CN108360545B - It tilts open caisson and combines deviation rectification construction method - Google Patents
It tilts open caisson and combines deviation rectification construction method Download PDFInfo
- Publication number
- CN108360545B CN108360545B CN201810252458.4A CN201810252458A CN108360545B CN 108360545 B CN108360545 B CN 108360545B CN 201810252458 A CN201810252458 A CN 201810252458A CN 108360545 B CN108360545 B CN 108360545B
- Authority
- CN
- China
- Prior art keywords
- hole
- lifting
- open caisson
- forced landing
- lifted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
- E02D23/14—Decreasing the skin friction while lowering
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
- E02D35/005—Lowering or lifting of foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Earth Drilling (AREA)
Abstract
The invention discloses a kind of inclination open caissons to combine deviation rectification construction method, it is characterized in that the side setting forced landing hole slow in well sinking, forced landing bore dia is 75~120mm, forced landing pitch of holes is 1.5~2.2m, in the fast side setting lifting hole of well sinking, lifting bore dia is 60~90mm, lifting pitch of holes is 1.8~2.5m, lifting hole depth is 2.2~2.5 times of open caisson height, hole is lifted using two rows of, it is lifted hole and injects cement slurry, the cement slurry ratio of mud is 0.45~0.5, and cement slurry mixes calcium sulphoaluminate class swelling agent;Correction sequence is first to force-land, then be lifted, and forced landing or lifting are all made of information-aided construction.
Description
Technical field
The present invention relates to deviation rectification construction method, in particular to a kind of inclination open caisson combines deviation rectification construction method.
Background technique
It is easy to appear inclination during open caisson construction, to be rectified a deviation after inclination of open caisson, traditional open caisson deviation rectification method has digging
Local method and increase external loads method, excavation method are cut the earth to the slow one side that sinks more, increase the gap between caisson cutting edge and soil,
Promote its sinking.To sinking, fast one side is optionally cut the earth less, is not cut the earth or mound and heap rammed earth, and sinking frictional resistance is increased,
Slow down subsidence velocity.Increasing external loads method is to increase load in the slow side of well sinking, while hollowing out under its blade foot, with
Benefit overcomes frictional resistance to correct deflection.The problems of these traditional technologies are difficult to control in work progress, and correction is easy
It exceeds the proper limits in righting a wrong.
Summary of the invention
For the deficiencies in the prior art, the purpose of the present invention is to provide a kind of inclination open caissons to combine Deviation Correction Construction
Method guarantees rectifying effect.
The present invention side setting forced landing hole slow in well sinking, forced landing bore dia is 75~120mm, and forced landing pitch of holes is
1.5~2.2m, forming forced landing hole using bore mode reduces caisson wall and its surrounding soil frictional force, in boring procedure
Constantly water filling makes well sinking, correction technique is instructed using intelligent control method, drilling machine drilling speed and water injection pressure are according to soil property
It is adjusted with correction rate.
In the fast side setting lifting hole of well sinking, lifting bore dia is 60~90mm, be lifted pitch of holes for 1.8~
2.5m, lifting hole depth are 2.2~2.5 times of open caisson height, and lifting hole is using two rows, and two rows lifting hole arrangement parameters are using such as
Under: first row lifting hole be it is vertical, it is 500~700mm that first row, which is lifted hole from open caisson Edge Distance, and second row is lifted hole to incline
Tiltedly, gradient is 60~70 degree, and gradient refers to that lifting hole and horizontal angle, second row are lifted hole from open caisson edge here
Distance is 1000~1200mm;Two rows lifting hole arrangement parameter can also use as follows: first row is lifted hole as inclination, gradient
It is 60~70 degree, it is 1000~1200mm that first row, which is lifted hole from open caisson Edge Distance, and it is inclination, gradient that second row, which is lifted hole,
It is 60~70 degree, second row is lifted hole and first row lifting hole parallel arrangement, and second row is lifted hole from open caisson Edge Distance and is
1500~1700mm;It is lifted hole and injects cement slurry, the cement slurry ratio of mud is 0.45~0.5, and it is swollen that cement slurry mixes calcium sulphoaluminate class
Swollen dose, enters after the soil body mixed with the cement slurry of calcium sulphoaluminate class swelling agent and will appear hydration reaction, foundation soil body in hydration process
Product expansion generates lifting force to open caisson, and the volume of calcium sulphoaluminate class swelling agent is directly related with the lifting force of open caisson, mixed with sulphur aluminium
The cement slurry of sour calcium class swelling agent has not only acted as the effect of expansion lifting after entering the soil body, and plays compacted compacting and make
With with the setting expansion of the cement slurry of calcium sulphoaluminate class swelling agent, foundation soil body compactness is obviously increased, and compressibility reduces.
The volume of calcium sulphoaluminate class swelling agent is determined according to Uplifting amount, when Uplifting amount is greater than or equal to 100mm, the expansion of calcium sulphoaluminate class
The volume of agent is 7%;When Uplifting amount is greater than 50mm and is less than 100mm, the volume of calcium sulphoaluminate class swelling agent is 6%;Uplifting amount
When less than 50mm, the volume of calcium sulphoaluminate class swelling agent is 5%.
Correction sequence is first to force-land, then be lifted, and forced landing or lifting are all made of information-aided construction, at the top of open caisson
Cloth displacement sensor, displacement sensor is connect with computer carries out intelligent control, and displacement sensor transfers data to electricity immediately
Brain, every sinking or lifting 2mm draw a curve to computer according to the collected data, and provide correction rate according to the slope of curve,
Analysis correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, when open caisson bottom
For muck soil, when fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to 120r/min and is greater than
110r/min, water injection pressure 1.3MPa;When the soil property that drills is muck soil, fall rate is greater than 0.02mm/min and is less than
When 0.03mm/min, drilling machine drilling speed is less than or equal to 110r/min and is greater than 100r/min, water injection pressure 1.3MPa;Work as drilling
Soil property be muck soil when, fall rate be greater than or equal to 0.03mm/min when, drilling machine drilling speed be less than or equal to 100r/min and
Greater than 90r/min, water injection pressure 1.3MPa;
When open caisson bottom is clay, and fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to
90r/min and be greater than 80r/min, water injection pressure 1.2MPa;When drilling soil property is clay, fall rate is greater than 0.02mm/min
And when being less than 0.03mm/min, drilling machine drilling speed is less than or equal to 80r/min and is greater than 75r/min, water injection pressure 1.2MPa;When
Drilling soil property is clay, and when fall rate is greater than or equal to 0.03mm/min, drilling machine drilling speed is less than or equal to 75r/min and is greater than
70r/min, water injection pressure 1.2MPa;
When open caisson bottom is silt, and fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to
70r/min and be greater than 65r/min, water injection pressure 1.1MPa;When drilling soil property is silt, fall rate is greater than 0.02mm/min
And when being less than 0.03mm/min, drilling machine drilling speed is less than or equal to 65r/min and is greater than 60r/min, water injection pressure 1.1MPa;When
Drilling soil property is silt, and when fall rate is greater than or equal to 0.03mm/min, drilling machine drilling speed is less than or equal to 60r/min and is greater than
55r/min, water injection pressure 1.1MPa;
When open caisson bottom is sand, and fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to
55r/min and be greater than 50r/min, water injection pressure 1.0MPa;When drilling soil property is sand, fall rate is greater than 0.02mm/min
And when being less than 0.03mm/min, drilling machine drilling speed is less than or equal to 50r/min and is greater than 45r/min, water injection pressure 1.0MPa;When
Drilling soil property is sand, and when fall rate is greater than or equal to 0.03mm/min, drilling machine drilling speed is less than or equal to 45r/min and is greater than
40r/min, water injection pressure 1.0MPa;
In silt or sand, open caisson can be difficult to, and can use following technical measures: pass through note after pore-forming
Slurry pipe injects the water mixed with montmorillonite, passes through Grouting Pipe injection hole at once after the montmorillonite of incorporation 1%~2% in water
In, it is expanded to the bead that diameter is 3~5mm after montmorillonite access aperture and is attached to open caisson wall, sliding friction is made to become rolling
Friction, reduces hole wall frictional force, is conducive to correction and tells on.If geology there are drifting sand layer, incorporation 2%~3% it is pure
Alkali improves slurry consistency, and increase receives ion to change the sub- hydrating capacity of grogs.
Construction is lifted using interval construction, i.e., first constructs and finishes the lifting hole of odd indexed, then the lift for even number serial number of constructing
Hole is risen, serial number carries out layout from left to right, prevents adjacent lifting hole from starching because pitch-row closely influences each other or be lifted hole in construction excessively
Liquid expansive force discharges and influences correcting and then reinforcing effect.Pass through the interval of 20~30min after the lifting hole construction of odd indexed
The lifting hole for even number serial number of constructing again after time, it is therefore an objective to which allowing swelling stress to obtain certain release ensures rectifying effect.
The present invention has the advantages that rectifying effect is good, safe and reliable, with good application prospect.
Detailed description of the invention
Fig. 1 is open caisson deviation rectification plan view one, and Fig. 2 is open caisson deviation rectification facade arrangement schematic diagram one, and Fig. 3 is open caisson
Correction plan view two, Fig. 4 are open caisson deviation rectification facade arrangement schematic diagram two.
Attached drawing mark: 1, hole of force-landing, 2, lifting hole, 3, open caisson.
Specific embodiment
The present embodiment is described in detail below in conjunction with attached drawing.
Embodiment one
Fig. 1 is open caisson deviation rectification plan view one, and Fig. 2 is open caisson deviation rectification facade arrangement schematic diagram one.The present embodiment
Forced landing hole 1 is set in the side that open caisson 3 sinks slow, forced landing 1 diameter of hole is 80mm, and forced landing 1 spacing of hole is 1.7m, using drilling side
Formula, which forms forced landing hole 1, reduces 3 borehole wall of open caisson and its surrounding soil frictional force, and constantly water filling makes under open caisson 3 in boring procedure
It is heavy, instruct correction technique, drilling machine drilling speed and water injection pressure to be adjusted according to soil property and correction rate using intelligent control method
It is whole.
Lifting hole 2 is set in the side that open caisson 3 sinks fast, lifting 2 diameter of hole is 70mm, and lifting 2 depth of hole is 2.2 times heavy
3 height of well, lifting 2 spacing of hole are 2m, and lifting hole 2 is using two rows, and two rows lifting 2 arrangement parameter of hole is using as follows: first row lift
Rise hole 2 be it is vertical, it is 600mm that first row, which is lifted hole 2 from 3 Edge Distance of open caisson, and second row is lifted hole 2 to tilt, and gradient is
65 degree, it is 1100mm that second row, which is lifted hole 2 from 3 Edge Distance of open caisson,;It is lifted hole 2 and injects cement slurry, the cement slurry ratio of mud is
0.45, cement slurry mixes calcium sulphoaluminate class swelling agent.Uplifting amount is 70mm, and the volume of calcium sulphoaluminate class swelling agent is 6%.
Correction sequence is first to force-land, then be lifted, and forced landing or lifting are all made of information-aided construction, is pushed up in open caisson 3
Portion's cloth displacement sensor, displacement sensor is connect with computer carries out intelligent control, and displacement sensor transfers data to immediately
Computer, every sinking or lifting 2mm draw a curve to computer according to the collected data, and provide correction speed according to the slope of curve
Rate, analysis correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, 3 bottom of open caisson
For clay, when fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to 90r/min and is greater than 80r/min,
Water injection pressure is 1.2MPa;When fall rate is greater than 0.02mm/min and is less than 0.03mm/min, drilling machine drilling speed is less than or equal to
80r/min and be greater than 75r/min, water injection pressure 1.2MPa;When fall rate is greater than or equal to 0.03mm/min, drilling machine drilling speed
Less than or equal to 75r/min and it is greater than 70r/min, water injection pressure 1.2MPa;
Construction is lifted using interval construction, i.e., first constructs and finishes the lifting hole 2 of odd indexed, then the lift for even number serial number of constructing
Hole 2 is risen, serial number carries out layout from left to right.The intermittent time of 20~30min is passed through in the lifting hole 2 of odd indexed after constructing
The lifting hole 2 for even number serial number of constructing again afterwards.
Embodiment two
Fig. 3 is open caisson deviation rectification plan view two, and Fig. 4 is open caisson deviation rectification facade arrangement schematic diagram two.
Forced landing hole 1 is arranged in the side that open caisson 3 sinks slow in the present embodiment, and forced landing 1 diameter of hole is 80mm, 1 spacing of hole of force-landing
For 1.7m, forming forced landing hole 1 using bore mode reduces 3 borehole wall of open caisson and its surrounding soil frictional force, in boring procedure
Constantly water filling makes open caisson 3 sink, and correction technique is instructed using intelligent control method, drilling machine drilling speed and water injection pressure are according to soil property
It is adjusted with correction rate.
Lifting hole 2 is set in the side that open caisson 3 sinks fast, lifting 2 diameter of hole is 70mm, and lifting 2 depth of hole is 2.3 times heavy
3 height of well, lifting 2 spacing of hole are 2m, and lifting hole 2 is using two rows, and two rows lifting 2 arrangement parameter of hole is using as follows: first row lift
Rising hole 2 is inclination, and gradient is 65 degree, and it is 1100mm that first row, which is lifted hole 2 from 3 Edge Distance of open caisson, and second row lifting hole 2 is
Inclination, gradient are 65 degree, and second row is lifted hole 2 and first row lifting hole 2 and is arranged in parallel, and second row is lifted hole 2 from 3 side of open caisson
Edge distance is 1600mm;It is lifted hole 2 and injects cement slurry, the cement slurry ratio of mud is 0.45, and cement slurry mixes the expansion of calcium sulphoaluminate class
Agent.Uplifting amount is 70mm, and the volume of calcium sulphoaluminate class swelling agent is 6%.
Correction sequence is first to force-land, then be lifted, and forced landing or lifting are all made of information-aided construction, is pushed up in open caisson 3
Portion's cloth displacement sensor, displacement sensor is connect with computer carries out intelligent control, and displacement sensor transfers data to immediately
Computer, every sinking 2mm draws a curve to computer according to the collected data, and provides correction rate according to the slope of curve, analyzes
Correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, 3 bottom of open caisson
For clay, when fall rate is less than or equal to 0.02mm/min, drilling machine drilling speed is less than or equal to 90r/min and is greater than 80r/min,
Water injection pressure is 1.2MPa;When fall rate is greater than 0.02mm/min and is less than 0.03mm/min, drilling machine drilling speed is less than or equal to
80r/min and be greater than 75r/min, water injection pressure 1.2MPa;When fall rate is greater than or equal to 0.03mm/min, drilling machine drilling speed
Less than or equal to 75r/min and it is greater than 70r/min, water injection pressure 1.2MPa;
Construction is lifted using interval construction, i.e., first constructs and finishes the lifting hole 2 of odd indexed, then the lift for even number serial number of constructing
Hole 2 is risen, serial number carries out layout from left to right.The intermittent time of 20~30min is passed through in the lifting hole 2 of odd indexed after constructing
The lifting hole 2 for even number serial number of constructing again afterwards.
Claims (1)
1. a kind of inclination open caisson combines deviation rectification construction method, it is characterized in that the side setting forced landing hole slow in well sinking, forced landing
Bore dia is 75~120mm, and forced landing pitch of holes is 1.5~2.2m, and forming forced landing hole using bore mode makes caisson wall and its
Surrounding soil frictional force is reduced, and constantly water filling makes well sinking in boring procedure, instructs to rectify a deviation using intelligent control method
Technique, drilling machine drilling speed and water injection pressure are adjusted according to soil property and correction rate;
In the fast side setting lifting hole of well sinking, lifting bore dia is 60~90mm, and lifting pitch of holes is 1.8~2.5m,
Lifting hole depth is 2.2~2.5 times of open caisson height, and cement slurry is injected using two rows, lifting hole in lifting hole, and the cement slurry ratio of mud is
0.45~0.5, cement slurry mixes calcium sulphoaluminate class swelling agent;
Correction sequence is first to force-land, then be lifted, and forced landing or lifting are all made of information-aided construction, in open caisson top layout
Displacement sensor, displacement sensor is connect with computer carries out intelligent control, and displacement sensor transfers data to computer immediately, electricity
Every sinking or lifting 2mm draw a curve to brain according to the collected data, and provide correction rate according to the slope of curve, and analysis is entangled
Inclined development trend;
In silt or sand, forced landing construction uses following technical measures: being injected by Grouting Pipe mixed with micro- after pore-forming
Brilliant kaolinic water, at once by Grouting Pipe injection hole after the montmorillonite of incorporation 1%~2% in water, montmorillonite
It is expanded to the bead that diameter is 3~5mm after access aperture and is attached to open caisson wall, so that sliding friction is become rolling friction, reduces hole
Wall friction power.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810252458.4A CN108360545B (en) | 2016-11-17 | 2016-11-17 | It tilts open caisson and combines deviation rectification construction method |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611062968.2A CN106592615B (en) | 2016-11-17 | 2016-11-17 | Tilt open caisson deviation rectification construction method |
CN201810252458.4A CN108360545B (en) | 2016-11-17 | 2016-11-17 | It tilts open caisson and combines deviation rectification construction method |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611062968.2A Division CN106592615B (en) | 2016-11-17 | 2016-11-17 | Tilt open caisson deviation rectification construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108360545A CN108360545A (en) | 2018-08-03 |
CN108360545B true CN108360545B (en) | 2019-09-10 |
Family
ID=58595003
Family Applications (7)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810252548.3A Active CN108396760B (en) | 2016-11-17 | 2016-11-17 | Combined deviation-rectifying construction technology for inclined open caisson |
CN201810252386.3A Active CN108396759B (en) | 2016-11-17 | 2016-11-17 | Deviation rectifying construction method for inclined open caisson under different soil conditions |
CN201611062968.2A Active CN106592615B (en) | 2016-11-17 | 2016-11-17 | Tilt open caisson deviation rectification construction method |
CN201810251485.XA Active CN108396758B (en) | 2016-11-17 | 2016-11-17 | Open caisson deviation rectifying construction method |
CN201810251650.1A Active CN108442425B (en) | 2016-11-17 | 2016-11-17 | Inclined open caisson deviation rectification construction technology |
CN201810252828.4A Active CN108487278B (en) | 2016-11-17 | 2016-11-17 | Open caisson deviation rectification construction technology |
CN201810252458.4A Active CN108360545B (en) | 2016-11-17 | 2016-11-17 | It tilts open caisson and combines deviation rectification construction method |
Family Applications Before (6)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810252548.3A Active CN108396760B (en) | 2016-11-17 | 2016-11-17 | Combined deviation-rectifying construction technology for inclined open caisson |
CN201810252386.3A Active CN108396759B (en) | 2016-11-17 | 2016-11-17 | Deviation rectifying construction method for inclined open caisson under different soil conditions |
CN201611062968.2A Active CN106592615B (en) | 2016-11-17 | 2016-11-17 | Tilt open caisson deviation rectification construction method |
CN201810251485.XA Active CN108396758B (en) | 2016-11-17 | 2016-11-17 | Open caisson deviation rectifying construction method |
CN201810251650.1A Active CN108442425B (en) | 2016-11-17 | 2016-11-17 | Inclined open caisson deviation rectification construction technology |
CN201810252828.4A Active CN108487278B (en) | 2016-11-17 | 2016-11-17 | Open caisson deviation rectification construction technology |
Country Status (1)
Country | Link |
---|---|
CN (7) | CN108396760B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108396760B (en) * | 2016-11-17 | 2020-02-04 | 叶香雄 | Combined deviation-rectifying construction technology for inclined open caisson |
CN107246037A (en) * | 2017-08-09 | 2017-10-13 | 上海岩土工程勘察设计研究院有限公司 | A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course |
CN110144921A (en) * | 2019-06-06 | 2019-08-20 | 广东水利电力职业技术学院(广东省水利电力技工学校) | A kind of simple and efficient open caisson deviation rectification method |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1021982C (en) * | 1991-06-26 | 1993-09-01 | 黄正轩 | Method for correcting and reinforcing inclination of house |
JP2002004296A (en) * | 2000-06-19 | 2002-01-09 | Takenaka Doboku Co Ltd | Surface preparation device for excavation of cutting edge part for enlarging diameter of open caisson |
CN2654698Y (en) * | 2003-06-30 | 2004-11-10 | 唐业清 | Negative frictional force inclined correction precipitation well |
CN100567660C (en) * | 2007-12-26 | 2009-12-09 | 南京工业大学 | Construction method for rectifying deviation of open caisson by using preset force |
CN101793098B (en) * | 2010-03-13 | 2011-09-07 | 中铁西北科学研究院有限公司 | Coordinated interactive combined rectification method |
CN102926394B (en) * | 2010-06-05 | 2015-03-25 | 朱虹 | Method for using lime piles to rectify deviation of open caisson |
CN102912807B (en) * | 2010-06-05 | 2015-11-25 | 朱虹 | A kind of open caisson jacking deviation rectifying method |
CN102251542A (en) * | 2011-04-18 | 2011-11-23 | 张继红 | Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same |
CN103938663A (en) * | 2013-10-29 | 2014-07-23 | 国家电网公司 | Correction device of inclined power transmission tower made of signal-splicing steel angle principal material |
JP6386829B2 (en) * | 2014-08-08 | 2018-09-05 | 大成建設株式会社 | Pneumatic caisson tilt correction method |
CN105863362B (en) * | 2016-04-13 | 2017-11-14 | 太原理工大学 | A kind of deviation correcting device for being used to tilt electric power pylon |
CN108396760B (en) * | 2016-11-17 | 2020-02-04 | 叶香雄 | Combined deviation-rectifying construction technology for inclined open caisson |
-
2016
- 2016-11-17 CN CN201810252548.3A patent/CN108396760B/en active Active
- 2016-11-17 CN CN201810252386.3A patent/CN108396759B/en active Active
- 2016-11-17 CN CN201611062968.2A patent/CN106592615B/en active Active
- 2016-11-17 CN CN201810251485.XA patent/CN108396758B/en active Active
- 2016-11-17 CN CN201810251650.1A patent/CN108442425B/en active Active
- 2016-11-17 CN CN201810252828.4A patent/CN108487278B/en active Active
- 2016-11-17 CN CN201810252458.4A patent/CN108360545B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108487278A (en) | 2018-09-04 |
CN108396760A (en) | 2018-08-14 |
CN108442425A (en) | 2018-08-24 |
CN108396760B (en) | 2020-02-04 |
CN108360545A (en) | 2018-08-03 |
CN108396758A (en) | 2018-08-14 |
CN108396759A (en) | 2018-08-14 |
CN108396758B (en) | 2020-02-21 |
CN108396759B (en) | 2020-02-04 |
CN108442425B (en) | 2020-01-17 |
CN106592615B (en) | 2018-08-07 |
CN108487278B (en) | 2020-02-28 |
CN106592615A (en) | 2017-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108661705B (en) | Strip goaf four-in-one comprehensive treatment construction method | |
CN103422511B (en) | A kind of reinforcement method for transmission tower shallow base foundation under composite soft soil foundation | |
CN108360545B (en) | It tilts open caisson and combines deviation rectification construction method | |
CN104878723A (en) | Earth-rock mixed dam integral vertical anti-seepage structure and construction method | |
CN105484266B (en) | The grouting equipment and its construction method of a kind of multifunctional information | |
CN109594575A (en) | A kind of open caisson periphery grouting and reinforcing soil body construction method | |
CN109024719A (en) | A kind of side disturbance drop resistance building inclination rectification method | |
CN101818647B (en) | Advance support fast construction method in shallow tunnelling loose pebble bed | |
CN105133641A (en) | Thin-wall continuous-wall-type foundation reinforcing structure and method | |
CN105040705A (en) | Ground foundation treatment construction technology under multi-karst-cave geological conditions | |
CN106087996B (en) | Manual digging pile construction method based on self leveling backpressure device | |
CN203129151U (en) | Grouting head capable of drilling and grouting synchronously | |
CN209603123U (en) | A kind of bottom-enlarging filling pile structure for cutting down negative friction | |
CN204877485U (en) | Basement rock massif shield constructs tool changing normal position reinforced structure | |
CN111396061B (en) | Shield construction method and construction operation surface thereof | |
CN102704909B (en) | Hole-deflection control construction method for deep hole drilling | |
CN206408638U (en) | Tilt open caisson deviation rectification structure | |
CN205907688U (en) | Manual hole digging pile construction is with self - leveling back pressure device | |
CN207469263U (en) | A kind of rotary digging stake and the compound Extra-Deep Foundation Pit system of high-pressure slip-casting pile pile | |
CN106869934A (en) | A kind of slip casting recovery method suitable for inclined seam | |
CN205224070U (en) | Compound foundation stabilization structure of drill bit anchor pile | |
CN109236232A (en) | Gun drilling drilling technology under the conditions of a kind of high artesian groundwater | |
CN105297760B (en) | Drill bit anchor pile composite foundation stabilization structure | |
CN109056751A (en) | A kind of bedding rock sloper reinforcement means and reinforcing construction | |
CN209243784U (en) | One kind wearing dike piping lane grouting with small pipe leakage preventing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP02 | Change in the address of a patent holder | ||
CP02 | Change in the address of a patent holder |
Address after: 242199 Room 501, Office Building of Market Supervision Bureau of Langchuan Avenue, Jianping Town, Langxi County, Xuancheng City, Anhui Province Patentee after: Ye Xiangxiong Address before: 325025, No. 26, North Sichuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Wenzhou, Zhejiang Patentee before: Ye Xiangxiong |