CN108256598A - A kind of construction monitoring method - Google Patents

A kind of construction monitoring method Download PDF

Info

Publication number
CN108256598A
CN108256598A CN201711466438.9A CN201711466438A CN108256598A CN 108256598 A CN108256598 A CN 108256598A CN 201711466438 A CN201711466438 A CN 201711466438A CN 108256598 A CN108256598 A CN 108256598A
Authority
CN
China
Prior art keywords
construction
personnel
identity information
monitoring
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711466438.9A
Other languages
Chinese (zh)
Inventor
尚凌辉
金杭
王丹
陈鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zechk Artificial Intelligence Research And Development Co Ltd
Original Assignee
Zhejiang Zechk Artificial Intelligence Research And Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zechk Artificial Intelligence Research And Development Co Ltd filed Critical Zhejiang Zechk Artificial Intelligence Research And Development Co Ltd
Priority to CN201711466438.9A priority Critical patent/CN108256598A/en
Publication of CN108256598A publication Critical patent/CN108256598A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/105Human resources
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • General Engineering & Computer Science (AREA)
  • Emergency Alarm Devices (AREA)
  • Alarm Systems (AREA)

Abstract

The invention discloses a kind of construction monitoring methods, include the following steps:Step 1:All construction personnel's identity information registrations;Step 2:Identify construction personnel's identity information, construction personnel enters construction area;Step 3:The treatment of the earth of construction site is recorded, divides safety zone, the structural security risk of real-time monitoring field;Step 4:Long-range monitoring construction site, commander's construction;Step 5:It tracks and shoots work progress, analyze construction information in real time and automatic clustering achieves.It can be compared by the electronic tag and presupposed information for including construction personnel's identity information, the construction personnel for entering construction site is accurately managed, convenient for the remote management of construction site, the security risk of monitoring construction site in real time, record, analysis work progress in real time, increase the safety of construction site, pass through voice communication and infrared camera to a certain extent, technical staff and administrative staff is facilitated to be linked up with scene, avoid the issuable error of simple speech exchange.

