CN107420104A - The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter - Google Patents

The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter Download PDF

Info

Publication number
CN107420104A
CN107420104A CN201710434548.0A CN201710434548A CN107420104A CN 107420104 A CN107420104 A CN 107420104A CN 201710434548 A CN201710434548 A CN 201710434548A CN 107420104 A CN107420104 A CN 107420104A
Authority
CN
China
Prior art keywords
areas
hole
construction
drilling
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710434548.0A
Other languages
Chinese (zh)
Inventor
苏春生
林羽
梁朋刚
何十美
汤振亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
5th Engineering Co Ltd of MBEC
Original Assignee
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dianchi College of Yunnan University, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Dianchi College of Yunnan University
Priority to CN201710434548.0A priority Critical patent/CN107420104A/en
Publication of CN107420104A publication Critical patent/CN107420104A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter, following construction procedure is specifically included:Preparation of construction, surveying setting-out;Barrel vault advanced support is constructed in hole;Horizontal prebored hole;Static blasting is excavated.The beneficial effects of the invention are as follows:The present invention can be effectively increased country rock static blasting free face, rock crusher efficiency high;It can effectively avoid blasting vibration, reduce country rock disturbance, it is good to earth's surface Deformation control effect so that fabric structure and safe to use;Dust and noise pollution in effective reduction hole, it is green;The effective shortening construction periods improve construction speed;It is effective to reduce out break.

Description

The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter
Technical field
The present invention relates to shallow soft stratum technical field, is the horizontal prebored hole of shallow tunnel super-large diameter specifically Static blasting excavation construction method.
Background technology
The general buried depth in urban track traffic tunnel is shallower and accident environment is complicated, when Tunnel Passing ground is built(Structure)Build thing When, scientific and reasonable excavation method is used to reduce country rock disturbance, control earth's surface deformation, to ensuring that overlying is built(Structure)Build thing structure Safety and safety for tunnel engineering are particularly critical.
New Austrian Tunneling Method be it is theoretical using rock mass mechanics, using safeguard and using country rock self-bearing ability as basic point, using anchor pole and Gunite concrete is main supporting means, timely carries out supporting, controls the deformation and relaxation of country rock, country rock is turned into prop The part of system, and constructed by the measurement to country rock and supporting, monitoring to instruct constructing tunnel and underground engineering design Method and principle.
New Austrian Tunneling Method is on the premise of using country rock in itself possessed carrying efficiency, using millisecond blasting and photoface exploision Technology, full-face excavation is carried out, and to form inside and outside combined type two layers of lining cutting to build the barrel in tunnel, i.e., to spray coagulation Soil, anchor pole, bar-mat reinforcement, bracing members etc. are outer layer support form, and referred to as first flexible support, tying up to tunnel cutting must stand afterwards The support work carried out.Because the crustal stress contained in massif produces reallocation due to excavating cavitation, tunnel space leans on Cavity effect and be maintained stabilization, that is to say, that carry the mainly country rock body of crustal stress in itself, and use first spray anchor soft Property supporting effect, be the country rock body bearing capacity of itself is played to greatest extent, second of lining cutting be mainly peace Full deposit and decoration effect.
The content of the invention
It is an object of the invention to provide the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter, energy Enough it is effectively increased country rock static blasting free face, rock crusher efficiency high;Blasting vibration can be effectively avoided, country rock is reduced and disturbs It is dynamic, it is good to earth's surface Deformation control effect so that fabric structure and safe to use;It is effective to reduce dust and noise dirt in hole Dye, it is green;The effective shortening construction periods improve construction speed.
The present invention is achieved through the following technical solutions:The present embodiment does further optimization on the basis of above-described embodiment, As shown in figure 1, the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter, specifically includes following construction step Suddenly:
Step S1:Preparation of construction, surveying setting-out;
Step S2:Barrel vault advanced support is constructed in hole;
Step S3:Horizontal prebored hole;Specifically include following construction procedure:
Step S31:Determine a drilling depth;
Step S32:Carry out the control of hole position axis;
Step S33:From large aperture professional standards rig pore-forming, core records are carried out;
Step S4:Static blasting is excavated;Specifically include following construction procedure:
Step S41:Small free face top heading excavates;The small sky top heading that faces includes upper left base tunnel and upper right base tunnel;It is described small Free face top heading excavate, in particular to:
Upper left base tunnel and upper right base tunnel are carried out first, using advance borehole as upper left base tunnel and upper right base tunnel static blasting free face Use, top heading static state blast hole eye of constructing, powder charge, explosion and crushing operation are carried out after the completion of construction;
Step S42:Big free face top heading excavates;Specifically refer to:
When upper left base tunnel and the supporting of upper right excavation with guide pit are completed, carrying out big free face top heading by two side-wall pilot tunnel construction opens Dig, arrangement drilling, powder charge is carried out after the completion of drilling;Explosion and crushing operation are carried out after the completion of powder charge;
Step S43:In lower excavation with guide pit;Specifically refer to:
After the completion of top heading construction, in lower base tunnel construction take vertical drilling, static presplitting;Arrangement drilling, after the completion of drilling Carry out powder charge;Explosion and crushing operation are carried out after the completion of powder charge.
Operation principle:The present invention uses New Austrian Tunneling Method principle, gives full play to bearing capacity of the wall rock, reduces country rock disturbance damage, Effective deformation controlling for rock surrounding gateways;It is effective to increase static blasting free face using super-large diameter horizontal drilling, greatly improve country rock Crushing efficiency, and provide geologic basis for subsequent construction;Using static blasting, using expanding attrition crushing caused by chemical agent Country rock, effectively avoid blasting vibration small to the disturbance damage of country rock, surrouding rock deformation and subsidence value;Matched somebody with somebody using static blasting Mechanical Crushing, finishing are closed, tunnel excavation profile is smoother, excavation face is smooth, effective to reduce country rock out break;Using being superimposed in hole Pipe canopy leading pre-supporting and double -side approach partial excavation, super deficient support system rigidity is improved, effectively become space-time effect using country rock Should, deformation controlling for rock surrounding gateways, reduce ground settlement.
Further, in order to preferably realize the present invention, the step S2 specifically includes following construction procedure:
Step S21:Drill hole of drilling machine;The drilling uses first low speed low pressure, and drilling speed and blast are gradually adjusted according to geological condition, bores Hole speed remains a constant speed;
Step S22:Drilling finishes, borehole cleaning and jacking steel pipe;
Step S23:Slip casting in hole;
Step S24:After pipe roof construction, preliminary bracing is carried out;Pipe canopy end is attached with first branch bow member.
Further, in order to preferably realize the present invention, the upper left base tunnel includes A areas, B areas, C areas, D areas and E areas; The advance borehole position is that A areas, B areas, C areas and D areas are from the close-by examples to those far off vertically arranged centered on A areas, the E areas It is configured along the edge of upper left base tunnel;According to said structure, the order of powder charge, the explosion of upper left base tunnel in the step S41 It is followed successively by A areas, B areas, C areas, D areas, E areas;Powder charge, explosion of the order of powder charge, the explosion of the upper right base tunnel with upper left base tunnel Sequence consensus.
Further, in order to preferably realize the present invention, the big free face top heading includes I areas, II areas and III Area, the center line of the II areas, I areas along big free face top heading from the close-by examples to those far off set III areas along big free face top heading edge It is configured;According to said structure, powder charge, the order of explosion are followed successively by II areas, I areas, III areas in the step S42.
Further, in order to preferably realize the present invention, upper left base tunnel and upper right base tunnel in the step S41 are broken to be made Industry, in particular to:Substep subregion presplitting is taken to crush, broken order is followed from bottom to top, by free face direction charge structure behaviour Make;The first step medicament reaction time is 15min, and second step, the 4th step, the 5th step medicament reaction time are 20min, the 3rd step medicine The agent reaction time is in 30-40min.
Further, in order to preferably realize the present invention, big free face top heading crushing operation, tool in the step S42 Body refers to:According to distribution subregion powder charge presplitting, inwardly crushed successively by free face, the medicament reaction time 15-25min with It is interior.
Further, in order to preferably realize the present invention, in the step S43 in lower base tunnel crushing operation, be specifically Refer to:Every drilling depth subregion concentrated charge presplitting is taken, the medicament reaction time determines according to hole count, powder charge number.
Further, in order to preferably realize the present invention, after the step S4, in addition to following construction procedure:
Step S5:Machine is broken and dregs is transported outward;
Step S6:Preliminary bracing and gib;
Step S7:Two lining constructions.
Further, in order to preferably realize the present invention, monitoring measurement is carried out in step S2- step S6 work progress; Specifically refer to:
Lay earth's surface and building deformation monitoring point in advance, the deformation monitoring of country rock should bury in time according to related specifications requirement in hole If measuring point, and carry out field monitoring by assigned frequency;
Monitoring and measurement data, feedback guidance design and construction are made full use of, the data abnormal to deflection, rate of deformation will be in time Analyzing and processing.
The present invention compared with prior art, has advantages below and beneficial effect:
(1)The present invention can be effectively increased country rock static blasting free face, rock crusher efficiency high;
(2)The present invention can effectively avoid blasting vibration, reduce country rock disturbance, good to earth's surface Deformation control effect so as to build Build thing structure and safe to use;
(3)Dust and noise pollution in effective reduction hole of the invention, it is green;
(4)The effective shortening construction periods of the invention improve construction speed;
(5)Effective reduction out break of the invention.
Brief description of the drawings
Fig. 1 is the construction process figure of the present invention;
Fig. 2 is the positive facade subregion schematic diagram of upper left base tunnel in the present invention;
Fig. 3 is the positive facade subregion schematic diagram of big free face top heading in the present invention.
Embodiment
Embodiments of the invention are described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning to end Same or similar label represents same or similar element or the element with same or like function.Below with reference to attached The embodiment of figure description is exemplary, it is intended to for explaining the present invention, and is not considered as limiting the invention.
In the description of the invention, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", " on ", " under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outer ", " up time The orientation or position relationship of the instruction such as pin ", " counterclockwise " are based on orientation shown in the drawings or position relationship, are for only for ease of Description is of the invention to be described with simplified, rather than the device or element of instruction or hint meaning must be with specific orientation, Yi Te Fixed azimuth configuration and operation, therefore be not considered as limiting the invention.
In the present invention, unless otherwise clearly defined and limited, term " installation ", " connected ", " connection ", " fixation " etc. Term should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;It can be machine Tool connects or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary, can be two members Connection inside part.For the ordinary skill in the art, above-mentioned term can be understood in this hair as the case may be Concrete meaning in bright.
The present invention is described in further detail with reference to embodiment, but the implementation of the present invention is not limited to this.
Embodiment 1:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, shallow tunnel super-large diameter is horizontal pre- Drill static blasting excavation construction method, specifically includes following construction procedure:
Step S1:Preparation of construction, surveying setting-out.
Step S2:Barrel vault advanced support is constructed in hole.
Step S3:Horizontal prebored hole.Specifically include following construction procedure:
Step S31:According to actual situations of construction, a drilling depth is determined.According to actual situations of construction, it is determined that once drilling is deep Degree, ensure safe construction.
Step S32:Carry out the control of hole position axis.When face pulls out of hole, raised up drilling rod according to drilling depth, while in hole Every a segment distance set locating ring, with prevent from creeping into it is too deep cause drilling drop.
Step S33:From large aperture professional standards rig pore-forming, core records are carried out.Bored from large aperture professional standards Machine pore-forming, increase static blasting free face, strengthen static blasting effect, while foundation is provided for advance geologic prediction.
Step S4:Static blasting is excavated.Tunnel is excavated using two side-wall pilot tunnel static blasting, and first choice is according to country rock physics Mechanics parameter, geologic feature, excavated section etc. design static blasting parameter.Including aperture, pitch-row, hole depth, the broken order of powder charge Deng then carrying out bore operation according to double -side approach branch piecemeal excavating sequences, finally carry out powder charge and crushing operation.
The step S4, specifically includes following construction procedure:
Step S41:Small free face top heading excavates.The small sky top heading that faces includes upper left base tunnel and upper right base tunnel.It is described small Free face top heading excavate, in particular to:
Upper left base tunnel and upper right base tunnel are carried out first, using advance borehole as upper left base tunnel and upper right base tunnel static blasting free face Use, top heading static state blast hole eye of constructing, powder charge, explosion and crushing operation are carried out after the completion of construction.
Step S42:Big free face top heading excavates.Specifically refer to:
When upper left base tunnel and the supporting of upper right excavation with guide pit are completed, carrying out big free face top heading by two side-wall pilot tunnel construction opens Dig, arrangement drilling, powder charge is carried out after the completion of drilling.The order of the powder charge is to be entered by two lateral middle parts of big free face top heading Luggage medicine.Explosion and crushing operation are carried out after the completion of powder charge.
Step S43:In lower excavation with guide pit.Specifically refer to:
After the completion of top heading construction, in lower base tunnel construction take vertical drilling, static presplitting.Arrangement drilling, after the completion of drilling Carry out powder charge.Explosion and crushing operation are carried out after the completion of powder charge.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 2:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, the step S2 specifically include it is following Construction procedure:
Step S21:Drill hole of drilling machine.The drilling uses first low speed low pressure, and drilling speed and blast are gradually adjusted according to geological condition, bores Hole speed remains a constant speed.
Step S22:Drilling finishes, borehole cleaning and jacking steel pipe.
Step S23:Slip casting in hole.
Step S24:After pipe roof construction, preliminary bracing is carried out.Pipe canopy end is attached with first branch bow member.
It should be noted that:The step S2 specifically includes following construction procedure:
The drilling direction of limb and drilling rod outside strict control conduit, prevents conduit from stretching into the construction of next endless tube canopy.
After rig spuds in, first low speed low pressure, after pore-forming reaches certain depth, gradually adjusted according to geological condition drilling speed and Blast.Penetration rate should remain a constant speed, and when particularly drill bit runs into folder mud burning into sand layer, answer keyhole speed, avoid pressing from both sides Bore phenomenon.
Drilling finishes and after borehole cleaning, timely jacking steel pipe.Steel pipe presses design requirement processing and fabricating, in-site installation shaping.Steel Pipe spreading is connected using 95mm inner sleeves, while notices that same section joint staggers in installation process.
Using interval continuous grouting, place is discontented with slip casting because of grout cures, places every hole grout leaking for slip casting.There is grout leaking When, to string hole close, treat that slurries placing finishes, not outward spillage when, injected hole is closed, to grout leaking hole carry out two Secondary reinforcement slip casting, ensure that slip casting is closely knit.
After the completion of pipe roof construction, the construction such as preliminary bracing of following up in time, pipe canopy end and first branch bow member etc. are effectively connected formation Stable pressure-bearing is overall, ensures supporting intensity.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 3:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in Fig. 2 the upper left base tunnel includes A areas, B Area, C areas, D areas and E areas.The advance borehole position be A areas, B areas, C areas and D areas centered on A areas by near and Remote vertically arranged, edge of the E areas along upper left base tunnel is configured.According to said structure, upper left base tunnel in the step S41 Powder charge, the order of explosion be followed successively by A areas, B areas, C areas, D areas, E areas;The order of powder charge, the explosion of the upper right base tunnel and a left side The powder charge of top heading, blasting sequence are consistent.
It should be noted that:As shown in figure 1, it is described exceed the time limit before drilling upper left base tunnel central part.The A areas are around super Preceding drilling.The B areas are distributed up and down along A areas, and the C areas are distributed along B areas or so, and the D areas are distributed in one of C areas away from B areas Side.The E areas are on the top in B areas, C areas and D areas.
The order of powder charge, the explosion of upper left base tunnel in the step S41, enters luggage by the A areas of super full borehole circumference first Medicine, the powder charge in B areas is carried out again, the order of B areas powder charge to the side away from advance borehole close to drilling from carrying out powder charge, in B C area's powder charges are carried out after the completion of area's powder charge, C areas sequence of loading principle to the side away from advance borehole close to drilling from entering luggage Medicine, D area's powder charges are then carried out, powder charge is carried out by the direction that C areas are laterally away from close to the one of C areas, finally carries out E area's powder charges, it is excellent The E areas of choosing mainly include two artillery salvo holes.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 4:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 3, the big free face top heading includes I areas, II areas and III areas, the center line of the II areas, I areas along big free face top heading from the close-by examples to those far off set III areas along facing greatly Empty face top heading edge is configured.According to said structure, powder charge, the order of explosion are followed successively by II areas, I in the step S42 Area, III areas.
It should be noted that:As shown in figure 1, the big free face top heading is divided into two parts by center line, this two Distribution includes I areas and II areas, and the II areas are positioned close to the side of center line, and the I areas are arranged on II areas away from center The side of line, the III areas are arranged on the top in I areas and II areas.
III areas mainly include two artillery salvo holes.Big free face top heading powder charge, the order of explosion are by big free face top heading Center line carries out powder charge to big free face top heading both sides, finally carries out the powder charge in III areas.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 5:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, the upper left in the step S41 is led Hole and upper right base tunnel crushing operation, in particular to:Substep subregion presplitting is taken to crush, broken order is followed from bottom to top, by facing The charge structure operation of empty face direction.The first step medicament reaction time is 15min, when second step, the 4th step, the 5th step medicament react Between be 20min, the 3rd step medicament reaction time is in 30-40min.
In the step S42 big free face top heading crushing operation, in particular to:According to distribution subregion powder charge presplitting, by Free face inwardly crushes successively, and the medicament reaction time is within 15-25min.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 6:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, being led under in the step S43 Cheat crushing operation, in particular to:Every drilling depth subregion concentrated charge presplitting is taken, the medicament reaction time is according to hole count, powder charge number It is determined that.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 7:
According to embodiment 3- embodiments 5, during construction and excavation, when carrying out bore operation, bore diameter and crushing effect There is direct relation, drilling is too small, is unfavorable for medicament and gives full play to effect.Drill excessive, easy punching.Remaining water and ash slag in drilling Clean using high-pressure blast purging, clean five native rock ballasts are answered on side of eating dishes without rice or wine.
When carrying out charging:Follow from bottom to top, by the principle operation of free face direction powder charge.
Horizontal powder charge:First with the height long fibered paper more smaller than bore diameter it is packed enter medicament, by an operation circulation institute The powder stick quantity needed, be placed in Peng and pour into clean water and be completely soaked, 50 seconds or so powder sticks are sufficiently humidified so as to, completely not bubbling when, Take out powder stick since bottom hole one by one to load and disclose tightly, closely knit is loaded into aperture, that is, concentrates immersion, full penetration, fill one by one Enter, consolidate respectively.
Vertical powder charge:Poured into after medicament is stirred with vessel or directly in hole, aperture periphery there must not be finger stone accumulation, prevent Only punching is hurted sb.'s feelings.
Each filling group is getting it filled plus water, is mixing and stirring, should keep synchronous in pouring process, can allow medicament in each hole Maximum swelling pressure is basic to be kept for the same period occur, and is advantageous to the broken of rock.
In pouring process, the medicament to chemically react is had begun to(Performance starts to steam scalds one's hand with temperature)Do not allow to fill Enter in hole.
Dose is mixed every time no more than the workload that can actually complete, and water is added to filling end, this mistake from medicament The no more than ten minutes time of journey, otherwise easy punching.
When carrying out crushing operation:
Upper left base tunnel and upper right base tunnel take substep subregion presplitting to crush, and broken order is followed from bottom to top, by free face direction Charge structure operates.The first step medicament reaction time is adjusted to 15min, and second step, the 4th step, the 5th step medicament reaction time adjust Whole is 20min, and the 3rd step medicament reaction time forbade the people that stands with the 30-40min powder charge aperture directions that are advisable.
After the completion of left and right top heading excavates, bracket groove or so just forms big free face, according to distribution subregion powder charge presplitting, by facing Empty face is inwardly crushed successively, and the medicament reaction time is advisable with 15-25min.
In the broken construction of lower base tunnel, take every drilling depth subregion concentrated charge presplitting, the medicament reaction time is according to hole count, powder charge Number etc. determines.
Broken constructing operation personnel should be by the way of group, and reasonable distribution often circulates responsibility hole count.
After rock extruding cracking, medicament sustained response can be supported into crack plus water, effect is more preferable.
After determining medicament reaction completely, from being applicable section requirement and with the digging machine of hydraulic crushing head, carry out Mechanical Crushing, Staff on duty is arranged during construction, forbids cross-operation, prevents rock failure from hurting sb.'s feelings.
Embodiment 8:
According to embodiment 5- embodiments 6, when being controlled when carrying out medicament reaction, it should be noted that it is following some:
(1), medicament reaction time control mode agent/inhibitor two ways is typically inspired using temperature control and addition;
(2), summer construction when, typically using add inhibitor by the way of, being put into of inhibitor is soaked medicament and mixed in water;Add Measure the 0.5%-0.6% for mixing water;Temperature is higher, and addition is fewer, on the contrary then few.
(3), winter temperature it is relatively low, the medicament reaction time can accordingly extend, and be made troubles to construction, and general solution is Addition inspires agent and coolant-temperature gage is mixed and stirred in raising;Inspire agent to add excessively, medicament expansive force can be reduced;Mixing water is according to actual appropriate Improve, not more than 40 °.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 9:
The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter, it is characterised in that:Specifically include following apply Work step is rapid:
Step S1:Preparation of construction, surveying setting-out.
Step S2:Barrel vault advanced support is constructed in hole.Specifically include following construction procedure:
Step S21:Drill hole of drilling machine.The drilling uses first low speed low pressure, and drilling speed and blast are gradually adjusted according to geological condition, bores Hole speed remains a constant speed.
Step S22:Drilling finishes, borehole cleaning and jacking steel pipe.
Step S23:Slip casting in hole.
Step S24:After pipe roof construction, preliminary bracing is carried out.Pipe canopy end is attached with first branch bow member.
Step S3:Horizontal prebored hole.Specifically include following construction procedure:
Step S31:According to actual situations of construction, a drilling depth is determined.
Step S32:Carry out the control of hole position axis.Inspecting hole tenesmus, off normal are prevented using addition locating ring.
Step S33:From large aperture professional standards rig pore-forming, core records are carried out.
Step S4:Static blasting is excavated.Specifically include following construction procedure:
Step S41:Small free face top heading excavates.The small sky top heading that faces includes upper left base tunnel and upper right base tunnel.
The small free face top heading excavate, in particular to:
Upper left base tunnel and upper right base tunnel are carried out first, using advance borehole as upper left base tunnel and upper right base tunnel static blasting free face Use, top heading static state blast hole eye of constructing, powder charge, explosion and crushing operation are carried out after the completion of construction.
The upper left base tunnel includes A areas, B areas, C areas, D areas and E areas.It is described exceed the time limit before drilling at the center of upper left base tunnel Portion.The advance borehole position is that A areas, B areas, C areas and D areas are from the close-by examples to those far off vertically arranged centered on A areas, the E Edge of the area along upper left base tunnel is configured.According to said structure, the powder charge, the order of explosion be followed successively by A areas, B areas, C areas, D areas, E areas.The upper right base tunnel powder charge, explosion and upper left base tunnel powder charge, explosion it is consistent.
Step S42:Big free face top heading excavates.The big free face top heading includes I areas, II areas and III areas, institute Stating the center line of II areas, I areas along big free face top heading from the close-by examples to those far off sets III areas to be set along big free face top heading edge Put.According to said structure, powder charge, the order of explosion are followed successively by II areas, I areas, III areas in the step S42.
Big free face top heading excavates.Specifically refer to:
When upper left base tunnel and the supporting of upper right excavation with guide pit are completed, carrying out big free face top heading by two side-wall pilot tunnel construction opens Dig, arrangement drilling, powder charge is carried out after the completion of drilling.The order of the powder charge is to be entered by two lateral middle parts of big free face top heading Luggage medicine.Explosion and crushing operation are carried out after the completion of powder charge.
Step S43:In lower excavation with guide pit.Specifically refer to:
After the completion of top heading construction, in lower base tunnel construction take vertical drilling, static presplitting.Arrangement drilling, after the completion of drilling Carry out powder charge.Explosion and crushing operation are carried out after the completion of powder charge.
Step S5:Machine is broken and dregs is transported outward.
Step S6:Preliminary bracing and gib;.
Step S7:Two lining constructions.
Monitoring measurement is carried out in step S2- step S6 work progress;Specifically refer to:
Lay earth's surface and building deformation monitoring point in advance, the deformation monitoring of country rock should bury in time according to related specifications requirement in hole If measuring point, and carry out field monitoring by assigned frequency.
Monitoring and measurement data, feedback guidance design and construction are made full use of, the data abnormal to deflection, rate of deformation will Analyzing and processing in time.
It is described above, be only presently preferred embodiments of the present invention, any formal limitation not done to the present invention, it is every according to Any simply modification, the equivalent variations made according to the technical spirit of the present invention to above example, each fall within the protection of the present invention Within the scope of.

Claims (9)

1. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter, it is characterised in that:Specifically include following Construction procedure:
Step S1:Preparation of construction, surveying setting-out;
Step S2:Barrel vault advanced support is constructed in hole;
Step S3:Horizontal prebored hole;Specifically include following construction procedure:
Step S31:Determine a drilling depth;
Step S32:Carry out the control of hole position axis;
Step S33:From large aperture professional standards rig pore-forming, core records are carried out;
Step S4:Static blasting is excavated;Specifically include following construction procedure:
Step S41:Small free face top heading excavates;The small sky top heading that faces includes upper left base tunnel and upper right base tunnel;
The small free face top heading excavate, in particular to:Carry out upper left base tunnel and upper right base tunnel first, using advance borehole as Upper left base tunnel and upper right base tunnel static blasting free face use, top heading static state blast hole eye of constructing, carried out after the completion of construction powder charge, Explosion and crushing operation;
Step S42:Big free face top heading excavates;Specifically refer to:When upper left base tunnel and upper right excavation with guide pit supporting completion, by double Side heading method construction carries out big free face top heading and excavated, and arrangement drilling, powder charge is carried out after the completion of drilling;After the completion of powder charge Carry out explosion and crushing operation;
Step S43:In lower excavation with guide pit;Specifically refer to:
After the completion of top heading construction, in lower base tunnel construction take vertical drilling, static presplitting;Arrangement drilling, after the completion of drilling Carry out powder charge;Explosion and crushing operation are carried out after the completion of powder charge.
2. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:The step S2 specifically includes following construction procedure:
Step S21:Drill hole of drilling machine;The drilling uses first low speed low pressure, and drilling speed and blast are gradually adjusted according to geological condition, bores Hole speed remains a constant speed;
Step S22:Drilling finishes, borehole cleaning and jacking steel pipe;
Step S23:Slip casting in hole;
Step S24:After pipe roof construction, preliminary bracing is carried out;Pipe canopy end is attached with first branch bow member.
3. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:The upper left base tunnel includes A areas, B areas, C areas, D areas and E areas;The advance borehole position is A areas, B areas, C Area and D areas are from the close-by examples to those far off vertically arranged centered on A areas, and edge of the E areas along upper left base tunnel is configured;According to upper State structure, the order of powder charge, the explosion of upper left base tunnel is followed successively by A areas, B areas, C areas, D areas, E areas in the step S41;The right side The order of powder charge, the explosion of top heading is consistent with the powder charge of upper left base tunnel, blasting sequence.
4. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:The big free face top heading includes I areas, II areas and III areas, and the II areas, I areas are along big free face top heading Heart line from the close-by examples to those far off sets III areas to be configured along big free face top heading edge;According to said structure, in the step S42 Powder charge, the order of explosion are followed successively by II areas, I areas, III areas.
5. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:Upper left base tunnel and upper right base tunnel crushing operation in the step S41, in particular to:Substep subregion presplitting is taken to crush, Broken order follows from bottom to top, operated by free face direction charge structure;The first step medicament reaction time is 15min, second Step, the 4th step, the 5th step medicament reaction time are 20min, and the 3rd step medicament reaction time is in 30-40min.
6. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:In the step S42 big free face top heading crushing operation, in particular to:According to distribution subregion powder charge presplitting, by facing sky Face inwardly crushes successively, and the medicament reaction time is within 15-25min.
7. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 1, its feature It is:In in the step S43 lower base tunnel crushing operation, in particular to:Take every drilling depth subregion concentrated charge presplitting, medicament Reaction time determines according to hole count, powder charge number.
8. according to the horizontal prebored hole static blasting excavation construction side of any one of the claim 1-7 shallow tunnel super-large diameters Method, it is characterised in that:After the step S4, in addition to following construction procedure:
Step S5:Machine is broken and dregs is transported outward;
Step S6:Preliminary bracing and gib;
Step S7:Two lining constructions.
9. the horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter according to claim 8, its feature It is:Monitoring measurement is carried out in step S2- step S6 work progress;Specifically refer to:
Lay earth's surface and building deformation monitoring point in advance, the deformation monitoring of country rock should bury in time according to related specifications requirement in hole If measuring point, and carry out field monitoring by assigned frequency;
Monitoring and measurement data, feedback guidance design and construction are made full use of, the data abnormal to deflection, rate of deformation will be in time Analyzing and processing.
CN201710434548.0A 2017-06-09 2017-06-09 The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter Pending CN107420104A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710434548.0A CN107420104A (en) 2017-06-09 2017-06-09 The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710434548.0A CN107420104A (en) 2017-06-09 2017-06-09 The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter

Publications (1)

Publication Number Publication Date
CN107420104A true CN107420104A (en) 2017-12-01

Family

ID=60428548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710434548.0A Pending CN107420104A (en) 2017-06-09 2017-06-09 The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter

Country Status (1)

Country Link
CN (1) CN107420104A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915695A (en) * 2018-07-09 2018-11-30 河南理工大学 A kind of projecting coal bed stope drift active workings static state fracturing speedy drivage method
CN110700843A (en) * 2019-11-20 2020-01-17 中铁二十局集团有限公司 Tunnel three-step synchronous excavation construction method based on partition blasting
CN111366046A (en) * 2020-04-09 2020-07-03 浙江省大成建设集团有限公司 Blasting vibration control method for excavation of adjacent existing tunnel
CN113203328A (en) * 2021-05-28 2021-08-03 江汉大学 Dynamic and static blasting combined forming method for tunnel excavation profile surface
CN113818888A (en) * 2021-10-22 2021-12-21 四川省交通勘察设计研究院有限公司 Hard rock multi-arch tunnel blasting process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536251A (en) * 2012-02-17 2012-07-04 中国建筑第六工程局有限公司 Adjacent construction excavating method for upper and lower dual-layer tunnel
CN103234403A (en) * 2013-04-24 2013-08-07 中国科学院武汉岩土力学研究所 Static blasting construction method for highway tunnel
CN104564085A (en) * 2014-12-23 2015-04-29 中铁十一局集团第五工程有限公司 Comprehensive construction method for excavating tunnel with super large cross-section under urban super shallow-buried condition
CN105804758A (en) * 2016-04-22 2016-07-27 中国电建集团铁路建设有限公司 Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel
CN106440984A (en) * 2016-12-20 2017-02-22 大连大学 Blasthole explosive pressing pipes for city shallow buried rock stratum tunnel static blasting construction and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536251A (en) * 2012-02-17 2012-07-04 中国建筑第六工程局有限公司 Adjacent construction excavating method for upper and lower dual-layer tunnel
CN103234403A (en) * 2013-04-24 2013-08-07 中国科学院武汉岩土力学研究所 Static blasting construction method for highway tunnel
CN104564085A (en) * 2014-12-23 2015-04-29 中铁十一局集团第五工程有限公司 Comprehensive construction method for excavating tunnel with super large cross-section under urban super shallow-buried condition
CN105804758A (en) * 2016-04-22 2016-07-27 中国电建集团铁路建设有限公司 Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel
CN106440984A (en) * 2016-12-20 2017-02-22 大连大学 Blasthole explosive pressing pipes for city shallow buried rock stratum tunnel static blasting construction and construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915695A (en) * 2018-07-09 2018-11-30 河南理工大学 A kind of projecting coal bed stope drift active workings static state fracturing speedy drivage method
CN110700843A (en) * 2019-11-20 2020-01-17 中铁二十局集团有限公司 Tunnel three-step synchronous excavation construction method based on partition blasting
CN111366046A (en) * 2020-04-09 2020-07-03 浙江省大成建设集团有限公司 Blasting vibration control method for excavation of adjacent existing tunnel
CN111366046B (en) * 2020-04-09 2022-07-08 浙江省建投交通基础建设集团有限公司 Blasting vibration control method for excavation of adjacent existing tunnel
CN113203328A (en) * 2021-05-28 2021-08-03 江汉大学 Dynamic and static blasting combined forming method for tunnel excavation profile surface
CN113203328B (en) * 2021-05-28 2022-08-26 江汉大学 Dynamic and static blasting combined forming method for tunnel excavation contour surface
CN113818888A (en) * 2021-10-22 2021-12-21 四川省交通勘察设计研究院有限公司 Hard rock multi-arch tunnel blasting process
CN113818888B (en) * 2021-10-22 2024-03-26 四川省交通勘察设计研究院有限公司 Hard rock multi-arch tunnel blasting process

Similar Documents

Publication Publication Date Title
CN107420104A (en) The horizontal prebored hole static blasting excavation construction method of shallow tunnel super-large diameter
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN101349064B (en) Construction method of hydroelectric power station surge chamber vertical shaft under soft rock geological condition
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN108533272A (en) A kind of minimum clear-distance tunnel goes out cavity construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN101929340B (en) Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN110318770A (en) A kind of hazy start tunneling method of vcehicular tunnel
CN105781573B (en) The two-tube canopy pipe-following drilling construction method of vcehicular tunnel bilayer sleeve reinforcement is worn under railway
CN109372517A (en) One kind is suitable for wearing water supplying pipe construction method under upper soft lower hard compound stratum tunnel
CN106194195A (en) Collapsible Loess District large cross-section tunnel three step is without remaining core soil in advance construction method
CN103306687A (en) Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN110374633A (en) The Portal Section Construction method of Tunnel Passing loose media
CN101122131A (en) Foundation pit supporting pile using pipe casting pile embedding in rock
JP6342126B2 (en) Ground injection method
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN109853399B (en) Large-section inclined tunnel type arch support structure for arch bridge and construction method thereof
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN108798702A (en) A kind of method for protecting support of big cross section large-deformation tunnel in soft rock
CN107642041A (en) The hollow clump of piles anchorage of super-large diameter
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN110230497A (en) A kind of positive barrel double -side approach construction method in threaded list road
CN110424460A (en) A kind of tunnel open excavation construction technology
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171201