CN108221688A - Ultra-deep-water main pier bearing platform cofferdam construction method - Google Patents

Ultra-deep-water main pier bearing platform cofferdam construction method Download PDF

Info

Publication number
CN108221688A
CN108221688A CN201711479114.9A CN201711479114A CN108221688A CN 108221688 A CN108221688 A CN 108221688A CN 201711479114 A CN201711479114 A CN 201711479114A CN 108221688 A CN108221688 A CN 108221688A
Authority
CN
China
Prior art keywords
cofferdam
fore shaft
pipe pile
pile
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711479114.9A
Other languages
Chinese (zh)
Inventor
刘怀刚
高世强
肖向荣
梁震
魏超
费永忠
吴建峰
杨杰
赵升辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Original Assignee
Road and Bridge South China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge South China Engineering Co Ltd filed Critical Road and Bridge South China Engineering Co Ltd
Priority to CN201711479114.9A priority Critical patent/CN108221688A/en
Publication of CN108221688A publication Critical patent/CN108221688A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention discloses a kind of ultra-deep-water main pier bearing platform cofferdam construction method, it employs fore shaft steel-pipe pile and builds main pier bearing platform to carry out cofferdam construction, this cofferdam structure is more stable, fore shaft steel-pipe pile is processed before construction, it is combined as long as mutually splicing when installation and welding, it is simple to operate;With the fore shaft steel-pipe pile of O c-types, sealing form is simple, and convenient for secondary sealing, due to being to be process in the factory, construction precision is convenient for control;The installation of inner support system uses first to support draws water afterwards, and layering draws water, is layered the mode supported, further enhances the stress in cofferdam, and this mounting means, and more convenient operation is quick when the inner support in cofferdam being made to construct.Using more conduits back cover mode mobile simultaneously, this mode accelerates back cover speed, and conduit can be moved, and diffusion and mobility by concrete ponding make lower concrete evenly smooth, also accelerate the speed of back cover to a certain extent.

Description

Ultra-deep-water main pier bearing platform cofferdam construction method
Technical field
This application involves the technical field of construction in bridge pier cofferdam, are enclosed more particularly to a kind of ultra-deep-water main pier bearing platform of bridge Weir construction method.
Background technology
For being located at, water level is deeper, and double-walled may be used in the bridge pier of the big cushion cap profile of fluctuation in stage amplitude greatly, construction The forms such as steel cofferdam, steel sheet-pile cofferdam, but use equipment requirement of being rivals in a contest under Double-Wall Steel Boxed Cofferdam, installation is high, needs are scattered to spell, early period Process long in time limit, construction correction difficulty high to machining accuracy, weldquality requirement;Steel using amount is larger simultaneously, removes difficult and tears open Use value is low afterwards.And using steel sheet-pile cofferdam, stiffness by itself is small, it is high that support is required;It is not easy to foundation construction;Deep water is applied Working hour malformation is big, easy leak, and to geologic requirements height, it is more difficult to punch intensive cambered surface, slabstone and boulder;Have to length It is required that more than 18m performance difficulties are big, thus large-scale floating crane can not be used, head difference is larger in cofferdam, and the item that the duration is shorter Mesh does not apply to.
Invention content
The purpose of the present invention is intended to provide a kind of ultra-deep-water main pier bearing platform cofferdam construction method, and bridge pier can be carried out in deep water Construction, and cofferdam structure is stablized, and without heavy construction equipment, installation is quick and convenient, and back cover is also quick smooth.
To achieve these goals, the invention discloses a kind of ultra-deep-water main pier bearing platform cofferdam construction method, including:
Determine cofferdam structure:The size in cofferdam is determined according to main pier bearing platform basis, and determines fore shaft steel used by cofferdam Quantity, the length of pile pile;
Process fore shaft steel-pipe pile:According to design structure, fore shaft steel-pipe pile is processed;
Cofferdam is installed:O-C type fore shaft steel-pipe piles are sequentially inserted into the position specified, is closely connected and carried out by fore shaft Sealing composition cofferdam frame, the cofferdam scuncheon install inner support system successively;
It draws water in cofferdam:To drawing water in cofferdam, and riverbed is arranged;
Underwater back cover:Back cover is carried out to cofferdam bottom by the way of the movement of more conduits;
Remove cofferdam:To cofferdam return water, inner support system and fore shaft steel-pipe pile are removed successively.
Further, processing fore shaft steel-pipe pile includes:Fore shaft steel-pipe pile is divided into first stake, standard pile, corner pile and closes up stake, It is processed according to quantity determined by design cofferdam structure.
Further, the method for processing fore shaft steel-pipe pile further includes, and first stake, standard pile, corner pile are processed into the lock of O-C types Mouthful steel-pipe pile respectively welds an O-shaped fore shaft on two symmetrical sides of the first stake;Divide on wherein two symmetrical sides of the standard pile It Han Jie not a 0 type fore shaft and a c-type fore shaft;An O-shaped fore shaft and a c-type fore shaft are respectively welded in the corner pile, but Be angle between two fore shafts it is in 90 degree.
Further, the method for processing fore shaft steel-pipe pile is further included and is processed to closing up stake, described to close up stake and include the One, which closes up stake and second, closes up stake, described second is closed up on two symmetrical sides of stake, an I-shaped fore shaft is respectively welded, described First, which closes up on two symmetrical sides of stake wherein one end, is provided with c-type fore shaft, and the other end sets a 0 type fore shaft with gap, institute Gap is stated more than I-shaped fore shaft wall thickness.
Further, the inserting piling sequence of the fore shaft steel-pipe pile is the first stake of first inserting piling, in the first stake both sides difference inserting piling Standard pile, corner pile in the corner location inserting piling in cofferdam, both ends are respectively first to close up among stake and connect at the closed position in cofferdam One second is closed up stake.
Further, it is further included before installation cofferdam:Main pier bearing platform is constructed since outmost turns pile foundation, last wheel of constructing The inserting piling for carrying out the fore shaft steel-pipe pile is synchronized when secondary pile foundation.
Further, after the fore shaft steel-pipe pile sealing, sealing material is added in the fore shaft position of fore shaft steel-pipe pile.
Further, the inner support system includes waling, to stay tube, angle brace pipe and stiffener, and waling is mounted on cofferdam Described stay tube to be mounted in the symmetric angle of cofferdam frame on frame inner ring, it is arbitrarily right that the angle brace pipe is mounted on cofferdam frame Bian Shang.
Further, the inner support system is provided with multilayer, is installed in each layer and propped up successively by sequence from top to bottom Support system dismantles inner support system successively by sequence from bottom to up.
Further, it needs to carry out underwater riverbed excavation before underwater back cover, riverbed is excavated directly to be stirred using high-power gravel pump It mixes, extract.
Compared with prior art, the solution of the present invention has the following advantages:Fore shaft steel-pipe pile is employed to carry out cofferdam construction, Structure is more stable, and fore shaft steel-pipe pile is processed before construction, exists as long as mutually splicing when installation and welding combination Together, it is simple to operate;With the fore shaft steel-pipe pile of O-C types, microorganism can be utilized to enter fore shaft seam with silt in water environment Gap forms sealing layer;And sealing form is simple, convenient for secondary sealing, due to being to be process in the factory, construction precision is convenient for Control;The installation of inner support system uses first to support draws water afterwards, and layering draws water, is layered the mode supported, further enhances cofferdam Stress, and this mounting means, more convenient operation is quick and easy when the inner support in cofferdam being made to construct.Using the same time shift of more conduits Dynamic this mode of back cover mode, accelerates back cover speed, and conduit can be moved, by concrete ponding diffusion and Mobility makes lower concrete evenly smooth, also accelerates the speed of back cover to a certain extent.
The additional aspect of the present invention and advantage will be set forth in part in the description, these will become from the following description It obtains significantly or is recognized by the practice of the present invention.
Description of the drawings
Above-mentioned and/or additional aspect and advantage of the invention will become from the following description of the accompanying drawings of embodiments Significantly and it is readily appreciated that, wherein:
Fig. 1 is ultra-deep-water main pier bearing platform cofferdam construction method overview flow chart of the present invention;
Fig. 2 is the main pier cofferdam structure schematic diagram of the present invention;
Fig. 3 encloses schematic diagram for fore shaft steel-pipe pile of the present invention;
Fig. 4 is the first stake of the present invention and standard pile connection diagram;
Fig. 5 is standard pile of the present invention and corner pile connection diagram;
Fig. 6 closes up a connection diagram for the present invention;
Fig. 7 is guide housing schematic diagram when the first stake of the present invention and the standard pile on wherein one side are installed.
Specific embodiment
The embodiment of the present invention is described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning to end Same or similar label represents same or similar element or the element with same or like function.Below with reference to attached The embodiment of figure description is exemplary, and is only used for explaining the present invention, and is not construed as limiting the claims.
It please refers to Fig.1 and Fig. 2, the invention discloses a kind of ultra-deep-water main pier bearing platform cofferdam construction method, including:
Determine cofferdam structure:Cushion cap foundation according to main pier determines the size in cofferdam, and determines fore shaft used by cofferdam Quantity, the length of steel-pipe pile 10;
This step is to build the primary preparation works in cofferdam, and the cushion cap foundation of main pier has determined among the construction of bridge Good, position has also been fixed, and needs to measure cushion cap size again before cofferdam is installed, and determines the size in cofferdam, and foundation is enclosed The size on weir, the model of fore shaft steel-pipe pile 10, diameter and length used by selection.
Process fore shaft steel-pipe pile 10:According to design structure, fore shaft steel-pipe pile 10 is processed into O-C type fore shafts steel-pipe pile 10;
In the present invention, fore shaft steel-pipe pile 10 of the selected fore shaft steel-pipe pile 10 for O-C types, O-C type fore shaft steel-pipe piles 10 include the hollow supervisor 11 of cylinder and the O-shaped fore shaft and/or c-type fore shaft that are welded on the outer wall of supervisor 11 respectively, use The fore shaft steel-pipe pile 10 of O-C types can utilize in water environment microorganism enter fore shaft gap with silt and form sealing layer;And sealing Form is simple, and convenient for secondary sealing, due to being to be process in the factory, construction precision is convenient for control.It, can in order to facilitate understanding Using O-shaped fore shaft as the positive fore shaft 12 of fore shaft steel-pipe pile 10, using c-type fore shaft as cloudy fore shaft 13, otherwise can also, only call It is different.Further, weld seam is using a face full weld, the form of another side intermittent weld between the supervisor 11 and fore shaft, such as The form of 30cm weldering 10cm long weld seams is spaced, effective weld seam of the intermittent weld is more than the wall thickness of steel-pipe pile and fore shaft, welds in this way It connects to reduce welding deformation.
Above fore shaft steel-pipe pile 10 is to be process in the factory, and fore shaft has been determined according to first above-mentioned step The model of steel-pipe pile 10 and the size of supervisor 11, you can welding processing is carried out to positive fore shaft 12 and cloudy fore shaft 13, it is to be processed complete Into, you can it is transported to construction site and carries out inserting piling installation.
Cofferdam is installed:The fore shaft steel-pipe pile 10 of O-C types is sequentially inserted into the position specified, is closely connected simultaneously by fore shaft Sealing composition cofferdam frame is carried out, the cofferdam scuncheon installs inner support system 20 successively;
This part, the inner support system 20 being previously mentioned are also the cofferdam design before passing through, and obtain specific inner support system The structure and corresponding length of system 20, and after factory process is good, is transported to construction site and carries out welded and installed.It should be noted that , inner support system 20 installation need all fore shaft steel-pipe piles 10 are installed and fixed after, held to strengthen it Loading capability and stability, in cofferdam, a kind of fixed system of the inside installation of frame, general inner support system 20 are provided with multilayer, When installation, typically gradually it is layered from the upper end of cofferdam frame, installs step by step down.
It draws water in cofferdam:To drawing water in cofferdam, and riverbed is arranged;
During drawing water to cofferdam, the installation of also interspersed pair of interior support system 20, is from upper based on inner support system 20 It is installed successively under, i.e., topmost one layer of inner support system 20 is first installed, after installing, is drawn water to cofferdam inside, It draws water and is evacuated to next layer and needs after installing under the position of inner support system 20, then next layer of inner support system 20 is installed, pacify After dress, it is further continued for drawing water to next layer, and next layer again of inner support system 20 is installed, until drawing water to river bed.Work as pumping It after water to river bed, needs to arrange riverbed, in order to underwater back cover.Riverbed, which arranges, to be included carrying out suction mud to cofferdam substrate, High-power gravel pump is usually used directly to stir, extract, inhale the riverbed absolute altitude control after mud in -1.0m and hereinafter, inhales mud mistake Repeatedly riverbed absolute altitude should be measured repeatedly in journey, suction was controlled as possible, prevent to owe suction.
Underwater back cover:Back cover is carried out to cofferdam bottom by the way of the movement of more conduits;
Cofferdam back cover is using concrete, the thickness of bottom concrete and the absolute altitude of top surface and substrate height, bottom concrete Total amount should be all defined according to the geological condition of Retaining wall.Underwater back cover actually includes back cover twice, first time back cover It is the underwater mixed mud back cover that first time is carried out after the inner support system 20 of top layer installs, treats all inner supports System 20 installs, and water is evacuated to when cheating bottom, then by concrete to second of back cover of substrate.Bottom concrete uses Block placement is gradually promoted since cushion cap one end to the other end, that is, is extended to line by point, then be extended to face by line.It is mixed When solidifying soil pours, control the quality of the pipe joint of casting concrete and ensure the continuous cast of concrete, concreting Bottom surface should be substantially smooth afterwards.
When underwater back cover for the first time, the mode of more conduit movements is employed, i.e., is inserted in cofferdam to cofferdam bottom Enter while be inserted into more conduits, the funnel for inculcating concrete in the upper end of conduit is installed, is constantly inculcated downwards by funnel Concrete carries out back cover, while conduit can be hung up by chain block and tower crane, in order to move at any time, implantation is mixed The conduit for coagulating soil is moved to the other end, then negative direction movement until for cofferdam bottom from the one end in cofferdam according to the route being pre-designed Portion's first time back cover is completed.This mode using the operation simultaneously of more conduits, accelerates back cover speed, and conduit can be moved It is dynamic, by the mobility of concrete, make lower concrete evenly, also accelerate the speed of back cover to a certain extent.
Remove cofferdam:To cofferdam return water, cofferdam is removed successively.
When cushion cap construction is finished after the completion of either sundry item based on cushion cap is built, return water is carried out successively, in dismounting Support, pulls out the fore shaft steel-pipe pile 10 in cofferdam, construction terminates.It should be noted that it is not disposable complete when return water Water, is first back under undermost inner support system 20 by return water and stage by stage, after inner support system 20 is removed, Water is back to the lower section of last layer inner support system 20 again, after removing this layer of inner support system 20, then carries out return water, according to this side Method, until the dismounting of inner support system 20 of most last layer is finished, water is consistent again inside and outside cofferdam at this time, then is pulled out successively Fore shaft steel-pipe pile 10 retains fore shaft steel-pipe pile 10 and inner support system 20 so that next time is used.
Referring to Fig. 3, it is further, in the present invention in one embodiment, fore shaft steel used by cofferdam is installed Pile pile 10 includes first stake 10A, standard pile 10B, corner pile 10C and closes up a 10D.First stake 10A is used for the initial position in cofferdam, standard Stake 10B is a kind of most fore shaft steel-pipe pile 10 of usage quantity connect with first stake 10A or so, and corner pile 10C is in cushion cap turning A kind of fore shaft steel-pipe pile 10 for using when being commutated of place, close up a 10D then for by first stake 10A successively towards two A kind of fore shaft steel-pipe pile 10 when the fore shaft steel-pipe pile 10 of direction extension installation finally merges together.The fore shaft steel of these types The quantity of pile pile 10 is designed and is calculated according to the cofferdam of the above-mentioned first step, and according to result of calculation, in the factory successively It processes.
Please refer to that Fig. 4-Fig. 5 is further, the method for processing fore shaft steel-pipe pile 10 further includes, by first stake 10A, standard pile 10B, corner pile 10C are processed into the fore shaft steel-pipe pile 10 of O-C types, and an O-shaped lock is respectively welded on the two symmetrical sides of the first stake 10A Mouthful;A 0 type fore shaft and a c-type fore shaft are respectively welded on the wherein two symmetrical sides of the standard pile 10B;The corner pile 10C On be respectively welded an O-shaped fore shaft and a c-type fore shaft, but the angle between two fore shafts is in 90 degree.
Further, referring to Fig. 6, the method for processing fore shaft steel-pipe pile 10 is further included and is processed to closing up a 10D, institute It states to close up a 10D and close up a 101D and second including first and closes up a 102D, the two symmetrical sides for closing up a 102D by described second On an I-shaped fore shaft is respectively welded, described first, which closes up wherein one end on the two symmetrical sides of a 101D, is provided with c-type fore shaft, The other end sets a 0 type fore shaft with gap, and the gap is more than I-shaped fore shaft wall thickness.
The inserting piling sequence of the fore shaft steel-pipe pile 10 is the first stake 10A of first inserting piling, the first stake 10A both sides difference inserting piling subscript Quasi- stake 10B, corner pile 10C in the corner location inserting piling in cofferdam, both ends are respectively first to close up a 101D at the closed position in cofferdam A 102D is closed up in centre connection one second.
But main pier bearing platform is needed to construct since outmost turns pile foundation before cofferdam is installed, last round pile foundation of constructing When synchronize the inserting piling for carrying out the fore shaft steel-pipe pile.It is specifically:Referring to Fig. 7, casing and dragon in cushion cap outmost turns Steel 30 is processed between door track foundation pile, work steel uses double-layer structure, to increase stress, supporting rack is installed again on work steel 30 50, support frame as described above 50 is multilayered structure, is superimposed up and down respectively, forms the guiding being oriented to for the installation of fore shaft steel-pipe pile Frame.Gantry rail foundation pile is existing when platform is set, and construction procedure is before cofferdam, casing and dragon in outmost turns Work steel 30 is welded between door track foundation pile and supporting rack 50 is set on work steel 30, convenient for constructor's walking and conveniently The installation settings of guide housing.
The direction that supporting rack 50 extends is typically also the direction of 10 inserting piling of fore shaft steel-pipe pile.Because fore shaft steel-pipe pile 10 is inserted When beating, in order to preferably control the inserting piling direction of fore shaft steel-pipe pile 10, need to weld a guiding on supporting rack 50 Frame, to ensure the degree control of 10 inserting piling of fore shaft steel-pipe pile ranging from ± 0.5%.
Guide housing further includes leading truck 31 in addition to supporting rack 50, and leading truck 31 is mounted on the pre-installation position of fore shaft steel-pipe pile 10 The left and right sides put, leading truck 31 enclose the frame-type structure of an one end open with supporting rack 50, when first fore shaft of installation When steel-pipe pile 10, guide housing at least three faces clamping fore shaft steel-pipe pile 10, fore shaft steel-pipe pile 10 under the guiding of guide housing, then Inserting piling is carried out using crawler crane cooperation vibration hammer.The degree control of first 10 inserting piling of fore shaft steel-pipe pile ranging from ± 0.5%. When first fore shaft steel-pipe pile 10 by inserting piling in place after, other fore shaft steel-pipe piles 10 are along 50 extending direction of supporting rack, It carries out inserting piling successively side by side with first fore shaft steel-pipe pile 10 to be welded and fixed, due to previous fore shaft steel-pipe pile 10 during inserting piling It is easily subjected to displacement, therefore preferably adds in the fore shaft steel-pipe pile 10 of each inserting piling in place with welding one piece of triangle on supporting rack 50 Strength plate 40, to be fixed.
When needing to install second fore shaft steel-pipe pile 10, by leading for the wherein side of first fore shaft steel-pipe pile 10 Distance and the fixation of a fore shaft steel-pipe pile 10 are moved to frame 31, and is smeared on the cloudy fore shaft 13 of first fore shaft steel-pipe pile 10 Butter ensures the leakproofness between the fore shaft steel-pipe pile 10 in cofferdam, makes dense extrusion between positive fore shaft 12 and cloudy fore shaft 13, it is ensured that Sealing.A fore shaft steel-pipe pile 10 is laid in the guiding underthrust of leading truck 31, repeats the above steps and installs all locks successively Mouth steel-pipe pile 10.To ensure that fore shaft steel-pipe pile 10 smoothly closes up, ensure that each 10 body of fore shaft steel-pipe pile keeps hanging down during inserting piling Directly, strengthen measuring work in construction, find to tilt, adjust in time, make every group of fore shaft steel-pipe pile 10 along cofferdam peripheral direction And its gradient of vertical direction is no more than 5 ‰.
In the inserting piling for carrying out fore shaft steel-pipe pile 10, when the verticality of fore shaft steel-pipe pile 10 is preferable, once stake can be got to It is required that depth, when verticality is poor, carry out injection, i.e., all fore shaft steel-pipe piles 10 first be squeezed into about half depth in two times After degree, then the depth of requirement is got to for the second time.Never vibrated during piling it is excessive, in order to avoid cause pile top twist or fore shaft deformation, lead Cause pile pulling difficulty or fore shaft leak.
It is further, above-mentioned that sticky butter is smeared on cloudy fore shaft 13 is for sealing, when all fore shafts on cofferdam 10 inserting piling of steel-pipe pile finishes, and when needing to close up, proportioning can also be used on the fore shaft steel-pipe pile 10 at mouth is closed up as 3:1 Artificial filling admaic earth sawdust is added to be filled sealing, while in the fore shaft of each two adjacent fore shaft steel-pipe piles 10 Can fill the filler of sealing, filler, which is not limited to manually to clog admaic earth, adds sawdust, can also be quilts or Timber wedge.
It further, can also be adjacent two if above water-stopping method is also not sufficient to ensure that water-stagnating effect The magnetic water proof rubber bar (not shown) of outside patch of the fore shaft of a fore shaft steel-pipe pile 10 is blocked, and magnetic water proof rubber bar is uses Strip shape body made of flexible material, strip shape body is interior to be embedded with magnetic substance along rubber strip direction, and rubber strip includes intermediate lug boss Position and the flap of both sides.Magnetic water proof rubber bar water-stagnating effect is preferable, and the flap realization pair of boss and its both sides can leak The sealing in hole, and because being made with flexible material, will not influence to cause fore shaft steel-pipe pile with extraneous factors such as stormy waves 10 deformation and leak, have it is good resist extraneous adverse circumstances ability, it can be used repeatedly, facilitates construction.
Further referring to Fig. 2, in the present invention, the inner support system 20 includes waling 22, to stay tube 23, angle brace pipe 24 and stiffener 21, waling 22 is mounted on the frame inner ring of cofferdam, is generally required to be connect with lock steel-pipe pile 10 with concrete and be consolidated It is fixed.Described stay tube 22 to be mounted on the symmetrical side of cofferdam frame, the angle brace pipe 23 is mounted on cofferdam angular position, stiffener 21 are mounted on the position that is connect with waling 22 to stay tube 23, angle brace pipe 24 to be supported and stress reinforcement.Further, when interior When support system 20 has multilayer, it is also necessary to weld upper and lower two layers of inner support system by supporting steel pipe (not shown) It is fixed, so that the inner support system of levels becomes an entirety, strengthen stress.
Further, in order to illustrate, if installing three layers of inner support system in cofferdam, a kind of optional inner support system System specification be:The inner support system of most last layer inner support and middle layer is waling 22, Φ 820 using 3HN700 × 300H shaped steel × 10mm steel pipes are done does angle brace pipe 24 to stay tube 23, Φ 1000 × 12mm helix tubes;Third layer inner support system uses 2HN700 × 300H shaped steel does waling 22, Φ 820 × 10mm spiral welded pipes do and do angle brace pipe to stay tube 23, Φ 1000 × 12mm spiral welded pipes 24.It is integral with the connection of 426 × 6mm of Φ spiral welded pipes between stiffener 21 and upper and lower layer supporting steel pipe.
In conclusion cofferdam design mainly considers following 11 kinds of operating modes when calculating:
Operating mode one:First of inner support system 20 of top layer is positioned at, inside and outside water level is consistent, is not considered;
Operating mode two:Carry out first time underwater concrete back cover;
Operating mode three:It draws water in cofferdam to second layer inner support;
Operating mode four:Second layer inner support system 20 that installation is complete, while will draw water in cofferdam to basecoat inner support system System 20;
Operating mode five:Third road inner support system 20 is installed;
Operating mode six:It is drawn water in cofferdam to hole bottom;Carry out second of concrete sealing bottom;
Operating mode seven:Remove third road inner support system 20;
Operating mode eight:In cofferdam at return water to second inner support system 20;
Operating mode nine:Remove second inner support system 20;
Operating mode ten:Return water is to first layer inner support system below 20 in cofferdam;
Operating mode 11:Remove first of inner support system 20.
Beneficial effects of the present invention are:
1) fore shaft steel-pipe pile is employed to carry out cofferdam construction, and structure is more stable, and fore shaft steel-pipe pile is in the advance of construction Row processing, as long as the simultaneously welding assembly that is mutually stitched together when installation is together, simple to operate;
2) using opening locked steel tube pilecofferdam structure, during installation, light lifting equipment can be used and installed simultaneously in pile foundation construction Steel pipe pile cofferdam makes process velocity faster, is more convenient;
3) maximum head difference up to 20m, is suitable for using in ultra-deep-water inside and outside cofferdam in the construction process;
4) opening locked steel tube pilecofferdam overall stiffness is big, and MAT'L recycling rate is high, and plane figure is adaptable, can be preferably Adapt to soft overburden;
5) can enter fore shaft gap with silt using microorganism using the fore shaft steel-pipe pile of O-C types, in water environment to be formed Sealing layer;And sealing form is simple, convenient for secondary sealing, due to being to be process in the factory, construction precision is convenient for control;
6) installation guide housing is synchronized during inserting piling fore shaft steel-pipe pile, ensure that the verticality during installation of fore shaft steel-pipe pile;
7) inner support installation uses first to support draws water afterwards, and layering draws water, is layered the mode supported, further enhances cofferdam Stress, and this mounting means, more convenient operation is quick and easy when the inner support in cofferdam being made to construct;
8) inner support system is made of various structures, and each structure interconnection forms a whole, and enabling capabilities are strong;
9) using more conduits this mode of back cover mode mobile simultaneously, back cover speed is accelerated, and conduit can be moved Dynamic, diffusion and mobility by concrete ponding make lower concrete evenly smooth, also accelerate to a certain extent The speed of back cover.
The above is only some embodiments of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (10)

1. a kind of ultra-deep-water main pier bearing platform cofferdam construction method, which is characterized in that including:
Determine cofferdam structure:The size in cofferdam is determined according to main pier bearing platform basis, and determines fore shaft steel-pipe pile used by cofferdam Quantity, length;
Process fore shaft steel-pipe pile:According to design structure, fore shaft steel-pipe pile is processed into O-C type fore shaft steel-pipe piles;
Cofferdam is installed:Fore shaft steel-pipe pile is sequentially inserted into the position specified, closely connected by fore shaft and carries out sealing composition Cofferdam frame, the cofferdam scuncheon install inner support system successively;
It draws water in cofferdam:To drawing water in cofferdam, and riverbed is arranged;
Underwater back cover:Back cover is carried out to cofferdam bottom using the synchronization-moving mode of more conduits;
Remove cofferdam:To cofferdam return water, inner support system and fore shaft steel-pipe pile are removed successively.
2. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 1, which is characterized in that processing fore shaft steel-pipe pile Including:Fore shaft steel-pipe pile is divided into first stake, standard pile, corner pile and closes up stake, according to design cofferdam structure determined by quantity into Row processing.
3. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 2, which is characterized in that processing fore shaft steel-pipe pile Method further include, first stake, standard pile, corner pile be processed into the fore shaft steel-pipe pile of O-C types, it is each on two symmetrical sides of the first stake From one O-shaped fore shaft of welding;A 0 type fore shaft and a c-type fore shaft are respectively welded on wherein two symmetrical sides of the standard pile; An O-shaped fore shaft and a c-type fore shaft are respectively welded in the corner pile, but the angle between two fore shafts is in 90 degree.
4. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 2, which is characterized in that processing fore shaft steel-pipe pile Method further include and be processed to closing up stake, it is described close up stake and close up stake and second including first close up stake, by described second Close up on two symmetrical sides of stake and an I-shaped fore shaft is respectively welded, described first, which closes up wherein one end on two symmetrical sides of stake, sets C-type fore shaft is equipped with, the other end sets a 0 type fore shaft with gap, and the gap is more than I-shaped fore shaft wall thickness.
5. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 3, which is characterized in that the fore shaft steel-pipe pile Inserting piling sequence be the first first stake of inserting piling, standard pile in the first stake both sides difference inserting piling, corner pile in the corner location inserting piling in cofferdam, Both ends are respectively first to close up stake at the closed position in cofferdam, and stake is closed up in centre connection one second.
6. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 2, which is characterized in that
Installation further includes before cofferdam:Main pier bearing platform is constructed since outmost turns pile foundation, when last round pile foundation of constructing The synchronous inserting piling for carrying out the fore shaft steel-pipe pile.
7. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 1, which is characterized in that the fore shaft steel-pipe pile After sealing, sealing material is added in the fore shaft position of fore shaft steel-pipe pile.
8. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 1, which is characterized in that the inner support system Including waling, to stay tube, angle brace pipe and stiffener, waling is mounted on the frame inner ring of cofferdam, described to be mounted on cofferdam to stay tube In the symmetric angle of frame, the angle brace pipe is mounted on the arbitrary opposite side of cofferdam frame.
9. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 8, which is characterized in that the inner support system Multilayer is provided with, each layer inner support system is installed by sequence from top to bottom successively, is torn open successively by sequence from bottom to up Unload inner support system.
10. ultra-deep-water main pier bearing platform cofferdam construction method according to claim 1, which is characterized in that needed before underwater back cover Underwater riverbed excavation is carried out, riverbed, which is excavated, directly to be stirred, extracted using high-power gravel pump.
CN201711479114.9A 2017-12-29 2017-12-29 Ultra-deep-water main pier bearing platform cofferdam construction method Pending CN108221688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711479114.9A CN108221688A (en) 2017-12-29 2017-12-29 Ultra-deep-water main pier bearing platform cofferdam construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711479114.9A CN108221688A (en) 2017-12-29 2017-12-29 Ultra-deep-water main pier bearing platform cofferdam construction method

Publications (1)

Publication Number Publication Date
CN108221688A true CN108221688A (en) 2018-06-29

Family

ID=62646109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711479114.9A Pending CN108221688A (en) 2017-12-29 2017-12-29 Ultra-deep-water main pier bearing platform cofferdam construction method

Country Status (1)

Country Link
CN (1) CN108221688A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111764417A (en) * 2020-06-23 2020-10-13 中铁隧道集团三处有限公司 Construction method for dismantling riverbank cofferdam structure
CN112709243A (en) * 2020-12-28 2021-04-27 中铁广州工程局集团有限公司 Construction method of lock catch steel pipe pile cofferdam bearing platform
CN113186958A (en) * 2021-03-31 2021-07-30 中交路桥华南工程有限公司 Locking steel pipe pile cofferdam
CN113186959A (en) * 2021-03-31 2021-07-30 中交路桥华南工程有限公司 Construction method of locking steel pipe pile cofferdam
CN114277819A (en) * 2021-12-25 2022-04-05 中铁广州工程局集团有限公司 Construction method of super-long CO male-female lock catch steel pipe pile cofferdam
WO2022141388A1 (en) * 2020-12-28 2022-07-07 中铁广州工程局集团有限公司 Fixed inner support ring beam of locking steel pipe pile cofferdam
CN117026835A (en) * 2023-10-08 2023-11-10 中国土木工程集团有限公司 Continuous beam pier underwater pouring support template for simple and easy quick construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001073357A (en) * 1999-09-07 2001-03-21 Tobishima Corp Coffering structure and constructing method therefor
CN101182717A (en) * 2007-07-30 2008-05-21 中铁十八局集团有限公司 Construction method of opening locked steel tube pilecofferdam
CN103882881A (en) * 2014-04-11 2014-06-25 山东黄河工程集团有限公司 Underwater construction method for bearing platform deeply embedded in rock
CN204151803U (en) * 2014-05-21 2015-02-11 中交二航局第四工程有限公司 A kind of opening locked steel tube pilecofferdam
CN107034907A (en) * 2017-06-09 2017-08-11 中铁十七局集团第五工程有限公司 Deep water foundation shallow embedding covering soft rock geology lock steel pipe pile cofferdam construction method
JP6200550B1 (en) * 2016-05-27 2017-09-20 鹿島建設株式会社 Temporary deadline method, temporary deadline structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001073357A (en) * 1999-09-07 2001-03-21 Tobishima Corp Coffering structure and constructing method therefor
CN101182717A (en) * 2007-07-30 2008-05-21 中铁十八局集团有限公司 Construction method of opening locked steel tube pilecofferdam
CN103882881A (en) * 2014-04-11 2014-06-25 山东黄河工程集团有限公司 Underwater construction method for bearing platform deeply embedded in rock
CN204151803U (en) * 2014-05-21 2015-02-11 中交二航局第四工程有限公司 A kind of opening locked steel tube pilecofferdam
JP6200550B1 (en) * 2016-05-27 2017-09-20 鹿島建設株式会社 Temporary deadline method, temporary deadline structure
CN107034907A (en) * 2017-06-09 2017-08-11 中铁十七局集团第五工程有限公司 Deep water foundation shallow embedding covering soft rock geology lock steel pipe pile cofferdam construction method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
上海铁路局: "《高速铁路施工工序管理要点 第1册 桥梁钻孔桩基础》", 30 September 2010, 中国铁道出版社 *
兰晴朋等: "新型C_O型锁扣钢管桩在围堰施工中的应用", 《建筑施工》 *
刘玉洪: "飞云江特大桥主桥8_10_墩承台施工", 《科技信息》 *
张杰: "汉江特大桥主墩水下大体积混凝土封底设计与施工", 《铁道建筑技术》 *
韩立军: "锁扣钢管桩在桥梁围堰施工中的应用", 《技术与市场》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111764417A (en) * 2020-06-23 2020-10-13 中铁隧道集团三处有限公司 Construction method for dismantling riverbank cofferdam structure
CN112709243A (en) * 2020-12-28 2021-04-27 中铁广州工程局集团有限公司 Construction method of lock catch steel pipe pile cofferdam bearing platform
WO2022141388A1 (en) * 2020-12-28 2022-07-07 中铁广州工程局集团有限公司 Fixed inner support ring beam of locking steel pipe pile cofferdam
CN113186958A (en) * 2021-03-31 2021-07-30 中交路桥华南工程有限公司 Locking steel pipe pile cofferdam
CN113186959A (en) * 2021-03-31 2021-07-30 中交路桥华南工程有限公司 Construction method of locking steel pipe pile cofferdam
CN114277819A (en) * 2021-12-25 2022-04-05 中铁广州工程局集团有限公司 Construction method of super-long CO male-female lock catch steel pipe pile cofferdam
CN117026835A (en) * 2023-10-08 2023-11-10 中国土木工程集团有限公司 Continuous beam pier underwater pouring support template for simple and easy quick construction
CN117026835B (en) * 2023-10-08 2023-12-08 中国土木工程集团有限公司 Continuous beam pier underwater pouring support template for simple and easy quick construction

Similar Documents

Publication Publication Date Title
CN108221688A (en) Ultra-deep-water main pier bearing platform cofferdam construction method
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN102691294B (en) Construction method of underground continuous wall
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN105133627B (en) Construction under single wall steel sheet-pile cofferdam flowing water state
CN102409688A (en) Construction method of steel plate pile cofferdam
CN100575618C (en) Construction method of opening locked steel tube pilecofferdam
CN102587387B (en) Construction method for foundation pit in Larson steel sheet pile retaining and protecting river
CN103031839B (en) Construction method of hand-dug piles
CN106759379A (en) A kind of construction method of the asymmetric water-stop curtain of foundation ditch
CN101864765A (en) Two-way stirring based SMW construction method and tri-axial stirring equipment
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN102363961A (en) Deepwater single-wall steel plate pile cofferdam structure with low buried depth and construction method thereof
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN110144914A (en) Construction method of locking steel pipe pile cofferdam by deep water topdown construction method
CN102134853A (en) CT sealed steel pipe pile foundation pit water stop supporting device and construction method thereof
CN207092107U (en) A kind of anti-subsidence structure using diaphram wall
CN102535490A (en) Method for dewatering foundation pit by using bored cast-in-place pile
CN105649094B (en) A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method
CN107059900B (en) A kind of construction method that Double-wall sin-gle-image radiography quickly sinks in sand-pebble layer
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
CN202401462U (en) Deep-water single-wall steel sheet pile cofferdam structure with small soil penetration depth
CN106545020A (en) A kind of construction method of deep foundation pit support
CN107905245A (en) Ultra-deep-water cofferdam fore shaft steel pipe pile construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20181115

Address after: 528400 19, 3, Central Plaza, 1 Xing Zheng Road, East District, Zhongshan, Guangdong.

Applicant after: ROAD & BRIDGE SOUTH CHINA ENGINEERING Co.,Ltd.

Applicant after: ROAD & BRIDGE INTERNATIONAL Co.,Ltd.

Address before: 528400 19, 3, Central Plaza, 1 Xing Zheng Road, East District, Zhongshan, Guangdong.

Applicant before: ROAD & BRIDGE SOUTH CHINA ENGINEERING Co.,Ltd.

TA01 Transfer of patent application right