CN108373115A - A kind of device of construction tower crane difference pedestal conversion - Google Patents

A kind of device of construction tower crane difference pedestal conversion Download PDF

Info

Publication number
CN108373115A
CN108373115A CN201810321319.2A CN201810321319A CN108373115A CN 108373115 A CN108373115 A CN 108373115A CN 201810321319 A CN201810321319 A CN 201810321319A CN 108373115 A CN108373115 A CN 108373115A
Authority
CN
China
Prior art keywords
tower crane
plate
top panel
lower panel
end plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810321319.2A
Other languages
Chinese (zh)
Inventor
黄卫国
龙峰
张力
罗先波
罗翱
陈贵全
彭畅
刘斌
彭波
吴宇航
陈显军
李凤
蔡灿
徐贵
蒲恒塘
陈丽红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Xinlian Blasting Engineering Group Co Ltd
Original Assignee
Guizhou Xinlian Blasting Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Xinlian Blasting Engineering Group Co Ltd filed Critical Guizhou Xinlian Blasting Engineering Group Co Ltd
Priority to CN201810321319.2A priority Critical patent/CN108373115A/en
Publication of CN108373115A publication Critical patent/CN108373115A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Jib Cranes (AREA)

Abstract

The invention discloses a kind of devices of construction tower crane difference pedestal conversion, including apparatus main body, described device main body includes top panel, lower panel, median ventral plate and end plate, the first bolt hole is offered on the top panel, the second bolt hole is offered on the lower panel, median ventral plate and end plate are welded between the top panel and lower panel, the median ventral plate and end plate are welded to connect.The present invention realizes the connection of different tower cranes and different tower cranes, the pulling force that can be born after welding is much larger than the pulling force of bolt, the pressure born is twice or more of tower crane base pressure, since area is big, frictional force is big, improves the shear ability of bolt, there are enough spaces for quadrangle, be easily installed, dismantle and use during maintenance, avoid basis from doing over again and cause economic loss.

Description

A kind of device of construction tower crane difference pedestal conversion
Technical field
The present invention relates to technical field of building construction more particularly to a kind of devices of construction tower crane difference pedestal conversion.
Background technology
Construction tower crane is indispensable basic equipment in modern architecture construction, and tower crane generally uses gravity type reinforcing bar Concrete foundation, common 50 tons of rice ~ 80 ton rice tower crane need 40 ~ 60 cubic metres of concrete, and cost is higher, tower crane Thumb screw is embedded, and once there is deviation or later stage, Concerning The Choice of Tower Crane is modified and may cause great economic loss again.Tower crane Switch base can be solved due to being reselected after the pre-buried inaccurate or tower crane construction of column foot under the premise that security is guaranteed Foundation built-in bolt caused by tower crane and the unmatched problem of tower crane base.
After past, tower crane was selected under normal circumstances, according to tower crane construction tower crane and pre-embedded bolt, it is contemplated that coagulation Native strength problem, tower crane, which need to shift to an earlier date 1 month or so, constructs.But frequently encounter for various reasons that selected tower crane cannot be timely The problem of showing up needs to reselect tower crane.Since the tower crane anchor screw distance of different manufacturers is different from, if there is thinking Can only construct basis again when replacing the tower crane of other producers, or re-work tower crane base, cause very big economic loss, construction Time is also greatly affected.Another situation is exactly to occur deviation when foundation bolt is buried, it is impossible in tower crane base Again trepanning, this aspect influence safety, it is also possible to cause scrapping for tower crane base.
Invention content
The purpose of the present invention is to solve disadvantages existing in the prior art, and a kind of construction tower crane difference base proposed The device of seat conversion.
To achieve the goals above, present invention employs following technical solutions:
A kind of device of construction tower crane difference pedestal conversion, including apparatus main body, described device main body include top panel, below Plate, median ventral plate and end plate offer the first bolt hole on the top panel, the second bolt hole, institute are offered on the lower panel It states and is welded with median ventral plate and end plate between top panel and lower panel, the median ventral plate and end plate are welded to connect.
Preferably, the thickness of the top panel and lower panel is millimeter, and top panel and lower panel are square, above The length of side of plate and lower panel is millimeter, and top panel and lower panel are made of Q235 steel plates.
Preferably, the thickness of the median ventral plate and end plate is millimeter, and the height of median ventral plate and end plate is millimeter, median ventral plate Q235 steel plates are all made of with end plate to be made.
Compared with prior art, the beneficial effects of the invention are as follows:
1, the present invention realizes the connection of different tower cranes and different tower cranes;
2, the pulling force that can be born after present invention welding is much larger than the pulling force of bolt, and the pressure born is tower crane base pressure Twice or more, since area is big, frictional force is big, improves the shear ability of bolt;
3, quadrangle of the present invention is there are enough spaces, be easily installed, dismantle and use during maintenance, avoid basis from doing over again and make At economic loss.
Description of the drawings
Fig. 1 is a kind of vertical view of the device of construction tower crane difference pedestal conversion proposed by the present invention;
Fig. 2 is a kind of side view of the device of construction tower crane difference pedestal conversion proposed by the present invention;
Fig. 3 is a kind of cross-sectional view of the device of construction tower crane difference pedestal conversion proposed by the present invention;
Fig. 4 is a kind of Longitudinal cross section schematic of the device of construction tower crane difference pedestal conversion proposed by the present invention;
Fig. 5 is the mounting structure schematic diagram of the device and tower crane of a kind of construction tower crane difference pedestal conversion proposed by the present invention;
Fig. 6 is the sectional view of a kind of device of construction tower crane difference pedestal conversion proposed by the present invention and the mounting structure of tower crane;
Fig. 7 is a kind of the partially schematic of the mounting structure of device and tower crane that construction tower crane difference pedestal is converted proposed by the present invention Figure.
In figure:1 top panel, 2 lower panels, 3 median ventral plates, 4 end plates, 5 first screw holes, 6 second screw holes, 7 apparatus main bodies, 8 tower crane tower bodies, 9 tower cranes, 10 foundation built-in bolts, 11 tower crane bases.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Referring to Fig.1-7, a kind of device of construction tower crane difference pedestal conversion, including apparatus main body 7, apparatus main body 7 include Top panel 1, lower panel 2, median ventral plate 3 and end plate 4 offer the first bolt hole 5 on top panel 1, second are offered on lower panel 2 Bolt hole 6 is welded with median ventral plate 3 and end plate 4 between top panel 1 and lower panel 2, median ventral plate 3 and end plate 4 are welded to connect, above The thickness of plate 1 and lower panel 2 is 30 millimeters, and top panel 1 and lower panel 2 are square, the side of top panel 1 and lower panel 2 Length is 600 millimeters, and top panel 1 and lower panel 2 are made of Q235 steel plates, and the thickness of median ventral plate 3 and end plate 4 is 20 millimeters, The height of median ventral plate 3 and end plate 4 is 190 millimeters, and median ventral plate 3 and end plate 4 are all made of Q235 steel plates and are made.
Operation principle:It is actual in use, the first bolt hole 5 and 11 bottom of tower crane base on top panel 1 bolt The arrangement and size all same in hole, the first bolt hole 5 and the bolt hole one of 11 bottom of tower crane base on top panel 1 are a pair of It answers, is bolted between top panel 1 and tower crane base 11;The second bolt hole 6 on lower panel 2 and the pre-buried spiral shell of tower crane The arrangement all same of bolt 10, the second bolt hole 6 on lower panel 2 are connected with tower crane pre-embedded bolt 10, real in this way The connection of different tower cranes 9 and different tower crane tower bodies 8 is showed.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Any one skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (3)

1. a kind of device of construction tower crane difference pedestal conversion, including apparatus main body(7), which is characterized in that described device main body (7)Including top panel(1), lower panel(2), median ventral plate(3)And end plate(4), the top panel(1)On offer the first bolt hole (5), the lower panel(2)On offer the second bolt hole(6), the top panel(1)And lower panel(2)Between be welded with midfield Plate(3)And end plate(4), the median ventral plate(3)And end plate(4)It is welded to connect.
2. a kind of device of construction tower crane difference pedestal conversion according to claim 1, which is characterized in that the top panel (1)And lower panel(2)Thickness be 30 millimeters, top panel(1)And lower panel(2)It is square, top panel(1)With it is following Plate(2)The length of side be 600 millimeters, top panel(1)And lower panel(2)It is made of Q235 steel plates.
3. a kind of device of construction tower crane difference pedestal conversion according to claim 1, which is characterized in that the median ventral plate (3)And end plate(4)Thickness be 20 millimeters, median ventral plate(3)And end plate(4)Height be 190 millimeters, median ventral plate(3)The end and Plate(4)Q235 steel plates are all made of to be made.
CN201810321319.2A 2018-04-11 2018-04-11 A kind of device of construction tower crane difference pedestal conversion Pending CN108373115A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810321319.2A CN108373115A (en) 2018-04-11 2018-04-11 A kind of device of construction tower crane difference pedestal conversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810321319.2A CN108373115A (en) 2018-04-11 2018-04-11 A kind of device of construction tower crane difference pedestal conversion

Publications (1)

Publication Number Publication Date
CN108373115A true CN108373115A (en) 2018-08-07

Family

ID=63032039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810321319.2A Pending CN108373115A (en) 2018-04-11 2018-04-11 A kind of device of construction tower crane difference pedestal conversion

Country Status (1)

Country Link
CN (1) CN108373115A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112299261A (en) * 2020-09-08 2021-02-02 中建四局第五建筑工程有限公司 Tower crane installation method with overlarge foundation bolt embedding distance

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201901879U (en) * 2010-11-12 2011-07-20 上海市机械施工有限公司 Nonstandard foundation used for fixing tower crane
CN202989945U (en) * 2012-12-28 2013-06-12 杨众 Steel and concrete mixed assembly type tower footing
CN203891057U (en) * 2014-05-09 2014-10-22 南通庞源机械工程有限公司 Adaption device for tower crane foundation leg
CN203947771U (en) * 2014-07-16 2014-11-19 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system
CN203946821U (en) * 2014-06-24 2014-11-19 上海市建工设计研究院有限公司 Tower crane tool base fixed degree detects detecting device in real time
WO2015080353A1 (en) * 2013-11-26 2015-06-04 한국지질자원연구원 High-pressure fluid storage tank and construction method thereof
CN208150820U (en) * 2018-04-11 2018-11-27 贵州新联***工程集团有限公司 A kind of device of construction tower crane difference pedestal conversion

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201901879U (en) * 2010-11-12 2011-07-20 上海市机械施工有限公司 Nonstandard foundation used for fixing tower crane
CN202989945U (en) * 2012-12-28 2013-06-12 杨众 Steel and concrete mixed assembly type tower footing
WO2015080353A1 (en) * 2013-11-26 2015-06-04 한국지질자원연구원 High-pressure fluid storage tank and construction method thereof
CN203891057U (en) * 2014-05-09 2014-10-22 南通庞源机械工程有限公司 Adaption device for tower crane foundation leg
CN203946821U (en) * 2014-06-24 2014-11-19 上海市建工设计研究院有限公司 Tower crane tool base fixed degree detects detecting device in real time
CN203947771U (en) * 2014-07-16 2014-11-19 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system
CN208150820U (en) * 2018-04-11 2018-11-27 贵州新联***工程集团有限公司 A kind of device of construction tower crane difference pedestal conversion

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112299261A (en) * 2020-09-08 2021-02-02 中建四局第五建筑工程有限公司 Tower crane installation method with overlarge foundation bolt embedding distance

Similar Documents

Publication Publication Date Title
CN100558996C (en) Steel reinforced concrete frame-steel supporting structure section-changeable conversion node
CN206844314U (en) A kind of new prefabricated assembled bean column node
CN209099741U (en) A kind of bolt connecting type builder's jack
CN108181191A (en) A kind of rigidity beam column and beam column built from concrete multinode fatigue to failure test device
CN207268073U (en) Novel flexible formwork bearing frame
CN206143719U (en) Concrete depends on ship components are installed supporting platform
CN108373115A (en) A kind of device of construction tower crane difference pedestal conversion
CN209456892U (en) Cable-stayed bridge steel overhangs structure of sidewalk
CN208150820U (en) A kind of device of construction tower crane difference pedestal conversion
CN108374493A (en) Novel low layer assembled wallboard structure energy dissipating steel plate welding node
CN107882234A (en) A kind of connecting node between the vertical member and floor of plate-column structure
CN109372009A (en) A kind of nigh-level synthesis embedded column base and its application method
CN208965581U (en) A kind of non-console mode tower crane platform
CN203160540U (en) Novel precast column
CN105350642B (en) The cap of one kind connection " rice " type Cast-in-place concrete beam
CN210134326U (en) Steel wall box type steel anchor beam combined cable tower anchoring structure
CN208280381U (en) A kind of connecting structure structure of the two-sided vertical node of folded type steel shear wall
CN106906749A (en) The construction method of full assembled steel-concrete combined structure box beam
CN109811650A (en) The structure that steel column is connect with concrete bearing platform
CN206174144U (en) Novel ring beam does ring shear connected node of steel corbel and steel pipe concrete post
CN102900096B (en) Fabricated tower footing
CN208965580U (en) A kind of non-console mode tower crane
CN205604730U (en) Be applied to novel built -in fitting device of external tower machine
CN212026598U (en) Structure system suitable for assembled steel structure building
CN105040828B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180807