CN206858019U - A kind of new attached wall embedded parts structure of derrick crane - Google Patents

A kind of new attached wall embedded parts structure of derrick crane Download PDF

Info

Publication number
CN206858019U
CN206858019U CN201720691042.3U CN201720691042U CN206858019U CN 206858019 U CN206858019 U CN 206858019U CN 201720691042 U CN201720691042 U CN 201720691042U CN 206858019 U CN206858019 U CN 206858019U
Authority
CN
China
Prior art keywords
mounting disc
anchor slab
screw rod
cone
attached wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720691042.3U
Other languages
Chinese (zh)
Inventor
汪勇华
黄艳芬
李章利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Kai Hui Mechanical Engineering Co Ltd
Original Assignee
Fujian Kai Hui Mechanical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Kai Hui Mechanical Engineering Co Ltd filed Critical Fujian Kai Hui Mechanical Engineering Co Ltd
Priority to CN201720691042.3U priority Critical patent/CN206858019U/en
Application granted granted Critical
Publication of CN206858019U publication Critical patent/CN206858019U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a kind of new attached wall embedded parts structure of derrick crane, including climbing cone, the cone of climbing includes position-arresting disk, round bar and mounting disc, the both ends of round bar offer external screw thread, and anchor slab is provided with the outside of mounting disc, and the medial surface contact of anchor slab connects column and climbs cone, the bolt hole in regular distribution is offered on anchor slab, the lateral surface of anchor slab is connected with screw rod, and screw rod run through bolt hole, one end of screw rod is flexibly connected mounting disc by screw thread;The new attached wall embedded parts structure of this derrick crane, by climbing cone column is pre-buried before pouring, anchor slab is tightened to by screw rod again and climbed on cone, live model of the column perforate workload is so reduced, shortens the time used in the pre-buried installation of embedded part, reduces follow-up cutting work after project completion, mounting process is simple, the cost of relatively direct pre embedded bolt is lower, and screw rod can also reuse, cost-effective.

Description

A kind of new attached wall embedded parts structure of derrick crane
Technical field
Technical field of building construction is the utility model is related to, especially a kind of new attached wall embedded parts structure of derrick crane.
Background technology
Conventional tower crane attached wall is often embedded in residential housing shear wall position, using pre-buried hollow circular-tube, uses spiral shell through walls The embedded parts structure of bar, reach the purpose of screw rod and steel plate recycling through walls.But shear wall is had no in more commercial building, only There is column, column size is larger, does not apply to upper type, so need that directly bolt embedment is entered, the spiral shell for column of nuzzling in advance Bolt can not take out, and cause cost to increase, and model of the column also needs corresponding bolt position perforate, and Tapping procedures are time-consuming longer, while mould Plate installation process is inconvenient, also needs to be cut prominent building part after project completion, tedious process.
Utility model content
The purpose of this utility model is to provide a kind of derrick crane new attached wall embedded parts structure possess the saving time, The advantages of mounting process is simple and cost-effective, to solve the problems mentioned in the above background technology.
To achieve the above object, the utility model provides following technical scheme:A kind of new attached wall embedded part of derrick crane Structure, including cone is climbed, the cone of climbing includes position-arresting disk, round bar and mounting disc, and the both ends of round bar offer external screw thread, round bar One end is connected through a screw thread position-arresting disk, and the other end of round bar is connected through a screw thread mounting disc, anchor slab is provided with the outside of mounting disc, The medial surface contact of the anchor slab connects column and climbs cone, and the bolt hole in regular distribution, the outside of anchor slab are offered on anchor slab Face is connected with screw rod, and the screw rod run through bolt hole, one end of screw rod is flexibly connected mounting disc by screw thread.
As further program of the utility model:The position-arresting disk and mounting disc are a kind of horn-like component.
As further program of the utility model:The opening surface of the mounting disc flushes with the side of column.
As further program of the utility model:The spiro keyhole position is in the side of mounting disc.
Compared with prior art, the utility model beneficial effect:The new attached wall embedded parts structure of this derrick crane, by Column is embedded with before pouring climbs cone, then anchor slab is tightened to by screw rod and climbed on cone, so reduces live model of the column Perforate workload, the time used in the pre-buried installation of embedded part is shortened, reduce follow-up cutting work after project completion, mounting process Simply, the cost of relatively direct pre embedded bolt is lower, and screw rod can also reuse, cost-effective.
Brief description of the drawings
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is the cross-sectional view that the utility model is installed on column;
Fig. 3 is anchor slab schematic diagram of the present utility model.
In figure:1- columns;2- climbs cone;21- position-arresting disks;22- round bars;23- mounting discs;3- anchor slabs;31- bolts hole;4- spiral shells Bar.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Refer to Fig. 1-3, in the utility model embodiment, a kind of new attached wall embedded parts structure of derrick crane, including it is vertical Post 1, column 1 are formed using concrete-bar component and concreting, and column 1 is embedded with before pouring climbs cone 2, climb cone 2 in advance with standing Steel bar piece in post 1 welds together, and avoids climbing the displacement of cone 2 during casting concrete, climbing cone 2 includes position-arresting disk 21, the and of round bar 22 Mounting disc 23, position-arresting disk 21 and mounting disc 23 are a kind of horn-like component, in horn-like position-arresting disk 21 and mounting disc 23 Contact can be increased to ensure to climb the adhesive force of cone 2, the both ends of round bar 22 offer external screw thread, and one end of round bar 22 passes through screw thread Position-arresting disk 21 is connected, the other end of round bar 22 is connected through a screw thread mounting disc 23, position-arresting disk 21 and the installation process side of mounting disc 23 Just, the opening surface of mounting disc 23 flushes with the side of column 1, so the not only joint face attractive in appearance for also ensuring anchor slab 3 and column 1 Smooth, the outside of mounting disc 23 is provided with anchor slab 3, and the medial surface contact of anchor slab 3 connects column 1 and climbs cone 2, opened up on anchor slab 3 There is the bolt hole 31 in regular distribution, bolt hole 31 is located at the side of mounting disc 23, the position of bolt hole 31 and the position for climbing cone 2 Alignment, the lateral surface of anchor slab 3 are connected with screw rod 4, the run through bolt hole 31 of screw rod 4, and one end of screw rod 4 is connected by screw thread activity Mounting disc 23 is connect, i.e., anchor slab 3 is tightened to by screw rod 4 climbs on cone 2, thus attached wall miscellaneous part can be welded on into anchor slab On 3, this new attached wall embedded parts structure can reduce the live template perforate workload of column 1, shorten used in the pre-buried installation of embedded part Time, reduce follow-up cutting work after project completion, mounting process is simple, and the cost of relatively direct pre embedded bolt is lower, spiral shell Bar 4 can also reuse, cost-effective.
In summary:The new attached wall embedded parts structure of this derrick crane, by climbing cone 2 column 1 is pre-buried before pouring, then Anchor slab 3 is tightened to by screw rod 4 and climbed on cone 2, the live template perforate workload of column 1 is so reduced, shortens embedded part Time used in pre-buried installation, reduce follow-up cutting work after project completion, mounting process is simple, relatively direct pre embedded bolt Cost it is lower, screw rod 4 can also reuse, cost-effective
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, it can realize that this practicality is new in other specific forms Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and is nonrestrictive, this practicality is new The scope of type limits by appended claims rather than described above, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are included in the utility model.Any reference in claim should not be considered as limitation Involved claim.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that those skilled in the art should for clarity Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It is appreciated that other embodiment.

Claims (4)

1. a kind of new attached wall embedded parts structure of derrick crane, including climb cone(2), climb cone(2)Including position-arresting disk(21), round bar (22)And mounting disc(23), round bar(22)Both ends offer external screw thread, round bar(22)One end be connected through a screw thread it is spacing Disk(21), round bar(22)The other end be connected through a screw thread mounting disc(23), mounting disc(23)Outside anchor slab is installed(3), The anchor slab(3)Medial surface contact connection column(1)Bored with climbing(2), anchor slab(3)On offer bolt hole in regular distribution (31), anchor slab(3)Lateral surface be connected with screw rod(4), the screw rod(4)Run through bolt hole(31), screw rod(4)One end Mounting disc is flexibly connected by screw thread(23).
A kind of 2. new attached wall embedded parts structure of derrick crane according to claim 1, it is characterised in that:The position-arresting disk (21)And mounting disc(23)It is a kind of horn-like component.
A kind of 3. new attached wall embedded parts structure of derrick crane according to claim 1, it is characterised in that:The mounting disc (23)Opening surface and column(1)Side flush.
A kind of 4. new attached wall embedded parts structure of derrick crane according to claim 1, it is characterised in that:The bolt hole (31)Positioned at mounting disc(23)Side.
CN201720691042.3U 2017-06-14 2017-06-14 A kind of new attached wall embedded parts structure of derrick crane Active CN206858019U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720691042.3U CN206858019U (en) 2017-06-14 2017-06-14 A kind of new attached wall embedded parts structure of derrick crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720691042.3U CN206858019U (en) 2017-06-14 2017-06-14 A kind of new attached wall embedded parts structure of derrick crane

Publications (1)

Publication Number Publication Date
CN206858019U true CN206858019U (en) 2018-01-09

Family

ID=60831881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720691042.3U Active CN206858019U (en) 2017-06-14 2017-06-14 A kind of new attached wall embedded parts structure of derrick crane

Country Status (1)

Country Link
CN (1) CN206858019U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112695897A (en) * 2020-12-30 2021-04-23 中交路桥华南工程有限公司 Embedded part embedding method and embedded part
CN112922361A (en) * 2021-01-22 2021-06-08 中交路桥华南工程有限公司 Bracket positioning and mounting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112695897A (en) * 2020-12-30 2021-04-23 中交路桥华南工程有限公司 Embedded part embedding method and embedded part
CN112922361A (en) * 2021-01-22 2021-06-08 中交路桥华南工程有限公司 Bracket positioning and mounting method

Similar Documents

Publication Publication Date Title
CN110528950B (en) Assembled hidden bracket type beam-column joint connecting device
CN206616862U (en) Formwork root bracing means
CN206858019U (en) A kind of new attached wall embedded parts structure of derrick crane
CN208792737U (en) For hanging the detachable connecting part of external platform hanging girder steel
CN105239726B (en) The prefabricated combined special-shaped power consumption post of steel reinforced concrete
CN108532796A (en) Assembly concrete shear wall and face inner beam rigid connection node and construction method
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN101936074A (en) Fast building earthquake-resisting reinforcing method and device
JP4901900B2 (en) Precast pile cap structure and joining method
CN105781019B (en) Assembled architecture bar connecting full grout sleeve and grouting method
CN103741944B (en) Fixation kit, template system containing this fixation kit and body of wall casting method
CN205637120U (en) Assembly structure of precast concrete beam and steel core concrete column
CN206352340U (en) Connecting node between precast concrete column and pedestal
CN107939042A (en) A kind of construction method of nothing to the adjustable post template concrete of drawing
CN209429263U (en) A kind of prefabricated column connected node fixing templates
CN103669831B (en) A kind of transformer station's cast-in-situ wall combined steel and construction method thereof
CN206815545U (en) A kind of assembled beam-column node
CN207228347U (en) A kind of connector, prefabricated component and prefabricated component and the connecting node on basis
CN107386633A (en) A kind of multifunctional building template system
CN113323137B (en) BIM-based assembly type component connecting structure and construction method thereof
CN203097290U (en) Assembled type split bolt
CN210622270U (en) Scaffold suitable for shear force wall
CN208733817U (en) A kind of assembling type steel structure building Special-Shaped Column
CN203755781U (en) Sectional type center pillar
CN209723379U (en) Prefabricated load-bearing shear wall plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant