CN107956475A - A kind of structure and construction method for protecting development work surrounding rock stability - Google Patents

A kind of structure and construction method for protecting development work surrounding rock stability Download PDF

Info

Publication number
CN107956475A
CN107956475A CN201711332613.5A CN201711332613A CN107956475A CN 107956475 A CN107956475 A CN 107956475A CN 201711332613 A CN201711332613 A CN 201711332613A CN 107956475 A CN107956475 A CN 107956475A
Authority
CN
China
Prior art keywords
relieving roadway
roadway
relieving
main entry
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711332613.5A
Other languages
Chinese (zh)
Inventor
黄克军
金声尧
王苏健
邓增社
李亮
沈会初
王鹏
朱兴攀
吴学明
薛卫峰
王宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Coal and Chemical Technology Institute Co Ltd
Original Assignee
Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Coal and Chemical Technology Institute Co Ltd filed Critical Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority to CN201711332613.5A priority Critical patent/CN107956475A/en
Publication of CN107956475A publication Critical patent/CN107956475A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Remote Sensing (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of structure and construction method for protecting development work surrounding rock stability; including the relieving roadway being opened between current stope protection coal pillar border and auxiliary fortune main entry; relieving roadway is connected with the air return way and haulage gate of current stope, and relieving roadway top plate offers presplitting band;Its construction method is:First, the digging position of relieving roadway is determined between the protection coal pillar border of current stope and auxiliary fortune main entry;Relieving roadway is dug along the direction parallel to auxiliary fortune main entry;And two country rock and top plate is helped to carry out supporting it;When relieving roadway, which is constructed, to be completed, top plate presplitting construction is carried out in relieving roadway;Again in the two-port construction fire dam of relieving roadway;Reduce the width needed for main entry protection coal pillar, improve working face recovery ratio, at the same time; relieving roadway protects tunnel jointly with main entry protection coal pillar; the service life in tunnel is improved, maintenance time is saved and fund, the safety and high efficiency to realizing colliery is of great significance.

Description

A kind of structure and construction method for protecting development work surrounding rock stability
Technical field
Patent of the present invention belongs to mining influence control technology field in colliery, and in particular to one kind protection development work country rock The structure and construction method of stability.
Background technology
Deformation of the surrounding rock in tunnel is a kind of common geological disaster, and deformation of the surrounding rock in tunnel can increase difficulty of construction, greatly prolong Duration, causing the waste of fund increases cost, more severe patient can cause engineering to terminate.In recent years, because of deformation of the surrounding rock in tunnel Caused production accident repeatedly occurs, and is one of crucial problem for perplexing coal undertaking development.The research of analysis and summary in recent years Achievement, surrouding rock deformation are broadly divided into three classes:Deformation, exploitation are lived caused by deformation, buried depth caused by rock mass self-strength is low are larger Deformation caused by dynamic.This three classes surrouding rock deformation can be seen in underground engineering, and resulting roadway with large deformation is also universal In the presence of.
For main entry as the tunnel for servicing full mine or a mining level, its service life is longer, and is responsible for whole As soon as a mine or a mining level transport, ventilation, pedestrian, the surrounding rock stability of main entry more it is particularly important that, therefore control Main entry processed is had great importance and is worth to the safe and efficient of whole mine, continuation exploitation by mining influence.
The content of the invention
To solve the above problems, the present invention provides a kind of structure for protecting development work surrounding rock stability and the side of constructing Method, weakens main entry by mining influence, improves the distribution of main entry surrouding rock stress, extend the service life of main entry, and then realize mine Safe and efficient, continuation exploitation.
To reach above-mentioned purpose, the technical solution adopted by the present invention is:A kind of knot for protecting development work surrounding rock stability Structure, including the relieving roadway being opened between the protection coal pillar border of current stope and auxiliary fortune main entry, relieving roadway perforation are worked as Preceding stope, and the both ends open of relieving roadway is provided with the fire dam for blocking relieving roadway, edge is unloaded on relieving roadway top plate Pressure lane trend offers presplitting groove, and presplitting groove runs through current stope.
Relieving roadway is arranged in parallel with auxiliary fortune main entry, return air main entry and adhesive tape main entry.
Relieving roadway is opened at distance protection coal column border 5m~20m, and apart from current stope minery at least 100m。
Presplitting groove needs the caving zone through work at present face top plate.
Relieving roadway is provided with the Simple anchor rod and anchor cable that country rock is helped for supporting roof and two.
A kind of construction method for protecting development work surrounding rock stability structure,
First, the digging position of relieving roadway is determined between the protection coal pillar border of current stope and auxiliary fortune main entry To put, relieving roadway is opened at distance protection coal column border 5m~20m, and apart from current stope minery at least 100m;
Then, relieving roadway is dug along the direction parallel to auxiliary fortune main entry;When digging relieving roadway, using Simple anchor rod and anchor cable Country rock and top plate is helped to carry out supporting to the two of relieving roadway;When the current stope of relieving roadway lateral direction penetrating, and two help country rock and When roof timbering construction is completed, top plate presplitting construction is carried out in relieving roadway;
Finally, move towards to form the presplitting groove through current stope along relieving roadway on relieving roadway top plate, that is, complete Top plate presplitting is constructed, then the two-port construction fire dam in relieving roadway.
Dig relieving roadway progress synchronous with stope coal work.
Carry out in top plate presplitting construction, the pre- ceasma of top plate of first constructing, then pressure break is carried out to top plate using high pressure water.
Compared with prior art, the present invention at least has the advantages that:Reduce the width needed for main entry protection coal pillar Degree, improves working face recovery ratio, and the pre- ceasma of top plate is set in relieving roadway, cuts off actual mining towards main entry stress transfer Layer, the mining induced stress of stope also obtain a degree of release in relieving roadway, meanwhile, relieving roadway and main entry protection coal Column collective effect reduces return air main entry, adhesive tape main entry, auxiliary fortune main entry by the mining influence of working face, extends return air main entry, glue Service life with main entry, auxiliary fortune main entry, road maintenance time, fund cost are saved, to realizing that the safe and efficient of colliery is opened Adopt and be of great significance.
Further, relieving roadway is arranged in parallel with auxiliary fortune main entry, return air main entry and adhesive tape main entry, it is ensured that relieving roadway top plate After pressure break, when by this working face mining influence, cutting action of the relieving roadway to roof strata mining induced stress transmission is given full play to.
Further, relieving roadway is opened at distance protection coal column border 5m~20m, makes protection coal pillar in stope With enough supporting roles, away from auxiliary fortune main entry, reduce the unfavorable shadow that relieving roadway digging process vibrations produce auxiliary fortune main entry Ring.
Further, the Simple anchor rod and anchor cable that country rock is helped for supporting roof and two are provided with relieving roadway, to open Dig relieving roadway and the digging condition of safety is provided, while avoid the cost of digging relieving roadway.
Further, fire dam has been constructed at both ends in relieving roadway after the setting pre- ceasma of top plate, and relieving roadway is suitable with return air Groove and haulage gate isolation, while having prevented that personnel from entering relieving roadway, avoid relieving roadway spoil in release from falling into return air suitable Groove and haulage gate, prevent relieving roadway string wind, leak out and gas gathers.
Further, carry out the relieving roadway after top plate presplitting softening construction and cut off top plate mining induced stress transfer layer, work Face mining influence stress is released in relieving roadway, weakens influence of the working face mining induced stress to main entry significantly.
Further, dig that relieving roadway is synchronous with stope coal work to carry out, improve it is mechanical used in digging and Assistant conveyance tunnel and the efficiency of return aircourse.
Brief description of the drawings
Fig. 1 is the structure diagram of the present invention.
Fig. 2 constructs the structure diagram after fire dam for relieving roadway of the present invention.
In attached drawing, the auxiliary fortune main entrys of 1-, 2- return air main entrys, 3- adhesive tape main entrys, 4- relieving roadways, 5- main entry protection coal pillars border, 6- stops adopting line, 7- upper curtate haulage gates, 8- air return way, 9- haulage gates, 10- lower curtate air return way, 11- fire dams.
Embodiment
The invention will be further described with example below in conjunction with the accompanying drawings.
Embodying the exemplary embodiments of feature of present invention and advantage will describe in detail in the following description, it should be understood that this Invention can have various changes in different embodiments, it is neither departed from the scope of the present invention, and it is therein explanation and Attached drawing is illustrated as being used in itself, and is not used to the limitation present invention.
It is a kind of to protect the structure of development work surrounding rock stability such as Fig. 1, including it is opened in the protection of current stope Relieving roadway 4 between coal column border 5 and auxiliary fortune main entry 1, relieving roadway 4 penetrates through current stope, and the both ends of relieving roadway 4 are opened Mouth is provided with the fire dam 11 for blocking relieving roadway 4, moves towards to offer presplitting groove, presplitting along relieving roadway on 4 top plate of relieving roadway Groove runs through current stope;Relieving roadway 4 is arranged in parallel with auxiliary fortune main entry 1, return air main entry 2 and adhesive tape main entry 3;
As the preferred embodiment of the present invention, relieving roadway 4 is opened at distance protection coal column border 5m~20m, and distance is worked as Preceding stope minery at least 100m.
Relieving roadway 4 is provided with the Simple anchor rod and anchor cable that country rock is helped for supporting roof and two;Presplitting groove needs to run through The caving zone of current stope.
The invention also discloses a kind of construction method for protecting development work surrounding rock stability structure:First, returned currently The digging position of relieving roadway 4 is determined between the protection coal pillar border 5 of mining face and auxiliary fortune main entry 1, relieving roadway 4 is opened in distance At the 5m~20m of protection coal pillar border, and apart from current stope minery at least 100m;
Then, relieving roadway 4 is dug along the direction parallel to auxiliary fortune main entry 1;When digging relieving roadway 4, using Simple anchor rod and Anchor cable helps country rock and top plate to carry out supporting to the two of relieving roadway 4;When the current stope of 4 lateral direction penetrating of relieving roadway, and two help When country rock and roof timbering construction are completed, top plate presplitting construction is carried out in relieving roadway 4;
Finally, move towards to form the presplitting groove through current stope along relieving roadway on 4 top plate of relieving roadway, that is, complete Top plate presplitting is constructed, then the two-port construction fire dam 11 in relieving roadway 4.
As the preferred embodiment of the present invention, digging relieving roadway 4 is synchronous with stope coal work to carry out;
As shown in Fig. 2, digging relieving roadway 4 is completed, and after the completion of top plate presplitting construction, construct in the two-port of relieving roadway 4 Fire dam 11.
As the preferred embodiment of the invention, carry out in top plate presplitting construction, the pre- ceasma of top plate of first constructing, then using high pressure Water carries out pressure break to top plate.
In a particular application, whole bank is provided with multiple working faces, the working face and upper curtate each normally exploited Haulage gate 7, lower curtate air return way 10 are adjacent;Upper curtate haulage gate 7 and air return way 8, fortune are returned along crossheading 9 and lower curtate Wind crossheading 10 tunnels at the same time respectively, and upper curtate haulage gate 7 and air return way 8 penetrate through, and transports suitable along crossheading 9 and lower curtate return air If it is provided with dry passage between groove 10 to be penetrated through;Upper curtate fortune along crossheading 7 and the suitable crossheading 9 of fortune respectively with adhesive tape main entry 3 and auxiliary Fortune main entry 1 connects, and air return way 8 and lower curtate air return way 10 are connected with return air main entry 2 and auxiliary fortune main entry 1 respectively.
Current stope air return way 8, fortune along set between crossheading 9 one with auxiliary fortune main entry 1, return air main entry 2, The parallel relieving roadway 4 of adhesive tape main entry 3, relieving roadway 4 are arranged in the coal seam between main entry protection coal pillar border 5 and auxiliary fortune main entry, When tunneling relieving roadway 4, it should be ensured that the position of relieving roadway 4 and the safe distance of working face.In addition, relieving roadway 4, using simple anchor Bar and cable bolting top plate and two help country rock, the safe construction for ensureing driving and top plate presplitting softening while does not increase supporting Cost.
As the preferred embodiment of the invention, the digging position of relieving roadway 4 and the distance met head on of current stope For 100m.
After being softened in relieving roadway 4 using top plate presplitting, construct in relieving roadway 4 and air return way 8,9 connectivity part of fortune crossheading close Wall 11 is closed, string wind is prevented, leaks out and gas gathers, while avoided personnel from entering relieving roadway 4;As working face is constantly to being pushed forward Into close to when stopping adopting line 6, the coal column, auxiliary fortune main entry 1, return air main entry 2, adhesive tape main entry 3 in protection coal pillar border 5 are by working face The stress influence of movable property life is adopted, and uses the relieving roadway 4 after top plate presplitting softening, top plate mining induced stress has been cut off and has transmitted key Block, working face mining influence stress are significantly discharged in relieving roadway 4, weaken return air main entry 2, adhesive tape main entry 3 and auxiliary Main entry 1 is transported by the mining influence of the working face, main entry surrounding rock stress distribution law is improved, improves the stabilization of main entry country rock Property.
Using the structure and construction method of protection development work surrounding rock stability of the present invention, reduce main entry protection coal Width needed for column, improves the recovery ratio of coal, meanwhile, relieving roadway 4 and 5 collective effect of main entry protection coal pillar border, reduce return air Main entry 2, adhesive tape main entry 3, auxiliary fortune main entry 1 are extended return air main entry 2, adhesive tape main entry 3, auxiliary fortune by the mining influence of exploitation working face The service life of main entry 1, reduces destruction of the mining influence to main entry, and then is greatly saved and reprocesses main entry time, fund Cost, the safety and high efficiency to realizing colliery are of great significance.
Technical scheme is disclosed as above by alternative embodiment.Artisan will appreciate that do not taking off The change and retouching made from the revealed the scope of the present invention of appended claims of the invention, belong to the right of the present invention Claimed scope.

Claims (8)

1. a kind of structure for protecting development work surrounding rock stability, it is characterised in that including being opened in current stope Relieving roadway (4) between protection coal pillar border (5) and auxiliary fortune main entry (1), relieving roadway (4) penetrates through current stope, and unloads The both ends open of pressure lane (4) is provided with for blocking the fire dams (11) of relieving roadway (4), along relieving roadway on relieving roadway (4) top plate Trend offers presplitting groove, and presplitting groove runs through current stope.
A kind of 2. structure for protecting development work surrounding rock stability according to claim 1, it is characterised in that relieving roadway (4) it is arranged in parallel with auxiliary fortune main entry (1), return air main entry (2) and adhesive tape main entry (3).
A kind of 3. structure for protecting development work surrounding rock stability according to claim 1, it is characterised in that relieving roadway (4) it is opened at distance protection coal column border (5) 5m~20m, and apart from current stope minery at least 100m.
4. a kind of structure for protecting development work surrounding rock stability according to claim 1, it is characterised in that presplitting groove needs To run through the caving zone of work at present face top plate.
A kind of 5. structure for protecting development work surrounding rock stability according to claim 1, it is characterised in that relieving roadway (4) Simple anchor rod and anchor cable that country rock is helped for supporting roof and two are provided with.
A kind of 6. construction method for protecting development work surrounding rock stability structure, it is characterised in that
First, opening for relieving roadway (4) is determined between the protection coal pillar border (5) of current stope and auxiliary fortune main entry (1) Position is dug, relieving roadway (4) is opened at distance protection coal column border (5) 5m~20m, and apart from current stope minery At least 100m;
Then, along the direction digging relieving roadway (4) parallel to auxiliary fortune main entry (1), when digging relieving roadway (4), using Simple anchor rod Country rock and top plate is helped to carry out supporting to the two of relieving roadway (4) with anchor cable;When the current stope of relieving roadway (4) lateral direction penetrating, And two help country rock and roof timbering to construct when completing, and top plate presplitting construction is carried out in relieving roadway (4);
Finally, move towards to form the presplitting groove through current stope along relieving roadway on relieving roadway (4) top plate, that is, complete top Plate presplitting is constructed, then the two-port construction fire dam (11) in relieving roadway (4).
A kind of 7. construction method for protecting development work surrounding rock stability structure according to claim 6, it is characterised in that Dig relieving roadway (4) progress synchronous with stope coal work.
A kind of 8. construction method for protecting development work surrounding rock stability structure according to claim 6, it is characterised in that Carry out in top plate presplitting construction, the pre- ceasma of top plate of first constructing, then pressure break is carried out to top plate using high pressure water.
CN201711332613.5A 2017-12-13 2017-12-13 A kind of structure and construction method for protecting development work surrounding rock stability Pending CN107956475A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711332613.5A CN107956475A (en) 2017-12-13 2017-12-13 A kind of structure and construction method for protecting development work surrounding rock stability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711332613.5A CN107956475A (en) 2017-12-13 2017-12-13 A kind of structure and construction method for protecting development work surrounding rock stability

Publications (1)

Publication Number Publication Date
CN107956475A true CN107956475A (en) 2018-04-24

Family

ID=61958755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711332613.5A Pending CN107956475A (en) 2017-12-13 2017-12-13 A kind of structure and construction method for protecting development work surrounding rock stability

Country Status (1)

Country Link
CN (1) CN107956475A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145326A (en) * 2019-04-23 2019-08-20 中国矿业大学(北京) Surrounding rock stability control method suitable for mine district main entry
CN116122811A (en) * 2023-02-21 2023-05-16 中煤科工开采研究院有限公司 Rock burst pressure relief method for large roadway area

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1482344A (en) * 2002-09-09 2004-03-17 神华集团有限责任公司 Fully-mechanized mining working plane supplementary laneway multiple passage quick-speed moving process
CN102061918A (en) * 2009-11-12 2011-05-18 中国矿业大学 Coal mining method for co-mining gas in mine
CN104564086A (en) * 2014-12-29 2015-04-29 中国矿业大学 Optimization method for stress field of area of main roadway
CN106089234A (en) * 2016-07-15 2016-11-09 北京科技大学 A kind of method of distance auxiliary lane multichannel Quick-return fully-mechanized mining working
CN106321049A (en) * 2016-09-27 2017-01-11 吴拥政 Method and device for optimizing mining stopping line position with hydrofracture pressure relieving
CN106437711A (en) * 2016-10-20 2017-02-22 山东科技大学 Coal seam impact type mine earthquake prevention and control method
CN107060760A (en) * 2017-06-13 2017-08-18 中国矿业大学 A kind of method that colliery withdraws tunnel presplit blasting caving release
CN107313777A (en) * 2017-05-09 2017-11-03 天地科技股份有限公司 The main return channel hydraulic fracturing pressure relief method of fully-mechanized mining working and device
CN207598238U (en) * 2017-12-13 2018-07-10 陕西煤业化工技术研究院有限责任公司 A kind of structure for protecting development work surrounding rock stability

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1482344A (en) * 2002-09-09 2004-03-17 神华集团有限责任公司 Fully-mechanized mining working plane supplementary laneway multiple passage quick-speed moving process
CN102061918A (en) * 2009-11-12 2011-05-18 中国矿业大学 Coal mining method for co-mining gas in mine
CN104564086A (en) * 2014-12-29 2015-04-29 中国矿业大学 Optimization method for stress field of area of main roadway
CN106089234A (en) * 2016-07-15 2016-11-09 北京科技大学 A kind of method of distance auxiliary lane multichannel Quick-return fully-mechanized mining working
CN106321049A (en) * 2016-09-27 2017-01-11 吴拥政 Method and device for optimizing mining stopping line position with hydrofracture pressure relieving
CN106437711A (en) * 2016-10-20 2017-02-22 山东科技大学 Coal seam impact type mine earthquake prevention and control method
CN107313777A (en) * 2017-05-09 2017-11-03 天地科技股份有限公司 The main return channel hydraulic fracturing pressure relief method of fully-mechanized mining working and device
CN107060760A (en) * 2017-06-13 2017-08-18 中国矿业大学 A kind of method that colliery withdraws tunnel presplit blasting caving release
CN207598238U (en) * 2017-12-13 2018-07-10 陕西煤业化工技术研究院有限责任公司 A kind of structure for protecting development work surrounding rock stability

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
祁和刚: "深部高应力巷道综合卸压技术研究与实践" *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145326A (en) * 2019-04-23 2019-08-20 中国矿业大学(北京) Surrounding rock stability control method suitable for mine district main entry
CN110145326B (en) * 2019-04-23 2020-05-05 中国矿业大学(北京) Surrounding rock stability control method suitable for coal mining area main roadway
WO2020216114A1 (en) * 2019-04-23 2020-10-29 中国矿业大学(北京) Method for controlling stability of surrounding rock applicable to mining region main roadway of coal mine
CN116122811A (en) * 2023-02-21 2023-05-16 中煤科工开采研究院有限公司 Rock burst pressure relief method for large roadway area

Similar Documents

Publication Publication Date Title
CN105221179B (en) A kind of highly gassy mine Y type method of ventilations
CN109339786A (en) A kind of prefabricated Fracture orientation hydraulic fracturing cracking method
CN103557000B (en) Method for preventing gob-side entry rock burst through side-drawing filling
CN107060760A (en) A kind of method that colliery withdraws tunnel presplit blasting caving release
CN103899350B (en) Fully mechanized coal face frame carries top coal gas drainage system
CN108397227A (en) A kind of progressive extinction roadway layout method of tendency
CN103953345B (en) A kind of small section entry retaining along gob side exploitation method
CN106285680B (en) Impact soft seam tunnel way of escape Controlling of Coal Outburst method
CN104632219A (en) Large mining height gob-side entry retaining method for thick coal seams
CN102587960A (en) Arrangement method of high gas coal seam extraction working face roadway
CN109882175B (en) Cooperative operation method for realizing one-lane three-purpose working face mining and stoping equipment withdrawal
CN109252860A (en) A kind of girdle continuous milling machine high mechanization recovery method
CN107905807A (en) A kind of future small coal pillar comprehensive mechanical coal mining supporting construction and construction method
CN111396118A (en) Coal seam group rapid rock cross-cut coal uncovering outburst eliminating method
CN112443351A (en) Precise outburst elimination method for cross-section coal uncovering of rock cross
CN107956475A (en) A kind of structure and construction method for protecting development work surrounding rock stability
CN115288681A (en) Method for preventing rock burst at fracture source in coal mine roof area
CN114592867A (en) Temporary top pillar induced caving and sill pillar-free sublevel caving combined mining method
CN207598238U (en) A kind of structure for protecting development work surrounding rock stability
CN111734414A (en) Coal mining method capable of recovering working face crossheading coal pillar
CN108506000A (en) A kind of projecting coal bed gallery speedy drivage method
CN112324499A (en) Method for preventing rock burst by blocking disturbance stress wave
CN101886546B (en) Method for inhibiting roof deformation of coal mine underground bolt and anchor cable roadway
CN108894783B (en) A kind of half-edge coal seam paste body filling coal-mining technique
CN111828005B (en) Face mining method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination