CN108035377A - A kind of turbine chamber fixing means - Google Patents
A kind of turbine chamber fixing means Download PDFInfo
- Publication number
- CN108035377A CN108035377A CN201711329621.4A CN201711329621A CN108035377A CN 108035377 A CN108035377 A CN 108035377A CN 201711329621 A CN201711329621 A CN 201711329621A CN 108035377 A CN108035377 A CN 108035377A
- Authority
- CN
- China
- Prior art keywords
- runner
- base plate
- wall
- envelope
- nut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03B—MACHINES OR ENGINES FOR LIQUIDS
- F03B11/00—Parts or details not provided for in, or of interest apart from, the preceding groups, e.g. wear-protection couplings, between turbine and generator
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2230/00—Manufacture
- F05B2230/60—Assembly methods
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Combustion & Propulsion (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Hydraulic Turbines (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of turbine chamber fixing means, include the following steps:1)The auger shell hole in the positioning of runner envelope and support plate;2)Drill-through hole on runner locular wall;3)It is with round steel that the reinforcement foundation net in base plate and former concrete is integrally welded before concrete is poured into a mould;4)Feather nail is welded on runner chamber outer wall, rigid support is set inside runner envelope;5)Runner envelope is adjusted in place by chock block, screw rod is passed through into runner locular wall, is screwed into the base plate of embedment;6)Nut is brought on the screw rod of inner wall of runner chamber one;7)Treat that nut all substitutes into, nut and inner wall of runner chamber spot welding are firm;8)Link into an integrated entity outside runner envelope with the base plate in Transducers Embedded in Concrete, secure runner envelope.Runner envelope is poured into a mould using the present invention is interior in a limited space, ensures the influence of pressure when runner envelope is poured into a mould from concrete, it is therefore prevented that the installation center offset of unit, ensure that unit operation safety and stability.
Description
Technical field
The present invention relates to a kind of hydraulic turbine construction method of installation, particularly a kind of turbine chamber fixing means.
Background technology
At present, kaplan turbine runner room is the installation center of the hydrogenerator unit, meanwhile, runner envelope is all
In Transducers Embedded in Concrete, its purpose is to ensure the stability and security of unit operation.But runner envelope is also that unit is easy
The position cavitated, once the destruction of runner envelope, will influence stable operation and the efficiency of unit.In situation at this stage
Under, power station destroyed for runner envelope in the case of be all that repair welding and polishing are carried out to local breakdown point, but for the broken of large area
In the case of bad, so far still without more preferable solution.
The content of the invention
Runner envelope is poured into a mould in the confined space it is an object of the invention to provide one kind and from concrete pressure shadow
Loud turbine chamber fixing means.
Realized the purpose of the present invention is technical solution in this way, a kind of turbine chamber fixing means, it is special
Sign is that described method includes following steps:
1)A certain number of screw holes are bored in the positioning of runner envelope and support plate;
2)Being bored on runner locular wall on the screwhole position of corresponding base plate can carry out by the via of screw rod, while crossing hole site
Cushion block thickeies;
3)Reinforcement foundation net in base plate and former concrete is welded into one by base plate before concrete is poured into a mould, using round steel
Body;
4)Feather nail is welded on fresh processed runner chamber outer wall, rigid support is set inside runner envelope;
5)After runner envelope is adjusted in place by chock block, screw rod is passed through into runner locular wall, is screwed into the base plate of embedment, until
Screw rod is screwed into place;
6)Nut is brought on the screw rod of inner wall of runner chamber one;
7)After nut all substitutes into, screw rod base plate and runner envelope between firm to nut and inner wall of runner chamber spot welding
Just play the role of tensing grasp;
8)Base plate in the outside and Transducers Embedded in Concrete of runner envelope links into an integrated entity, and there is rigid support in inside, secures runner
Room.
Wherein, in the step 6)In, need to symmetrically it be tensed when nut is installed.
By adopting the above-described technical solution, the present invention has the advantages that easy for construction, of low cost, service-strong, adopt
With its influence poured into a mould runner envelope, ensure pressure when runner envelope is poured into a mould from concrete interior in a limited space, prevent
The installation center offset of unit, ensure that safely and steadily running for unit.
Brief description of the drawings
The brief description of the drawings of the present invention is as follows:
Fig. 1 is the structure diagram of the present invention;
Fig. 2 is the top view of Fig. 1.
Embodiment
The embodiment of the present invention is described in further detail below in conjunction with the accompanying drawings, but the present invention does not limit to
In these embodiments, any improvement or replacement on the present embodiment essence spirit, still falls within the claims in the present invention and wants
Seek the scope of protection.
Embodiment 1:As shown in Figure 1, 2, a kind of turbine chamber fixing means, described method includes following steps:
1)A certain number of screw holes are bored in the positioning of runner envelope and support plate 1;
2)Being drilled with runner locular wall on the screwhole position of corresponding base plate 2 can be by the via of screw rod, while should be in via position
Put and carry out cushion block thickening;
3)Base plate 2 need to use round steel 3 to weld the reinforcement foundation net in base plate 2 and former concrete before concrete is poured into a mould
Integrally;
4)Feather nail is welded on fresh processed runner chamber outer wall, rigid support 4 is set inside runner envelope;
5)After runner envelope is adjusted in place by chock block 5, screw rod 6 is passed through into runner locular wall, is screwed into the base plate 2 of embedment,
Until screw rod 6 is screwed into place;
6)Nut 7 is brought on the screw rod 6 of inner wall of runner chamber one;
7)After nut 7 all substitutes into, spiral shell base plate 2 and runner envelope between firm to nut 7 and inner wall of runner chamber spot welding
Bar just plays the role of tensing grasp;
8)Base plate 2 in the outside and Transducers Embedded in Concrete of runner envelope links into an integrated entity, and there is rigid support in inside, secures runner
Room.
Wherein, in the step 6)In, need to symmetrically it be tensed when nut 7 is installed.
In the present invention, by above-mentioned steps, quickly runner envelope can be fixed, solves axial-flow type well
Runner envelope, from the influence of concrete pressure, can be completely fixed on installation by turbine chamber in cast Concrete
On position, it ensure that concrete does not produce irreversible influence in casting process on runner envelope, ensure that unit running process
In safety and stability.
Claims (2)
1. a kind of turbine chamber fixing means, it is characterized in that, described method includes following steps:
1)Positioning and support plate in runner envelope(1)It is upper to bore a certain number of screw holes;
2)In corresponding base plate on runner locular wall(2)Screwhole position on bore can by the via of screw rod, while cross hole site
Carry out cushion block thickening;
3)Base plate(2)Before concrete is poured into a mould, round steel is used(3)By base plate(2)With the reinforcement foundation net in former concrete
It is integrally welded;
4)Feather nail is welded on fresh processed runner chamber outer wall, rigid support is set inside runner envelope(4);
5)Pass through chock block(5)After runner envelope is adjusted in place, by screw rod(6)Through runner locular wall, the base plate of embedment is screwed into
(2)It is interior, until screw rod(6)It is screwed into place;
6)By nut(7)Bring the screw rod in inner wall of runner chamber one into(6)On;
7)Treat nut(7)After all substituting into, to nut(7)It is firm with inner wall of runner chamber spot welding, in base plate(2)With runner envelope it
Between screw rod just play the role of tense grasp;
8)Base plate in the outside and Transducers Embedded in Concrete of runner envelope(2)Link into an integrated entity, there is rigid support in inside, secures and turns
Engineer room.
2. turbine chamber fixing means as claimed in claim 1, it is characterized in that:In the step 6)In, nut is installed
(7)When need to symmetrically be tensed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711329621.4A CN108035377B (en) | 2017-12-13 | 2017-12-13 | A kind of turbine chamber fixing means |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711329621.4A CN108035377B (en) | 2017-12-13 | 2017-12-13 | A kind of turbine chamber fixing means |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108035377A true CN108035377A (en) | 2018-05-15 |
CN108035377B CN108035377B (en) | 2019-06-11 |
Family
ID=62103024
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711329621.4A Active CN108035377B (en) | 2017-12-13 | 2017-12-13 | A kind of turbine chamber fixing means |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108035377B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112692537A (en) * | 2020-12-29 | 2021-04-23 | 中铁科工集团轨道交通装备有限公司 | Construction process for cutting and dismantling runner chamber |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003083224A (en) * | 2001-09-07 | 2003-03-19 | Mitsubishi Heavy Ind Ltd | Hydraulic rotating machine |
CN201031765Y (en) * | 2007-04-28 | 2008-03-05 | 天津市天发重型水电设备制造有限公司 | Hydroturbine runner chamber and base-ring connecting structure |
CN101196000A (en) * | 2008-01-07 | 2008-06-11 | 四川东风电机厂有限公司 | Installing method for bulb through-flow turbine |
CN201582034U (en) * | 2009-11-13 | 2010-09-15 | 天津市天发重型水电设备制造有限公司 | Structure for fastening runner chamber and expansion joint of through-flow turbine |
CN202483781U (en) * | 2011-11-17 | 2012-10-10 | 东方电气集团东方电机有限公司 | Water turbine rotating wheel supporting device |
JP2013189957A (en) * | 2012-03-15 | 2013-09-26 | Toshiba Corp | Cover device of hydraulic machinery, and hydraulic machinery |
CN104176619A (en) * | 2013-05-22 | 2014-12-03 | 东方电气集团东方电机有限公司 | Axial-flow kaplan turbine rotating-wheel hoisting and suspension method |
CN204082421U (en) * | 2014-09-25 | 2015-01-07 | 广东梅雁吉祥水电股份有限公司 | Rotary wheel of water turbine cell structure |
CN204126806U (en) * | 2014-09-11 | 2015-01-28 | 广东梅雁吉祥水电股份有限公司 | There is the runner envelope of seal arrangement |
CN204140262U (en) * | 2014-03-05 | 2015-02-04 | 浙江迅和机械制造有限公司 | A kind of welding type runner envelope |
-
2017
- 2017-12-13 CN CN201711329621.4A patent/CN108035377B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003083224A (en) * | 2001-09-07 | 2003-03-19 | Mitsubishi Heavy Ind Ltd | Hydraulic rotating machine |
CN201031765Y (en) * | 2007-04-28 | 2008-03-05 | 天津市天发重型水电设备制造有限公司 | Hydroturbine runner chamber and base-ring connecting structure |
CN101196000A (en) * | 2008-01-07 | 2008-06-11 | 四川东风电机厂有限公司 | Installing method for bulb through-flow turbine |
CN201582034U (en) * | 2009-11-13 | 2010-09-15 | 天津市天发重型水电设备制造有限公司 | Structure for fastening runner chamber and expansion joint of through-flow turbine |
CN202483781U (en) * | 2011-11-17 | 2012-10-10 | 东方电气集团东方电机有限公司 | Water turbine rotating wheel supporting device |
JP2013189957A (en) * | 2012-03-15 | 2013-09-26 | Toshiba Corp | Cover device of hydraulic machinery, and hydraulic machinery |
CN104176619A (en) * | 2013-05-22 | 2014-12-03 | 东方电气集团东方电机有限公司 | Axial-flow kaplan turbine rotating-wheel hoisting and suspension method |
CN204140262U (en) * | 2014-03-05 | 2015-02-04 | 浙江迅和机械制造有限公司 | A kind of welding type runner envelope |
CN204126806U (en) * | 2014-09-11 | 2015-01-28 | 广东梅雁吉祥水电股份有限公司 | There is the runner envelope of seal arrangement |
CN204082421U (en) * | 2014-09-25 | 2015-01-07 | 广东梅雁吉祥水电股份有限公司 | Rotary wheel of water turbine cell structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112692537A (en) * | 2020-12-29 | 2021-04-23 | 中铁科工集团轨道交通装备有限公司 | Construction process for cutting and dismantling runner chamber |
Also Published As
Publication number | Publication date |
---|---|
CN108035377B (en) | 2019-06-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105484157B (en) | Positioning device and construction method of capping beam of prefabricated bridge | |
MX2021005928A (en) | Foundation for wind turbine towers. | |
CN107429496A (en) | Wind energy plant ground and wind energy plant | |
CN108035377A (en) | A kind of turbine chamber fixing means | |
CN208293427U (en) | A kind of bent cap concrete cast template steel hoop support system | |
CN105899741A (en) | Method for improving the structural stability of an existing building construction | |
CN104389437A (en) | Construction method for connecting steel pipe concrete column connection structure to reinforced concrete column | |
CN206352340U (en) | Connecting node between precast concrete column and pedestal | |
CN104141390B (en) | AP1000 nuclear power dome assembly moulding bed | |
CN107012974A (en) | A kind of assembled steel fiber high-strength concrete steel plate combination Antiknock wall body | |
CN210395407U (en) | Anchor rod gravity type offshore wind power foundation | |
CN104032768A (en) | Foundation bolt structure and construction method thereof | |
CN106499176A (en) | Template and its installation method of section is poured after being applied to assembled beam-column | |
CN206769106U (en) | A kind of assembled steel fiber high strength concrete steel plate combination Antiknock wall body | |
CN203729605U (en) | Inter-column reinforcing structure for preventing historic building from collapsing continuously | |
CN108071097A (en) | A kind of turbine chamber integral replacing method | |
CN206858019U (en) | A kind of new attached wall embedded parts structure of derrick crane | |
JP2016130388A (en) | Hole-in anchor, installation method for hole-in anchor, and frame for hole-in anchor | |
CN205342405U (en) | Installation device is rectified to portable flange | |
KR20110003305U (en) | Pile making unit | |
CN103726672A (en) | Inter-pillar reinforcing structure and method for preventing historic building from continuously collapsing | |
CN206903185U (en) | Pre-buried board-like carrier setting bolt structure | |
JP2017180083A (en) | Fixing strut stand for erosion control net, and installation method of erosion control net using the same | |
JP6345328B1 (en) | Original position building method and original position structure | |
CN105804293A (en) | Prefabricated concrete-filled steel tube construction column rammed earth wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |