CN108521129A - Micro-capacitance sensor off-load method, apparatus, system and storage medium - Google Patents

Micro-capacitance sensor off-load method, apparatus, system and storage medium Download PDF

Info

Publication number
CN108521129A
CN108521129A CN201810365906.1A CN201810365906A CN108521129A CN 108521129 A CN108521129 A CN 108521129A CN 201810365906 A CN201810365906 A CN 201810365906A CN 108521129 A CN108521129 A CN 108521129A
Authority
CN
China
Prior art keywords
load
priority
active power
power
cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810365906.1A
Other languages
Chinese (zh)
Other versions
CN108521129B (en
Inventor
魏阳
徐光福
余群兵
陈俊
朱皓斌
华秀娟
姜淼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NR Electric Co Ltd
NR Engineering Co Ltd
Original Assignee
NR Electric Co Ltd
NR Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NR Electric Co Ltd, NR Engineering Co Ltd filed Critical NR Electric Co Ltd
Priority to CN201810365906.1A priority Critical patent/CN108521129B/en
Publication of CN108521129A publication Critical patent/CN108521129A/en
Application granted granted Critical
Publication of CN108521129B publication Critical patent/CN108521129B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The embodiment of the invention discloses a kind of micro-capacitance sensor off-load methods, including:Monitor the mains frequency of the micro-capacitance sensor;Receive the operation of power networks parameter that intelligent monitoring terminal is sent;When the mains frequency drops to the frequency values of setting, according to the operation of power networks parameter acquiring active power shortage;According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;The cutting load instruction of the load for needing to cut off is sent to intelligent monitoring terminal.The embodiment of the invention also discloses a kind of micro-capacitance sensor load-shedding equipment, system and computer readable storage mediums.

Description

Micro-capacitance sensor off-load method, apparatus, system and storage medium
Technical field
The present invention relates to micro-capacitance sensor technical fields, and in particular to a kind of micro-capacitance sensor off-load method, apparatus, system and storage are situated between Matter.
Background technology
Concern with the increasingly failure and people of earth resource to environmental problem, the access of regenerative resource is increasingly By the most attention of countries in the world.Micro-capacitance sensor be by distributed generation resource, energy storage device, energy conversion device, load, monitoring and The small-sized electric system of the compositions such as protective device.
Micro-capacitance sensor compares bulk power grid, and there are inherent advantage, scale is much smaller than bulk power grid, power supply, load limited amount, Grid structure is simple, thus is easy that micro-capacitance sensor is monitored and controlled.And frequency stabilization has the stable operation of micro-capacitance sensor It is significant.Under the pattern of being incorporated into the power networks, frequency is controlled micro-capacitance sensor by bulk power grid, thus the stabilization of frequency is tieed up by bulk power grid It holds;When micro-capacitance sensor and bulk power grid, which disconnect, enters islet operation pattern, frequency need to be controlled by itself, since micro-capacitance sensor is at this time A independent hair system, equivalent moment of inertia very little, a small amount of power swing will cause significant frequency shift (FS), and each distribution Formula power supply is using small-scale dispersion access way, so the concentration access way of the more traditional bulk power grid of its fluctuation, randomness is bright Seem more, thus micro-capacitance sensor must configure a certain proportion of energy-storage travelling wave tube, to safeguard the stability of mains frequency.But even if Micro-capacitance sensor is configured with certain proportion energy-storage travelling wave tube, the problem of can not being fully solved the frequency stabilization of micro-capacitance sensor.
Invention content
In order to solve problem above, the embodiment of the present invention provides a kind of micro-capacitance sensor low frequency deloading method, device, system and deposits Storage media, can be when micro-capacitance sensor frequency declines, and quickly and accurately cutting load, makes frequency retrieval to rated value, to protect Demonstrate,prove the stable operation of micro-capacitance sensor.
In order to achieve the above object, the technical solution of the embodiment of the present invention is realized in:
A kind of micro-capacitance sensor off-load method, the method includes:
Monitor the mains frequency of the micro-capacitance sensor;
Receive the operation of power networks parameter that intelligent monitoring terminal is sent;
When the mains frequency drops to the frequency values of setting, lacked according to the operation of power networks parameter acquiring active power Volume;
According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;
The cutting load instruction of the load for needing to cut off is sent to intelligent monitoring terminal.
In said program, the operation of power networks parameter for receiving intelligent monitoring terminal transmission includes:It is whole to receive intelligent monitoring Hold the power supply active power sent and distributed generation resource that can issue additional power;
It is described according to the operation of power networks parameter acquiring active power shortage, including:According to the power supply active power and The distributed generation resource can issue additional power and obtain active power shortage.
In said program, the operation of power networks parameter for receiving intelligent monitoring terminal and sending, including:Receive intelligent terminal hair The active power of the load sent and the reference numeral of load;
Wherein, the determination of the reference numeral of the load, including:Load is grouped according to different brackets, it is negative to organizing Lotus sets the first priority orders, to the second priority orders of load setting in group load;The load is preferential according to first Grade sequence and the second priority orders are numbered.
It is described according to active power shortage and cutting load priority orders in said program, determine need to cut off it is negative Lotus sends the cutting load instruction of the load for needing to cut off to intelligent monitoring terminal, including:
Judge whether the active power shortage is greater than or equal to the group load of lower priority sequence in the first priority Total active power;
Determine that the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority When active power, the group load for cutting off lower priority sequence in first priority is determined, sent to intelligent monitoring terminal Cut off the cutting load instruction of the reference numeral of the load of the group load of lower priority sequence in first priority.
It is described to judge whether the active power shortage is relatively low preferential more than or equal in the first priority in said program Grade sequence group load total active power, further include:
Determine that the active power shortage is less than total wattful power of the group load of lower priority sequence in the first priority When rate, then judge whether the active power shortage is greater than or equal in described group of load that lower priority is suitable in the second priority The active power of the load of sequence;
Determine that the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority Load active power when, the load for cutting off lower priority sequence in second priority is determined, to intelligent monitoring end End sends the cutting load instruction for cutting off the reference numeral of the load of lower priority sequence in second priority.
In said program, the method further includes:
Judge whether the active power shortage is less than or equal to the threshold value of setting;
When the active power shortage is less than or equal to the threshold value of setting, is sent to intelligent monitoring terminal and utilize energy storage Control unit realizes the control instruction of active power balance.
A kind of micro-capacitance sensor off-load method, the method includes:
Operation of power networks parameter is obtained, the operation of power networks parameter is sent to piconet controller;
Receive the cutting load instruction that piconet controller is sent;Wherein, the cutting load instruction is according to cutting load priority Sequentially and from the active power shortage of the operation of power networks parameter acquiring determine;
It is instructed according to the cutting load and carries out load excision.
In said program, the operation of power networks parameter is sent to piconet controller by the acquisition operation of power networks parameter, packet It includes:
According to the signal of the power supply, switch that acquire in real time, obtaining the distributed generation resource of power supply active power and input can increase Power is sent out, the power supply active power and the distributed generation resource can be issued additional into power and are sent to piconet controller.
In said program, operation of power networks parameter is sent to piconet controller, also wrapped by the acquisition operation of power networks parameter It includes:The active power for obtaining load in power grid, determines the reference numeral of the load;Wherein, the reference numeral of the load It determines, including:Load is grouped according to different brackets, to the first priority orders of group load setting, to being born in group load Lotus sets the second priority orders;The load is numbered according to the first priority orders and the second priority orders;It will The reference numeral of the active power of the load and the load is sent to piconet controller.
In said program, the cutting load instruction for receiving piconet controller and sending is instructed according to the cutting load and is carried out Load is cut off, including:
Receive the load of the group load of lower priority sequence in excision first priority that piconet controller is sent Reference numeral cutting load instruction, and the group load of lower priority sequence in first priority is cut off.
In said program, the cutting load instruction for receiving piconet controller and sending is instructed according to the cutting load and is carried out Load is cut off, and further includes:
The corresponding of load for receiving lower priority sequence in excision second priority that piconet controller is sent is compiled Number cutting load instruction, and the load of lower priority sequence in second priority is cut off.
In said program, the method further includes:
The control instruction that piconet controller is sent is received, the balance of active power is realized according to the control instruction.
A kind of micro-capacitance sensor load-shedding equipment, described device include:
Monitoring unit, the mains frequency for monitoring the micro-capacitance sensor;
First receiving unit, the operation of power networks parameter for receiving intelligent monitoring terminal transmission;
First processing units, when frequency values for dropping to setting when the mains frequency, according to the operation of power networks Parameter acquiring active power shortage;It is additionally operable to according to active power shortage and cutting load priority orders, determination needs to cut off Load;
First transmission unit, the cutting load instruction for sending the load for needing to cut off to intelligent monitoring terminal.
In said program, first receiving unit is additionally operable to receive the power supply active power that intelligent monitoring terminal is sent Power can be issued additional with distributed generation resource;The first processing units are additionally operable to according to the power supply active power and the distribution Formula power supply can issue additional power and obtain active power shortage.
In said program, first receiving unit, be additionally operable to receive intelligent terminal send load active power and The reference numeral of load;
Wherein, the determination of the reference numeral of the load, including:Load is grouped according to different brackets, it is negative to organizing Lotus sets the first priority orders, to the second priority orders of load setting in group load;The load is preferential according to first Grade sequence and the second priority orders are numbered.
In said program, the first processing units are additionally operable to judge whether the active power shortage is greater than or equal to Total active power of the group load of lower priority sequence in first priority;
Determine that the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority When active power, the group load for cutting off lower priority sequence in first priority is determined;
First transmission unit is additionally operable to send to intelligent monitoring terminal relatively low preferential in excision first priority The cutting load instruction of the reference numeral of the load of the group load of grade sequence.
In the above method, the first processing units are additionally operable to determine that the active power shortage is less than the first priority When total active power of the group load of middle lower priority sequence, then judge whether the active power shortage is greater than or equal to institute State the active power of the load of lower priority sequence in the second priority in group load;
Determine that the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority Load active power when, determine the load for cutting off lower priority sequence in second priority;
First transmission unit is additionally operable to send to intelligent monitoring terminal relatively low preferential in excision second priority The cutting load instruction of the reference numeral of the load of grade sequence.
In said program, the first processing units are additionally operable to judge whether the active power shortage is less than or equal to The threshold value of setting;
First transmission unit is additionally operable to send to intelligent monitoring terminal and realizes active power using energy storage control unit The control instruction of balance.
A kind of micro-capacitance sensor load-shedding equipment, described device include:
Second processing unit, for obtaining operation of power networks parameter;
Second transmission unit, for the operation of power networks parameter to be sent to piconet controller;
Second receiving unit, the cutting load instruction for receiving piconet controller transmission;Wherein, the cutting load, which instructs, is It is determined according to cutting load priority orders and from the active power shortage of the operation of power networks parameter acquiring;
Unit is cut off, load excision is carried out for being instructed according to the cutting load.
In said program, the second processing unit, also with the signal according to the power supply of acquisition, switch, obtaining power supply has Work(power and the distributed generation resource of input can issue additional power;Second transmission unit, also with by the power supply active power and The distributed generation resource can issue additional power and be sent to piconet controller.
In said program, the second processing unit is additionally operable to obtain the active power of load in power grid, determines described negative The reference numeral of lotus;The determination of the corresponding number of the wherein described load, including:Load is grouped according to different brackets, To the first priority orders of group load setting, to the second priority orders of load setting in group load;By the load according to One priority orders and the second priority orders are numbered;
Second transmission unit is additionally operable to the reference numeral of the active power of the load and the load being sent to Piconet controller.
In said program, it is excellent to be additionally operable to the excision described first that reception piconet controller is sent for second receiving unit The cutting load instruction of the load reference numeral of the group load of lower priority sequence in first grade;
The excision unit is additionally operable to cut off the group load of lower priority sequence in first priority.
In said program, it is excellent to be additionally operable to the excision described second that reception piconet controller is sent for second receiving unit The cutting load instruction of the reference numeral of the load of lower priority sequence in first grade;
The excision unit is additionally operable to cut off the load of lower priority sequence in second priority.
In said program, described device further includes:Energy storage control unit;Second receiving unit, is additionally operable to receive micro- The control instruction that net controller is sent;The energy storage control unit, for realizing the flat of active power by the control instruction Weighing apparatus.
The embodiment of the present invention additionally provides a kind of micro-capacitance sensor unloading system, the system comprises:Piconet controller and intelligence Monitor terminal;
Wherein, the piconet controller is used to monitor the mains frequency of the micro-capacitance sensor;Intelligent monitoring terminal is received to send Operation of power networks parameter;When the mains frequency drops to the frequency values of setting, had according to the operation of power networks parameter acquiring Work(power shortage;According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;To intelligent monitoring Terminal sends the cutting load instruction of the load for needing to cut off;
The operation of power networks parameter is sent to microgrid control by the intelligent monitoring terminal for obtaining operation of power networks parameter Device;Receive the cutting load instruction that piconet controller is sent;Wherein, cutting load instruction be according to cutting load priority orders and It is determined from the active power shortage of the operation of power networks parameter acquiring;It is instructed according to the cutting load and carries out load excision.
An embodiment of the present invention provides a kind of storage medium, there are computer executable instructions in the storage medium, it is described Computer executable instructions are executed by processor the micro-capacitance sensor off-load method for realizing that any embodiment of the present invention is provided.
Micro-capacitance sensor off-load method, apparatus, system and storage medium provided in an embodiment of the present invention, by monitoring micro- electricity The mains frequency of net can understand the frequency situation of change of micro-capacitance sensor in real time, once the mains frequency drops to the frequency of setting When rate value, you can carry out load according to the operation of power networks parameter acquiring active power shortage that the control of the intelligent terminal of reception is sent Excision, so as to quickly, timely cut off load, it is tight to avoid the micro-capacitance sensor frequency caused by cutting off load not in time Decline the problem of even collapsing again;By the active power shortage and cutting load priority orders, determine what needs were cut off Load, for example, when cutting load priority orders are related to the importance of load, based on the selection excision of cutting load priority orders Load may be implemented to determine load that needs are cut off according to the importance degree of load, avoid due to blindness excision load and Important load is caused to be removed;It is instructed so that intelligence by sending the cutting load for needing excision load to intelligent monitoring terminal Energy monitor terminal cuts off the load for needing to cut off, and passes through the excision of the load, it is possible to reduce load institute in micro-capacitance sensor The active power that need to be consumed, to reduce active power shortage, to reduce the frequency of active power shortage micro-capacitance sensor caused greatly The instability problem of micro-capacitance sensor caused by rate declines, to promote the stable operation of micro-capacitance sensor.
Description of the drawings
Fig. 1 is the flow diagram of micro-capacitance sensor off-load embodiment of the method one of the present invention;
Fig. 2 is the flow diagram of micro-capacitance sensor off-load embodiment of the method two of the present invention;
Fig. 3 is the implementation process schematic diagram of micro-capacitance sensor off-load method in an embodiment;
Fig. 4 is the implementation process schematic diagram of micro-capacitance sensor off-load method in another implementation;
Fig. 5 is the implementation process schematic diagram of micro-capacitance sensor off-load method in another implementation;
Fig. 6 is the flow diagram of micro-capacitance sensor off-load embodiment of the method three of the present invention;
Fig. 7 is micro-capacitance sensor load-shedding equipment structural schematic diagram in one embodiment of the invention;
Fig. 8 is micro-capacitance sensor load-shedding equipment structural schematic diagram in another embodiment of the present invention;
Fig. 9 is the structural schematic diagram of micro-capacitance sensor unloading system in one embodiment of the invention;
Figure 10 is the hardware architecture diagram of micro-capacitance sensor load-shedding equipment in one embodiment of the invention.
Specific implementation mode
Micro-capacitance sensor off-load method, apparatus, system and storage medium provided in an embodiment of the present invention, are mainly used in micro-capacitance sensor In power supply system, by the real time monitoring to load, power supply, switch and energy-storage travelling wave tube etc., obtains micro-capacitance sensor and urgent feelings occur Condition and when frequency being caused to drop to the frequency values of setting active power vacancy, pass through the excision by load according to priority orders Or the power back-off using energy-storage travelling wave tube is restored micro-capacitance sensor frequency value and is arrived to reach the balance of active power shortage in micro-capacitance sensor Rated value maintains micro-capacitance sensor frequency in a rational fluctuation range, to realize the stable operation of micro-capacitance sensor.Research hair It is existing:
(1), low-frequency load shedding function is integrated in line protective devices, when the line protective devices detect micro- electricity When the frequency for the circuit protected described in net is less than setting valve, and after meeting certain delay requirement, the line protective devices Control cuts off the circuit of the protection to achieve the purpose that cut off load.But since the line protective devices are distributed collection At it is each the action between each line protective devices need to can be made to be independent from each other in circuit to be protected, be can not phase Mutually coordinate;And the control logic of the line protective devices is very simple, only considers the Control of decreasing load of a wheel, can not be accurate Ground cuts off load.Therefore low-frequency load shedding function is integrated in line protective devices it is not high to cut off the accuracy of load, And harmony is excessively poor, it is difficult to effectively solve the stability problem of micro-capacitance sensor frequency.
(2), centralized low frequency load shedding equipment is configured.Whole feeder lines are divided into base by the method by load importance Epicycle and special wheel, when micro-capacitance sensor frequency declines, according to drop to different frequency setting values come by take turns substantially with it is special Wheel cuts off load respectively.But due to this method investment when on-site cable be laid with workload it is very big, cause the method at This is very high, and due to the centrality of centralized low frequency load shedding equipment function, can make the reliability requirement of described device It is very high, if described device itself goes wrong, then can make a big impact to Control of decreasing load.Therefore, configuration centralization is low Frequency load-shedding equipment is of high cost and device itself such as goes wrong will cause prodigious influence come the method for cutting off load, therefore The method also is difficult to effectively solve the stability problem of micro-capacitance sensor frequency.
In addition, belonging to opened loop control for the implementation process of above two micro-capacitance sensor off-load method, distribution is had ignored The influence of load real time information in mains side does not account for the different brackets of the concrete condition and failure when operation, past It is cut toward that can cross, causes unnecessary economic loss;And low frequency load shedding equipment must wait for that frequency is reduced to setting valve in the above method It is following just to act, the best mute time may be missed.
A kind of micro-capacitance sensor off-load method, apparatus of offer of the embodiment of the present invention, system and storage medium, high-precision can cut Except load, excision load can be begun to when frequency begins to decline the frequency values of setting, avoid frequency further under Drop, can fast and accurately cut off load, to reach the balance of the active power of micro-capacitance sensor, to make the extensive of micro-capacitance sensor frequency Rated value is arrived again, ensures the stable operation of micro-capacitance sensor.The realization, the function and the advantages of the object of the present invention will in conjunction with the embodiments, It is described further with reference to attached drawing.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and do not have to It is of the invention in limiting.
As shown in Figure 1, one embodiment of the invention proposes a kind of micro-capacitance sensor off-load method, it is applied to piconet controller, it should Method includes the following steps.
Step 101, the mains frequency of the micro-capacitance sensor is monitored.
Specifically, piconet controller monitors the mains frequency of the micro-capacitance sensor in real time.
Here, the piconet controller can be distributed in the master control room of substation in equal room areas.Usually, power grid Frequency stabilization maintains 50HZ or so, i.e. the rated value of power grid is generally 50HZ.When micro-capacitance sensor off-grid operation, such as occur non- When planned off-network or power failure tripping, micro-capacitance sensor frequency may drastically decline, and utilize piconet controller It monitors the mains frequency of the micro-capacitance sensor in real time, can make the frequency situation of change of piconet controller real-time awareness micro-capacitance sensor, Be conducive to micro-capacitance sensor frequency once occur fluctuating range it is unreasonable when, corresponding measure can be acquired immediately with reach maintain frequency it is steady The purpose being scheduled near rated value.
Step 103, the operation of power networks parameter that intelligent monitoring terminal is sent is received.
Specifically, the operation of power networks parameter that piconet controller real-time reception intelligent monitoring terminal is sent.
Further, the operation of power networks parameter for receiving intelligent monitoring terminal and sending, including:Receive intelligent monitoring terminal The power supply active power and distributed generation resource of transmission can issue additional power;Wherein, the power supply active power includes:Micro-capacitance sensor is by simultaneously When net switchs to off-network, the active power absorbed from bulk power grid when grid-connected, alternatively, one or more power supply trippings in micro-capacitance sensor When, the active power that is provided by one or more of power supplys before tripping;It is micro- electricity that the distributed generation resource, which can issue additional power, Net own power source can put into the active power in micro-capacitance sensor, including:In micro-capacitance sensor energy-storage travelling wave tube store energy and provide Active power.
Further, it is described receive intelligent monitoring terminal send power supply operating parameter, further include:Receive intelligent terminal hair The active power of the load sent and the reference numeral of load;Wherein, the determination of the reference numeral of the load, including:According to not Ad eundem is grouped load, to the first priority orders of group load setting, to the second priority of load setting in group load Sequentially;The load is numbered according to the first priority orders and the second priority orders.
Specifically, in one embodiment, the load in micro-capacitance sensor is divided into m groups according to load level, indicates to participate in subtracting with s Load group load group priority orders (i.e. the first priority orders), s for since 1 a series of natural numbers (s=1, 2 ... ..., m), this group of load priority of the smaller expressions of s is lower;Load number has n in every group, indicates that the group for participating in off-load is negative with q A priority orders (i.e. the second priority orders) of load in lotus, q be since 1 a series of natural numbers (q=1, 2 ... ..., n), the load priority is lower in q this group of load of smaller expression;By the load in micro-capacitance sensor according to the first priority Sequence and the second priority orders are numbered.Wherein, the load in micro-capacitance sensor is excellent according to the first priority orders and second First grade sequence is numbered, can be as shown in table 1 below:
Table 1 is based on the reference numeral of the load of " section thinking "
As shown in table 1, wherein (P11, P12, P13... ... P1q) indicate that one group of lowest priority in the first priority is born Lotus, (Ps1, Ps2, Ps3... ... Psq) indicate the first priority in highest priority one group of load;Wherein, (P11, P21... ... Ps1) indicate that the load of lowest priority in the second priority in load, (P are organized in place1q, P2q... ... Psq) indicate that load is organized at place In in the second priority highest priority load;Wherein, P11Indicate lowest priority and the second priority in the first priority The load of middle lowest priority, PsqIndicate the negative of highest priority in highest priority in the first priority and the second priority Lotus.
It should be noted that here, the load of the micro-capacitance sensor is grouped according to load level, can according to load confession Electric reliability and power supply are divided into different group loads, for heavier in political, economically caused loss or influence degree etc. The first priority that the group load wanted defines is higher.For example, in one embodiment, can load in micro-capacitance sensor be divided into level-one group and born Lotus, secondary groups load, three-level group load three groups of loads;Wherein, completely non-critical load is level-one group load, not too important Load be secondary groups load, very important load is three-level group load.In this way, according to the hierarchal grouping of load importance, The importance degree of each load in micro-capacitance sensor can be distinguished, can make when the decline of micro-capacitance sensor occurrence frequency, active power occur When vacancy, completely non-critical load can be first cut off, then cuts off the little load etc. of importance, it is more rational to realize The sequence of cutting load reduces the damage of its people brought because cut off load economically, political, in life etc. to the greatest extent Evil.
It should be noted that piconet controller receives pair of the active power and load for the load that intelligent monitoring terminal is sent It should number, the active power of each load can be recorded in real time according to the carrying out practically situation of distributed electrical source load, also, By making reference numeral to each load, piconet controller can be enable quickly and accurately to count the total active power of group load And in described group of load single load active power value, follow-up intelligent monitoring terminal can be enable to be instructed according to cutting load accurate True finds mutually the group load in requisition for excision or single load.
Step 105, when the mains frequency drops to the frequency values of setting, had according to the operation of power networks parameter acquiring Work(power shortage.
Specifically, when piconet controller monitoring mains frequency drops to the frequency values of setting, piconet controller is according to connecing The operation of power networks parameter that intelligent monitoring terminal is sent is received, active power shortage is obtained.
Further, when piconet controller monitoring mains frequency drop to the frequency values of setting when, piconet controller according to The power supply active power and distribution for receiving intelligent monitoring terminal transmission can issue additional power, according to the power supply active power and divide Cloth can issue additional power and obtain active power shortage.
Specifically, in one embodiment, for grid type micro-capacitance sensor, frequency is mainly supported by bulk power grid, if bulk power grid It breaks down and makes micro-capacitance sensor off-grid operation, such as when unplanned property off-network, have little time to control dominant eigenvalues, if before off-network Micro-capacitance sensor absorbs active power from bulk power grid, and it will cause micro-capacitance sensor active power shortages, if there are many active power shortage, and Load shedding may be such that frequency degradation even collapses not in time.Here, it is opened when piconet controller monitors micro-capacitance sensor frequency When beginning drops to the frequency values of setting, piconet controller is according to the power supply active power and distribution for receiving intelligent monitoring terminal transmission Formula can issue additional power and obtain active power shortage;Wherein, the power supply active power is the micro-capacitance sensor that intelligent monitoring terminal obtains The active-power P absorbed on interconnection before off-networkL, the distributed generation resource can issue additional power and be considered for intelligent monitoring terminal The active-power P that the distributed generation resource that can be put into after off-network can be issued additionalDG;Here, the active power shortage can be power supply Active-power PLPower P can be issued additional with distributionDGDifference, i.e. PLQ=PL- PDG
In another embodiment, for the micro-capacitance sensor of off-network type, when occurring the case where power failure tripping in micro-capacitance sensor, Frequency may also can rapid decrease.Here, when piconet controller monitors the frequency values that micro-capacitance sensor frequency begins to decline setting When, piconet controller according to receive intelligent monitoring terminal send power supply active power and distribution can issue additional power obtain it is active Power shortage;Wherein, the power supply active power be intelligent monitoring terminal obtain micro-capacitance sensor before power supply tripping power supply send out Active-power PG, it is that can be put into after intelligent monitoring terminal considers power supply tripping that the distributed generation resource, which can issue additional power, The active-power P that distributed generation resource can be issued additionalDG;Here, the active power shortage can be power supply active-power PGWith distribution Formula power supply can issue additional power PDGDifference, i.e. PLQ=PG- PDG
It should be noted that here, realize micro-capacitance sensor by it is grid-connected switch to off-network and off-grid operation when frequency variation Real-time tracking, when frequency drops to the frequency values of setting, so that it may with the operation of power networks sent by receiving intelligent monitoring terminal Parameter obtains active power shortage, can timely respond to the operation of cutting load, avoids missing the best mute time;Also, may be used also It can be increased with the power supply active power and the distributed generation resource that can be put into that determine micro-capacitance sensor according to the carrying out practically situation of micro-capacitance sensor Power is sent out, to provide reliable data source for the determination of micro-capacitance sensor active power shortage.
It should be noted that here, piconet controller by receive power supply active power that intelligent monitoring terminal is sent and Distributed generation resource can issue additional power, can determine active power shortage according to the carrying out practically situation of distributed electrical source, make Corresponding active power shortage can be obtained in time by obtaining when micro-capacitance sensor occurrence frequency declines, accurate to be provided for cutting load operation Required excision load total active power.
Step 107, according to active power shortage and cutting load priority orders, the load for needing to cut off is determined.
Specifically, piconet controller determines what needs switched according to active power shortage and cutting load priority orders Load.Wherein, the priority orders of the cutting load can be determined according to the importance degree of load.
Step 109, the cutting load instruction of the load for needing to cut off is sent to intelligent monitoring terminal.
Specifically, piconet controller sends the cutting load instruction of the load for needing to cut off to intelligent monitoring terminal.
Further, described according to active power shortage and cutting load priority orders, determine the load for needing to cut off, The cutting load instruction for the load for needing to cut off is sent to intelligent monitoring terminal, including:Judge whether the active power shortage is big In or equal in the first priority the group load of lower priority sequence total active power;
Determine that the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority When active power, the group load for cutting off lower priority sequence in first priority is determined, sent to intelligent monitoring terminal Cut off the cutting load instruction of the reference numeral of the load of the group load of lower priority sequence in first priority;
Further, it is determined that the active power shortage is less than the group load of lower priority sequence in the first priority When total active power, then it is relatively low in the second priority in described group of load to judge whether the active power shortage is greater than or equal to The active power of the load of priority orders;
Determine that the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority Load active power when, the load for cutting off lower priority sequence in second priority is determined, to intelligent monitoring end End sends the cutting load instruction for cutting off the reference numeral of the load of lower priority sequence in second priority.
Specifically, in one embodiment, piconet controller judges the active power shortage PLQWhether the is greater than or equal to Total active-power P of the group load of lowest priority sequence in one priority1, however, it is determined that the active power shortage PLQBe more than or Equal to total active-power P of the group load of lowest priority sequence in the first priority1When, it is determined that it needs to cut off described first The group load of lowest priority sequence in priority is sent minimum preferential in excision first priority to intelligent monitoring terminal The cutting load instruction of the reference numeral of all loads of the group load of grade sequence, by the active power shortage PLQSubtract described Total active-power P of the group load of lowest priority sequence in one priority1, obtain the active power shortage P for also needing excisionLQ1; Judge the active power shortage P for also needing to cut offLQ1Whether the group load of in first priority second low-priority sequence is greater than or equal to Total active-power P2, however, it is determined that the active power shortage P for also needing excisionLQ1It is low more than or equal in the first priority times Total active-power P of the group load of priority orders2When, it is determined that it is suitable to need to cut off second low-priority in first priority The group load of sequence sends all of the group load for cutting off second low-priority sequence in first priority to intelligent monitoring terminal The cutting load of the reference numeral of load instructs, by the active power shortage PLQ1It subtracts secondary low preferential in first priority Total active-power P of the group load of grade sequence2, obtain the active power shortage P for also needing excisionLQ2;And so on, until described Also need the active power shortage P of excisionLQs-1Always have less than the group load of a lower priority sequence in first priority Work(power PsWhen, then the active power shortage P of excision is also needed described in judgementLQs-1Whether it is greater than or equal to second in described group of load The active-power P of the load of lowest priority sequence in prioritys1, however, it is determined that the active power shortage for also needing excision PLQs-1More than or equal to the active-power P of the load of lowest priority sequence in the second priority in described group of loads1When, then It determines the load for needing to cut off lowest priority sequence in the second priority in described group of load, is cut to intelligent monitoring terminal transmission It, will be described active except the cutting load instruction of the load reference numeral of lowest priority sequence in the second priority in described group of load Power shortage PLQs-1Subtract the active-power P of lowest priority sequence payloads in the second priority in described group of loads1, obtain Also need the active power shortage P of excision1 LQs-1;The active power shortage P of excision is also needed described in judging1 LQs-1Whether it is greater than or equal to In described group of load in the second priority the load of second low-priority sequence active-power Ps2, however, it is determined that it is described also need excision Active power shortage P1 LQs-1More than or equal in the second priority in described group of load the load of second low-priority sequence it is active Power Ps2When, it is determined that it needs to cut off the load of second low-priority sequence in the second priority in described group of load, to intelligent prison Control terminal sends the cutting load instruction for cutting off the load reference numeral of second low-priority sequence in second priority, will be described Active power shortage P1 LQs-1Subtract the active-power P of second low-priority sequence payloads in second prioritys2, obtaining also needs The active power shortage P of excision2 LQs-1;And so on, until the active-power P for also needing excisionq-1 LQs-1It is negative less than described group In lotus in the second priority a lower priority sequence load active-power PsqWhen, it is determined that it need not be to intelligent monitoring terminal Send the instruction of cutting load.
It should be noted that judging the active power shortage whether more than or equal to described relatively low excellent by above-mentioned use Total active power of the group load of first grade, and when the active power shortage is less than the total of the group load of the lower priority By judging whether the active power shortage is greater than or equal to the single of lower priority in described group of load when active power The excision load method for having power of load is the excision mode that will be organized load and single load and be combined, avoids existing skill Defect caused by the load of excision one by one of blindness in art can guarantee and be further increased on the basis of improving excision load speed The precision of excision load, is conducive to the fast quick-recovery of micro-capacitance sensor frequency.
In an alternative embodiment, as shown in Fig. 2, after step 109, further include:
Step 111, judge whether the active power shortage is less than or equal to the threshold value of setting;When the active power When vacancy is less than or equal to the threshold value of setting, is sent to intelligent monitoring terminal and realize that active power is flat using energy storage control unit The control instruction of weighing apparatus.
Specifically, piconet controller judges whether the active power shortage is less than or equal to the threshold value of setting, also It is to say, when the total active power of load and the absolute value of the difference of total active power of cutting load that require excision are less than or wait When the threshold value of setting, micro-capacitance sensor active power may be have it is a small amount of it is deficient cut or cross cut, cut off load without continuing, then Piconet controller stops sending cutting load instruction to intelligent monitoring terminal, and sends control instruction to intelligent monitoring terminal, so that The compensation that energy-storage travelling wave tube in intelligent monitoring terminal control micro-capacitance sensor carries out the remaining active power shortage is obtained, to realize The balance of active power in micro-capacitance sensor.In this way, control instruction is sent to intelligent monitoring terminal by piconet controller, to utilize Intelligent monitoring terminal controls the compensation that energy-storage travelling wave tube carries out remaining active power shortage, can prevent active power in micro-capacitance sensor It owes to cut or cross to cut, ensures that the frequency of micro-capacitance sensor can be operated in always within the scope of a rational frequency fluctuation, further ensure The stability of micro-capacitance sensor operation.
The technical solution of the embodiment of the present invention is described in further detail below by specific embodiment.
Fig. 3 is the flow diagram of micro-capacitance sensor off-load method in one embodiment of the invention, wherein with micro-capacitance sensor according to power grid After operating parameter obtains active power shortage, how according in the way of cutting group load and single load is combined needs are determined It is illustrated for the load of excision.Wherein, micro-capacitance sensor internal loading is divided into m groups according to load level, and the first priority is indicated with s Middle priority orders, s are a series of natural numbers (s=1,2 ... ..., m) since 1, s this group of load priority of smaller expression It is lower;Load number has n in every group, indicates that priority orders in the second priority, q are a series of natural numbers since 1 with q (q=1,2 ... ..., n), load priority is lower in q this group of load of smaller expression.Wherein, PsIndicate always having for s group loads Work(power, PsqIndicate the active power of q-th of load in s groups, PLQIndicate the active power shortage for needing to cut off.This method, Include the following steps:
Step S11 determines the active power shortage P for needing to cut offLQ, and s=1, q=1;
Specifically, piconet controller determines active power shortage that needs are cut off according to the active power shortage of acquisition PLQ, at this point, priority orders are:First priority s=1, the second priority q=1, if the active power cut off is needed to press Group load starts to cut off, then is cut off the group load of priority orders s=1 since the first priority, if pressing single load Start to cut off, then from priority orders in the first priority be s=1 and the second priority in priority orders be the negative of q=1 Lotus starts to cut off.
Step S12, PLQ≥Ps
Specifically, piconet controller judges the active-power P for needing to cut offLQWhether the first priority is greater than or equal to The total active-power P for the group load that middle priority orders are ss;If so, S13 is thened follow the steps, if not, thening follow the steps S15.Wherein, the s is a series of natural numbers (s=1,2 ... ..., m) since 1, that is, when judging for the first time, the microgrid Controller is to judge the active-power P for needing to cut offLQIt is 1 whether to be greater than or equal to priority orders in the first priority Total active-power P of group load1;When judging for the second time, the piconet controller is to judge the active power for needing to cut off PLQ1Whether the total active-power P of group load that in first priority priority orders be 2 is greater than or equal to2;And so on;S When secondary judgement, the piconet controller is to judge the active-power P for needing to cut offLQs-1Whether first is greater than or equal to preferential Priority orders are the total active-power P of group load of s in grades
Step S13 sends excision P to intelligent monitoring terminalsInstruction;
Specifically, when the piconet controller determines the active-power P for needing to cut off by judgingLQIt is greater than or waits Priority orders are the total active-power P of group load of s in the first prioritysWhen, the piconet controller is whole to intelligent monitoring End sends the cutting load instruction for cutting off all loads that first priority orders are s groups.
Step S14 redefines the active power shortage P for needing to cut offLQ, and s=s+1;
Specifically, cutting when the group load that priority orders are s into intelligent monitoring terminal transmission the first priority of excision After load instruction, the active power shortage P for needing to cut off is redefinedLQ;And redefine the priority orders of the first priority For s=s+1;For example, last, that need to cut off is P1Group load, then it is described to redefine the active power for needing to cut off PLQ1Can be:The active-power P cut off is needed when last time judgesLQTotal wattful power of the group load cut off with last needs Rate P1Difference, and determine and need to judge that the sequence of priority of the group load cut off is s=1+1 next time.
Step S15, PLQ≥Psq
Specifically, when piconet controller determines the active-power P for needing to cut off by judgingLQIt is preferential to be less than first The total active-power P for the group load that priority orders are s in gradesWhen, then it is active to judge that the needs are cut off for piconet controller Power PLQWhether in second priority priority orders are greater than or equal in the group load that priority orders are s in the first priority For the active-power P of the load of qsq;If so, S16 is thened follow the steps, if not, thening follow the steps S18;Wherein, the q is A series of natural numbers (q=1,2 ... ..., n) since 1, that is, when judging for the first time, the piconet controller is described in judgement Need the active-power P cut offLQs-1It is excellent in the group load of s second whether in first priority priority orders are greater than or equal to The active-power P for the load that first grade sequence is 1s1;When judging for the second time, the piconet controller judges that the needs are cut off Active-power P1 LQs-1Whether in group load that in first priority priority orders be s second priority orders are greater than or equal to For the active-power P of 2 loads2;And so on;When judging for the q times, the piconet controller judges that the needs are cut off Active-power Pq-1 LQs-1Whether in group load that in first priority priority orders be s second priority orders are greater than or equal to For the active-power P of the load of qsq
Step S16 sends excision P to intelligent monitoring terminalsqInstruction;
Specifically, when the piconet controller determines the active-power P for needing to cut off by judgingLQIt is greater than or waits The active-power P for the load that the second priority orders are q in the group load that priority orders are s in the first prioritysqWhen, institute It is that the second priority orders are q in s groups to state piconet controller and send excision first priority orders to intelligent monitoring terminal Load cutting load instruction.
Step S17 redefines the active power shortage P for needing to cut offLQ, and q=q+1;
Specifically, excellent in the group of s second when sending priority orders in the first priority of excision to intelligent monitoring terminal After the cutting load instruction for the load that first grade sequence is q, the active power shortage P for needing to cut off is redefinedLQ;And it redefines The priority orders of second priority are q=q+1;For example, it is P that last time, which needs cut off,21Load, then described redefine need The active-power P to be cut off1 LQ1Can be:The active-power P cut off is needed when last time judgesLQ1It needs to cut off with the last time Load active-power P21Difference, and determine and need to judge that the sequence of priority of excision load is s=2 and q next time =1+1.
Step S18 stops cutting load.
Specifically, piconet controller stops the transmission of cutting load instruction.
It should be noted that the method can be to need direct excision group load also according to the judgement of active power shortage It is single load, so that intelligent monitoring terminal can carry out load excision in such a way that group load and single load are combined, can protects The speed demonstrate,proved the while of cutting off load accuracy raising, improve cutting load, it is specified to be conducive to quickly recovering to for micro-capacitance sensor frequency Value.
Fig. 4 is the flow instance figure of micro-capacitance sensor off-load method in one embodiment of the invention, wherein with micro-capacitance sensor according to power grid After operating parameter obtains active power shortage, how according in the way of cutting group load and single load is combined needs are determined The load of excision and how determining illustrates for the transmission of control instruction.Wherein, micro-capacitance sensor internal loading is according to load etc. Grade is divided into m groups, and priority orders in the first priority are indicated with s, s be since 1 a series of natural numbers (s=1,2 ... ..., M), this group of load priority of the smaller expressions of s is lower;Load number has n in every group, indicates that priority is suitable in the second priority with q Sequence, q are a series of natural numbers (q=1,2 ... ..., n) since 1, and load priority is lower in q this group of load of smaller expression. Wherein, PsIndicate total active power of s group loads, PsqIndicate the active power of q-th of load in s groups, PLQIt indicates to need The active power shortage of excision, PthresholdIndicate the threshold value of setting, wherein the threshold value PthresholdIt may be configured as:Respectively The active power for organizing peak load in the set of the active power of minimum load in load, for example, priority in the first priority Active power for minimum load in 1 group load is P1min, minimum load in priority is 2 in the first priority group load Active power be P2min..., the active power of minimum load is P in the group load that priority is s in the first prioritysmin, Then the threshold value can be set as Pthreshold=max (P1min, P2min... ..., Psmin).This method includes the following steps:
Step 21~the step 24 is corresponded with step 11 described in Fig. 3 corresponding embodiments~step 14;
Step S25 sends excision P to intelligent monitoring terminalsqInstruction does not send excision instruction;
Specifically, piconet controller determines the active-power P for needing to cut off by judgingLQIt is less than the first priority The total active-power P for the group load that middle priority orders are ssWhen, then piconet controller judges the wattful power for needing to cut off Rate PLQWhether it is greater than or equal in the group load that priority orders are s in the first priority that priority orders are in the second priority The active-power P of the load of qsq, first priority orders are cut off as in s groups if it is, being sent to intelligent monitoring terminal Second priority orders are the cutting load instruction of the load of q, if it is not, then cutting load instruction need not be sent.
Step S26 redefines the active power shortage P for needing to cut offLQ
Specifically, piconet controller redefines the active power shortage PL for needing to cut offQ
Step S27, | PLQ|≤Pthreshold
Specifically, piconet controller judge described in also need to excision remaining active power shortage whether be less than or equal to set Fixed threshold value Pthreshold, if so, S29 is thened follow the steps, if not, thening follow the steps S28.
Step S28, q=q+1;
Specifically, micro-capacitance sensor control determines that the remaining active power shortage for also needing to excision is greater than described set by judging Fixed threshold value PthresholdWhen, then sequentially it is the preferential of the second priority q in s groups by q=q+1, i.e., in described first priority Grade sequence plus 1.
Step 29, it sends energy-storage travelling wave tube to intelligent monitoring terminal and compensates PLQControl instruction.
Specifically, when piconet controller is by judging that it is described that the determining remaining active power shortage for also needing to excision is less than The threshold value P of settingthresholdWhen, piconet controller sends energy-storage travelling wave tube to intelligent monitoring terminal and compensates remaining active power Vacancy PLQControl instruction so that intelligent monitoring terminal control energy-storage travelling wave tube compensates the remaining active power shortage PLQ
It should be noted that the method can be to need direct excision group load according to the judgement of active power shortage, Or single load is cut off in a manner of approaching the threshold value of the setting by singulation load, so that intelligent monitoring terminal can be pressed The mode that group load and single load are combined carries out load excision, and energy-storage travelling wave tube can also be utilized to balance remaining wattful power Rate vacancy, enables micro-capacitance sensor frequency to be quickly restored to rated value.
Fig. 5 is the flow instance figure of micro-capacitance sensor off-load method in one embodiment of the invention, wherein with micro-capacitance sensor according to power grid After operating parameter obtains active power shortage, how according in the way of cutting group load and single load is combined needs are determined The load of excision and how determining illustrates for the transmission of control instruction.Wherein, micro-capacitance sensor internal loading is according to load etc. Grade is divided into m groups, and priority orders in the first priority are indicated with s, s be since 1 a series of natural numbers (s=1,2 ... ..., M), this group of load priority of the smaller expressions of s is lower;Load number has n in every group, indicates that priority is suitable in the second priority with q Sequence, q are a series of natural numbers (q=1,2 ... ..., n) since 1, and load priority is lower in q this group of load of smaller expression. Wherein, PsIndicate total active power of s group loads, PsqIndicate the active power of q-th of load in s groups, PLQIt indicates to need The active power shortage of excision, PthresholdIndicate the threshold value of setting.This method includes the following steps:
Step 31~the step 37 is corresponded with step 11 described in Fig. 3 corresponding embodiments~step 17;
Step S38:|PLQ-Psq|≤Pthreshold
Specifically, when piconet controller determines the active power shortage P for needing to cut off by judgingLQIt is less than first The active-power P for the load that priority orders are q in the second priority in the group load that priority orders are s in prioritysqWhen, Then piconet controller judges the active power shortage PL for needing to cut offQIt is s with priority orders in first priority Group load in priority orders are q in the second priority load active-power PsqDifference absolute value whether be less than or Equal to threshold value Pthreshold, that is, judge | PLQ-Psq| whether it is less than or equal to Pthreshold;If so, thening follow the steps S39, such as Fruit is no, thens follow the steps S310.
Here, it should be noted that when | PLQ-Psq|≤PthresholdWhen, the active power shortage P for needing to cut offLQ With the single load P organized in load for needing to be removedsqThe two difference is smaller, therefore just considers to sacrifice the Psq, cut off the Psq Corresponding load;When | PLQ-Psq| > PthresholdWhen, the active power shortage P for needing to cut offLQWith the group for needing to be removed Single load P in loadsqThe two difference is bigger, even if cutting off the P at this timesqCorresponding load, remaining wattful power Rate is also greater than threshold value, therefore the P of active power shortage is directly carried out using energy-storage travelling wave tubeLQBalance.
Step S39:Excision P is sent to intelligent monitoring terminalsqInstruction, redefines PLQ
Specifically, when piconet controller determines the active power shortage P for needing to cut off by judgingLQWith described first The active-power P for the load that priority orders are q in the second priority in the group load that priority orders are s in prioritysq's The absolute value of difference is less than or equal to threshold value PthresholdWhen, the piconet controller is to described in intelligent monitoring terminal transmission First priority orders are the cutting load instruction for the load that the second priority orders are q in s groups, and redefine and also need to cut off Active-power PLQ
Step S310:Energy-storage travelling wave tube, which is sent, to intelligent monitoring terminal compensates PLQControl instruction.
Specifically, when piconet controller determines the active power shortage P for needing to cut off by judgingLQWith described first The active-power P for the load that priority orders are q in the second priority in the group load that priority orders are s in prioritysq's The absolute value of difference is greater than threshold value PthresholdWhen, piconet controller sends energy-storage travelling wave tube to intelligent monitoring terminal and compensates institute State remaining active power shortage PLQControl instruction so that intelligent monitoring terminal control energy-storage travelling wave tube compensation it is described remaining Active power shortage PLQ
It should be noted that the method can be to need direct excision group load also according to the judgement of active power shortage Be by single load, so that intelligent monitoring terminal can carry out load excision in such a way that group load and single load are combined, and And energy-storage travelling wave tube can also be utilized to balance remaining active power shortage, so that micro-capacitance sensor frequency is quickly restored to rated value.
The embodiment of the present invention also proposed a kind of micro-capacitance sensor off-load method, be applied to intelligent monitoring terminal, as shown in fig. 6, This method includes:
Step 201, operation of power networks parameter is obtained, the operation of power networks parameter is sent to micro-electronic control device.
Specifically, intelligent monitoring terminal obtains operation of power networks parameter, and the operation of power networks parameter is sent to microgrid control Device.
Here, the intelligent monitoring terminal be mounted on distributed electrical source, the intelligent monitoring terminal acquire in real time power supply, The signal of switch;Wherein, the signal of the power supply includes the analog quantitys such as the voltage, electric current and frequency of power supply, the switch Signal includes the switching values such as on off state.
Further, intelligent monitoring terminal obtains power supply active power and input according to the power supply of acquisition, the signal of switch Distributed generation resource can issue additional power, the power supply active power and the distributed generation resource, which can be issued additional power, is sent to microgrid Controller;Wherein, the active power includes:Micro-capacitance sensor by it is grid-connected switch to off-network when, when grid-connected from bulk power grid absorb having Work(power, alternatively, in micro-capacitance sensor when one or more power supply trippings, the active power that is provided by the power supply before tripping;It is described It is the active power that micro-capacitance sensor own power source can be put into micro-capacitance sensor that distributed generation resource, which can issue additional power, including:Micro-capacitance sensor The energy of middle energy-storage travelling wave tube storage and the active power provided.
Specifically, in one embodiment, the unplanned property off-network of micro-capacitance sensor, here, when micro-capacitance sensor starts off-network, intelligence is supervised Control terminal obtains the active power that micro-capacitance sensor is absorbed before off-network on interconnection, and the active power is denoted as PL, and intelligence The active power that the distributed generation resource that can be put into after the considerations of monitor terminal obtains to off-network can be issued additional, by the distributed electrical Source can issue additional power and be denoted as PDG;Intelligent monitoring terminal is by the PLAnd PDGIt is sent to piconet controller.
In another embodiment, for off-grid micro-capacitance sensor, when there is the case where power failure tripping, intelligent monitoring is whole The active power that the power supply is sent out before the power failure tripping that end passes through acquisition, P is denoted as by the active powerG, Yi Jizhi The active power that the distributed generation resource that can be put into after the considerations of energy monitor terminal obtains to power supply tripping can be issued additional, will be described point Cloth power supply can issue additional power and be denoted as PDG;Intelligent monitoring terminal is by the PGAnd PDGIt is sent to piconet controller.
Further, the acquisition operation of power networks parameter, is sent to piconet controller by operation of power networks parameter, further includes: The active power for obtaining load in power grid, determines the reference numeral of the load;By the active power of the load and described negative The reference numeral of lotus is sent to piconet controller.
Here, it should be noted that the determination of the reference numeral of the load, including:According to different brackets to load into Row grouping, to the first priority orders of group load setting, to the second priority orders of load setting in group load;By the load It is numbered according to the first priority orders and the second priority orders.
Specifically, in one embodiment, the load in micro-capacitance sensor is divided into m groups by intelligent monitoring terminal according to load level, With s indicate participate in off-load group load group priority orders (i.e. the first priority orders), s be since 1 it is a series of oneself So number (s=1,2 ... ..., m), this group of load priority of the smaller expressions of s are lower;Load number has n in every group, indicates to participate in q Off-load group load in load a priority orders (i.e. the second priority orders), with q indicate participation off-load group load in A priority orders (i.e. the second priority orders) of load, q are a series of natural numbers (q=1,2 ... ..., n) since 1, The load priority is lower in q this group of load of smaller expression;By the load in micro-capacitance sensor according to the first priority orders and second Priority orders are numbered.As shown in Table 1 above, wherein (P11, P12, P13... ... P1q) indicate minimum in the first priority One group of load of priority, (Ps1, Ps2, Ps3... ... Psq) indicate the first priority in highest priority one group of load;Wherein, (P11, P21... ... Ps1) indicate that the load of lowest priority in the second priority in load, (P are organized in place1q, P2q... ... Psq) table The load of highest priority in the second priority in load is organized where showing;Wherein, P11Indicate lowest priority in the first priority, And second lowest priority in priority load, PsqIt indicates in the first priority in highest priority and the second priority most The load of high priority.
It should be noted that here, the load of the micro-capacitance sensor is grouped according to load level, can according to load confession Electric reliability and power supply are divided into different group loads, for heavier in political, economically caused loss or influence degree etc. The first priority that the group load wanted defines is higher.For example, in one embodiment, can load in micro-capacitance sensor be divided into level-one group and born Lotus, secondary groups load, three-level group load three groups of loads;Wherein, completely non-critical load is level-one group load, not too important Load be secondary groups load, very important load is three-level group load.In this way, according to the hierarchal grouping of load importance, The importance degree of each load in micro-capacitance sensor can be distinguished, can make when the decline of micro-capacitance sensor occurrence frequency, active power occur When vacancy, completely non-critical load can be first cut off, then cuts off the little load etc. of importance, it is more rational to realize The sequence of cutting load reduces the damage of its people brought because cut off load economically, political, in life etc. to the greatest extent Evil.
It should be noted that intelligent monitoring terminal obtains the reference numeral of the active power and load of load, and will be described The active power of load and the reference numeral of load are sent to piconet controller, piconet controller can be made according to distributed electrical The carrying out practically situation of source load determines the real-time active power of each load;It can enable piconet controller quickly and accurately The value for counting single load active power in the total active power of group load and described group of load, can make follow-up intelligent monitoring Terminal can instruct according to cutting load and accurately find mutually the group load in requisition for excision or single load.
Step 203, the cutting load instruction that piconet controller is sent is received;Wherein, the cutting load instruction is negative according to cutting Lotus priority orders and from the active power shortage of the operation of power networks parameter acquiring determine.
Specifically, intelligent monitoring terminal receives the cutting load instruction that piconet controller is sent;Wherein, the cutting load instruction It is to be determined according to cutting load priority orders and from the active power shortage of the operation of power networks parameter acquiring.
Step 205, it is instructed according to the cutting load and carries out load excision.
Specifically, intelligent monitoring terminal is instructed according to the cutting load that piconet controller is sent, and carries out load excision.Wherein, The load is cut off:Intelligent monitoring terminal controls the load and directly trips.
Further, the cutting load instruction for receiving piconet controller and sending, is cut according to cutting load instruction It removes, including:Intelligent monitoring terminal receives lower priority sequence in excision first priority that piconet controller is sent The cutting load instruction of the reference numeral of the load of group load, and to the group load of lower priority sequence in first priority It is cut off;
Further, intelligent monitoring terminal receives relatively low preferential in excision second priority that piconet controller is sent Grade sequence load reference numeral cutting load instruction, and to the load of lower priority sequence in second priority into Row excision.
In an alternative embodiment, as shown in fig. 6, this method further includes:
Step 207, the control instruction that piconet controller is sent is received, the flat of active power is realized according to the control instruction Weighing apparatus.
Specifically, intelligent monitoring terminal receives the control instruction that piconet controller is sent, and intelligent monitoring terminal is according to Control instruction control energy-storage travelling wave tube carries out the compensation of the remaining active power shortage, to realize the balance of active power. In this way, controlling the compensation that energy-storage travelling wave tube carries out remaining active power shortage by intelligent monitoring terminal, can prevent in micro-capacitance sensor The deficient of active power cuts or cuts excessively, ensures that the frequency of micro-capacitance sensor is operated in always within the scope of a rational frequency fluctuation, into one Step ensure that the stability of micro-capacitance sensor operation.
The embodiment of the present invention also proposed a kind of micro-capacitance sensor load-shedding equipment, be applied to piconet controller, referring to Fig. 7, institute Stating micro-capacitance sensor load-shedding equipment includes:Monitoring unit 31, the first receiving unit 32, first processing units 33 and the first transmission unit 34;Wherein,
The monitoring unit 31, the mains frequency for monitoring the micro-capacitance sensor;
First receiving unit 32, the operation of power networks parameter for receiving intelligent monitoring terminal transmission;
The first processing units 33, when frequency values for dropping to setting when the mains frequency, according to the electricity Network operation parameter acquiring active power shortage;It is additionally operable to according to active power shortage and cutting load priority orders, determining needs The load to be cut off;
First transmission unit 34 refers to for sending the cutting load for needing the load cut off to intelligent monitoring terminal It enables.
Optionally, first receiving unit 32, be additionally operable to receive intelligent monitoring terminal send power supply active power and Distributed generation resource can issue additional power;
The first processing units 33 are additionally operable to be issued additional according to the active power and the distributed generation resource of power supply Power obtains active power shortage.
Optionally, first receiving unit 32 is additionally operable to receive the active power for the load that intelligent terminal is sent and bear The reference numeral of lotus;
Wherein, the determination of the reference numeral of the load, including:Load is grouped according to different brackets, it is negative to organizing Lotus sets the first priority orders, to the second priority orders of load setting in group load;The load is preferential according to first Grade sequence and the second priority orders are numbered.
Optionally, the first processing units 33, are additionally operable to judge whether the active power shortage is greater than or equal to the Total active power of the group load of lower priority sequence in one priority;
Determine that the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority When active power, the group load for cutting off lower priority sequence in first priority is determined;
First transmission unit 34 is additionally operable to send to intelligent monitoring terminal relatively low excellent in excision first priority The cutting load instruction of the reference numeral of the load of the group load of first grade sequence.
Optionally, the first processing units 33 are additionally operable to determine that the active power shortage is less than in the first priority When total active power of the group load of lower priority sequence, then it is described to judge whether the active power shortage is greater than or equal to Organize the active power of the load of lower priority sequence in the second priority in load;
Determine that the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority Load active power when, determine the load for cutting off lower priority sequence in second priority;
First transmission unit 34 is additionally operable to send to intelligent monitoring terminal relatively low excellent in excision second priority The cutting load of the reference numeral of the load of first grade sequence instructs.
Optionally, the first processing units 33 are additionally operable to judge whether the active power shortage is less than or equal to and set Fixed threshold value;First transmission unit 34, being additionally operable to send to intelligent monitoring terminal has using the realization of energy storage control unit The control instruction of work(power.
The embodiment of the present invention also proposed a kind of micro-capacitance sensor load-shedding equipment, using intelligent monitoring terminal, referring to Fig. 8, institute Stating micro-capacitance sensor load-shedding equipment includes:Second processing unit 41, the second transmission unit 42, the second receiving unit 43 and excision unit 44;Wherein,
The second processing unit 41, for obtaining operation of power networks parameter;
Second transmission unit 42, for the operation of power networks parameter to be sent to piconet controller;
Second receiving unit 43, the cutting load instruction for receiving piconet controller transmission;Wherein, the cutting load Instruction is determined according to cutting load priority orders and from the active power shortage of the operation of power networks parameter acquiring;
The excision unit 44 carries out load excision for being instructed according to the cutting load.
Optionally, the second processing unit 41, also with the signal according to each power supply of acquisition, switch, obtaining power supply has Work(power and the distributed generation resource of input can issue additional power;
Second transmission unit 42 can also issue additional power hair with by the power supply active power and the distributed generation resource Give piconet controller.
Optionally, the second processing unit 41 is additionally operable to obtain the active power of load in power grid, determines the load Reference numeral;The determination of the reference numeral of the wherein described load, including:Load is grouped according to different brackets, to group The first priority orders of load setting, to the second priority orders of load setting in group load;The load is excellent according to first First grade sequence and the second priority orders are numbered;
Second transmission unit 42 is additionally operable to send the reference numeral of the active power of the load and the load To piconet controller.
Optionally, second receiving unit 43, the excision described first for being additionally operable to receive piconet controller transmission are preferential The cutting load instruction of the load reference numeral of the group load of lower priority sequence in grade;
The excision unit 44 is additionally operable to cut the group load of lower priority sequence in first priority It removes.
Optionally, second receiving unit 43, the excision described second for being additionally operable to receive piconet controller transmission are preferential The cutting load instruction of the reference numeral of the load of lower priority sequence in grade;
The excision unit 44 is additionally operable to cut off the load of lower priority sequence in second priority.
Optionally, referring to Fig. 8, described device further includes:Energy storage control unit 45;
Second receiving unit 43 is additionally operable to receive the control instruction that piconet controller is sent;
The energy storage control unit 45, the balance for realizing active power according to the control instruction.
The embodiment of the present invention also proposed a kind of micro-capacitance sensor unloading system, referring to Fig. 9, the system comprises:Microgrid control Device 51 and intelligent monitoring terminal 52 processed;Wherein,
The piconet controller 51, the mains frequency for monitoring the micro-capacitance sensor;Receive what intelligent monitoring terminal was sent Operation of power networks parameter;It is active according to the operation of power networks parameter acquiring when the mains frequency drops to the frequency values of setting Power shortage;According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;To intelligent monitoring end End sends the cutting load instruction of the load for needing to cut off;
The operation of power networks parameter is sent to microgrid by the intelligent monitoring terminal 52 for obtaining operation of power networks parameter Controller;Receive the cutting load instruction that piconet controller is sent;Wherein, the cutting load instruction is suitable according to cutting load priority Sequence and from the active power shortage of the operation of power networks parameter acquiring determine;Progress load is instructed to cut according to the cutting load It removes.
Optionally, the system also includes:Communication network 53;Wherein,
The piconet controller 51 is located in transformer station's master control room in equal room areas, the intelligent monitoring terminal 52 is located at Distributed electrical source, the piconet controller 51 and intelligent monitoring terminal 52 are connected with each other by the communication network 53 to carry out Communication;Wherein, the communication network 54 includes following one or more:Fiber optic Ethernet, ether passive network, power carrier, Cordless communication network.
Optionally, the piconet controller 51 and the intelligent monitoring terminal 52 contain the transformer substation case towards general object GOOSE transmission-receiving functions simultaneously have corresponding communication interface;Wherein, the GOOSE signals include:The piconet controller 51 and institute State the message signals that intelligent monitoring terminal 52 is communicated.
It should be noted that GOOSE is a kind of rapid message transmission mechanism in IEC61850, it can be used for Real time signal Transmission, communication delay are calculated with Millisecond.It is communicated using GOOSE signals, that is, uses network communication mode to replace device Between hardwire communication mode, enormously simplify the connection of the secondary cable between device;Also, the repeating transmission that the GOOSE holds Mechanism can guarantee the reliability of the transmission of message, and gradually the increased characteristic for sending interval can effectively balance network flow to GOOSE The requirement of amount.
Optionally, the system also includes:Information encryption device 54;Wherein,
Described information encryption device 54 is integrated in the piconet controller 51 and the intelligent monitoring terminal 52, for pair GOOSE signals are encrypted, decrypt.
It should be noted that hacker attack in order to prevent, ensures information security, the GOOSE signal transmissions are through the letter Encryption for information device is encrypted, decrypts, and can guarantee the safety of information described in micro-capacitance sensor operation, avoids described by hacker attack And the damage brought.
It should be understood by those skilled in the art that, the embodiment of the present invention can be provided as method, system or computer program Product.Therefore, the shape of hardware embodiment, software implementation or embodiment combining software and hardware aspects can be used in the present invention Formula.Moreover, the present invention can be used can use storage in the computer that one or more wherein includes computer usable program code The form for the computer program product implemented on medium (including but not limited to magnetic disk storage and optical memory etc.).
In another embodiment, the piconet controller of micro-capacitance sensor load-shedding equipment and intelligence are supervised in any embodiment of the present invention Control terminal can be server, and as shown in Figure 10, the server includes:Processor 61, for store can be in processor The memory 62 of the computer program run on 61 is appointed when the computer program is executed by processor 61 for realizing the present invention The micro-capacitance sensor off-load method that one embodiment is provided.
Further embodiment of this invention additionally provides a kind of computer readable storage medium, which deposits Executable program is contained, it can be achieved that the following steps of micro-capacitance sensor off-load method when the executable code processor 61 executes:
Monitor the mains frequency of the micro-capacitance sensor;
Receive the operation of power networks parameter that intelligent monitoring terminal is sent;
When the mains frequency drops to the frequency values of setting, lacked according to the operation of power networks parameter acquiring active power Volume;
According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;
The cutting load instruction of the load for needing to cut off is sent to intelligent monitoring terminal.
Optionally, when the executable code processor 61 executes, also realizing following steps:
The power supply active power and distributed generation resource for receiving intelligent monitoring terminal transmission can issue additional power, according to the power supply Active power and the distributed generation resource can issue additional power and obtain active power shortage.
Optionally, when the executable code processor 61 executes, also realizing following steps:
Receive the reference numeral of the active power and load of the load that intelligent terminal is sent;
Wherein, the determination of the reference numeral of the load, including:Load is grouped according to different brackets, it is negative to organizing Lotus sets the first priority orders, to the second priority orders of load setting in group load;The load is preferential according to first Grade sequence and the second priority orders are numbered.
Optionally, when the executable code processor 61 executes, also realizing following steps:
Judge whether the active power shortage is greater than or equal to the group load of lower priority sequence in the first priority Total active power;
Determine that the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority When active power, the group load for cutting off lower priority sequence in first priority is determined, sent to intelligent monitoring terminal Cut off the cutting load instruction of the reference numeral of the load of the group load of lower priority sequence in first priority.
Optionally, when the executable code processor 61 executes, also realizing following steps:
Determine that the active power shortage is less than total wattful power of the group load of lower priority sequence in the first priority When rate, then judge whether the active power shortage is greater than or equal in described group of load that lower priority is suitable in the second priority The active power of the load of sequence;
Determine that the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority Load active power when, the load for cutting off lower priority sequence in second priority is determined, to intelligent monitoring end End sends the cutting load instruction for cutting off the reference numeral of the load of lower priority sequence in second priority.
Optionally, when the executable code processor 61 executes, also realizing following steps:
Judge whether the active power shortage is less than or equal to the threshold value of setting;
When the active power shortage is less than or equal to the threshold value of setting, is sent to intelligent monitoring terminal and utilize energy storage Control unit realizes the control instruction of active power balance.
Another embodiment of the present invention additionally provides a kind of storage medium, which is stored with executable program, described , it can be achieved that the following steps of micro-capacitance sensor off-load method when executable code processor 61 executes:
Operation of power networks parameter is obtained, the operation of power networks parameter is sent to piconet controller;
Receive the cutting load instruction that piconet controller is sent;Wherein, the cutting load instruction is according to cutting load priority Sequentially and from the active power shortage of the operation of power networks parameter acquiring determine;
It is instructed according to the cutting load and carries out load excision.
Optionally, when the executable code processor 61 executes, also realizing following steps:
According to the power supply of acquisition, the signal of switch, work(can be issued additional by obtaining the distributed generation resource of power supply active power and input The power supply active power and the distributed generation resource can be issued additional power and be sent to piconet controller by rate.
Optionally, when the executable code processor 61 executes, also realizing following steps:
The active power for obtaining load in power grid, determines the reference numeral of the load;Wherein, the corresponding of the load is compiled Number determination, including:Load is grouped according to different brackets, to the first priority orders of group load setting, to a group load The second priority orders of middle load setting;The load is compiled according to the first priority orders and the second priority orders Number;The load active power and the load reference numeral are sent to piconet controller.
Optionally, when the executable code processor 61 executes, also realizing following steps:
Receive the load of the group load of lower priority sequence in excision first priority that piconet controller is sent Reference numeral cutting load instruction, and the group load of lower priority sequence in first priority is cut off.
Optionally, when the executable code processor 61 executes, also realizing following steps:
The corresponding of load for receiving lower priority sequence in excision second priority that piconet controller is sent is compiled Number cutting load instruction, and the load of lower priority sequence in second priority is cut off.
Optionally, when the executable code processor 61 executes, also realizing following steps:
The control instruction that piconet controller is sent is received, the balance of active power is realized according to the control instruction.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (16)

1. a kind of micro-capacitance sensor off-load method, which is characterized in that this method includes:
Monitor the mains frequency of the micro-capacitance sensor;
Receive the operation of power networks parameter that intelligent monitoring terminal is sent;
When the mains frequency drops to the frequency values of setting, according to the operation of power networks parameter acquiring active power shortage;
According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;
The cutting load instruction of the load for needing to cut off is sent to intelligent monitoring terminal.
2. according to the method described in claim 1, it is characterized in that, the operation of power networks ginseng for receiving intelligent monitoring terminal and sending Number, including:The power supply active power and distributed generation resource for receiving intelligent monitoring terminal transmission can issue additional power;
It is described according to the operation of power networks parameter acquiring active power shortage, including:According to the power supply active power and described Distributed generation resource can issue additional power and obtain active power shortage.
3. according to the method described in claim 1, it is characterized in that, the operation of power networks ginseng for receiving intelligent monitoring terminal and sending It counts, further includes:
Receive the reference numeral of the active power and load of the load that intelligent terminal is sent;
Wherein, the determination of the reference numeral of the load, including:Load is grouped according to different brackets, a group load is set Fixed first priority orders, to the second priority orders of load setting in group load;The load is suitable according to the first priority Sequence and the second priority orders are numbered.
4. according to the method described in claim 3, it is characterized in that, described according to active power shortage and cutting load priority Sequentially, it determines the load for needing to cut off, the cutting load instruction of the load for needing to cut off, packet is sent to intelligent monitoring terminal It includes:
Judge whether the active power shortage is greater than or equal to the total of the group load of lower priority sequence in the first priority Active power;
Determine that the active power shortage is greater than or equal to the total active of the group load of lower priority sequence in the first priority When power, the group load for cutting off lower priority sequence in first priority is determined, send and cut off to intelligent monitoring terminal The cutting load instruction of the reference numeral of the load of the group load of lower priority sequence in first priority.
5. according to the method described in claim 4, it is characterized in that, described judge whether the active power shortage is more than or waits In the first priority lower priority sequence group load total active power, further include:
When determining that the active power shortage is less than total active power of group load of lower priority sequence in the first priority, Then judge whether the active power shortage is greater than or equal in described group of load lower priority sequence in the second priority The active power of load;
Determine that the active power shortage is greater than or equal in described group of load the negative of lower priority sequence in the second priority When the active power of lotus, the load for cutting off lower priority sequence in second priority is determined, sent out to intelligent monitoring terminal Send the cutting load instruction for cutting off the reference numeral of the load of lower priority sequence in second priority.
6. method according to claim 1 or 5, which is characterized in that this method further includes:
Judge whether the active power shortage is less than or equal to the threshold value of setting;
When the active power shortage is less than or equal to the threshold value of setting, sends to intelligent monitoring terminal and controlled using energy storage Unit realizes the control instruction of active power balance.
7. a kind of micro-capacitance sensor off-load method, which is characterized in that this method includes:
Operation of power networks parameter is obtained, the operation of power networks parameter is sent to piconet controller;
Receive the cutting load instruction that piconet controller is sent;Wherein, the cutting load instruction is according to cutting load priority orders And determined from the active power shortage of the operation of power networks parameter acquiring;
It is instructed according to the cutting load and carries out load excision.
8. the method according to the description of claim 7 is characterized in that the acquisition operation of power networks parameter, by the operation of power networks Parameter is sent to piconet controller, including:
According to the power supply of acquisition, the signal of switch, power can be issued additional by obtaining the distributed generation resource of power supply active power and input, will The power supply active power and the distributed generation resource can issue additional power and be sent to piconet controller.
9. the method according to the description of claim 7 is characterized in that the acquisition operation of power networks parameter, by operation of power networks parameter It is sent to piconet controller, further includes:
The active power for obtaining load in power grid, determines the reference numeral of the load;Wherein, the reference numeral of the load It determines, including:Load is grouped according to different brackets, to the first priority orders of group load setting, to being born in group load Lotus sets the second priority orders;The load is numbered according to the first priority orders and the second priority orders;
The reference numeral of the active power of the load and the load is sent to piconet controller.
10. according to the method described in claim 9, it is characterized in that, it is described receive piconet controller send cutting load instruction, It is instructed according to the cutting load and carries out load excision, including:
Receive pair of the load of the group load of lower priority sequence in excision first priority that piconet controller is sent The cutting load instruction that should be numbered, and the group load of lower priority sequence in first priority is cut off.
11. according to the method described in claim 10, it is characterized in that, the cutting load for receiving piconet controller transmission refers to It enables, is instructed according to the cutting load and carry out load excision, further include:
Receive the reference numeral of the load of lower priority sequence in excision second priority that piconet controller is sent Cutting load instructs, and is cut off to the load of lower priority sequence in second priority.
12. the method according to claim 7 or 11, which is characterized in that this method further includes:
The control instruction that piconet controller is sent is received, the balance of active power is realized according to the control instruction.
13. a kind of micro-capacitance sensor load-shedding equipment, which is characterized in that the device includes:
Monitoring unit, the mains frequency for monitoring the micro-capacitance sensor;
First receiving unit, the operation of power networks parameter for receiving intelligent monitoring terminal transmission;
First processing units, when frequency values for dropping to setting when the mains frequency, according to the operation of power networks parameter Obtain active power shortage;It is additionally operable to, according to active power shortage and cutting load priority orders, determine that need to cut off bears Lotus;
First transmission unit, the cutting load instruction for sending the load for needing to cut off to intelligent monitoring terminal.
14. a kind of micro-capacitance sensor load-shedding equipment, which is characterized in that the device includes:
Second processing unit, for obtaining operation of power networks parameter;
Second transmission unit, for the operation of power networks parameter to be sent to piconet controller;
Second receiving unit, the cutting load instruction for receiving piconet controller transmission;Wherein, the cutting load instruction is basis Cutting load priority orders and from the active power shortage of the operation of power networks parameter acquiring determine;
Unit is cut off, load excision is carried out for being instructed according to the cutting load.
15. a kind of micro-capacitance sensor low-frequency load shedding system, which is characterized in that the system includes:Piconet controller and intelligent monitoring terminal;
Wherein, the piconet controller is used to monitor the mains frequency of the micro-capacitance sensor;Receive the electricity that intelligent monitoring terminal is sent Network operation parameter;When the mains frequency drops to the frequency values of setting, according to the operation of power networks parameter acquiring wattful power Rate vacancy;According to active power shortage and cutting load priority orders, the load for needing to cut off is determined;To intelligent monitoring terminal Send the cutting load instruction of the load for needing to cut off;
The operation of power networks parameter is sent to piconet controller by the intelligent monitoring terminal for obtaining operation of power networks parameter; Receive the cutting load instruction that piconet controller is sent;Wherein, cutting load instruction be according to cutting load priority orders and from What the active power shortage of the operation of power networks parameter acquiring determined;It is instructed according to the cutting load and carries out load excision.
16. a kind of storage medium, there are computer executable instructions in the storage medium, which is characterized in that the computer can It executes instruction to be executed by processor and realizes claim 1 to 12 any one of them micro-capacitance sensor low frequency deloading method.
CN201810365906.1A 2018-04-23 2018-04-23 Micro-grid load shedding method, device and system and storage medium Expired - Fee Related CN108521129B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810365906.1A CN108521129B (en) 2018-04-23 2018-04-23 Micro-grid load shedding method, device and system and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810365906.1A CN108521129B (en) 2018-04-23 2018-04-23 Micro-grid load shedding method, device and system and storage medium

Publications (2)

Publication Number Publication Date
CN108521129A true CN108521129A (en) 2018-09-11
CN108521129B CN108521129B (en) 2020-12-18

Family

ID=63428957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810365906.1A Expired - Fee Related CN108521129B (en) 2018-04-23 2018-04-23 Micro-grid load shedding method, device and system and storage medium

Country Status (1)

Country Link
CN (1) CN108521129B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109193654A (en) * 2018-11-01 2019-01-11 珠海格力电器股份有限公司 Power peak regulation methods, devices and systems
CN109292626A (en) * 2018-10-17 2019-02-01 青岛港国际股份有限公司 A kind of track crane DC power-supply system and method
CN109617085A (en) * 2019-01-28 2019-04-12 深圳供电局有限公司 Fast cut back optimal control method under a kind of malfunction
CN109830964A (en) * 2019-02-27 2019-05-31 燕山大学 A kind of micro-capacitance sensor dynamic power balance method and system
CN110429615A (en) * 2019-07-15 2019-11-08 内蒙古电力(集团)有限责任公司电力调度控制分公司 Wind storage exchange micro-capacitance sensor automated power balance control method and system
CN110429614A (en) * 2019-07-12 2019-11-08 杭州电子科技大学 Simulate the distributed energy storage device control method for frequency of low-frequency load shedding control model
CN111130138A (en) * 2020-01-02 2020-05-08 湖南大学 Multi-energy complementary microgrid off-grid stable operation control method and system
CN112350307A (en) * 2020-10-28 2021-02-09 中国华电科工集团有限公司 Control method and control device for regional distribution network and computer readable storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101789605A (en) * 2010-03-30 2010-07-28 华中科技大学 Frequency reestablishment method used for microgrid
CN102938588A (en) * 2012-12-10 2013-02-20 上海市电力公司 Intelligent power grid safety and stability early-warning and control system
CN105762809A (en) * 2015-11-05 2016-07-13 天津大学 Power system intelligent low-frequency low-voltage load reduction method based on intelligent household electrical appliance
US20170254840A1 (en) * 2016-03-07 2017-09-07 Schneider Electric Industries Sas Frequency measurement device, frequency measurement method and under frequency load shedding device
CN107516904A (en) * 2017-08-31 2017-12-26 国电南瑞科技股份有限公司 A kind of reply power supply off-grid impacts and counted and the accurate duty control method of unit regulating power

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101789605A (en) * 2010-03-30 2010-07-28 华中科技大学 Frequency reestablishment method used for microgrid
CN102938588A (en) * 2012-12-10 2013-02-20 上海市电力公司 Intelligent power grid safety and stability early-warning and control system
CN105762809A (en) * 2015-11-05 2016-07-13 天津大学 Power system intelligent low-frequency low-voltage load reduction method based on intelligent household electrical appliance
US20170254840A1 (en) * 2016-03-07 2017-09-07 Schneider Electric Industries Sas Frequency measurement device, frequency measurement method and under frequency load shedding device
CN107516904A (en) * 2017-08-31 2017-12-26 国电南瑞科技股份有限公司 A kind of reply power supply off-grid impacts and counted and the accurate duty control method of unit regulating power

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109292626A (en) * 2018-10-17 2019-02-01 青岛港国际股份有限公司 A kind of track crane DC power-supply system and method
CN109193654A (en) * 2018-11-01 2019-01-11 珠海格力电器股份有限公司 Power peak regulation methods, devices and systems
CN109617085A (en) * 2019-01-28 2019-04-12 深圳供电局有限公司 Fast cut back optimal control method under a kind of malfunction
CN109830964A (en) * 2019-02-27 2019-05-31 燕山大学 A kind of micro-capacitance sensor dynamic power balance method and system
CN110429614A (en) * 2019-07-12 2019-11-08 杭州电子科技大学 Simulate the distributed energy storage device control method for frequency of low-frequency load shedding control model
CN110429614B (en) * 2019-07-12 2020-10-23 杭州电子科技大学 Distributed energy storage device frequency control method simulating low-frequency load shedding control mode
CN110429615A (en) * 2019-07-15 2019-11-08 内蒙古电力(集团)有限责任公司电力调度控制分公司 Wind storage exchange micro-capacitance sensor automated power balance control method and system
CN111130138A (en) * 2020-01-02 2020-05-08 湖南大学 Multi-energy complementary microgrid off-grid stable operation control method and system
CN112350307A (en) * 2020-10-28 2021-02-09 中国华电科工集团有限公司 Control method and control device for regional distribution network and computer readable storage medium

Also Published As

Publication number Publication date
CN108521129B (en) 2020-12-18

Similar Documents

Publication Publication Date Title
CN108521129A (en) Micro-capacitance sensor off-load method, apparatus, system and storage medium
CN105514966B (en) A kind of direct-current grid group energy storage optimization and control method for coordinating
EP2721710B1 (en) Hybrid electric generating power plant that uses a combination of real-time generation facilities and energy storage system
US10965153B2 (en) Methods of microgrid communications and connection transitions
CN108599379B (en) Power monitoring system for micro-grid group
WO2012032111A2 (en) Detecting islanding conditions in power networks
CN206471840U (en) A kind of many fired power generating unit electrochemical energy storages auxiliary frequency modulation control device
CN109617103A (en) A kind of echelon of energy storage unit utilizes energy-storage battery energy control method and system
CN109904866A (en) A kind of the micro-grid connection control method for coordinating and its system of polynary energy storage
CN115833402A (en) Artificial intelligence network command management and issuing system based on power dispatching
Xiang et al. IoT and edge computing based direct load control for fast adaptive frequency regulation
CN109560608B (en) Intelligent management and control system of distributed photovoltaic access power distribution network
CN104569691A (en) Parameter detection method and system for multi-type energy storage system
CN109560556A (en) A kind of voltage-regulating system adjusted based on flexible multimode regulating switch
CN105743082A (en) Overload switching device suitable for DC power distribution system
CN104393602A (en) Adjusting method and device for distributed energy resource network
CN111048849A (en) Battery energy management system and method of direct-hanging energy storage system
WO2014018884A1 (en) Methods and systems for managing distributed energy resources
CN102074966B (en) System and method for combining distributed generation and distribution network in distribution network terminal
CN216312687U (en) Photovoltaic energy storage direct current intelligent micro-grid monitoring management system
CN204258300U (en) Supplying power allocation safeguards system
CN204334379U (en) The V/f-with hysteretic characteristic falls down vertical microgrid inverter power supply
CN114336658A (en) Distribution network reactive power control method containing distributed photovoltaic and reactive power regulation equipment
KR101610699B1 (en) Power management system for frequency regulation based on energy storage sytem and method thereof
CN202550689U (en) Intelligent management control system for enhancing stability of small power grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201218