CN107503365A - Super High elevator high and big die plate installation engineering method - Google Patents

Super High elevator high and big die plate installation engineering method Download PDF

Info

Publication number
CN107503365A
CN107503365A CN201710814510.6A CN201710814510A CN107503365A CN 107503365 A CN107503365 A CN 107503365A CN 201710814510 A CN201710814510 A CN 201710814510A CN 107503365 A CN107503365 A CN 107503365A
Authority
CN
China
Prior art keywords
box body
template
stupefied
construction
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710814510.6A
Other languages
Chinese (zh)
Other versions
CN107503365B (en
Inventor
沈育龙
杨统元
丁恩亮
王杰
闫富华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201710814510.6A priority Critical patent/CN107503365B/en
Publication of CN107503365A publication Critical patent/CN107503365A/en
Application granted granted Critical
Publication of CN107503365B publication Critical patent/CN107503365B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/013Shuttering specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of Super High elevator high and big die plate installation engineering method, including two stages of Construction in Preparatory Stage and constructing operation process;Described constructing operation process includes:1)Template is processed;2)Bed die installation, fix;3)Inner support frame is installed;4)Side form installation, fix;5)Integral reinforcing;6)Box body lifting is in place;7)Tension rib is installed;8)Concreting, monitoring;9)Form removable.Traditional template, flitch, steel pipe are used as raw material the invention provides a kind of, it is that panel, flitch stupefied are fabricated to " box body " as interior stupefied, steel pipe as outer by the use of template, it is arranged on using loop wheel machine in elevator, to solve the problems, such as lateral pressure of the concrete to " box body ", steel pipe support is set in " box body ", to solve the problems, such as the anti-floating of " box body " to concrete, " box body " is locked using steel pipe, using round steel by the Super High elevator high and big die plate strengthening construction engineering method of steel pipe and raft plate bottom reinforcement bars drawknot.

Description

Super High elevator high and big die plate installation engineering method
Technical field
Design building construction field of the present invention is specially a kind of suitable for being applied to elevator in Super High raft plate, catchmenting The construction of well model sheetinstallat in the Equipment Foundations such as hole, large stadium, industrial premises.
Background technology
With the development of society, the especially continuous quickening of urbanization process, in some societies caused by the big flowing of population The city of meeting resource Relatively centralized, population are largely converged so that more populations and other societies are accommodated in limited land area It is very nervous that meeting resource causes soil.Therefore, develop skyscraper and hypogee, have become and solve limited soil most The method of more utilization rates.
With the development of high-rise building technology, building height is refreshed again and again by new record, to make full use of underground Space and resistance horizontal loading need, and building height is higher, and its embedded depth of foundation is increasingly deeper, raft plate is more and more thicker.Ordinary circumstance Under, more than the thickness in general 2m of building raft plate, most thick reachable 10m even more than 10m, are mass concrete;To prevent substantially Product concrete because pour mode it is unreasonable formed it is cold seam or because internal-external temperature difference it is excessive produce cause concrete cracking situations such as, one As take layering, segmentation casting concrete, extend the construction period.If adopting an effective measure primary concreting concrete, can keep away Exempt to produce construction joint or cold seam, improve the globality of concrete.
Super High elevator and its catch pit are generally disposed in raft plate, according to the size of lift car and elevator speed, Its general well depth >=3m, it is complex by concrete lateral pressure and buoyancy, this formwork reinforcement system.Raft foundation mixes Solidifying soil can one-time-concreting shaping, be heavily dependent on elevator, whether formwork reinforcement system firm at catch pit.
Under normal circumstances, it is deeper to similar well, to prevent its template system anti-side unstability, take in framework of steel reinforcement Upper embedded lead screw carries out binding, and inside is taken to be reinforced to support;To prevent template anti-floating, preloading is generally taken on template system Form, such as the counterweight such as heap template, reinforcing bar, engineering time length, working procedure are complicated.
Therefore, to solve inconvenience, the mass defect that the usual way of the well formwork reinforcement system such as elevator is brought, there is provided Go out the construction that a kind of new Super High elevator high and big die plate is reinforced, be a good problem to study.
The content of the invention
In order to overcome above-mentioned deficiency of the prior art, the invention provides a kind of using traditional template, flitch, steel pipe For raw material, by the use of template be panel, flitch as interior stupefied, steel pipe as it is outer it is stupefied be fabricated to " box body ", be arranged on using loop wheel machine In elevator, to solve the problems, such as lateral pressure of the concrete to " box body ", steel pipe support is set in " box body ", to solve " box body " To the anti-floating problem of concrete, " box body " is locked using steel pipe, using round steel by the super of steel pipe and raft plate bottom reinforcement bars drawknot High rise elevator well high and big die plate strengthening construction engineering method.
The object of the present invention is achieved like this:
Super High elevator high and big die plate installation engineering method, including two stages of Construction in Preparatory Stage and constructing operation process; It is characterized in that:Described Construction in Preparatory Stage, including:1)The construction technology preparatory stage;2)The Farm Planning stage;3)Material is accurate Standby, personnel prepare;Described constructing operation process includes:1)Template is processed;2)Bed die installation, fix;3)Inner support frame is installed; 4)Side form installation, fix;5)Integral reinforcing;6)Box body lifting is in place;7)Tension rib is installed;8)Concreting, monitoring; 9) Form removable;
Described 1)The construction technology preparatory stage:Comprise the following steps:(1)Formwork reinforcement system and steel tie design, calculate; (2)Work out model sheetinstallat special construction plan and confide a technological secret;(3)To use raw material site acceptance, recheck;(4)It is overweight The technical performance data and acceptance(check) file of mechanical and its supporting lifting gear;(5)Design or code requirement other needs carry The data of confession;
2)The Farm Planning stage:Including(1)Levelling of the land work, the pine for being unfavorable for mechanical movement in place are carried out before construction Soft position, take reinforcing, change the measure such as fill out, it is ensured that the safety of crane walking;(2)For the pre- laydown area of material, template processing Area carries out levelling of the land, compacting;(3)In the venue according to the actual conditions in place, reasonable Arrangement measurement control stake and bench mark; Control point should be laid in not by the position of construction infection, and sets up obvious mark, carry out safeguard measure, inspected periodically, checked;
3)Material mechanical, personnel's preparatory stage:Including(1)Material preparation phase and(2)Personnel's preparatory stage;Described(1)Material Expect that the mechanical preparatory stage is:According to material analysis and the requirement of construction schedule, materials requirements plan is worked out, for construction Stock, determine that material stacks place, foundation is provided for organization material transport;According to construction requirement, suitable lifting is selected Machinery and suspender;Tension rib uses HPB300 20mm, processes in advance in place, and termination is 180 degree crotch, straightway 10d;(2) Personnel's preparatory stage:Carpenter, scaffolder, play the work personnel arrangement preparations such as heavy industry, commander's work in place;
Described 1)The template process segment:Including the timber used in template and its support system, must not have fragility, serious distortion and The timber being easily deformed after making moist;Wood plywood corner should scribble edge sealing adhesive, in order to protect the edge sealing adhesive of template corner, in formwork When at formwork edge joint paste adhesive waterproof tape be protected by, mortar leakage prevention;Wood plywood plate face does not drill hole as far as possible, meets reserved Hole, repaired in time with common plank;Wood plywood, which is prepared, answers whole directly to use, and reduces arbitrarily saw as far as possible and cuts, causes Waste;The length of nail should be 1.5-2 times of template thickness;
2)Bed die installation, fixed stage:During including bed die assembling, first spread that wooden springboard is levelling on ground, according to the plane of well Size determines scantling, then be 450mm as spacing by the use of steel pipe outer stupefied lateral arrangement, by the use of steel pipe as spacing be 600mm Reinforcement in it is stupefied be longitudinally arranged, and by it is outer it is stupefied with it is interior it is stupefied be connected by fastener, between interior steel is stupefied by spacing 150mm laying flitch As interior stupefied then flitch is stupefied firm using iron wire colligation with outer steel;Then block-by-block template is followed closely on flitch with nail, and nail is indulged To being smaller than 100mm;Box body bed die integral assembling and after brushing releasing agent, bed die is integrally overturn, template is face-down;
3)Inner support frame erection stage:After being installed including bottom plate, start by longitudinal pitch 800mm, horizontal spacing 600mm, step pitch Inner support steel pipe frame is set up for 450mm, support body vertical rod is connected with the stupefied use fastener of the interior steel on bottom plate;Erection of frames presses scaffold Related specifications are operated;To ensure the globality of inner support frame, support body longitudinally outboard face sets bridging;Frame during setting up External side, which is set, throws support;
4)Side form installation, fixed stage:After the completion of being set up including inner support frame, flitch is pressed into spacing 150mm iron wire colligation framves On the outer steel of body surrounding is stupefied, vertical direction, check flitch fix after each surface flatness, start to fix first after meeting the requirements Layer vertical formwork, with nail by being smaller than 100mm stickfast, after first layer installation, set up outer operating platform, fixed above second Layer, third layer template, until side form whole installation;
5)The box body integral reinforcing stage:After side form installation, the flatness of each side is checked, and support frame is examined Look into, it is ensured that each fastener is connected firmly, rod member is smooth vertical and horizontal, stress is reliable;If there is box body size distortion or support body locally loosening, Consolidation process should be carried out to support body, finally in side form surface brush releasing agent;
6)Box body lifts the stage in place:Including the weight according to box body and operating radius selection lifting machine, described hoisting machine Tool includes:Truck crane;When live tower crane satisfies the requirements, lifted with tower crane;Suspension centre is arranged on the branch of four angle points of box body In support vertical rod, connected by the suspension hook of shackle, steel wire rope and loop wheel machine;Box body overall package is completed and after tripartite checks and accepts, side Lifting can be prepared;Meanwhile the reinforcing bar colligation and its support system installation of raft plate;Commander's truck crane is transferred to lifting position, Lifting work point does not install the shackle of suspension centre, puts on steel wire rope;After the installation situation and stress center of gravity that check steel wire rope, order command It after box body is slowly hung into 0.3m~0.5m from the ground, should check whether box body is steady, after inspection is errorless, box body is hung vertically Rise;It is suitable for reading that box body is hung to well, slowly transferred to after contraposition in well, is manually coordinated using crowbar etc., it is ensured that box body does not touch Hit reinforcing bar and protective layer cushion block;After dress is in place, the support frame and template of tray interior are checked, prevent from sending out in hoisting process It is raw to loosen;
7)Tension rib erection stage:After being installed including box body, in the box body horizontal steel pipe of setting suitable for reading as tension rib upper end drawknot Point, steel pipe are connected with the rod member of the supporting frame the superiors with fastener;The lower end of tension rib and raft plate baseplate reinforcing bar drawknot, raft plate are whole The deadweight of body framework of steel reinforcement and box body lower concrete pour the weight formed after initial set as anchoring body weight, much larger than drawknot The tensile strength of reinforcing bar;The quantity of tension rib is installed according to result of calculation;
8)Concreting, monitoring stage:It is included in concreting process, particularly is starting to pour box body altitude range Interior concrete, will be settled and the monitoring of displacement to box body, and frequency is is monitored once an hour, until concreting is complete Into and after reaching initial set, can stop monitoring;Including monitoring process box body occur spillage, off normal floating situation, should stop immediately The position concrete pours, and after studying and defining processing scheme and implementing, can continue concreting;After large volume pours, Covering curing must be carried out, at well, removing template is also doubled as outside Insulation, to prevent temperature difference between inside and outside concrete at well It is excessive, gunnysack etc. is equally spread well is suitable for reading, strengthens insulation;
9)The form removable stage:Including generally, the curing time of mass concrete is at least 14 days, in concrete After the outer temperature difference is basicly stable, insulation material can be removed, equally, the template at well also can just remove;First, by well The drawknot steel pipe of mouth is removed, tension rib cuts off, then support frame, outer stupefied, interior stupefied, side form are removed from top to bottom, is finally torn open Stupefied in addition to bed die, interior stupefied, template.
Positive beneficial effect:The present invention discuss, study repeatedly in programming phase, finally the elevator in raft plate foundation ditch, Effectively used in catch pit model sheetinstallat, template system is safe and reliable so that raft board concrete one-time-concreting is molded, and is accelerated The speed of application of Core Walls Structure, shorten high building construction period.Traditional template, flitch, steel pipe is used to utilize template for raw material For panel, flitch as interior stupefied, steel pipe as it is outer it is stupefied be fabricated to " box body ", be arranged on using loop wheel machine in elevator, it is mixed to solve Solidifying soil sets steel pipe support in " box body ", the anti-floating of concrete is asked to solve " box body " to the lateral pressure problem of " box body " Topic, " box body " is locked using steel pipe, using round steel by steel pipe and raft plate bottom reinforcement bars drawknot;Often planning construction method is compared Compared with this engineering method has not only saved the construction period, it is ensured that engineering safety, quality, also save construction cost.Incorporation engineering is real Trample, Super High elevator high and big die plate construction technique be compiled into enterprise's engineering method, be Bao Ye groups in Super High engineering or Offered reference in industrial premises Large Equipment Foundation and reference significance, to improve the competition that Bao Ye groups construct in Super High Power is contributed share, and has good promotional value.
Brief description of the drawings
Fig. 1 is the process flow diagram of the present invention.
Embodiment
Below in conjunction with the accompanying drawings, the present invention is described further:
As shown in figure 1, elevator high and big die plate strengthening construction engineering method, including two ranks of Construction in Preparatory Stage and constructing operation process Section;Described Construction in Preparatory Stage includes:1)The construction technology preparatory stage;2)The Farm Planning stage;3)Material prepares, Ren Yuanzhun It is standby;Described constructing operation process includes:1)Template is processed;2)Bed die installation, fix;3)Inner support frame is installed;4)Side form is pacified Dress, fix;5)Integral reinforcing;6)Box body lifting is in place;7)Tension rib is installed;8)Concreting, monitoring; 9)Form removable.
Described 1)The construction technology preparatory stage:Comprise the following steps:(1)Formwork reinforcement system and steel tie design, Calculate;Template uses 15mm thickness glued boards, interior stupefied using 40mm × 80mm flitches, spacing@150mm, it is outer it is stupefied using Ф 48 × 3.5mm flitches, spacing@450mm;After concrete is calculated to the buoyancy of box body, according to the tensile strength of reinforcing bar, height is calculated respectively Area's elevator pit(It is two-in-one), middle area's elevator pit(It is two-in-one), low area's elevator pit(It is two-in-one), low area's elevator pit(Solely Erect and put), Fire lift well, the quantity of each steel tie of catch pit, respectively 12 pieces/, 8 pieces/, 4 pieces/, 2 pieces/; (2)Work out model sheetinstallat special construction plan and confide a technological secret;(3)To the raw material site acceptance used, recheck;(4)It is overweight The technical performance data and acceptance(check) file of mechanical and its supporting lifting gear;(5)Design or code requirement other needs carry The data of confession.
2)The Farm Planning stage:Including(1)Levelling of the land work is carried out before construction, for being unfavorable for mechanical movement in place Soft position, take reinforcing, change the measure such as fill out, it is ensured that the safety of crane walking;(2)For the pre- laydown area of material, template Processing district carries out levelling of the land, compacting;(3)In the venue according to the actual conditions in place, reasonable Arrangement measurement control stake and water On schedule.Control point should be laid in not by the position of construction infection, and sets up obvious mark, carry out safeguard measure, inspect periodically, Review.
3)Material mechanical, personnel's preparatory stage:Including(1)Material preparation phase and(2)Personnel's preparatory stage;Described (1)The material mechanical preparatory stage is:According to material analysis and the requirement of construction schedule, materials requirements plan is worked out, is Construction stock, determine that material stacks place, foundation is provided for organization material transport;It is suitable according to construction requirement, selection Hoisting machinery and suspender.Tension rib uses HPB300 20mm, processes in advance in place, and termination is 180 degree crotch, and straightway is 10d.(2)Personnel's preparatory stage:Carpenter, scaffolder, play the work personnel arrangement preparations such as heavy industry, commander's work in place.
Described 1)The template process segment, including:Timber used in template and its support system, there must not be fragility, serious The timber for distorting and being easily deformed after making moist;Wood plywood corner should scribble edge sealing adhesive, in order to protect the edge sealing adhesive of template corner, Adhesive waterproof tape is pasted in formwork at formwork edge joint to be protected by, mortar leakage prevention;Wood plywood plate face does not drill hole as far as possible, meets There is reserving hole, can be repaired in time with common plank;Wood plywood, which is prepared, answers whole directly to use, and reduces arbitrarily saw as far as possible Cut, cause to waste;The length of nail should be 1.5-2 times of template thickness.
2)Bed die installation, fixed stage;During including bed die assembling, it is levelling first to spread wooden springboard on ground, according to well Plane sizes determine scantling, then by the use of steel pipe as outer stupefied(Spacing is 450mm)Lateral arrangement, by the use of steel pipe as strengthen in it is stupefied (Spacing is 600mm)Be longitudinally arranged, and by it is outer it is stupefied with it is interior it is stupefied be connected by fastener, between interior steel is stupefied by spacing 150mm lay Flitch(As interior stupefied), then flitch is stupefied firm using iron wire colligation with outer steel;Then block-by-block template is followed closely on flitch with nail, Nail longitudinal pitch is less than 100mm;Box body bed die integral assembling and after brushing releasing agent, bed die is integrally overturn, template faces Under.
3)Inner support frame erection stage:Including bottom plate install after, start by longitudinal pitch 800mm, horizontal spacing 600mm, Step pitch is that 450mm sets up inner support steel pipe frame, and support body vertical rod is connected with the stupefied use fastener of the interior steel on bottom plate.Erection of frames presses pin Hand cradle related specifications are operated.To ensure the globality of inner support frame, support body longitudinally outboard face sets bridging.Set up process Set on the outside of middle support body and throw support.
4)Side form installation, fixed stage:After the completion of being set up including inner support frame, flitch is tied up by spacing 150mm with iron wire Prick support body surrounding outer steel it is stupefied on, vertical direction, check flitch fix after each surface flatness, start to fix after meeting the requirements First layer vertical formwork, with nail by 100mm stickfast is smaller than, after first layer installation, outer operating platform is set up, is fixed above The second layer, third layer template, until side form whole installation.
5)The box body integral reinforcing stage:After side form installation, the flatness of each side is checked, and support frame is entered Row checks, it is ensured that each fastener is connected firmly, rod member is smooth vertical and horizontal, stress is reliable.If there is box body size distortion or support body is local Loosen, consolidation process should be carried out to support body, finally in side form surface brush releasing agent.
6)Box body lifts the stage in place:Including the weight according to box body and operating radius selection lifting machine, vapour may be selected Car is hung, when live tower crane satisfies the requirements, it is also possible to which tower crane is lifted, and this example is computed, high area's elevator(It is two-in-one)Box The weight of body is 7.2t/, totally 4;Middle area's elevator(It is two-in-one)Box body, low area's elevator(It is two-in-one)The weight of box body is 4.8t/, totally 4;Low area's elevator(Solely set)Weight 2.7t/, totally 3 of box body, Fire lift well box body;Catch pit box The weight of body is 1.8t/, totally 2.According to operating radius(It is up to 25m), lifting capacity(It is up to 7.2t), from QY130K Truck crane, 9.6t is reached in 26m operating radius, outfit 38t, lifting capacity, meets lifting requirements;Suspension centre is set -- and each box body is all provided with 4 suspension centres are put, with the crosspoint of cross bar in the middle part of each right angle vertical rod, is connected, used with vertical rod using 4 5t bow shackle 2 steel wire ropes(A diameter of 11mm, lifting capacity 6.3t)The shackle of two longitudinal edges is connected respectively, to ensure to lift angle More than 60 degree, top hangs over the steel wire rope of suspension hook by 2 10t bow shackle by again(A diameter of 12.5mm, lifting capacity For 8t)It is connected with 2 steel wire ropes of bottom;Box body overall package is completed and after tripartite checks and accepts, and can prepare to lift by crane.Meanwhile The reinforcing bar colligation and its support system installation of raft plate.Commander's truck crane is transferred to lifting position, and lifting work point is not installed and hung The shackle of point, puts on steel wire rope.Check steel wire rope installation situation and stress center of gravity after, order command box body is slowly hung to from It after the 0.3m~0.5m of ground, should check whether box body is steady, after inspection is errorless, box body is sling vertically.Box body is hung to well It is suitable for reading, slowly transfer in well, manually coordinated using crowbar etc., it is ensured that box body does not collide reinforcing bar and protective layer pad after contraposition Block.After dress is in place, the support frame and template of tray interior are checked, prevent from loosening in hoisting process.
7)Tension rib erection stage:After being installed including box body, in the box body horizontal steel pipe of setting suitable for reading as tension rib upper end Drawknot node, steel pipe are connected with the rod member of the supporting frame the superiors with fastener.The lower end of tension rib and raft plate baseplate reinforcing bar drawknot, raft The deadweight of plate entirety framework of steel reinforcement and box body lower concrete pour the weight formed after initial set as anchoring body weight(It is much larger than The tensile strength of steel tie).The quantity of tension rib is installed according to result of calculation:
High area's elevator(It is two-in-one), totally 4, piece/of tension rib quantity 12, each each 6 of box body longitudinal edge, per root long degree 9m. Middle area's elevator(It is two-in-one), low area's elevator(It is two-in-one), it is 2, totally 4, piece/of tension rib quantity 8, each box body Each 4 of longitudinal edge, per root long degree 7m.Low area's elevator(It is independently arranged), Fire lift well, each 2,1, totally 3, tension rib number 4 pieces/are measured, each box body is per each 1 of side, per root long degree 7m.Catch pit, totally 2, piece/of tension rib quantity 2, each box body Each 1 of longitudinal edge, per root long degree 10m, 8m.
8)Concreting, monitoring stage:It is included in concreting process, particularly is starting to pour box body height In the range of concrete, box body is settled and the monitoring of displacement, frequency is is monitored once an hour, until concrete pours After building completion and reaching initial set, it can stop monitoring.As monitoring process box body occur spillage, off normal, float situations such as, should stop immediately Only the position concrete pours, and after studying and defining processing scheme and implementing, can continue concreting.Large volume pours Afterwards, it is necessary to carry out covering curing, at well, removing template is also doubled as outside Insulation, to prevent at well inside and outside concrete Excessive temperature differentials, gunnysack etc. is equally spread well is suitable for reading, strengthens insulation.
9)The form removable stage:Including generally, the curing time of mass concrete is at least 14 days, coagulation After native internal-external temperature difference is basicly stable, insulation material can be removed, equally, the template at well also can just remove.First, by well Cheat that drawknot steel pipe suitable for reading is removed, tension rib cuts off, then support frame, outer stupefied, interior stupefied, side form are removed from top to bottom, most Outer stupefied, the interior stupefied, template of bed die is removed afterwards.
Embodiment 1
Project profile:The positive supporting comprehensive development item of transportation work style tower of No. 7 lines three of certain urban track traffic is by a high building and annex group Into, 3 layers of underground, 46 layers on the ground of high building, 7 layers on the ground of podium.Overall floorage is 118461m2, wherein ground overall floorage 94295.8m2, underground overall floorage 24165.2m2, building height 229.1m.
The plank thickness of high building area Core Walls Structure periphery and elevator bottom is 3.3m, other plank thickness of high building Core Walls Structure area For totally 7 kinds of 4m, 4.95m, 6m, 7m, 8m, 9m, 10m;High building area raft floor elevation is -16.3m, bosom bottom absolute altitude for - 26.3m.High building area(Containing elevator, catch pit etc.)Absolute altitude face shares 14 kinds.
The size of elevator(Length × width × height):5600mm×2500mm×5700mm(High area's elevator, 2-in-1 1, totally 4 It is individual,),
5600mm×2500mm×3700mm(Middle area's elevator, 2-in-1 1, totally 2,), 5600mm × 2500mm × 3700mm(Low area Elevator, 2-in-1 1, totally 2,), 2700mm × 2500mm × 3700mm(Low area's elevator, is independently arranged, totally 2,), 2700mm × 2500mm×3700mm(1, Fire lift), wherein elevator most depth is 5.7m.
The size of catch pit(Length × width × height):1000mm×1500mm×6700mm.
The defects of being existed according to Super High elevator, sump high and big die plate conventional mounting arrangements, with reference to certain city rail In the supporting comprehensive development item raft plate of the positive transportation work style tower of No. 7 lines three of traffic the characteristics of elevator, catch pit, this project passes through to template The further investigation of installation system, take elevator high and big die plate and this new construction technology is installed.This construction technology passes through general Lead to template, flitch, steel pipe manufacturing into well size consistent " box body ", be used as inside " box body " using steel pipe to supportting, then box Body installation is in place, suitable for reading to be locked using steel pipe, and with round steel by steel pipe suitable for reading and raft plate bottom reinforcement bars drawknot, raft board concrete is once Pouring molding, no longer pour by several times.In casting process, steel pipe pair of the concrete to side force caused by box body by inside setting Support to arrive in it is anti-, and concrete to buoyancy caused by box bottom by drawknot round steel resist.From construction technology preparation, Farm Planning, Material preparation, personnel's preparation are installed and fixed to template processing, bed die, inner support frame is installed, side form installation and fixed, entirety add Gu, box body lifting is in place, tension rib installation, concreting and monitoring, form removable etc. are described in detail.
Application time:This engineering method is in the supporting comprehensive development item application of the positive transportation work style tower of No. 7 lines three of certain urban track traffic Between be in April, -2017 in March, 2017.
Application effect:Super High elevator high and big die plate installation engineering method in this item purpose application, accelerate construct into Degree, reduces engineering cost, achieves preferable economic effect, while ensure that construction safety, improve construction quality.With biography System construction method is compared, and has been saved fund 300,000, has been saved the duration 7 days, has had good application and promotional value, can produce good Good benefit.
The key control point of the present invention:1st, formwork reinforcement system is carried out in detail, accurately to calculate, and works out detailed special project Arrangement and method for construction;2nd, establish, perfect quality certification system, carry out detailed technical annotation in construction;3rd, material is tested in strict accordance with marching into the arena Receive, sample the programs such as reinspection, it is ensured that raw material quality;4th, the biggest lifting capacity and maximum are pressed in the selection of hoisting machinery, lifting device Operating radius determines;5th, template construct place, the necessary smooth, compacting in loop wheel machine erect-position region;6th, template and support frame are strictly by side Case is set up, reinforced;7th, hoisting process strict implement " ten do not hang " provides, special messenger commander, box body must not touch with raft slab muscle Hit;8th, after box body is in place, it is necessary to overall to be checked, reinforced;9th, the necessary stress of tension rib installation is reliable;10th, template surface must Palpus brush releasing agent, it is ensured that real outer light in concrete.11st, after concrete reaches intensity and conserved, template can be carried out and support body is torn open Remove.
Safety measure:Adhere to the policy of " Safety first, precaution crucial ", full-time accredited security official, Gong Renjin are set up in building site Before, educated by security official, periodically carry out site safety activity, further clear and definite security responsibility and security inspection task. Mechanism of WSO and safety management network are established in scene, work out perfect safety in production system, safety inspection system and safety Operational procedure, each work post, each teams and groups set up part-time security official.Perform the safe practice before construction to tell somebody what one's real intentions are, conscientiously carry out safe life Produce diary.Building site sets obvious safety warning-panel, hangs safe poster, carries out safe construction propaganda work.Construction usage Mechanical tool should inspect periodically performance condition, particularly stress instrument should be complete, to prevent because slip, skid etc. it is unexpected caused by hinder People, hinder oneself.Electromechanical equipment must special messenger's operation, have to comply with operational procedure during work.Special operation workers (electrician, welder, are hung Turner and commander's work etc.), except examining through enterprise security, also need to participate in safety operation examination by regulation, obtain supervisory department's core hair 's《Certificate of safety operation》, it is necessary to take appointment with certificate.
Environmental protective measure:Production, the unified management of house refuse:In life, Office Area, some moving refuse boxes are set, Personal management and cleaning are sent, forbids burning the waste of residual in building site.Living area is set up health and is responsible for a task until it is completed area, sets up interim rubbish heap , rubbish and tailing are cleared up in time.The regular maintenance set and management are faced in reinforcement, are removed in time after completion, are recovered smooth shape State.Job site is forbidden to huddle rubbish and excess, and interim stacking point should be set in appropriate place, personal management, concentrates and stacks, and Periodically outward transport.Dregs rubbish and fluid products are cleared, to take covering dust prevention, transporting must not scatter in way.To prevent from applying Work dirt ash fouling, in the ground watering dust prevention of hot weather construction temporary road.The unified management that placing of material, equipment are parked:Material root Marched into the arena successively according to project progress.Various placings of material classify, and stack neatly, and mark is clear, stack, support body assembly place is done Neatly cleaned to inside and outside, construction waste material reclaims in time, deals carefully with.Worker is when completing darg, cleaning construction in time Place, accomplish that the complete field of work is clear.The storage keeping of all kinds of inflammable explosive articles, acetylene and oxygen in use, two bottles of spacing be more than 5 meters with On, closing isolation during storage;Non-smoking area delimited, effective fire-proof apparatus are set.Forbid arbitrarily taking live surrounding road, hamper Hinder traffic.Equipment periodic maintenance is used in construction, and live marshalling is attractive in appearance, and plant is parked neatly.Set to large-scale Standby, accessory considers its transporting and hoisting passage, and tissue installation in place in time, must not damage the product of other unit.Onsite application Plant equipment, to be deposited by plane fixing point, in accordance with machine security code, often keep safeguarding cleaning.The mark of machinery, compile Number obvious, safety device is reliable.Sewage, waste water is forbidden disorderly to discharge:Job site keeps the coast is clear with Lin She areas, and sets rain Water open drain, live draining is set to be protected.Drinking equipment is set in Office Area, Lin She areas and job site, ensures worker The sanitation and hygiene of drinking water.Running water, altar lamp are eliminated in line with the measure of saving.Sewage, flushing water in construction and other apply Work water discharges after being discharged into interim sedimentation basin precipitation process.The sewage of machinery discharge formulates emission measure, must not trickle everywhere. Effective control noise pollution:Carrying on construction work at night must permit through units such as city's environmental protection, departments of municipal administration.And strictly limit the production of noise It is raw, noise pollution is limited in minimum degree.In order to reduce construction noise, prevent construction noise from polluting, the confidential dress of electric rotating disappears Sound device, compressor bass will operate as far as possible, and be mounted remotely from the place for closing on house as far as possible, during reasonable arrangement operation Between, reduction carries on construction work at night, and reduces noise pollution.Construction noise and dust are reduced to closing on the influence of the masses, to big machinery Take easy noise control measure.Speed limit travels vehicle on-site.Avoid producing dust, and often watering reduces the dirt of dust Dye.The placing of material and transport of live easily dusting soil will be covered.Low noise is selected as far as possible or has noise elimination device Construction machinery.The very noisy machinery of job site(Such as:Electric planer, abrasive machine etc.)The mechanical canopy of closing is set, to reduce very noisy Diffusion.Involve produce very noisy finished product, semi-finished product processing, production job, be placed on closing workplace in complete avoid because Noise caused by the processing and fabricating of job site.Prevent and treat dust pollution measure:Forbid high-altitude to shed construction rubbish, prevent dust from flying Raise.Packaging air-tight manner must be taken to carry out when removing building discarded object, cleaned after watering must be first played when cleaning place.It is right Caused airborne dust in industrial derusting, operator's band protective mask in operation.Progress occupational disease inspection regular to operating personnel.Sternly Prohibit burning discarded object of ancient India at the construction field (site), prevent flue dust and toxic gas from producing.
Constructed using this engineering method, accelerate construction speed, reduce engineering cost, achieve preferable economic effect, together When ensure that construction safety, improve construction quality that there is good application and promotional value, good benefit can be produced.
The supporting comprehensive development item high building raft plate of the positive transportation work style tower in certain city three is constructed with this this engineering method, and saving is applied 7 days between man-hour, save cost of labor 150,000, construction machinery etc. and save 100,000, material economy 50,000, directly produce economic benefit and be total to Count 300,000.
The present invention often is provided with elevator, sump, equipment installation preformed hole etc. in deep mass concrete, Typically by setting construction joint in shaft bottom or bottom hole, concrete pours at twice, first pours raft plate bottom section, then carry out well Locate model sheetinstallat, upper reinforcement colligation, then pour top concrete, template is produced during preventing one-time-concreting concrete compared with Big side force and buoyancy.This construction technology by common templates, flitch, steel pipe manufacturing into well size consistent " box body ", It is used as using steel pipe to support inside " box body ", then box body installation is in place, suitable for reading to be locked using steel pipe, with round steel by steel pipe suitable for reading With raft plate bottom reinforcement bars drawknot, the shaping of raft board concrete one-time-concreting, no longer pour by several times.In casting process, concrete pair Side force caused by box body by inside set steel pipe it is anti-to supporting to arrive in, and concrete to buoyancy caused by box bottom by drawknot Round steel is resisted.
Embodiment of above is merely to illustrate the preferred embodiment of the present invention, but the present invention is not limited to above-mentioned embodiment party Formula, in the field those of ordinary skill possessed knowledge, that is made within the spirit and principles in the present invention is any Modification, equivalent substitute and improvement etc., it is regarded as the protection domain of the application.

Claims (10)

1. Super High elevator high and big die plate installation engineering method, including two ranks of Construction in Preparatory Stage and constructing operation process Section;It is characterized in that:Described Construction in Preparatory Stage, including:1)The construction technology preparatory stage;2)The Farm Planning stage;3)Material Material prepares, personnel prepare;Described constructing operation process includes:1)Template is processed;2)Bed die installation, fix;3)Inner support frame Installation;4)Side form installation, fix;5)Integral reinforcing;6)Box body lifting is in place;7)Tension rib is installed;8)Concreting, prison Survey; 9)Form removable.
2. Super High elevator high and big die plate installation engineering method according to claim 1, it is characterised in that:Described 1) The construction technology preparatory stage:Comprise the following steps:(1)Formwork reinforcement system and steel tie design, calculate;(2)Work out template Special construction plan is installed and confided a technological secret;(3)To use raw material site acceptance, recheck;(4)It is overweight mechanical and its supporting The technical performance data and acceptance(check) file of lifting gear;(5)Design or code requirement other data for providing of needs;2) The ground preparatory stage:Including(1)Carry out levelling of the land before construction to work, the soft position for being unfavorable for mechanical movement in place, Take reinforcing, change the measure such as fill out, it is ensured that the safety of crane walking;(2)Field is carried out for the pre- laydown area of material, template processing district Ground is smooth, compacting;(3)In the venue according to the actual conditions in place, reasonable Arrangement measurement control stake and bench mark;Control point should It is laid in not by the position of construction infection, and sets up obvious mark, carry out safeguard measure, inspects periodically, checks;3)Material machine Tool, personnel's preparatory stage:Including(1)Material preparation phase and(2)Personnel's preparatory stage;Described(1)Material mechanical prepares rank Duan Wei:According to material analysis and the requirement of construction schedule, materials requirements plan is worked out, is stocked up for construction, determines goods and materials Placing of material place, foundation is provided for organization material transport;According to construction requirement, suitable hoisting machinery and suspender are selected;Draw Knot muscle uses HPB300 20mm, processes in advance in place, and termination is 180 degree crotch, straightway 10d;(2)Personnel's preparatory stage: Carpenter, scaffolder, play the work personnel arrangement preparations such as heavy industry, commander's work in place.
3. Super High elevator high and big die plate installation engineering method according to claim 1, described described 1)Template Process segment:Including the timber used in template and its support system, must not there are fragility, serious distortion and be easily deformed after making moist Timber;Wood plywood corner should scribble edge sealing adhesive, in order to protect the edge sealing adhesive of template corner, be glued in formwork at formwork edge joint Patch adhesive waterproof tape is protected by, mortar leakage prevention;Wood plywood plate face does not drill hole as far as possible, reserving hole is met, with common plank Repaired in time;Wood plywood, which is prepared, answers whole directly to use, and reduces arbitrarily saw as far as possible and cuts, causes to waste;The length of nail It should be 1.5-2 times of template thickness.
4. Super High elevator high and big die plate installation engineering method according to claim 1, described 2)Bed die is installed, is solid Determine the stage:During including bed die assembling, first spread that wooden springboard is levelling on ground, scantling determined according to the plane sizes of well, The outer stupefied lateral arrangement for being again 450mm as spacing by the use of steel pipe, by the use of steel pipe as spacing be stupefied longitudinal cloth in 600mm reinforcement Put, and by it is outer it is stupefied with it is interior it is stupefied be connected by fastener, by spacing 150mm laying flitches as interior stupefied between interior steel is stupefied, then by wood It is square stupefied firm using iron wire colligation with outer steel;Then block-by-block template is followed closely on flitch with nail, and nail longitudinal pitch is less than 100mm;Box body bed die integral assembling and after brushing releasing agent, bed die is integrally overturn, template is face-down.
5. Super High elevator high and big die plate installation engineering method according to claim 1, described 3)Inner support frame is pacified The dress stage:After being installed including bottom plate, it is that 450mm sets up inner support to start by longitudinal pitch 800mm, horizontal spacing 600mm, step pitch Steel pipe frame, support body vertical rod are connected with the stupefied use fastener of the interior steel on bottom plate;Erection of frames is operated by scaffold related specifications; To ensure the globality of inner support frame, support body longitudinally outboard face sets bridging;Set during setting up on the outside of support body and throw support.
6. Super High elevator high and big die plate installation engineering method according to claim 1, described 4)Side form is installed, is solid Determine the stage:After the completion of being set up including inner support frame, by flitch by spacing 150mm with the outer steel of iron wire colligation support body surrounding it is stupefied on, Vertical direction, the flatness on each surface after flitch fixation is checked, starts to fix first layer vertical formwork after meeting the requirements, uses nail By 100mm stickfast is smaller than, after first layer installation, outer operating platform is set up, fixes the second layer, third layer template above, directly To side form whole installation.
7. Super High elevator high and big die plate installation engineering method according to claim 1, described 5)Box body integrally adds Gu the stage:After side form installation, the flatness of each side is checked, and support frame is checked, it is ensured that each fastener connects Connect firmly, rod member is smooth vertical and horizontal, stress is reliable;If box body size distortion occur or support body locally loosening, support body should be added Gu processing, finally in side form surface brush releasing agent.
8. Super High elevator high and big die plate installation engineering method according to claim 1, described 6)Box body lifts just The position stage:Include including the weight according to box body and operating radius selection lifting machine, described lifting machine:Truck crane;It is existing When field tower crane satisfies the requirements, lifted with tower crane;Suspension centre is arranged in the support frame vertical rod of four angle points of box body, by unloading The suspension hook of button, steel wire rope and loop wheel machine connects;Box body overall package is completed and after tripartite checks and accepts, and can prepare to lift by crane;Meanwhile raft The reinforcing bar colligation and its support system installation of plate;Commander's truck crane is transferred to lifting position, and lifting work point does not install suspension centre Shackle, put on steel wire rope;After the installation situation and stress center of gravity that check steel wire rope, box body is slowly hung to liftoff by order command It after the 0.3m~0.5m of face, should check whether box body is steady, after inspection is errorless, box body is sling vertically;Box body is hung on well Mouthful, slowly transfer in well, manually coordinated using crowbar etc., it is ensured that box body does not collide reinforcing bar and protective layer cushion block after contraposition; After dress is in place, the support frame and template of tray interior are checked, prevent from loosening in hoisting process.
9. Super High elevator high and big die plate installation engineering method according to claim 1, described 7)Tension rib is installed Stage:After being installed including box body, in the box body horizontal steel pipe of setting suitable for reading as tension rib upper end drawknot node, steel pipe and supporting frame The rod member of the superiors is connected with fastener;The lower end of tension rib and raft plate baseplate reinforcing bar drawknot, the deadweight of raft plate entirety framework of steel reinforcement And box body lower concrete pours the weight formed after initial set as anchoring body weight, much larger than the tensile strength of steel tie; The quantity of tension rib is installed according to result of calculation.
10. Super High elevator high and big die plate installation engineering method according to claim 1, described 8)Concrete pours Build, the monitoring stage:It is included in concreting process, particularly is starting to pour the concrete in box body altitude range, Box body is settled and the monitoring of displacement, frequency until concreting completion and reach initial set to be monitored once an hour Afterwards, can stop monitoring;Including monitoring process box body occur spillage, off normal floating situation, the position concrete should be stopped immediately Pour, study and define processing scheme and implement after, concreting can be continued;After large volume pours, it is necessary to covered Maintenance, at well, removing template is also doubled as outside Insulation, to prevent that temperature difference between inside and outside concrete is excessive at well, in well It is suitable for reading equally to spread gunnysack etc., strengthen insulation;Described 9)The form removable stage:Including generally, mass concrete Curing time at least be 14 days, after temperature difference between inside and outside concrete is basicly stable, insulation material can be removed, equally, at well Template also can just remove;First, well drawknot steel pipe suitable for reading is removed, tension rib is cut off, then by support frame, outer stupefied, interior Stupefied, side form is removed from top to bottom, finally removes outer stupefied, the interior stupefied, template of bed die.
CN201710814510.6A 2017-09-11 2017-09-11 Super High elevator high and big die plate installation engineering method Active CN107503365B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710814510.6A CN107503365B (en) 2017-09-11 2017-09-11 Super High elevator high and big die plate installation engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710814510.6A CN107503365B (en) 2017-09-11 2017-09-11 Super High elevator high and big die plate installation engineering method

Publications (2)

Publication Number Publication Date
CN107503365A true CN107503365A (en) 2017-12-22
CN107503365B CN107503365B (en) 2019-07-30

Family

ID=60696378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710814510.6A Active CN107503365B (en) 2017-09-11 2017-09-11 Super High elevator high and big die plate installation engineering method

Country Status (1)

Country Link
CN (1) CN107503365B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952082A (en) * 2018-08-03 2018-12-07 徽都建设有限公司 A kind of high rise elevator well construction method
CN110424710A (en) * 2019-07-31 2019-11-08 云南省建设投资控股集团有限公司 Elevator tool-type all steel operation platform construction
CN110453689A (en) * 2019-09-03 2019-11-15 中国建筑一局(集团)有限公司 Circular foundation pit lining wall formwork construction system and construction method
CN110565847A (en) * 2019-09-18 2019-12-13 上海建工一建集团有限公司 construction method for super high-rise fire elevator shaft wall and reinforced concrete wall

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101113642A (en) * 2007-07-19 2008-01-30 河北建设集团有限公司 Formworkfor elevator well of high rising building and construction method thereof
US20140096473A1 (en) * 2012-10-08 2014-04-10 KWOLM Industries, LLC Unitary form for poured foundation pad and method
CN105756341A (en) * 2016-04-06 2016-07-13 中国十七冶集团有限公司 Installation process of elevator shaft formwork
CN106801482A (en) * 2017-02-13 2017-06-06 山东送变电工程公司 A kind of current conversion station fire wall construction technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101113642A (en) * 2007-07-19 2008-01-30 河北建设集团有限公司 Formworkfor elevator well of high rising building and construction method thereof
US20140096473A1 (en) * 2012-10-08 2014-04-10 KWOLM Industries, LLC Unitary form for poured foundation pad and method
CN105756341A (en) * 2016-04-06 2016-07-13 中国十七冶集团有限公司 Installation process of elevator shaft formwork
CN106801482A (en) * 2017-02-13 2017-06-06 山东送变电工程公司 A kind of current conversion station fire wall construction technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑少瑛,周东明,王东升: "《建筑工程施工技术与管理》", 30 June 2010, 徐州:中国矿业大学出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952082A (en) * 2018-08-03 2018-12-07 徽都建设有限公司 A kind of high rise elevator well construction method
CN110424710A (en) * 2019-07-31 2019-11-08 云南省建设投资控股集团有限公司 Elevator tool-type all steel operation platform construction
CN110453689A (en) * 2019-09-03 2019-11-15 中国建筑一局(集团)有限公司 Circular foundation pit lining wall formwork construction system and construction method
CN110565847A (en) * 2019-09-18 2019-12-13 上海建工一建集团有限公司 construction method for super high-rise fire elevator shaft wall and reinforced concrete wall
CN110565847B (en) * 2019-09-18 2024-03-29 上海建工一建集团有限公司 Construction method for super high-rise fire elevator well wall body and reinforced concrete wall

Also Published As

Publication number Publication date
CN107503365B (en) 2019-07-30

Similar Documents

Publication Publication Date Title
CN107503365A (en) Super High elevator high and big die plate installation engineering method
Fitchen Building construction before mechanization
CN106150001B (en) A kind of fabricated assembly overall stair construction method
CN107882321A (en) Diameter Silo slding form operation engineering method
CN106988525A (en) A kind of skyscraper aluminum alloy mould plate construction method
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN104790675B (en) Reinforced concrete block masonry structure assemblage construction method
CN205576955U (en) Raft foundation's reinforced structure is displaced into to strip footing
CN111005557A (en) Construction method of bare concrete external wall formwork
CN102251670A (en) Construction process for self-heat-insulation system of autoclaved aerated concrete block wall
CN108457243A (en) A kind of construction method of assembly concrete wave wall
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN107143141A (en) External wall of high-rise building warming plate construction
CN106088657B (en) Reinforcing structure of empty bucket wall and construction method thereof
CN106978907A (en) Construction method for secondary structure of high and large arc-shaped wall
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN105155836B (en) Aluminum alloy mould plate for building and its using method
CN113957802A (en) Construction method for long-span upper beam of single-tower asymmetric cable-stayed bridge high tower
CN109594477A (en) A kind of big bent cap strutting system construction technology of only pier
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
CN206538685U (en) Twin shaft pier and middle binder truss move integrally system
CN115030064A (en) Construction method for rebuilding and moving beam of high-speed rail elevated station
CN115256615B (en) Highway precast box Liang Zhineng shower maintenance standard construction system
CN114961047A (en) Novel construction method of composite concrete shear wall structure
CN113601699A (en) Prefabrication method of 40m simply supported box girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant