CN108560705A - The connecting node and construction method of assembled integral energy consumption frame - Google Patents

The connecting node and construction method of assembled integral energy consumption frame Download PDF

Info

Publication number
CN108560705A
CN108560705A CN201810149150.7A CN201810149150A CN108560705A CN 108560705 A CN108560705 A CN 108560705A CN 201810149150 A CN201810149150 A CN 201810149150A CN 108560705 A CN108560705 A CN 108560705A
Authority
CN
China
Prior art keywords
prefabricated post
precast beam
damper
connecting node
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810149150.7A
Other languages
Chinese (zh)
Inventor
李琰
李天际
王晓旻
侯羽中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201810149150.7A priority Critical patent/CN108560705A/en
Publication of CN108560705A publication Critical patent/CN108560705A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/025Structures with concrete columns

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention belongs to fabricated construction technical fields, and in particular to a kind of connecting node and construction method of assembled integral energy consumption frame.The connecting node, including prefabricated post, precast beam, a pair of of damper built-in fitting and a fluid linking damper, wherein, one end of precast beam and the top of the prefabricated post form entirety by cast-in-place concrete, and the both ends of fluid linking damper are separately fixed on two damper built-in fittings.The connecting node realizes dissipation energy by the damping force that fluid linking damper provides, reduce the vibration amplitude and the frequency of the connecting node of precast beam and prefabricated post, prefabricated integral frame structure premature failure in geological process is avoided, to have better ability of against earthquakes and disaster reduction.The construction method step is simple, process is reasonable, and can guarantee that the connecting node for the assembled integral energy consumption frame that construction is completed has preferable ability of against earthquakes and disaster reduction.

Description

The connecting node and construction method of assembled integral energy consumption frame
Technical field
The invention belongs to fabricated construction technical fields, and in particular to a kind of connecting node of assembled integral energy consumption frame And construction method.
Background technology
With the propulsion of building industrialization process, assembled monolithic concrete structure has become the heat of national construction market Point, scale and prefabricated rate are constantly soaring.With the enhancing of environmental consciousness, green building plan has been released in drug in some provinces, must The making for so having more and more supporting members uses prefabrication and assembly construction technique.
Assembled monolithic concrete structure refers to that concrete prefabricated element to form rigidly connected coagulation by being poured behind scene Soil structure, such as rigid frame structure.Frequently with mode be that negative reinforcement is stayed on precast beam, cast in situs hogging moment area Domain makes prefabricated concrete structure have the characteristic substantially equivalent with cast-in-place concrete structure.
And China's most area is at the area that provides fortification against earthquakes, the practical ability of against earthquakes and disaster reduction of cast in place and precast construction also has It waits in discussion.
Invention content
The problem of people worry, this hair can not be eliminated for the practical ability of against earthquakes and disaster reduction of existing cast in place and precast construction The bright connecting node and construction method for providing a kind of assembled integral energy consumption frame, it is attached in precast beam and prefabricated post connecting portion Nearly a pair of of damper built-in fitting of setting, and fluid linking damper is installed, the damping force provided by fluid linking damper dissipates to realize Energy reduces the vibration amplitude and the frequency of the connecting node of precast beam and prefabricated post, avoids prefabricated integral frame structure on ground Premature failure when shake acts on, to have better ability of against earthquakes and disaster reduction.
In order to solve the above technical problems, the present invention includes following technical solution:
A kind of connecting node of assembled integral energy consumption frame, including:
Vertically arranged prefabricated post;
Horizontally disposed precast beam, and one end of the precast beam and the top of the prefabricated post pass through cast-in-place concrete shape It is integral;
A pair of of damper built-in fitting, an inside top for being set to the prefabricated post, another is set to described prefabricated Below the end of beam;And
Fluid linking damper, both ends are separately fixed on the damper built-in fitting.
Preferably, the damper built-in fitting includes socket joint plate, the connecting plate that is fixedly installed on socket joint plate one end, sets The peg being placed on the socket joint plate, and it is set to the suspension otic placode of the connecting plate other end, the socket joint plate is embedded in The inside of the precast beam or prefabricated post.
Preferably, the outer surface of the connecting plate and the precast beam or the flush of prefabricated post.
Preferably, the socket joint plate is H-type or cross, and is provided with the longitudinal reinforcement for the prefabricated post or precast beam The bar connecting hole passed through.
Preferably, it is provided with earhole on the suspension otic placode, the end set of the fluid linking damper has connecting hole, described Fluid linking damper across the axis pin of the connecting hole, earhole by being fixed on the suspension otic placode.
Preferably, the prefabricated post is reinforced concrete structure, stretches out concrete at the top of the longitudinal reinforcement of the prefabricated post Top is simultaneously provided with sleeve, and the sleeve is provided with grouting liquid with the gap of the longitudinal reinforcement of the prefabricated post.
Correspondingly, the present invention also provides a kind of construction method of the connecting node, include the following steps:
S1. then sleeve is fixed on the longitudinal reinforcement of the prefabricated post by hoisting prefabricated column to design position, and to institute It states and injects grouting material in sleeve;
S2. hoisting prefabricated beam is to the top of the prefabricated post, makes the precast beam, the damper built-in fitting phase in prefabricated post To setting, the absolute altitude of the precast beam is then adjusted to design position;
S3. formwork erection and the precast beam and the connecting portion of prefabricated post are poured, after concrete strength reaches strength of mould stripping, Form removal;
S4. the both ends of fluid linking damper are separately fixed on the damper built-in fitting.
Due to using the technology described above, the connecting node of assembled integral energy consumption frame provided by the invention has as follows Advantage:(1) components such as precast beam, prefabricated post are prefabricated in the factory, and damper built-in fitting is prefabricated in precast beam, prefabricated post, Only precast beam, prefabricated post need to be transported to on-site consolidation, the cast-in-place rear installation fluid linking damper of connecting portion is greatly improved existing Field construction efficiency;(2) it when there is seismic energy input, realizes dissipation energy by the damping force of fluid linking damper offer, reaches To the vibratory response for reducing structure, the vibration amplitude and the frequency of the connecting node of precast beam and prefabricated post are reduced, avoids assembling whole Body formula frame structure premature failure in geological process, to have better ability of against earthquakes and disaster reduction;(3) fluid linking damper is fixed On damper built-in fitting, it is provided with peg and bar connecting hole on the socket joint plate socket joint plate of damper built-in fitting, to make resistance Buddhist nun's device built-in fitting forms overall structure with precast beam.
In addition, the construction method of the connecting node of assembled integral provided in this embodiment energy consumption frame, step is simple, work Sequence is reasonable, and can guarantee that the connecting node for the assembled integral energy consumption frame that construction is completed has preferable protection against and mitigation of earthquake disasters energy Power.
Description of the drawings
Fig. 1 is the structural schematic diagram of the connecting node of the assembled integral energy consumption frame in one embodiment of the invention;
Fig. 2 is the connection diagram of the fluid linking damper and damper built-in fitting in one embodiment of the invention;
Fig. 3 is a kind of structural schematic diagram for damper built-in fitting that one embodiment of the invention provides;
Fig. 4 is the structural schematic diagram for another damper built-in fitting that one embodiment of the invention provides.
Figure label is as follows:
1- prefabricated posts;11- longitudinal reinforcements;12- sleeves;2- precast beams;3- damper built-in fittings;31- socket joint plates;31a- steel Muscle connecting hole;32- connecting plates;33- pegs;34- hangs otic placode;34a- earholes;4- fluid linking dampers.
Specific implementation mode
Below in conjunction with the drawings and specific embodiments to assembled integral provided by the invention consume energy frame connecting node and Construction method is described in further detail.In conjunction with following explanation and claims, advantages and features of the invention will become apparent from. It should be noted that attached drawing is all made of very simplified form and uses non-accurate ratio, only to it is convenient, lucidly assist Illustrate the purpose of the embodiment of the present invention.
Embodiment one
As depicted in figs. 1 and 2, the connecting node of assembled integral energy consumption frame provided in this embodiment, including prefabricated post 1, precast beam 2, a pair of of damper built-in fitting 3 and a fluid linking damper 4.Wherein, prefabricated post 1 is vertically arranged, and precast beam 2 is horizontal Setting, and one end of precast beam 2 and the top of the prefabricated post 1 form entirety by cast-in-place concrete.One of damper Built-in fitting 3 is set to the inside top (prefabricated post 1 and precast beam 2 be inside to opposite) of the prefabricated post 1, another setting Below the end of the precast beam 2, the both ends of fluid linking damper 4 are separately fixed on two damper built-in fittings 3.
The connecting node of the assembled integral energy consumption frame of the present invention, damper built-in fitting 3 is prefabricated in precast beam 2 and pre- In column 1 processed, at the construction field (site) by the cast-in-place formation prefabricated integral frame structure of connecting portion of precast beam 2 and prefabricated post 1, and will Fluid linking damper 4 is fixed on damper built-in fitting 3, is realized dissipation energy by the damping force of the offer of fluid linking damper 4, is kept away Exempt from the destruction of prefabricated integral frame structure.Therefore, the connecting node of assembled integral energy consumption frame provided by the invention has such as Lower advantage:(1) components such as precast beam 2, prefabricated post 1 are prefabricated in the factory, and damper built-in fitting 3 it is prefabricated in precast beam 2, it is prefabricated In column 1, only precast beam 2, prefabricated post 1 need to be transported to on-site consolidation, by connecting portion it is cast-in-place after install fluid linking damper 4, Site operation efficiency is greatly improved;(2) it when there is seismic energy input, is realized by the damping force of the offer of fluid linking damper 4 Dissipation energy reaches the vibratory response for reducing structure, reduces the vibration amplitude and frequency of the connecting node of precast beam 2 and prefabricated post 1 It is secondary, prefabricated integral frame structure premature failure in geological process is avoided, to have better ability of against earthquakes and disaster reduction.
Fig. 3 and Fig. 4 illustrates the structure type of two kinds of damper built-in fittings 3, and the damper built-in fitting 3 of both forms is all Including socket joint plate 31, the connecting plate 32 for being fixedly installed on described 31 one end of socket joint plate, the peg being set on the socket joint plate 31 33, and it is set to the suspension otic placode 34 of 32 other end of the connecting plate, the socket joint plate 31 is embedded in the precast beam 2 or pre- The inside of column 1 processed.Difference lies in Fig. 3, socket joint plate 31 is H-type, and socket joint plate 31 is cross in Fig. 4.It is provided with peg 33 Socket joint plate 31 is embedded in prefabricated components, and damper built-in fitting 3 is made to be securely fastened in prefabricated components, wherein the number of peg 33 Amount and spacing can be damped according to the maximum of the design of damper built-in fitting 3, the actual size of precast beam 2 and fluid linking damper Power etc. is adjusted.Preferably, prefabricated post 1, precast beam 2 use reinforced concrete structure, are provided on socket joint plate 31 for prefabricated The bar connecting hole 31a that passes through of longitudinal reinforcement of column 1, precast beam 2, to which socket joint plate 31 is fixed on prefabricated post 1 or precast beam 2 Longitudinal reinforcement on, so that damper built-in fitting 3 and prefabricated post 1 or precast beam 2 is formed overall structure, wherein bar connecting hole 31a Quantity and spacing and the quantity and spacing of prefabricated post 1 or the longitudinal reinforcement of precast beam 2 match.Wherein connecting plate 32 and hold The material specification (including material, specific size) of plate 31 should be determined according to the damping force numerical value of design.Further, described The outer surface of connecting plate 32 and the precast beam 2 or the flush of prefabricated post 1.
As shown in Figure 3 and Figure 4, it hangs on otic placode 34 and is provided with earhole 34a, the end set of the fluid linking damper 4 has Connecting hole, the fluid linking damper 4 across the axis pin of the connecting hole, earhole 34a by being fixed on the suspension otic placode 34. It is connected by axis pin between fluid linking damper 4 and damper built-in fitting 3, connection type is simple, and splicing is convenient.
Preferably, as shown in Figure 1, the prefabricated post 1 is reinforced concrete structure, the longitudinal reinforcement 11 of the prefabricated post 1 Concrete top is stretched out at top, and is provided with sleeve 12, in the gap of the longitudinal reinforcement 11 of the sleeve 12 and the prefabricated post 1 It is provided with grouting liquid.Sleeve 12 is set on the longitudinal reinforcement 11 of prefabricated post 1, it is convenient right with the longitudinal reinforcement 11 of upper layer prefabricated post 1 It connects, the longitudinal reinforcement that prefabricated components are connected with sleeve 12 is the prior art, is not repeated herein.
Embodiment two
The construction method of the connecting node of the assembled integral energy consumption frame in a kind of embodiment one is present embodiments provided, Shown in Fig. 1 to Fig. 4, which is further described, is specifically comprised the following steps:
S1. then sleeve 12 is fixed on the longitudinal reinforcement of the prefabricated post 1 by hoisting prefabricated column 1 to design position, and Grouting material is injected into the sleeve 12.Prefabricated post 1 is vertically arranged, and is arranged sleeve 12 on the longitudinal reinforcement of prefabricated post 1, it is convenient with The longitudinal reinforcement of upper layer prefabricated post 1 docks.
S2. hoisting prefabricated beam 2 is to the top of the prefabricated post 1, keeps the precast beam 2, the damper in prefabricated post 1 pre-buried Part 3 is oppositely arranged, and then adjusts the absolute altitude of the precast beam 2 to design position.
S3. formwork erection and the connecting portion of the precast beam 2 and prefabricated post 1 is poured, waits for that concrete strength reaches strength of mould stripping Afterwards, form removal.Pass through cast-in-place formation prefabricated integral frame at precast beam 2 and the connecting node of prefabricated post 1.
S4. the both ends of fluid linking damper 4 are separately fixed on the damper built-in fitting 3.As an example, damper is pre- Embedded part 3 includes suspension otic placode 34, hangs and is provided with earhole 34a on otic placode 34, and fluid linking damper 4 is provided at both ends with pin hole, will After pin hole is aligned with earhole 34a, fixed with axis pin.
The construction method of the connecting node of assembled integral energy consumption frame provided in this embodiment, step is simple, process is closed Reason, and can guarantee that the connecting node for the assembled integral energy consumption frame that construction is completed has preferable ability of against earthquakes and disaster reduction.
Each technical characteristic of embodiment described above can be combined arbitrarily, to keep description succinct, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, it is all considered to be the range of this specification record.
Several embodiments of the invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the protection of the present invention Range.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (7)

1. a kind of connecting node of assembled integral energy consumption frame, which is characterized in that including:
Vertically arranged prefabricated post;
Horizontally disposed precast beam, and the top of one end of the precast beam and the prefabricated post formed by cast-in-place concrete it is whole Body;
A pair of of damper built-in fitting, an inside top for being set to the prefabricated post, another is set to the precast beam Below end;And
Fluid linking damper, both ends are separately fixed on the damper built-in fitting.
2. connecting node as described in claim 1, which is characterized in that
The damper built-in fitting includes socket joint plate, is fixedly installed on socket joint plate one end connecting plate is set to described hold Peg on plate, and it is set to the suspension otic placode of the connecting plate other end, the socket joint plate is embedded in the precast beam Or the inside of prefabricated post.
3. connecting node as claimed in claim 2, which is characterized in that the outer surface of the connecting plate is with the precast beam or in advance The flush of column processed.
4. connecting node as claimed in claim 2, which is characterized in that
The socket joint plate is H-type or cross, and is provided with the reinforcing bar passed through for the longitudinal reinforcement of the prefabricated post or precast beam Connecting hole.
5. connecting node as claimed in claim 2, which is characterized in that
Earhole is provided on the suspension otic placode, the end set of the fluid linking damper has connecting hole, the fluid linking damper By being fixed on the suspension otic placode across the axis pin of the connecting hole, earhole.
6. connecting node as described in claim 1, which is characterized in that
The prefabricated post is reinforced concrete structure, and concrete top is stretched out at the top of the longitudinal reinforcement of the prefabricated post and is provided with Sleeve, the sleeve are provided with grouting liquid with the gap of the longitudinal reinforcement of the prefabricated post.
7. a kind of construction method of such as claim 1 to 6 any one of them connecting node, which is characterized in that including walking as follows Suddenly:
S1. then sleeve is fixed on the longitudinal reinforcement of the prefabricated post by hoisting prefabricated column to design position, and to the set Grouting material is injected in cylinder;
S2. hoisting prefabricated beam is to the top of the prefabricated post, makes that the precast beam, the damper built-in fitting in prefabricated post is opposite sets It sets, then adjusts the absolute altitude of the precast beam to design position;
S3. formwork erection and the precast beam and the connecting portion of prefabricated post are poured, after concrete strength reaches strength of mould stripping, removed Template;
S4. the both ends of fluid linking damper are separately fixed on the damper built-in fitting.
CN201810149150.7A 2018-02-13 2018-02-13 The connecting node and construction method of assembled integral energy consumption frame Pending CN108560705A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810149150.7A CN108560705A (en) 2018-02-13 2018-02-13 The connecting node and construction method of assembled integral energy consumption frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810149150.7A CN108560705A (en) 2018-02-13 2018-02-13 The connecting node and construction method of assembled integral energy consumption frame

Publications (1)

Publication Number Publication Date
CN108560705A true CN108560705A (en) 2018-09-21

Family

ID=63531183

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810149150.7A Pending CN108560705A (en) 2018-02-13 2018-02-13 The connecting node and construction method of assembled integral energy consumption frame

Country Status (1)

Country Link
CN (1) CN108560705A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258791A (en) * 2019-06-14 2019-09-20 中国建筑股份有限公司 A kind of hingedly not damaged energy consumption precast frame bean column node and its construction method
CN110528777A (en) * 2019-09-10 2019-12-03 东南大学 Anti-seismic structure between a kind of assembled beam
CN112376939A (en) * 2020-10-23 2021-02-19 安徽一品小院建筑科技有限公司 Prefabricated reinforced concrete frame structure supports and consolidates node component
CN112854438A (en) * 2021-03-15 2021-05-28 重庆大学 Assembly type concrete frame system with exposed flat net rack floor and exposed truss girder
CN113463755A (en) * 2021-06-25 2021-10-01 无锡市亨利富建设发展有限公司 Concrete frame column anti-seismic structure and construction method thereof
CN114909011A (en) * 2022-05-11 2022-08-16 重庆大学 Floor damage-free replaceable assembled beam column node

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202007535U (en) * 2010-11-30 2011-10-12 上海维固工程实业有限公司 Supporting reinforcing structure
CN203924361U (en) * 2014-06-12 2014-11-05 新疆电力设计院 For the corner energy dissipation apparatus of thermal power plant's bent structure
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system
CN104652600A (en) * 2015-02-25 2015-05-27 海南大学 Recoverable function framework structure system
CN105804262A (en) * 2016-03-25 2016-07-27 合肥工业大学 Energy consumption support and assembly type concrete framework dual energy consumption node and assembly method
CN105821960A (en) * 2016-03-25 2016-08-03 合肥工业大学 Energy consumption support assembly type concrete framework structure splicing node and assembling method thereof
CN107447885A (en) * 2017-09-20 2017-12-08 青岛理工大学 Suitable for the plug and play energy dissipation apparatus of assembling frame structure
CN208088501U (en) * 2018-02-13 2018-11-13 上海建工五建集团有限公司 The connecting node of assembled integral energy consumption frame

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202007535U (en) * 2010-11-30 2011-10-12 上海维固工程实业有限公司 Supporting reinforcing structure
CN203924361U (en) * 2014-06-12 2014-11-05 新疆电力设计院 For the corner energy dissipation apparatus of thermal power plant's bent structure
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system
CN104652600A (en) * 2015-02-25 2015-05-27 海南大学 Recoverable function framework structure system
CN105804262A (en) * 2016-03-25 2016-07-27 合肥工业大学 Energy consumption support and assembly type concrete framework dual energy consumption node and assembly method
CN105821960A (en) * 2016-03-25 2016-08-03 合肥工业大学 Energy consumption support assembly type concrete framework structure splicing node and assembling method thereof
CN107447885A (en) * 2017-09-20 2017-12-08 青岛理工大学 Suitable for the plug and play energy dissipation apparatus of assembling frame structure
CN208088501U (en) * 2018-02-13 2018-11-13 上海建工五建集团有限公司 The connecting node of assembled integral energy consumption frame

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258791A (en) * 2019-06-14 2019-09-20 中国建筑股份有限公司 A kind of hingedly not damaged energy consumption precast frame bean column node and its construction method
CN110258791B (en) * 2019-06-14 2024-04-26 中国建筑股份有限公司 Hinged nondestructive energy consumption prefabricated frame beam column node and construction method thereof
CN110528777A (en) * 2019-09-10 2019-12-03 东南大学 Anti-seismic structure between a kind of assembled beam
CN112376939A (en) * 2020-10-23 2021-02-19 安徽一品小院建筑科技有限公司 Prefabricated reinforced concrete frame structure supports and consolidates node component
CN112854438A (en) * 2021-03-15 2021-05-28 重庆大学 Assembly type concrete frame system with exposed flat net rack floor and exposed truss girder
CN113463755A (en) * 2021-06-25 2021-10-01 无锡市亨利富建设发展有限公司 Concrete frame column anti-seismic structure and construction method thereof
CN114909011A (en) * 2022-05-11 2022-08-16 重庆大学 Floor damage-free replaceable assembled beam column node
CN114909011B (en) * 2022-05-11 2024-06-11 重庆大学 Replaceable assembled beam column node free of floor damage

Similar Documents

Publication Publication Date Title
CN108560705A (en) The connecting node and construction method of assembled integral energy consumption frame
CN108104273B (en) Assembled self- recoverage concrete filled steel tube combined joint and installation method and structural system
CN105155685B (en) A kind of assembled beam-column node and its construction method
CN106401018B (en) A kind of assembled self-resetting swinging steel plate wall structural system
CN205776734U (en) A kind of assembly concrete connecting structure of beam column nodes
CN100547187C (en) A kind of storied-building board energy-eliminating shock-insulating structure
CN106382041B (en) A kind of assembled waves Self-resetting steel support structure system
CN207919751U (en) Assembled self- recoverage concrete filled steel tube combined joint and structural system
CN106978853A (en) A kind of controllable steel node of prefabricated assembled concrete structural plasticity
CN103967127B (en) The different strong coupled column assembled beam frame of built-in stem stem and constructional method thereof
CN208501878U (en) A kind of Self-resetting prefabrication and assembly construction frame structure interior joint
CN206189976U (en) Assembled waves from restoring to throne steel supporting structural system
CN106758786A (en) A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier
CN207003652U (en) A kind of compound concrete-filled tubular column and steel tube concrete beam composite frame structure
CN109629403B (en) Concrete support column structure and manufacturing method thereof
KR101565543B1 (en) A Joint Structures Between Steel Frame and Iron Concrete and A Joint Method
CN108412128A (en) A kind of connection structure of steel core concrete column
CN106836490A (en) A kind of prestressing force assembled high-performance concrete-filled steel square tubular column concrete girder connection and its construction method
CN103741817A (en) Enhancement method of X-shaped reinforcing bars for improving seismic resistance of special-shaped column nodes
CN101024987A (en) Storied-building energ-eliminating shock-damping structure
CN206256622U (en) Damage with runback bit function can repair assembled coupled column
CN110528777A (en) Anti-seismic structure between a kind of assembled beam
Hemmati et al. Experimental study of reinforced concrete frame rehabilitated by concentric and eccentric bracing
CN206267356U (en) A kind of assembled self-resetting swinging steel plate wall structural system
CN208088501U (en) The connecting node of assembled integral energy consumption frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180921