Description

A kind of construction monitoring method
Technical field
The present invention relates to a kind of construction site management method more particularly to a kind of construction monitoring methods.
Background technology
Construction site now is all often that construction personnel voluntarily constructs on-site, and technical staff and administrative staff It is less to reconnoitre or supervise to construction site, but often action and environment are all complex for construction site, to technical and Safety has very high requirement, is even effectively instructed according to specific action.At present, technical staff or pipe When reason personnel are not had at the scene, the mode that generally use is made a phone call is linked up or is instructed, and simple voice communication easily has Deviation in understanding, it tends to be difficult to get a desired effect.In addition, construction site belongs to the higher place of danger coefficient, it is non-to apply Worker person enters construction site not only there are great security risk, but also influences construction speed.It being capable of essence so lacking one kind at present It really manages and convenient for communication, and can ensure the method for the site operation supervision of construction safety to a certain extent.
Invention content
To solve the deficiencies in the prior art, the present invention provides a kind of construction monitoring method, can by monitoring device into The construction personnel for entering construction site accurately manages, meanwhile, the security risk of construction site is monitored in real time, is recorded in real time, analysis is applied Work process, and technical staff and administrative staff is facilitated to be linked up with scene.
To achieve the above object, using following technical scheme:
A kind of construction monitoring method, which is characterized in that include the following steps:
Step 1:All construction personnel's identity information registrations;
Step 2:Identify construction personnel's identity information, construction personnel enters construction area;
Step 3:The treatment of the earth of construction site is recorded, divides safety zone, the structural safety of real-time monitoring field is hidden Suffer from;
Step 4:Long-range monitoring construction site, commander's construction;
Step 5:It tracks and shoots work progress, analyze construction information in real time and automatic clustering achieves.
Further, step 1 specifically includes:
1a:The identity information of all construction personnel is registered, including basic identity information, identity class information;
1b:Unique corresponding electronic tag is formulated according to the identity information of registration.
Further, the electronic tag in 1b is radio frequency chip card.
Further, in step 2, construction personnel uses the electronic tag of carrying before any one construction area is entered It is contacted with the identification device of monitoring device, identity information included in monitoring device identification electronic tag, when identity grade is believed When breath reaches the access qualification in the region, construction personnel can enter the construction area, and record the basic identity of construction personnel Information;By identity grade, construction personnel intelligently enters corresponding construction area, and the management of construction site can be allowed more to advise Model, while the safety of construction site is increased to a certain extent.
Further, step 3 includes:
3a:Monitoring device records the treatment of the earth of construction site when each construction starts again, marks off safety zone, And safe escape route is formulated, it is stored after Security Officer confirms;
3b:The structural security risk of construction site is monitored in real time, construction site occurs sending out alarm during dangerous situation.
The treatment of the earth of construction site is recorded again, and formulate safe escape route so that be in when construction starts every time Existing escape way can be properer with live actual conditions.
Further, in step 4, commander's construction is carried out by speech talkback and video, avoids simple speech exchange can The error that can be generated.
Further, it in step 5, is tracked using infrared camera and shoots work progress, divided in real time by image analysis The operation of construction personnel is analysed, construction speed is recorded, prompt message is sent out when violation operation occurs in construction personnel;By applying for shooting It is preserved after the classification of work procedural information.
Beneficial effects of the present invention:
1. it can be compared by the electronic tag and presupposed information for including construction personnel's identity information, it is existing to entering construction The construction personnel of field accurately manages, convenient for the remote management of construction site.
2. the security risk of monitoring construction site in real time, record, analysis work progress, increase to a certain extent in real time The safety of construction site.
3. by voice communication and infrared camera, technical staff and administrative staff is facilitated to be linked up with scene, avoid list The issuable error of pure speech exchange.
Description of the drawings
Fig. 1 is a kind of flow diagram of construction monitoring method of the present invention;
Specific embodiment
With reference to shown in Fig. 1, a kind of construction monitoring method, which is characterized in that include the following steps:
Step 1:All construction personnel's identity information registrations;Step 1 specifically includes:
1a:The identity information of all construction personnel is registered, including basic identity information, identity class information;
1b:Unique corresponding electronic tag is formulated according to the identity information of registration, includes construction personnel's in electronic tag Identity information.
Step 2:Identify construction personnel's identity information, construction personnel enters construction area;
Step 3:The treatment of the earth of construction site is recorded, divides safety zone, the structural safety of real-time monitoring field is hidden Suffer from;Step 3 specifically includes:
3a:Monitoring device records the treatment of the earth of construction site when each construction starts again, marks off safety zone, And safe escape route is formulated, it is stored after Security Officer confirms;
3b:The structural security risk of construction site is monitored in real time, construction site occurs sending out alarm during dangerous situation; Structural security risk refers to mechanical equipment, fabric structure and security risk existing for other facilities in kind.
Step 4:Long-range monitoring construction site, commander's construction;
Step 5:It tracks and shoots work progress, analyze construction information in real time and automatic clustering achieves.
Preferably, the electronic tag in 1b is radio frequency chip card, which is contact chip card, in chip card Basic identity information comprising construction personnel and identity class information.
Preferably, in step 2, construction personnel enter any one construction area before, using carrying electronic tag with The identification device contact of monitoring device, identity information included in monitoring device identification electronic tag, when identity class information When reaching the access qualification in the region, construction personnel can enter the construction area;If the identity registration that electronic tag is included The access qualification in the not no region of information, then corresponding construction personnel cannot enter the region, and record into the construction area Construction personnel basic identity information.
Preferably, in step 4, commander's construction is carried out by speech talkback and video, during speech talkback and video, Construction personnel and remote technician can see construction site picture, but construction personnel cannot see that remote technician draws Face.
Preferably, it in step 5, is tracked using infrared camera and shoots work progress, analyzed in real time by image analysis The operation of construction personnel records construction speed, prompt message is sent out when violation operation occurs in construction personnel;By the construction of shooting It is preserved after procedural information classification, image is captured at scene when classification normal construction procedural image, violation operation image, danger occur.
The basic principles, main features and advantages of the invention have been shown and described above.The technical staff of the industry should Understand, the invention is not limited in any way above-described embodiment, all to be obtained by the way of equivalent substitution or equivalent transformation Technical solution is all fallen in protection scope of the present invention.

Claims (7)

1. a kind of construction monitoring method, which is characterized in that include the following steps:
Step 1:All construction personnel's identity information registrations;
Step 2:Identify construction personnel's identity information, construction personnel enters construction area;
Step 3:The treatment of the earth of construction site is recorded, divides safety zone, the structural security risk of real-time monitoring field;
Step 4:Long-range monitoring construction site, commander's construction;
Step 5:It tracks and shoots work progress, analyze construction information in real time and automatic clustering achieves.
2. construction monitoring method according to claim 1, which is characterized in that step 1 includes:
1a:The identity information of all construction personnel is registered, including basic identity information, identity class information;
1b:Unique corresponding electronic tag is formulated according to the identity information of registration.
3. construction monitoring method according to claim 2, it is characterised in that:Electronic tag in 1b is radio frequency chip card.
4. construction monitoring method according to claim 2, it is characterised in that:In step 2, construction personnel is entering arbitrarily It before one construction area, is contacted using the electronic tag of carrying with the identification device of monitoring device, monitoring device identification electronics mark Identity information included in label, when identity class information reaches the access qualification in the region, construction personnel can enter should Construction area, and record the basic identity information of construction personnel.
5. construction monitoring method according to claim 4, which is characterized in that step 3 includes:
3a:Monitoring device records the treatment of the earth of construction site when each construction starts again, marks off safety zone, and make The full escape route in Dingan County, stores after Security Officer confirms;
3b:The structural security risk of construction site is monitored in real time, construction site occurs sending out alarm during dangerous situation.
6. construction monitoring method according to claim 5, it is characterised in that:In step 4, pass through speech talkback and video Carry out commander's construction.
7. construction monitoring method according to claim 6, it is characterised in that:In step 5, tracked using infrared camera And work progress is shot, it analyzes the operation of construction personnel in real time by image analysis, records construction speed, when construction personnel occurs Prompt message is sent out during violation operation;It is preserved after the work progress information of shooting is classified.
CN201711466438.9A 2017-12-28 2017-12-28 A kind of construction monitoring method Pending CN108256598A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711466438.9A CN108256598A (en) 2017-12-28 2017-12-28 A kind of construction monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711466438.9A CN108256598A (en) 2017-12-28 2017-12-28 A kind of construction monitoring method

Publications (1)

Publication Number Publication Date
CN108256598A true CN108256598A (en) 2018-07-06

Family

ID=62724344

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711466438.9A Pending CN108256598A (en) 2017-12-28 2017-12-28 A kind of construction monitoring method

Country Status (1)

Country Link
CN (1) CN108256598A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109118054A (en) * 2018-07-18 2019-01-01 青岛地铁集团有限公司运营分公司 A kind of metro operation construction dispatching management system
CN109459966A (en) * 2018-12-07 2019-03-12 合肥诺必达信息技术有限责任公司 A kind of construction safety intelligent management system
CN109688386A (en) * 2019-01-31 2019-04-26 广州轨道交通建设监理有限公司 A kind of video monitoring method, system and equipment
CN109905675A (en) * 2019-03-13 2019-06-18 武汉大学 A kind of mine personnel monitoring system based on computer vision and method
CN110009261A (en) * 2019-04-27 2019-07-12 何铖 A kind of power transmission project construction field real time commanding system
CN111290342A (en) * 2018-12-07 2020-06-16 国网山西省电力公司运城供电公司 Safety monitoring method for power grid engineering construction site
CN111652147A (en) * 2020-06-04 2020-09-11 中电建路桥集团有限公司 Monitoring system and method for construction process of load reduction component in hollow floor system of underground garage
CN111667597A (en) * 2020-06-05 2020-09-15 李建华 Constructor monitoring system based on big data and task presetting
CN112542027A (en) * 2020-12-04 2021-03-23 国网浙江德清县供电有限公司 Construction site personnel safety warning system based on image recognition
CN114037299A (en) * 2021-11-15 2022-02-11 广西科技大学 Monitoring method for building bridge construction
CN114927001A (en) * 2022-04-19 2022-08-19 天津二建建筑工程有限公司 Video monitoring method, system, intelligent terminal and storage medium
CN115619204A (en) * 2022-12-20 2023-01-17 天津建设发展集团有限公司 Engineering field monitoring method and system based on wireless Internet of things

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103116926A (en) * 2013-01-30 2013-05-22 上海城建市政工程(集团)有限公司 Real-time monitoring system based on RFID (Radio Frequency Identification Devices) safety helmet and application method thereof
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN105847769A (en) * 2016-06-16 2016-08-10 苏州安控物联网科技有限公司 Construction site behavior analysis system and analysis method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103116926A (en) * 2013-01-30 2013-05-22 上海城建市政工程(集团)有限公司 Real-time monitoring system based on RFID (Radio Frequency Identification Devices) safety helmet and application method thereof
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN105847769A (en) * 2016-06-16 2016-08-10 苏州安控物联网科技有限公司 Construction site behavior analysis system and analysis method

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109118054A (en) * 2018-07-18 2019-01-01 青岛地铁集团有限公司运营分公司 A kind of metro operation construction dispatching management system
CN109459966A (en) * 2018-12-07 2019-03-12 合肥诺必达信息技术有限责任公司 A kind of construction safety intelligent management system
CN111290342A (en) * 2018-12-07 2020-06-16 国网山西省电力公司运城供电公司 Safety monitoring method for power grid engineering construction site
CN109688386A (en) * 2019-01-31 2019-04-26 广州轨道交通建设监理有限公司 A kind of video monitoring method, system and equipment
CN109905675A (en) * 2019-03-13 2019-06-18 武汉大学 A kind of mine personnel monitoring system based on computer vision and method
CN110009261A (en) * 2019-04-27 2019-07-12 何铖 A kind of power transmission project construction field real time commanding system
CN111652147A (en) * 2020-06-04 2020-09-11 中电建路桥集团有限公司 Monitoring system and method for construction process of load reduction component in hollow floor system of underground garage
CN111667597A (en) * 2020-06-05 2020-09-15 李建华 Constructor monitoring system based on big data and task presetting
CN112542027A (en) * 2020-12-04 2021-03-23 国网浙江德清县供电有限公司 Construction site personnel safety warning system based on image recognition
CN114037299A (en) * 2021-11-15 2022-02-11 广西科技大学 Monitoring method for building bridge construction
CN114037299B (en) * 2021-11-15 2022-05-31 广西科技大学 Monitoring method for building bridge construction
CN114927001A (en) * 2022-04-19 2022-08-19 天津二建建筑工程有限公司 Video monitoring method, system, intelligent terminal and storage medium
CN114927001B (en) * 2022-04-19 2023-09-26 天津二建建筑工程有限公司 Video monitoring method, system, intelligent terminal and storage medium
CN115619204A (en) * 2022-12-20 2023-01-17 天津建设发展集团有限公司 Engineering field monitoring method and system based on wireless Internet of things

Similar Documents

Publication Publication Date Title
CN108256598A (en) A kind of construction monitoring method
CN207301750U (en) Power grid construction intelligence control platform system
US10812761B2 (en) Complex hardware-based system for video surveillance tracking
CN106412501B (en) A kind of the construction safety behavior intelligent monitor system and its monitoring method of video
CN109214276A (en) A kind of system and method for the target person track following based on face recognition technology
CN112396658B (en) Indoor personnel positioning method and system based on video
CN104463174A (en) Multi-angle dynamic people recognition and behavior prediction system
CN107944838A (en) A kind of intelligent barrier gate Field Monitoring System and method
CN108364374A (en) Face access control device based on deep learning and method
CN105427528B (en) A kind of monitoring method and system
CN112488483A (en) AI technology-based EHS transparent management system and management method
CN103920270B (en) Fire-fighting equipment inspection video monitoring method and system
TW201911118A (en) Method for tracing track of target in cross regions, and data processing method, apparatus and system
CN113408683A (en) Construction site safety supervision method and system
CN107426533A (en) A kind of video monitoring image recognition system based on video-encryption compression and image identification
CN110490126B (en) Safe deposit box safety control system based on artificial intelligence
CN103021053A (en) Security system for human face recognition
CN111259682B (en) Method and device for monitoring safety of construction site
CN110599129A (en) Campus attendance checking method, device, identification terminal and system based on image tracking
CN110264723A (en) A kind of traffic engineering construction intelligent Warning Systrm and method
CN110738691A (en) Luggage tracking system based on online intelligent visual network
CN115512304A (en) Subway station safety monitoring system based on image recognition
CN109019213A (en) A kind of personal safety early warning elevator implementation method and its system
CN111383409A (en) Safety video monitoring device for intelligent building and use method thereof
CN110602453A (en) Internet of things big data intelligent video security monitoring system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180706