CN106592615A - Deviation rectification construction method for inclined sink - Google Patents

Deviation rectification construction method for inclined sink Download PDF

Info

Publication number
CN106592615A
CN106592615A CN201611062968.2A CN201611062968A CN106592615A CN 106592615 A CN106592615 A CN 106592615A CN 201611062968 A CN201611062968 A CN 201611062968A CN 106592615 A CN106592615 A CN 106592615A
Authority
CN
China
Prior art keywords
equal
less
open caisson
lifting hole
injection pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611062968.2A
Other languages
Chinese (zh)
Other versions
CN106592615B (en
Inventor
叶香雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Ruisheng Water Conservancy And Hydropower Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to CN201810252458.4A priority Critical patent/CN108360545B/en
Priority to CN201810251485.XA priority patent/CN108396758B/en
Priority to CN201611062968.2A priority patent/CN106592615B/en
Priority to CN201810252386.3A priority patent/CN108396759B/en
Priority to CN201810251650.1A priority patent/CN108442425B/en
Application filed by Individual filed Critical Individual
Priority to CN201810252548.3A priority patent/CN108396760B/en
Priority to CN201810252828.4A priority patent/CN108487278B/en
Publication of CN106592615A publication Critical patent/CN106592615A/en
Application granted granted Critical
Publication of CN106592615B publication Critical patent/CN106592615B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • E02D23/14Decreasing the skin friction while lowering
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Earth Drilling (AREA)

Abstract

The invention provides a deviation rectification construction method for an inclined sink and discloses a basement concrete equal-height-beam construction method. The deviation rectification construction method is characterized in that forced landing holes with the diameters of 75-120 mm and the spaces of 1.5-2.2 m are formed in the side, sinking slowly, of a sink, lifting holes with the diameters of 60-90 mm, the spaces of 1.8-2.5 m and the depths of 2.2-2.5 times of the height of the sink are formed in the side, sinking quickly, of the sink, the lifting holes are arranged into two rows, cement paste with the water-cement ratio of 0.45-0.5 is injected into the lifting holes and doped with a calcium sulphoaluminate expanding agent, the deviation rectification sequence is that forced landing is performed at first and then lifting is performed, and forced landing and lifting adopt informationized construction.

Description

Incline open caisson deviation rectification construction method
Technical field
The present invention relates to deviation rectification construction method, more particularly to a kind of to incline open caisson deviation rectification construction method.
Background technology
Easily occur inclining during open caisson construction, to be rectified a deviation after inclination of open caisson, traditional open caisson deviation rectification method has digging Local method and increase external loads method, shoveling method is cut the earth to the slow one side that sinks more, increases the space between caisson cutting edge and soil, It is promoted to sink.To sinking, fast one side is optionally cut the earth less, is not cut the earth or mound, and heap rammed earth, increases sinking frictional resistance, Slow down subsidence velocity.It is to increase load in the slow side of well sinking to increase external loads method, while hollow out under its cutting shoe, with Profit overcomes frictional resistance to correct deflection.The problems of these conventional arts are difficult to control in work progress, and correction is easy Exceed the proper limits in righting a wrong.
The content of the invention
For the deficiencies in the prior art, it is an object of the invention to provide a kind of incline open caisson deviation rectification construction method To ensure rectifying effect.
The present invention arranges forced landing hole in the slow side of well sinking, and forced landing bore dia is 75~120mm, and forced landing pitch of holes is 1.5~2.2m, forming forced landing hole using bore mode makes caisson wall reduce with its surrounding soil frictional force, in boring procedure Constantly water filling makes well sinking, and correction technique is instructed using intelligent control method, and rig drilling speed and water injection pressure are according to soil property It is adjusted with correction speed.
Lifting hole being set in well sinking fast side, lifting bore dia is 60~90mm, lifting pitch of holes is 1.8~ 2.5m, lifting hole depth is 2.2~2.5 times of open caisson height, and lifting hole adopts two rows, and two row's lifting hole arrangement parameters are using such as Under:First row lifting hole is vertical, and first row lifting hole is 500~700mm from open caisson Edge Distance, and second row lifting hole is to incline Tiltedly, gradient is 60~70 degree, and here gradient refers to lifting hole and horizontal angle, and second row lifting hole is from open caisson edge Distance is 1000~1200mm;Two row's lifting hole arrangement parameters can also adopt as follows:First row lifting hole is inclination, gradient For 60~70 degree, first row lifting hole is 1000~1200mm from open caisson Edge Distance, and second row lifting hole is inclination, gradient For 60~70 degree, second row lifting hole and first row lifting hole are arranged in parallel, and second row lifting hole is from open caisson Edge Distance 1500~1700mm;Cement mortar is injected in lifting hole, and the cement mortar ratio of mud is 0.45~0.5, and it is swollen that cement mortar mixes calcium sulphoaluminate class Swollen dose, hydration reaction occurs into after the soil body mixed with the cement mortar of calcium sulphoaluminate class swelling agent, foundation soil body in hydration process Product expansion, to open caisson lifting force is produced, and the volume of calcium sulphoaluminate class swelling agent is directly related with the lifting force of open caisson, mixed with sulphur aluminium The cement mortar of sour calcium class swelling agent has not only acted as the effect of expansion lifting into after the soil body, and serves compacted compacting work With with the setting expansion of the cement mortar of calcium sulphoaluminate class swelling agent, foundation soil body packing substantially increases, and compressibility reduces. The volume of calcium sulphoaluminate class swelling agent determines according to open caisson amount, when Uplifting amount is more than or equal to 100mm, the expansion of calcium sulphoaluminate class The volume of agent is 7%;More than 50mm and during less than 100mm, the volume of calcium sulphoaluminate class swelling agent is 6% to Uplifting amount;Uplifting amount During less than 50mm, the volume of calcium sulphoaluminate class swelling agent is 5%.
Correction order is first to be force-landed, then carries out lifting, and forced landing or lifting adopt information-aided construction, at the top of open caisson Cloth displacement sensor, displacement transducer is connected with computer carries out Based Intelligent Control, and displacement transducer transfers data to electricity immediately Brain, computer often sinks according to the data of collection or lifting 2mm draws a curve, and provides correction speed according to the slope of curve, Analysis correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, when open caisson bottom For muck soil, when fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 120r/min and is more than 110r/min, water injection pressure is 1.3MPa;When the soil property that drills is muck soil, fall rate is more than 0.02mm/min and is less than During 0.03mm/min, less than or equal to 110r/min and more than 100r/min, water injection pressure is 1.3MPa to rig drilling speed;Work as drilling When soil property is muck soil, when fall rate is more than or equal to 0.03mm/min, rig drilling speed less than or equal to 100r/min and More than 90r/min, water injection pressure is 1.3MPa;
When open caisson bottom is clay, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 90r/min and more than 80r/min, water injection pressure is 1.2MPa;When drilling soil property is clay, fall rate is more than 0.02mm/min And during less than 0.03mm/min, less than or equal to 80r/min and more than 75r/min, water injection pressure is 1.2MPa to rig drilling speed;When Drilling soil property is clay, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 75r/min and is more than 70r/min, water injection pressure is 1.2MPa;
When open caisson bottom is silt, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 70r/min and more than 65r/min, water injection pressure is 1.1MPa;When drilling soil property is silt, fall rate is more than 0.02mm/min And during less than 0.03mm/min, less than or equal to 65r/min and more than 60r/min, water injection pressure is 1.1MPa to rig drilling speed;When Drilling soil property is silt, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 60r/min and is more than 55r/min, water injection pressure is 1.1MPa;
When open caisson bottom is sand, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 55r/min and more than 50r/min, water injection pressure is 1.0MPa;When drilling soil property is sand, fall rate is more than 0.02mm/min And during less than 0.03mm/min, less than or equal to 50r/min and more than 45r/min, water injection pressure is 1.0MPa to rig drilling speed;When Drilling soil property is sand, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 45r/min and is more than 40r/min, water injection pressure is 1.0MPa;
In silt or sand, open caisson can be difficult to, and can adopt following technical measures:Pore-forming passes through note after finishing Slurry pipe injects the water mixed with montmorillonite, mixes in water and pass through at once after 1%~2% montmorillonite Grouting Pipe hand-hole In, the bead that a diameter of 3~5mm is expanded to after montmorillonite access aperture is attached to open caisson wall, makes sliding friction be changed into rolling Friction, reduces hole wall frictional force, is conducive to correction to tell on.If there is drifting sand layer in geology, mix 2%~3% it is pure Alkali improving slurry consistency, receive ion to change the sub- hydrating capacity of grogs by increase.
Using interval construction, i.e., first construction finishes the lifting hole of odd indexed, then the lift of even number sequence number of constructing for lifting construction Hole is risen, sequence number carries out from left to right layout, prevent adjacent lifting hole from closely influencing each other in construction excessively or lifting hole slurry because of pitch-row Liquid expansive force discharges and affects correcting and then reinforcing effect.Construct after finishing through the interval of 20~30min in the lifting hole of odd indexed The lifting hole of even number sequence number of constructing again after the time, it is therefore an objective to which allowing swelling stress to obtain certain release guarantees rectifying effect.
The present invention has the advantages that rectifying effect is good, safe and reliable, with preferable application prospect.
Description of the drawings
Fig. 1 is open caisson deviation rectification horizontal layout schematic diagram one, and Fig. 2 is that open caisson deviation rectification facade arranges schematic diagram one, and Fig. 3 is open caisson Correction horizontal layout schematic diagram two, Fig. 4 is that open caisson deviation rectification facade arranges schematic diagram two.
Accompanying drawing mark:1st, force-land hole, 2, lifting hole, 3, open caisson.
Specific embodiment
The present embodiment is described in detail below in conjunction with accompanying drawing.
Embodiment one
Fig. 1 is open caisson deviation rectification horizontal layout schematic diagram one, and Fig. 2 is that open caisson deviation rectification facade arranges schematic diagram one.The present embodiment The side for sinking slow in open caisson 3 arranges forced landing hole 1, and force-land a diameter of 80mm in hole 1, and the forced landing spacing of hole 1 is 1.7m, using drilling side Formula forms forced landing hole 1 makes the borehole wall of open caisson 3 reduce with its surrounding soil frictional force, and the continuous water filling in boring procedure is made under open caisson 3 It is heavy, instruct correction technique, rig drilling speed and water injection pressure to be adjusted according to soil property and correction speed using intelligent control method It is whole.
The side for sinking fast in open caisson 3 arranges lifting hole 2, and a diameter of 70mm in lifting hole 2, the depth of lifting hole 2 is heavy for 2.2 times The height of well 3, the spacing of lifting hole 2 is 2m, and lifting hole 2 adopts two rows, and the arrangement parameter of two row's lifting hole 2 is using as follows:First row is lifted It is vertical to rise hole 2, and first row lifting hole 2 is 600mm from the Edge Distance of open caisson 3, and to incline, gradient is in second row lifting hole 2 65 degree, second row lifting hole 2 is 1100mm from the Edge Distance of open caisson 3;Cement mortar is injected in lifting hole 2, and the cement mortar ratio of mud is 0.45, cement mortar mixes calcium sulphoaluminate class swelling agent.Uplifting amount is 70mm, and the volume of calcium sulphoaluminate class swelling agent is 6%.
Correction order is first to be force-landed, then carries out lifting, and forced landing or lifting adopt information-aided construction, push up in open caisson 3 Portion's cloth displacement sensor, displacement transducer is connected with computer carries out Based Intelligent Control, and displacement transducer is transferred data to immediately Computer, computer often sinks according to the data of collection or lifting 2mm draws a curve, and provides correction speed according to the slope of curve Rate, analysis correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, the bottom of open caisson 3 For clay, when fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 90r/min and more than 80r/min, Water injection pressure is 1.2MPa;More than 0.02mm/min and during less than 0.03mm/min, rig drilling speed is less than or equal to fall rate 80r/min and more than 75r/min, water injection pressure is 1.2MPa;When fall rate is more than or equal to 0.03mm/min, rig drilling speed Less than or equal to 75r/min and more than 70r/min, water injection pressure is 1.2MPa;
Using interval construction, i.e., first construction finishes the lifting hole 2 of odd indexed, then the lift of even number sequence number of constructing for lifting construction Hole 2 is risen, sequence number carries out from left to right layout.Construct after finishing through the intermittent time of 20~30min in the lifting hole 2 of odd indexed The lifting hole 2 of even number sequence number of constructing again afterwards.
Embodiment two
Fig. 3 is open caisson deviation rectification horizontal layout schematic diagram two, and Fig. 4 is that open caisson deviation rectification facade arranges schematic diagram two.
The present embodiment arranges forced landing hole 1 in the side that open caisson 3 sinks slow, and force-land a diameter of 80mm in hole 1, the spacing of hole 1 of force-landing For 1.7m, forming forced landing hole 1 using bore mode makes the borehole wall of open caisson 3 reduce with its surrounding soil frictional force, in boring procedure Constantly water filling makes open caisson 3 sink, and correction technique is instructed using intelligent control method, and rig drilling speed and water injection pressure are according to soil property It is adjusted with correction speed.
The side for sinking fast in open caisson 3 arranges lifting hole 2, and a diameter of 70mm in lifting hole 2, the depth of lifting hole 2 is heavy for 2.3 times The height of well 3, the spacing of lifting hole 2 is 2m, and lifting hole 2 adopts two rows, and the arrangement parameter of two row's lifting hole 2 is using as follows:First row is lifted Hole 2 is risen to incline, gradient is 65 degree, and first row lifting hole 2 is 1100mm from the Edge Distance of open caisson 3, and second row lifting hole 2 is Incline, gradient is 65 degree, and second row lifting hole 2 and first row lifting hole 2 are arranged in parallel, and second row lifting hole 2 is from the side of open caisson 3 Edge distance is 1600mm;Cement mortar is injected in lifting hole 2, and the cement mortar ratio of mud is 0.45, and cement mortar mixes the expansion of calcium sulphoaluminate class Agent.Uplifting amount is 70mm, and the volume of calcium sulphoaluminate class swelling agent is 6%.
Correction order is first to be force-landed, then carries out lifting, and forced landing or lifting adopt information-aided construction, push up in open caisson 3 Portion's cloth displacement sensor, displacement transducer is connected with computer carries out Based Intelligent Control, and displacement transducer is transferred data to immediately Computer, according to the data of collection, often sinking 2mm draws a curve to computer, and provides correction speed according to the slope of curve, analyzes Correction development trend.
Penetration rate and water injection pressure are adjusted according to soil property and fall rate in forced landing work progress, the bottom of open caisson 3 For clay, when fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 90r/min and more than 80r/min, Water injection pressure is 1.2MPa;More than 0.02mm/min and during less than 0.03mm/min, rig drilling speed is less than or equal to fall rate 80r/min and more than 75r/min, water injection pressure is 1.2MPa;When fall rate is more than or equal to 0.03mm/min, rig drilling speed Less than or equal to 75r/min and more than 70r/min, water injection pressure is 1.2MPa;
Using interval construction, i.e., first construction finishes the lifting hole 2 of odd indexed, then the lift of even number sequence number of constructing for lifting construction Hole 2 is risen, sequence number carries out from left to right layout.Construct after finishing through the intermittent time of 20~30min in the lifting hole 2 of odd indexed The lifting hole 2 of even number sequence number of constructing again afterwards.

Claims (9)

1. it is a kind of to incline open caisson deviation rectification construction method, it is characterized in that arranging forced landing hole in the slow side of well sinking, force-land Kong Zhi Footpath be 75~120mm, forced landing pitch of holes be 1.5~2.2m, using bore mode formed force-land hole make caisson wall and its around Soil body frictional force is reduced, and the continuous water filling in boring procedure is made well sinking, correction technique is instructed using intelligent control method, Rig drilling speed and water injection pressure are adjusted according to soil property and correction speed;
Lifting hole is set in well sinking fast side, lifting bore dia is 60~90mm, and lifting pitch of holes is 1.8~2.5m, Lifting hole depth is 2.2~2.5 times of open caisson height, and lifting hole adopts two rows, lifting hole to inject cement mortar, and the cement mortar ratio of mud is 0.45~0.5, cement mortar mixes calcium sulphoaluminate class swelling agent;
Correction order is first to be force-landed, then carries out lifting, and forced landing or lifting adopt information-aided construction, in open caisson top layout Displacement transducer, displacement transducer is connected with computer carries out Based Intelligent Control, and displacement transducer transfers data to computer immediately, electricity Brain often sinks according to the data of collection or lifting 2mm draws a curve, and provides correction speed according to the slope of curve, and analysis is entangled Inclined development trend.
2. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that two row's lifting hole arrangement parameters are adopted It is as follows:First row lifting hole is vertical, and first row lifting hole is 500~700mm from open caisson Edge Distance, and second row lifting hole is Incline, gradient is 60~70 degree, second row lifting hole is 1000~1200mm from open caisson Edge Distance.
3. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that two row's lifting hole arrangement parameters are adopted It is as follows:To incline, gradient is 60~70 degree in first row lifting hole, first row lifting hole from open caisson Edge Distance for 1000~ 1200mm, to incline, gradient is 60~70 degree, second row lifting hole cloth parallel with first row lifting hole in second row lifting hole Put, second row lifting hole is 1500~1700mm from open caisson Edge Distance.
4. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that the volume of calcium sulphoaluminate class swelling agent Determined according to open caisson amount, when Uplifting amount is more than or equal to 100mm, the volume of calcium sulphoaluminate class swelling agent is 7%;Uplifting amount is big During in 50mm and less than 100mm, the volume of calcium sulphoaluminate class swelling agent is 6%;When Uplifting amount is less than 50mm, calcium sulphoaluminate class is swollen Swollen dose of volume is 5%.
5. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that penetration rate in forced landing work progress It is adjusted according to soil property and fall rate with water injection pressure, when open caisson bottom is muck soil, fall rate is less than or equal to During 0.02mm/min, less than or equal to 120r/min and more than 110r/min, water injection pressure is 1.3MPa to rig drilling speed;Work as drilling When soil property is muck soil, more than 0.02mm/min and during less than 0.03mm/min, rig drilling speed is less than or equal to fall rate 110r/min and more than 100r/min, water injection pressure is 1.3MPa;When drill soil property be muck soil when, fall rate be more than or During equal to 0.03mm/min, less than or equal to 100r/min and more than 90r/min, water injection pressure is 1.3MPa to rig drilling speed;
When open caisson bottom is clay, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 90r/min And more than 80r/min, water injection pressure is 1.2MPa;When drilling soil property is clay, fall rate is more than 0.02mm/min and is less than During 0.03mm/min, less than or equal to 80r/min and more than 75r/min, water injection pressure is 1.2MPa to rig drilling speed;When drilling soil Matter is clay, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 75r/min and more than 70r/ Min, water injection pressure is 1.2MPa;
When open caisson bottom is silt, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 70r/min And more than 65r/min, water injection pressure is 1.1MPa;When drilling soil property is silt, fall rate is more than 0.02mm/min and is less than During 0.03mm/min, less than or equal to 65r/min and more than 60r/min, water injection pressure is 1.1MPa to rig drilling speed;When drilling soil Matter is silt, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 60r/min and more than 55r/ Min, water injection pressure is 1.1MPa;
When open caisson bottom is sand, and fall rate is less than or equal to 0.02mm/min, rig drilling speed is less than or equal to 55r/min And more than 50r/min, water injection pressure is 1.0MPa;When drilling soil property is sand, fall rate is more than 0.02mm/min and is less than During 0.03mm/min, less than or equal to 50r/min and more than 45r/min, water injection pressure is 1.0MPa to rig drilling speed;When drilling soil Matter is sand, and when fall rate is more than or equal to 0.03mm/min, rig drilling speed is less than or equal to 45r/min and more than 40r/ Min, water injection pressure is 1.0MPa.
6. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that forced landing is applied in silt or sand Work adopts following technical measures:Pore-forming finish after by Grouting Pipe inject mixed with montmorillonite water, in water mix 1%~ At once by Grouting Pipe hand-hole, a diameter of 3~5mm being expanded to after montmorillonite access aperture after 2% montmorillonite Bead be attached to open caisson wall, make sliding friction be changed into rolling friction, reduce hole wall frictional force.
7. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that if geology has drifting sand layer, mix 2%~3% soda ash is improving slurry consistency.
8. inclination open caisson deviation rectification construction method according to claim 1, is characterized in that horizon bar top root with a distance from beam bottom It is adjusted according to deck-molding;When deck-molding is 400mm, horizon bar top adopts 500mm with a distance from beam bottom;When deck-molding be 500mm, level Bar top adopts 450mm with a distance from beam bottom;When deck-molding is 600mm, horizon bar top adopts 400mm with a distance from beam bottom;Work as deck-molding For 700mm and more than, horizon bar top adopt 350mm with a distance from beam bottom.
9. inclination open caisson deviation rectification construction method according to claim 2, is characterized in that lifting construction is constructed using interval, i.e., First construction finishes the lifting hole of odd indexed, then the lifting hole of even number sequence number of constructing, and sequence number carries out from left to right layout.Odd number sequence Number the construction of lifting hole finish after construct again after the intermittent time of 20~30min the lifting hole of even number sequence number.
CN201611062968.2A 2016-11-17 2016-11-17 Tilt open caisson deviation rectification construction method Active CN106592615B (en)

Priority Applications (7)

Application Number Priority Date Filing Date Title
CN201810251485.XA CN108396758B (en) 2016-11-17 2016-11-17 Open caisson deviation rectifying construction method
CN201611062968.2A CN106592615B (en) 2016-11-17 2016-11-17 Tilt open caisson deviation rectification construction method
CN201810252386.3A CN108396759B (en) 2016-11-17 2016-11-17 Deviation rectifying construction method for inclined open caisson under different soil conditions
CN201810251650.1A CN108442425B (en) 2016-11-17 2016-11-17 Inclined open caisson deviation rectification construction technology
CN201810252458.4A CN108360545B (en) 2016-11-17 2016-11-17 It tilts open caisson and combines deviation rectification construction method
CN201810252548.3A CN108396760B (en) 2016-11-17 2016-11-17 Combined deviation-rectifying construction technology for inclined open caisson
CN201810252828.4A CN108487278B (en) 2016-11-17 2016-11-17 Open caisson deviation rectification construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611062968.2A CN106592615B (en) 2016-11-17 2016-11-17 Tilt open caisson deviation rectification construction method

Related Child Applications (6)

Application Number Title Priority Date Filing Date
CN201810252828.4A Division CN108487278B (en) 2016-11-17 2016-11-17 Open caisson deviation rectification construction technology
CN201810252458.4A Division CN108360545B (en) 2016-11-17 2016-11-17 It tilts open caisson and combines deviation rectification construction method
CN201810252548.3A Division CN108396760B (en) 2016-11-17 2016-11-17 Combined deviation-rectifying construction technology for inclined open caisson
CN201810251485.XA Division CN108396758B (en) 2016-11-17 2016-11-17 Open caisson deviation rectifying construction method
CN201810252386.3A Division CN108396759B (en) 2016-11-17 2016-11-17 Deviation rectifying construction method for inclined open caisson under different soil conditions
CN201810251650.1A Division CN108442425B (en) 2016-11-17 2016-11-17 Inclined open caisson deviation rectification construction technology

Publications (2)

Publication Number Publication Date
CN106592615A true CN106592615A (en) 2017-04-26
CN106592615B CN106592615B (en) 2018-08-07

Family

ID=58595003

Family Applications (7)

Application Number Title Priority Date Filing Date
CN201810252458.4A Active CN108360545B (en) 2016-11-17 2016-11-17 It tilts open caisson and combines deviation rectification construction method
CN201810252548.3A Active CN108396760B (en) 2016-11-17 2016-11-17 Combined deviation-rectifying construction technology for inclined open caisson
CN201810252386.3A Active CN108396759B (en) 2016-11-17 2016-11-17 Deviation rectifying construction method for inclined open caisson under different soil conditions
CN201611062968.2A Active CN106592615B (en) 2016-11-17 2016-11-17 Tilt open caisson deviation rectification construction method
CN201810251485.XA Active CN108396758B (en) 2016-11-17 2016-11-17 Open caisson deviation rectifying construction method
CN201810252828.4A Active CN108487278B (en) 2016-11-17 2016-11-17 Open caisson deviation rectification construction technology
CN201810251650.1A Active CN108442425B (en) 2016-11-17 2016-11-17 Inclined open caisson deviation rectification construction technology

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201810252458.4A Active CN108360545B (en) 2016-11-17 2016-11-17 It tilts open caisson and combines deviation rectification construction method
CN201810252548.3A Active CN108396760B (en) 2016-11-17 2016-11-17 Combined deviation-rectifying construction technology for inclined open caisson
CN201810252386.3A Active CN108396759B (en) 2016-11-17 2016-11-17 Deviation rectifying construction method for inclined open caisson under different soil conditions

Family Applications After (3)

Application Number Title Priority Date Filing Date
CN201810251485.XA Active CN108396758B (en) 2016-11-17 2016-11-17 Open caisson deviation rectifying construction method
CN201810252828.4A Active CN108487278B (en) 2016-11-17 2016-11-17 Open caisson deviation rectification construction technology
CN201810251650.1A Active CN108442425B (en) 2016-11-17 2016-11-17 Inclined open caisson deviation rectification construction technology

Country Status (1)

Country Link
CN (7) CN108360545B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107246037A (en) * 2017-08-09 2017-10-13 上海岩土工程勘察设计研究院有限公司 A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course
CN110144921A (en) * 2019-06-06 2019-08-20 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of simple and efficient open caisson deviation rectification method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360545B (en) * 2016-11-17 2019-09-10 叶香雄 It tilts open caisson and combines deviation rectification construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1058069A (en) * 1991-06-26 1992-01-22 黄正轩 Method for correcting and reinforcing inclination of house
CN2654698Y (en) * 2003-06-30 2004-11-10 唐业清 Negative frictional force inclined correction precipitation well
CN101793098A (en) * 2010-03-13 2010-08-04 中铁西北科学研究院有限公司 Coordinated interactive combined rectification method
CN101845830A (en) * 2010-06-05 2010-09-29 朱虹 Open caisson deviation rectification construction method
CN102251542A (en) * 2011-04-18 2011-11-23 张继红 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same
JP2016037784A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Method for correcting inclination of pneumatic caisson

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004296A (en) * 2000-06-19 2002-01-09 Takenaka Doboku Co Ltd Surface preparation device for excavation of cutting edge part for enlarging diameter of open caisson
CN100567660C (en) * 2007-12-26 2009-12-09 南京工业大学 Construction method for rectifying deviation of open caisson by using preset force
CN102926394B (en) * 2010-06-05 2015-03-25 朱虹 Method for using lime piles to rectify deviation of open caisson
CN103938663A (en) * 2013-10-29 2014-07-23 国家电网公司 Correction device of inclined power transmission tower made of signal-splicing steel angle principal material
CN105863362B (en) * 2016-04-13 2017-11-14 太原理工大学 A kind of deviation correcting device for being used to tilt electric power pylon
CN108360545B (en) * 2016-11-17 2019-09-10 叶香雄 It tilts open caisson and combines deviation rectification construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1058069A (en) * 1991-06-26 1992-01-22 黄正轩 Method for correcting and reinforcing inclination of house
CN2654698Y (en) * 2003-06-30 2004-11-10 唐业清 Negative frictional force inclined correction precipitation well
CN101793098A (en) * 2010-03-13 2010-08-04 中铁西北科学研究院有限公司 Coordinated interactive combined rectification method
CN101845830A (en) * 2010-06-05 2010-09-29 朱虹 Open caisson deviation rectification construction method
CN102251542A (en) * 2011-04-18 2011-11-23 张继红 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same
JP2016037784A (en) * 2014-08-08 2016-03-22 大成建設株式会社 Method for correcting inclination of pneumatic caisson

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107246037A (en) * 2017-08-09 2017-10-13 上海岩土工程勘察设计研究院有限公司 A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course
CN110144921A (en) * 2019-06-06 2019-08-20 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of simple and efficient open caisson deviation rectification method

Also Published As

Publication number Publication date
CN108396760A (en) 2018-08-14
CN108487278B (en) 2020-02-28
CN108360545B (en) 2019-09-10
CN108487278A (en) 2018-09-04
CN108442425A (en) 2018-08-24
CN108396760B (en) 2020-02-04
CN108396759B (en) 2020-02-04
CN108442425B (en) 2020-01-17
CN108360545A (en) 2018-08-03
CN108396758B (en) 2020-02-21
CN106592615B (en) 2018-08-07
CN108396759A (en) 2018-08-14
CN108396758A (en) 2018-08-14

Similar Documents

Publication Publication Date Title
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN210858745U (en) Loess tunnel advance reinforced structure based on sleeve valve pipe slip casting
CN112081155B (en) Reinforcing and lifting method for bar-shaped or box-shaped foundation building
CN112081154B (en) Method for reinforcing and lifting high-rise building with raft foundation
CN106592615B (en) Tilt open caisson deviation rectification construction method
CN106320403A (en) Inclination rectification and reinforcement method for existing building
CN104878723A (en) Earth-rock mixed dam integral vertical anti-seepage structure and construction method
CN114483109B (en) Curtain grouting advanced large pipe shed through construction method for crossing tunnel fault fracture zone
CN109594575A (en) A kind of open caisson periphery grouting and reinforcing soil body construction method
WO2021004007A1 (en) Foundation reinforcement method for conventional building
CN211081894U (en) Water-rich stratum tunnel is precipitation structure in coordination
CN105133641A (en) Thin-wall continuous-wall-type foundation reinforcing structure and method
CN112855029B (en) Goaf drilling external pipe expansion construction method
CN108570982A (en) The quiet brill of one kind taking root in energy stake and its construction method
CN106087996B (en) Manual digging pile construction method based on self leveling backpressure device
CN106192987A (en) A kind of construction method that stake periphery is crushed geology reinforcing
CN206721875U (en) A kind of pressure-bearing type boulder and cobble soil layer enlarging anchor rod
CN209603123U (en) A kind of bottom-enlarging filling pile structure for cutting down negative friction
CN106869934A (en) A kind of slip casting recovery method suitable for inclined seam
CN207469263U (en) A kind of rotary digging stake and the compound Extra-Deep Foundation Pit system of high-pressure slip-casting pile pile
CN205907688U (en) Manual hole digging pile construction is with self - leveling back pressure device
CN205975627U (en) Ultradeep foundation pit supports no intermittent type combined type transform structure
CN106149731A (en) Main building basement construction method for supporting with annex
CN105297760B (en) Drill bit anchor pile composite foundation stabilization structure
CN206956756U (en) Tilt open caisson deviation rectification construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201126

Address after: 730314 No. 6328, Weihe street, Lanzhou New District, Gansu, Lanzhou

Patentee after: Gansu Ruisheng water conservancy and Hydropower Engineering Co., Ltd

Address before: 325025, No. 26, North Sichuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Wenzhou, Zhejiang

Patentee before: Ye Xiangxiong