydraulic tongs, fixing-line device etc.), electrical network restoring material (wire rope, insulator, bracing wire dop etc.) and electrical network rush repair equipment (repairing rifle tower, transformer substation framework, baking oven etc.) and allot quantity; And the degree that is damaged of the type of event and grid equipment facility, the troops such as dispatch emergency troop and corresponding expert.
5) Algorithm Analysis is alloted
According to the geographic position of accident geographic position and material depot, call the Analysis Service of the road of GIS map, certain speed of a motor vehicle (as 60km/h), the capacity (being not less than 2000kVA) etc. of generator car carry out analytical calculation.If when in warehouse, material storage is not enough, can allot from contiguous material depot.If rush to repair Work tool in goods and materials storehouse, Dezhou when can not meet the demand of Rush Repair Scheme, just can allot from the material depot in Jinan, the request of alloting can be distributed to power supply administration of Jinan City operator on duty and carry out confirmation and reply.Through a series of analytical calculation, draw and finally need the quantity of the goods and materials alloted and the position of depositing of goods and materials.
6) scheme is alloted in formation
According to analytical calculation above, formed and allot scheme for current emergency.
7) scheme fine setting
For 6) generate allot scheme, emergency personnel can finely tune according to actual conditions.Such as according to icy road situation, the route of advancing is finely tuned.
8) final plan
Through above-mentioned comprehensive analysis, formed and final allot scheme, be handed down to emergency personnel and need the electric company of cooperation.
By reference to the accompanying drawings the specific embodiment of the present invention is described although above-mentioned; but not limiting the scope of the invention; one of ordinary skill in the art should be understood that; on the basis of technical scheme of the present invention, those skilled in the art do not need to pay various amendment or distortion that creative work can make still within protection scope of the present invention.

Claims (8)

1. a method is alloted in the intellectuality of power emergency disposal goods and materials, it is characterized in that: specifically comprise the following steps:
(1) decision event type and grade; According to character, the content of event, event type is divided, according to the event order of severity, divide its concrete grade;
(2) carry out analysis to the time to study and judge; According to event type and grade, in conjunction with topological structure and the spatial geographic information of electrical network, analysis is carried out on the scope of accident impact and the installations and facilities of electrical network and studies and judges;
(3) emergency disposal prediction scheme is called; Emergency disposal prediction scheme is divided into different templates according to the type difference of accident, it is a set of standardized, normalized disposal template, the all corresponding Response project template of each event, call corresponding Response project masterplate according to the type of accident, read the disposal route to accident in prediction scheme masterplate;
(4) personnel's goods and materials are analyzed: the result through step (1)-(3) and call existing material information in material on hand database, determine the goods and materials needing to allot; According to event class, determine the quantity that will allot;
(5) Algorithm Analysis is alloted; According to the geographic position of accident geographic position, material depot, road link and the speed of a motor vehicle, select the preferential vehicle arrived; And consider that material storage deficiency needs the situation of alloting from contiguous material depot, time of arrival and the goods and materials quantity of alloting warehouse are comprehensively analyzed; Evaluate optimal case;
(6) optimum is alloted scheme and actual conditions combine, finely tune, form final plan; Disposal personnel carries out the fine setting of scheme according to the actual conditions of traffic congestion, road construction.
2. method is alloted in the intellectuality that a kind of power emergency as claimed in claim 1 disposes goods and materials, it is characterized in that: in described step (1), type, the divided rank of event are determined according to " the overall emergency preplan of Utilities Electric Group Co.'s accident "; Event type specifically comprises electric power accident class, power supply service class, public health event class, disaster class, accident class and security incident class, and wherein, electric power accident class comprises electric power accident and large-area power-cuts event; Power supply service class comprises electricity shortage time, important guarantor electricity event and power supply service event; Disaster class comprises bloods and droughts, meteorological disaster, earthquake disaster, geologic hazard, Oceanic disasters and forest fire; Accident class comprises fire, road public transport event, power infrastructures accident, communication system accident and environmental pollution accident; Security incident class comprises the accident of Mass disturbance network and information, casualties event and event concerning foreign affairs.
3. method is alloted in the intellectuality that a kind of power emergency as claimed in claim 1 disposes goods and materials, it is characterized in that: the concrete grammar of described step (5) is as follows: according to geographic position and the road distribution of accident geographic position, material depot, calculate the path between accident, material depot, the setting speed of a motor vehicle is n, 60km/h≤n≤110km/h, calculates running time T 1i, i=1,2 ..., m, m are the total quantity of material depot, if the allocated supplies quantity of this material depot is inadequate, need to calculate the running time T from other warehouse relaies 2i; Calculate the running time T=T between different material depots and accident successively 1i+ T 2i, obtain T less, then think that scheme is optimum.
4. an application rights requires that the power emergency of method any one of 1-3 disposes goods and materials calling system, it is characterized in that: comprise data input/output module, distribution of materials computing module, database and data preprocessing module, wherein, data input/output module connection data storehouse and data preprocessing module, data preprocessing module also communicates with distribution of materials computing module, and database is connected with data preprocessing module, data input/output module and distribution of materials computing module.
5. power emergency as claimed in claim 4 disposes goods and materials calling system, it is characterized in that: described data input/output module, for the geographic position of the character of the request of typing goods and materials, event, content, accident geographic position, material depot, road link and the speed of a motor vehicle, be connected with processing module with database and data.
6. power emergency as claimed in claim 4 disposes goods and materials calling system, it is characterized in that: described data preprocessing module, for decision event type, grade with carry out analysis to the scope of accident impact and the installations and facilities of electrical network and study and judge, with data input/output module, distribution of materials computing module and DataBase combining.
7. power emergency as claimed in claim 4 disposes goods and materials calling system, it is characterized in that: described database, for storing the topological structure of electrical network, spatial geographic information, emergency disposal prediction scheme template and alloting the goods and materials quantity in warehouse.
8. power emergency as claimed in claim 4 disposes goods and materials calling system, it is characterized in that: described distribution of materials computing module, for calculating running time and assessment optimal case, with data input/output module, data preprocessing module and DataBase combining.
CN201410448406.6A 2014-09-04 2014-09-04 A kind of power emergency is disposed the intellectuality of goods and materials and is alloted method Active CN105303285B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410448406.6A CN105303285B (en) 2014-09-04 2014-09-04 A kind of power emergency is disposed the intellectuality of goods and materials and is alloted method
PCT/CN2015/088917 WO2016034142A1 (en) 2014-09-04 2015-09-02 Smart allocation method for electric emergency response supplies

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410448406.6A CN105303285B (en) 2014-09-04 2014-09-04 A kind of power emergency is disposed the intellectuality of goods and materials and is alloted method

Publications (2)

Publication Number Publication Date
CN105303285A true CN105303285A (en) 2016-02-03
CN105303285B CN105303285B (en) 2016-11-09

Family

ID=55200527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410448406.6A Active CN105303285B (en) 2014-09-04 2014-09-04 A kind of power emergency is disposed the intellectuality of goods and materials and is alloted method

Country Status (2)

Country Link
CN (1) CN105303285B (en)
WO (1) WO2016034142A1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106484966A (en) * 2016-09-22 2017-03-08 北京交通大学 A kind of urban track traffic accident dynamic effect scope and strength determining method
CN108921443A (en) * 2018-07-11 2018-11-30 广东电网有限责任公司 A kind of power grid early warning scheduling system, method, apparatus and server
CN109508887A (en) * 2018-11-19 2019-03-22 国网四川省电力公司攀枝花供电公司 Intelligent emergency matenal support decision system based on artificial intelligence
CN110020778A (en) * 2019-02-21 2019-07-16 国网山东省电力公司临沂供电公司 The power emergency distribution of materials and configuration system and method
CN111539618A (en) * 2020-04-21 2020-08-14 全球能源互联网研究院有限公司 Emergent scheme system of electric power wisdom
CN111639817A (en) * 2020-06-05 2020-09-08 山东大学 Emergency material demand prediction method and system for power grid meteorological disasters
CN112446619A (en) * 2020-11-27 2021-03-05 国网北京市电力公司 Power distribution network emergency repair processing method and device
CN112488583A (en) * 2020-12-18 2021-03-12 国网山东省电力公司临沂供电公司 Hazardous chemical substance accident power emergency treatment resource allocation processing method
CN112766844A (en) * 2021-01-05 2021-05-07 国网安徽省电力有限公司 Multi-level guarantee deployment method based on networked system
CN112926854A (en) * 2021-02-24 2021-06-08 贵州电网有限责任公司 Distribution network emergency material demand reporting method based on data intelligent perception
CN113962596A (en) * 2021-11-10 2022-01-21 应急管理部国家减灾中心 Method and device for generating intelligent emergency material allocation scheme
CN115796520A (en) * 2022-11-29 2023-03-14 国网山东省电力公司应急管理中心 Emergency resource matching analysis method and device based on multi-source scene element driving
CN116308082A (en) * 2023-02-24 2023-06-23 国网四川省电力公司物资公司 Accurate storage and allocation management method and system for electric power emergency materials

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622365A (en) * 2017-08-18 2018-01-23 国网山东省电力公司聊城供电公司 A kind of Power Material storage management method
CN109087398A (en) * 2018-07-09 2018-12-25 天维尔信息科技股份有限公司 A kind of Rescue Plan simulative training system based on virtual reality
CN109460938A (en) * 2018-11-23 2019-03-12 中国城市和小城镇改革发展中心 A kind of city intelligent central control system and its method
CN111026370B (en) * 2019-12-02 2023-09-29 江苏伟岸纵横科技股份有限公司 Plan visualization method, computer storage medium and electronic device
CN111709636B (en) * 2020-06-11 2024-02-20 全球能源互联网研究院有限公司 Emergency treatment strategy evaluation method and device, electronic equipment and storage medium
CN111898877B (en) * 2020-07-13 2023-07-04 西安交通大学 Pre-deployment method for pre-disaster repair personnel for improving recovery speed of power grid
CN112200378A (en) * 2020-10-21 2021-01-08 中铁第四勘察设计院集团有限公司 Underground complex emergency dispatching command method and system under dynamic feedback mechanism
CN112308250A (en) * 2020-11-04 2021-02-02 海南电网有限责任公司信息通信分公司 Distribution network emergency repair scheduling system and method
CN112396371B (en) * 2020-11-12 2022-12-02 青岛海信网络科技股份有限公司 Multi-target material allocation method and device based on GIS
CN112632341A (en) * 2020-12-29 2021-04-09 清华大学 Emergency processing method, device, equipment and storage medium in sports meeting
CN113255097A (en) * 2021-04-06 2021-08-13 中国核电工程有限公司 Customization platform and method for cold source water taking system
CN113537703B (en) * 2021-06-04 2022-12-02 广东电网有限责任公司广州供电局 Power distribution network pre-disaster emergency resource deployment method and device and computer equipment
CN113222475A (en) * 2021-06-09 2021-08-06 江苏省兴安科技发展有限公司 Natural resource disaster emergency system and method
CN114066328A (en) * 2021-12-27 2022-02-18 南方电网数字电网研究院有限公司 Power grid material allocation method and device
CN114925864B (en) * 2022-06-08 2024-06-07 武汉理工大学 Emergency repair method under typhoon disaster
CN115345465B (en) * 2022-08-10 2023-08-01 航天神舟智慧***技术有限公司 Multicolor level management method and system based on basic level treatment event
CN115545343B (en) * 2022-11-07 2023-04-07 广东电网有限责任公司湛江供电局 Emergency generator car scheduling method, system, equipment and storage medium
CN115796399B (en) * 2023-02-06 2023-04-25 佰聆数据股份有限公司 Intelligent scheduling method, device, equipment and storage medium based on electric power supplies
CN115828353B (en) * 2023-02-10 2023-05-23 武汉智图科技有限责任公司 Emergency map drawing method based on drawing scheme set
CN116307568B (en) * 2023-03-14 2024-01-26 国电南瑞南京控制***有限公司 Electric power material warehouse collaborative scheduling management system based on artificial intelligence
CN116596299A (en) * 2023-04-03 2023-08-15 中国消防救援学院 Emergency management method and system for forest fire control
CN116629628A (en) * 2023-04-26 2023-08-22 中国安全生产科学研究院 Comprehensive evaluation method for disaster prevention and reduction and accident emergency capability of regional space in rural area
CN116800558B (en) * 2023-08-25 2023-11-17 山东未来互联科技有限公司 Emergency scheduling system and method based on deterministic provincial backbone network
CN117035375B (en) * 2023-10-09 2024-01-12 北京国电通网络技术有限公司 Post-disaster evaluation and resource configuration method, device and equipment based on power data

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020143469A1 (en) * 2001-03-30 2002-10-03 Alexander John Franklin Emergency management system
CN102376039A (en) * 2011-12-08 2012-03-14 重庆市电力公司 Method for realizing three-dimensional real-time scheduling commanding of power materials
CN102496089A (en) * 2011-12-16 2012-06-13 江西省电力公司信息通信中心 One-ticket type power emergency command linkage method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8359248B2 (en) * 2006-08-24 2013-01-22 Blue Pillar, Inc. Systems, methods, and devices for managing emergency power supply systems
CN103839188A (en) * 2012-11-22 2014-06-04 国家电网公司 Treatment method and system for power-grid emergency
CN103065270B (en) * 2013-01-05 2017-08-22 深圳供电局有限公司 A kind of electric network fault rushes to repair Visualized Monitoring System

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020143469A1 (en) * 2001-03-30 2002-10-03 Alexander John Franklin Emergency management system
CN102376039A (en) * 2011-12-08 2012-03-14 重庆市电力公司 Method for realizing three-dimensional real-time scheduling commanding of power materials
CN102496089A (en) * 2011-12-16 2012-06-13 江西省电力公司信息通信中心 One-ticket type power emergency command linkage method

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106484966B (en) * 2016-09-22 2019-05-21 北京交通大学 A kind of urban track traffic emergency event dynamic effects range and strength determining method
CN106484966A (en) * 2016-09-22 2017-03-08 北京交通大学 A kind of urban track traffic accident dynamic effect scope and strength determining method
CN108921443A (en) * 2018-07-11 2018-11-30 广东电网有限责任公司 A kind of power grid early warning scheduling system, method, apparatus and server
CN109508887A (en) * 2018-11-19 2019-03-22 国网四川省电力公司攀枝花供电公司 Intelligent emergency matenal support decision system based on artificial intelligence
CN110020778A (en) * 2019-02-21 2019-07-16 国网山东省电力公司临沂供电公司 The power emergency distribution of materials and configuration system and method
CN111539618A (en) * 2020-04-21 2020-08-14 全球能源互联网研究院有限公司 Emergent scheme system of electric power wisdom
CN111639817A (en) * 2020-06-05 2020-09-08 山东大学 Emergency material demand prediction method and system for power grid meteorological disasters
CN112446619B (en) * 2020-11-27 2024-04-26 国网北京市电力公司 Power distribution network rush-repair processing method and device
CN112446619A (en) * 2020-11-27 2021-03-05 国网北京市电力公司 Power distribution network emergency repair processing method and device
CN112488583A (en) * 2020-12-18 2021-03-12 国网山东省电力公司临沂供电公司 Hazardous chemical substance accident power emergency treatment resource allocation processing method
CN112766844A (en) * 2021-01-05 2021-05-07 国网安徽省电力有限公司 Multi-level guarantee deployment method based on networked system
CN112926854A (en) * 2021-02-24 2021-06-08 贵州电网有限责任公司 Distribution network emergency material demand reporting method based on data intelligent perception
CN112926854B (en) * 2021-02-24 2024-03-29 贵州电网有限责任公司 Distribution network emergency material demand reporting method based on data intelligent perception
CN113962596A (en) * 2021-11-10 2022-01-21 应急管理部国家减灾中心 Method and device for generating intelligent emergency material allocation scheme
CN115796520A (en) * 2022-11-29 2023-03-14 国网山东省电力公司应急管理中心 Emergency resource matching analysis method and device based on multi-source scene element driving
CN115796520B (en) * 2022-11-29 2024-02-02 国网山东省电力公司应急管理中心 Emergency resource matching analysis method and device based on multisource scene element driving
CN116308082A (en) * 2023-02-24 2023-06-23 国网四川省电力公司物资公司 Accurate storage and allocation management method and system for electric power emergency materials
CN116308082B (en) * 2023-02-24 2024-05-17 国网四川省电力公司物资公司 Accurate storage and allocation management method and system for electric power emergency materials

Also Published As

Publication number Publication date
CN105303285B (en) 2016-11-09
WO2016034142A1 (en) 2016-03-10

Similar Documents

Publication Publication Date Title
CN105303285B (en) A kind of power emergency is disposed the intellectuality of goods and materials and is alloted method
CN105005827B (en) A kind of emergency response method for early warning based on electric power accident
CN102722767B (en) Electromobile charging and exchanging power station stationing and planning system and method
CN105320712B (en) The dynamic posture drawing method of situation automatic plotting system based on GIS map
CN112365100B (en) Disaster risk comprehensive assessment-based power grid disaster early warning and response method
CN103593712B (en) A kind of Resource Scheduling System and dispatching method
CN105608541A (en) Electric power material supply whole-course early-warning supervise system and method
CN111452669B (en) Intelligent bus charging system and method and medium
CN100498869C (en) GPS vehicle monitoring and scheduling system applying in electric power system
CN104951865A (en) Material allocation tracking method and material allocation tracking system based on power grid GIS (geographic information system)
CN103116825A (en) Intelligent city management system
CN105069100B (en) A kind of mobile terminal Collaborative Plotting method based on power grid GIS
CN106651074A (en) Intelligent underground pipeline management system
CN104992254A (en) Forest fire trend pre-judging method based on power grid GIS and referring to meteorological data
CN104464344B (en) A kind of vehicle running path Forecasting Methodology and system
CN104965854A (en) Automatic plotting method and system for material allocation based on electrical network GIS
Ghasemi et al. Simulation of fire stations resources considering the downtime of machines: A case study
CN114584204B (en) Emergency command system
CN102982407B (en) Electric automobile emergency rescue platform based on natural selection particle swarm optimization (PSO) decision algorithm
CN113177858B (en) Multi-dimensional power grid typhoon resistance evaluation method
Statsenko et al. Developing software and hardware for automation of ground urban transport traffic management
CN109449930B (en) Power distribution network reliability assessment and repair time parameter modeling method, equipment and medium
CN113902346B (en) Intelligent allocation method for electric power rush-repair team
CN105139327A (en) Linkage system and method for traffic line and network command platform
Runhua et al. Design scheme of public transport comprehensive dispatching MIS based on MAS

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Jiang Bin

Inventor after: Yang Xiaoshuai

Inventor after: Wang Bo

Inventor after: Cheng Zhonghua

Inventor after: Di Jiqing

Inventor after: Sun Hongzhi

Inventor after: He Zhiqiang

Inventor after: Sun Shijun

Inventor after: Zhang Zhiqu

Inventor after: Sun Weimin

Inventor after: Su Chuanlin

Inventor after: Zhao Wei

Inventor after: Li Dong

Inventor after: Han Hong

Inventor after: Zhang Peng

Inventor before: Jiang Bin

Inventor before: Cheng Zhonghua

Inventor before: Sun Weimin

Inventor before: Sun Shijun

Inventor before: Zhang Peng

Inventor before: Li Dong

Inventor before: Zhang Zhiqu

Inventor before: Han Hong

Inventor before: Yang Xiaoshuai

Inventor before: Wang Bo

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant