CN107299773A - 承重墙洞口加固施工方法 - Google Patents

承重墙洞口加固施工方法 Download PDF

Info

Publication number
CN107299773A
CN107299773A CN201710707381.0A CN201710707381A CN107299773A CN 107299773 A CN107299773 A CN 107299773A CN 201710707381 A CN201710707381 A CN 201710707381A CN 107299773 A CN107299773 A CN 107299773A
Authority
CN
China
Prior art keywords
reinforcing steel
presstressed reinforcing
brick wall
arched girder
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710707381.0A
Other languages
English (en)
Other versions
CN107299773B (zh
Inventor
叶香竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Zhonglin Engineering Construction Co ltd
Qiaozhi Construction Co ltd
Fuzhou University
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710707381.0A priority Critical patent/CN107299773B/zh
Publication of CN107299773A publication Critical patent/CN107299773A/zh
Application granted granted Critical
Publication of CN107299773B publication Critical patent/CN107299773B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0222Replacing or adding wall ties
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0244Increasing or restoring the load-bearing capacity of building construction elements of beams at places of holes, e.g. drilled in them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0274Temporary shoring of wall opening

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

本发明公开了一种承重墙洞口加固施工方法,其特征是施工步骤包括:(1)设置楼板支撑,将承重墙荷载卸掉;(2)承重墙设置凹槽使拱形梁预应力筋穿过凹槽通至构造柱,绑扎拱形梁钢筋,支设拱形梁模板及拱形梁支墩模板,拱形梁侧模板设置混凝土浇筑孔;(3)砖墙预应力筋固定完毕后浇筑混凝土;(4)根据张拉单元将支撑筋焊接在砖墙预应力筋;(5)泵送商品混凝土通过混凝土浇筑孔进入并浇筑;(6)进行拱形梁预应力筋的张拉;张拉完毕后将拱形梁预应力筋通过锚具固定在构造柱;(7)砖墙预应力筋张拉采用竖向张拉,竖向张拉完毕后用拉筋焊接固定。

Description

承重墙洞口加固施工方法
技术领域
本发明涉及一种承重墙洞口加固施工方法,适用于建筑领域。
背景技术
承重墙进行开洞会造成受力上失衡,一方面由于洞口上方的荷载需要承载,如果结构不合理重则会造成砖墙坍塌,轻则在洞口周围出现裂缝。传统采用水平混凝土过梁形式在工程实践中常常出现洞口边部出现八字裂缝或者竖向裂缝。另一方面会由于应力重分布在承重墙洞口上方的砖墙出现高应力区,如果没有技术措施承重墙洞口上方的砖墙会出现不规则裂缝。另外,承重墙洞口边部的砖墙会出现局部承压,如果不引起高度的重视会酿成安全事故。
发明内容
本发明是提供一种承重墙洞口加固施工方法,解决传统加固方法安全性能不好的问题。
由于拱形梁结构在受力时比较合理,能将拱形梁上方的荷载进行合理传递,故本发明在承重墙洞口顶部设置拱形梁,拱形梁高度为350~600mm,拱形梁宽度与砖墙宽度相同,拱形梁两端设置拱形梁支墩,拱形梁支墩高度为350~600mm,拱形梁下部设置拱形梁预应力筋,拱形梁预应力筋直径为18~25mm,拱形梁预应力筋穿过拱形梁支墩一直通到构造柱,拱形梁预应力筋预应力张拉后通过锚具固定在构造柱,拱形梁上部设置拱形梁非预应力筋,拱形梁非预应力筋直径为18~25mm,拱形梁非预应力筋伸入拱形梁支墩。拱形梁支墩部位砖墙两侧设置加固钢板,加固钢板厚度为12~15mm,加固钢板对拱形梁支墩下面局部砖墙进行加固,加固钢板加固范围延伸至洞口以下0.5~0.7m,加固钢板通过对拉螺栓进行固定,对拉螺栓直径为16~18mm,对拉螺栓设置间距为350~450mm。加固钢板的设置有效避免了拱形梁支墩部位的局部承压破坏。
由于拱形梁上方的砖墙形成应力集中容易出现开裂,必须对拱形梁上方的砖墙进行加固。根据计算机仿真分析,拱形梁上方会形成弧形应力集中区,根据应力分布特点,拱形梁上方设置承重墙预应力筋,承重墙预应力筋直径为12~16mm,砖墙预应力筋初布置时为水平,砖墙预应力筋在水平时的竖向间距为200~250mm,砖墙预应力筋在水平时的位置尽可能地设置在砖墙灰缝位置,砖墙预应力筋经预应力张拉后形成折线。根据应力特点布置六排砖墙预应力筋或者四排砖墙预应力筋,第一排砖墙预应力筋和第二排砖墙预应力筋齐平,第三排砖墙预应力筋和第四排砖墙预应力筋相对于第二排砖墙预应力筋缩进,缩进长度为40~60mm,第五排砖墙预应力筋和第六排砖墙预应力筋相对于第四排砖墙预应力筋缩进,缩进长度为40~60mm;第一排砖墙预应力筋离拱形梁竖向距离为50~70mm。砖墙预应力筋两端设置墙孔,墙孔宽度、长度、高度与承重墙宽度相同,墙孔内放置钢垫板,砖墙预应力筋与钢垫板进行焊接,在墙孔内填塞强度为C30或者以上的混凝土。砖墙预应力筋划分为若干个张拉单元,每个张拉单元长度为1.5~2m,张拉单元两端焊接支撑筋,砖墙预应力筋张拉完毕后用拉筋固定。
施工步骤包括:
(1)设置楼板支撑,将承重墙荷载卸掉。
(2)用切割机开设承重墙洞口,承重墙设置凹槽使拱形梁预应力筋穿过凹槽通至构造柱,绑扎拱形梁钢筋,支设拱形梁模板及拱形梁支墩模板,拱形梁侧模板设置混凝土浇筑孔,混凝土浇筑孔直径为80~120mm,混凝土浇筑孔设置间距为2~3m。
(3)用切割机开设砖墙预应力筋两端的墙孔,墙孔内放置钢垫板,将砖墙预应力筋焊接在钢垫板,砖墙预应力筋固定完毕后浇筑混凝土。
(4)根据张拉单元将支撑筋焊接在砖墙预应力筋。
(5)拱形梁混凝土和拱形梁支墩混凝土采用泵送商品混凝土,塌落度为8~10mm,泵送商品混凝土通过混凝土浇筑孔进入并浇筑。
(6)进行拱形梁预应力筋的张拉,张拉工艺如下:将拱形梁预应力筋初张拉至10%的控制张拉应力,持荷3min建立初始应力,再张拉至控制张拉应力,持荷5min建立预应力。张拉完毕后将拱形梁预应力筋通过锚具固定在构造柱。
(7)待砖墙预应力筋两端的墙孔混凝土达到设计强度90%以上后进行砖墙预应力筋张拉,砖墙预应力筋张拉采用竖向张拉,竖向张拉完毕后用拉筋焊接固定。
本发明力学性能好,操作安全可靠。
附图说明
图1为承重墙洞口加固结构示意图。
附图标记:1、拱形梁,2、拱形梁预应力筋,3、拱形梁非预应力筋,4、拱形梁支墩,5、锚具,6、加固钢板,7、对拉螺栓,8、构造柱,9、砖墙预应力筋,10、钢垫板,11混凝土,12、支撑筋,13、拉筋。
具体实施方式
以下结合附图对本实施例进行详细描述。
本实施例在承重墙洞口顶部设置拱形梁1,拱形梁1高度为400mm,拱形梁1宽度与砖墙宽度相同,拱形梁1两端设置拱形梁支墩4,拱形梁支墩4高度为400mm,拱形梁1下部设置拱形梁预应力筋2,拱形梁预应力筋2直径为22mm,拱形梁预应力筋2穿过拱形梁支墩4一直通到构造柱8,拱形梁预应力筋2预应力张拉后通过锚具5固定在构造柱8,拱形梁1上部设置拱形梁非预应力筋3,拱形梁非预应力筋3直径为22mm,拱形梁非预应力筋3伸入拱形梁支墩4。拱形梁支墩4部位砖墙两侧设置加固钢板6,加固钢板6厚度为14mm,加固钢板6对拱形梁支墩4下面局部砖墙进行加固,加固钢板6加固范围延伸至洞口以下0.6m,加固钢板6通过对拉螺栓7进行固定,对拉螺栓7直径为16mm,对拉螺栓7设置间距为400mm。
拱形梁1上方设置承重墙预应力筋,承重墙预应力筋直径为12~16mm,砖墙预应力筋9初布置时为水平,砖墙预应力筋9在水平时的竖向间距为240mm,砖墙预应力筋9在水平时的位置尽可能地设置在砖墙灰缝位置,砖墙预应力筋9经预应力张拉后形成折线。根据应力特点布置六排砖墙预应力筋9,第一排砖墙预应力筋9和第二排砖墙预应力筋9齐平,第三排砖墙预应力筋9和第四排砖墙预应力筋9相对于第二排砖墙预应力筋9缩进,缩进长度为50mm,第五排砖墙预应力筋9和第六排砖墙预应力筋9相对于第四排砖墙预应力筋9缩进,缩进长度为50mm;第一排砖墙预应力筋9离拱形梁1竖向距离为60mm。砖墙预应力筋9两端设置墙孔,墙孔宽度、长度、高度与承重墙宽度相同,墙孔内放置钢垫板10,砖墙预应力筋9与钢垫板10进行焊接,在墙孔内填塞强度为C30或者以上的混凝土11。砖墙预应力筋9划分为若干个张拉单元,每个张拉单元长度为1.8m,张拉单元两端焊接支撑筋12,砖墙预应力筋9张拉完毕后用拉筋13固定。
施工步骤包括:
(1)设置楼板支撑,将承重墙荷载卸掉。
(2)用切割机开设承重墙洞口,承重墙设置凹槽使拱形梁预应力筋2穿过凹槽通至构造柱8,绑扎拱形梁1钢筋,支设拱形梁1模板及拱形梁支墩4模板,拱形梁1侧模板设置混凝土浇筑孔,混凝土浇筑孔直径为100mm,混凝土浇筑孔设置间距为2.5m。
(3)用切割机开设砖墙预应力筋9两端的墙孔,墙孔内放置钢垫板10,将砖墙预应力筋9焊接在钢垫板10,砖墙预应力筋9固定完毕后浇筑混凝土11。
(4)根据张拉单元将支撑筋12焊接在砖墙预应力筋9。
(5)拱形梁1混凝土和拱形梁支墩4混凝土采用泵送商品混凝土,塌落度为8~10mm,泵送商品混凝土通过混凝土浇筑孔进入并浇筑。
(6)进行拱形梁预应力筋2的张拉,张拉工艺如下:将拱形梁预应力筋2初张拉至10%的控制张拉应力,持荷3min建立初始应力,再张拉至控制张拉应力,持荷5min建立预应力。张拉完毕后将拱形梁预应力筋2通过锚具5固定在构造柱8。
(7)待砖墙预应力筋9两端的墙孔混凝土11达到设计强度90%以上后进行砖墙预应力筋9张拉,砖墙预应力筋9张拉采用竖向张拉,竖向张拉完毕后用拉筋13焊接固定。

Claims (2)

1.一种承重墙洞口加固施工方法,其特征是施工步骤包括:
(1)设置楼板支撑,将承重墙荷载卸掉;
(2)用切割机开设承重墙洞口,承重墙设置凹槽使拱形梁预应力筋穿过凹槽通至构造柱,绑扎拱形梁钢筋,支设拱形梁模板及拱形梁支墩模板,拱形梁侧模板设置混凝土浇筑孔,混凝土浇筑孔直径为80~120mm,混凝土浇筑孔设置间距为2~3m;
(3)用切割机开设砖墙预应力筋两端的墙孔,墙孔内放置钢垫板,将砖墙预应力筋焊接在钢垫板,砖墙预应力筋固定完毕后浇筑混凝土;
(4)根据张拉单元将支撑筋焊接在砖墙预应力筋;
(5)拱形梁混凝土和拱形梁支墩混凝土采用泵送商品混凝土,塌落度为8~10mm,泵送商品混凝土通过混凝土浇筑孔进入并浇筑;
(6)进行拱形梁预应力筋的张拉,张拉工艺如下:将拱形梁预应力筋初张拉至10%的控制张拉应力,持荷3min建立初始应力,再张拉至控制张拉应力,持荷5min建立预应力;张拉完毕后将拱形梁预应力筋通过锚具固定在构造柱;
(7)待砖墙预应力筋两端的墙孔混凝土达到设计强度90%以上后进行砖墙预应力筋张拉,砖墙预应力筋张拉采用竖向张拉,竖向张拉完毕后用拉筋焊接固定。
2.根据权利要求1所述的承重墙洞口加固施工方法,其特征是根据应力特点布置六排砖墙预应力筋或者四排砖墙预应力筋,第一排砖墙预应力筋和第二排砖墙预应力筋齐平,第三排砖墙预应力筋和第四排砖墙预应力筋相对于第二排砖墙预应力筋缩进,缩进长度为40~60mm,第五排砖墙预应力筋和第六排砖墙预应力筋相对于第四排砖墙预应力筋缩进,缩进长度为40~60mm;第一排砖墙预应力筋离拱形梁竖向距离为50~70mm。
CN201710707381.0A 2016-03-02 2016-03-02 承重墙洞口加固施工方法 Expired - Fee Related CN107299773B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710707381.0A CN107299773B (zh) 2016-03-02 2016-03-02 承重墙洞口加固施工方法

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610181708.0A CN105672690B (zh) 2016-03-02 2016-03-02 承重墙洞口加固方法
CN201710707381.0A CN107299773B (zh) 2016-03-02 2016-03-02 承重墙洞口加固施工方法

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610181708.0A Division CN105672690B (zh) 2016-03-02 2016-03-02 承重墙洞口加固方法

Publications (2)

Publication Number Publication Date
CN107299773A true CN107299773A (zh) 2017-10-27
CN107299773B CN107299773B (zh) 2019-08-30

Family

ID=56224368

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610181708.0A Expired - Fee Related CN105672690B (zh) 2016-03-02 2016-03-02 承重墙洞口加固方法
CN201710707381.0A Expired - Fee Related CN107299773B (zh) 2016-03-02 2016-03-02 承重墙洞口加固施工方法

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610181708.0A Expired - Fee Related CN105672690B (zh) 2016-03-02 2016-03-02 承重墙洞口加固方法

Country Status (1)

Country Link
CN (2) CN105672690B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999422A (zh) * 2018-08-15 2018-12-14 庐江荣睿建设工程有限公司 一种承重墙体开设门窗洞口的方法
CN110331795A (zh) * 2019-07-25 2019-10-15 石家庄市住宅开发建设公司 拱券结构逆作法施工方法

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867931B (zh) * 2018-07-02 2019-12-13 中国建筑第八工程局有限公司 剪力墙建筑门洞结构
CN109653533A (zh) * 2019-02-13 2019-04-19 程勇俊 一种混凝土楼板加固施工方法
CN115653346B (zh) * 2022-12-26 2023-03-10 上海建工一建集团有限公司 一种既有房屋墙梁置换结构及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6505450B1 (en) * 1997-10-29 2003-01-14 Reginald A. J. Locke Masonry reinforcement system
CN201206337Y (zh) * 2008-03-14 2009-03-11 中建三局建设工程股份有限公司 预应力混凝土结构
CN101446138A (zh) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 改建工程墙体外挂饰材防渗漏施工方法
CN201531124U (zh) * 2009-09-24 2010-07-21 马人乐 分级体外预应力加固砌体结构
CN202509790U (zh) * 2012-01-12 2012-10-31 中国水电顾问集团华东勘测设计研究院 构筑物水池的加固结构
CN103352581A (zh) * 2013-07-09 2013-10-16 北京筑福国际工程技术有限责任公司 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100693137B1 (ko) * 2004-06-15 2007-03-13 김상남 프리스트레스를 이용한 건축물 보강구조
CN102434008B (zh) * 2010-09-29 2015-02-25 贵阳铝镁设计研究院有限公司 一种现浇砼板上开洞后的洞口加固方法
CN102877656B (zh) * 2012-08-10 2016-08-03 南京工业大学 钢结构加固砌体墙的方法
CN103741842A (zh) * 2014-01-22 2014-04-23 天津大学建筑设计研究院 一种轻型装配式剪力墙结构
CN204212447U (zh) * 2014-10-17 2015-03-18 中国十七冶集团有限公司 门窗混凝土拱形过梁加固施工装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6505450B1 (en) * 1997-10-29 2003-01-14 Reginald A. J. Locke Masonry reinforcement system
CN201206337Y (zh) * 2008-03-14 2009-03-11 中建三局建设工程股份有限公司 预应力混凝土结构
CN101446138A (zh) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 改建工程墙体外挂饰材防渗漏施工方法
CN201531124U (zh) * 2009-09-24 2010-07-21 马人乐 分级体外预应力加固砌体结构
CN202509790U (zh) * 2012-01-12 2012-10-31 中国水电顾问集团华东勘测设计研究院 构筑物水池的加固结构
CN103352581A (zh) * 2013-07-09 2013-10-16 北京筑福国际工程技术有限责任公司 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999422A (zh) * 2018-08-15 2018-12-14 庐江荣睿建设工程有限公司 一种承重墙体开设门窗洞口的方法
CN110331795A (zh) * 2019-07-25 2019-10-15 石家庄市住宅开发建设公司 拱券结构逆作法施工方法

Also Published As

Publication number Publication date
CN105672690A (zh) 2016-06-15
CN107299773B (zh) 2019-08-30
CN105672690B (zh) 2017-11-28

Similar Documents

Publication Publication Date Title
CN105672690B (zh) 承重墙洞口加固方法
CN101886466B (zh) 捣固式焦炉煤塔模板支撑结构的施工方法
CN103615053B (zh) 现浇钢筋混凝土结构后浇带施工工法
CN101748681B (zh) 50m折线配筋混凝土T梁先张法施工工艺
CN108005387B (zh) 一种装配式墙板与短肢剪力墙现浇主体同步施工方法
CN101818570B (zh) 高层建筑梁式结构转换层的施工方法
CN110259184A (zh) 基于托梁拔柱组合支撑顶升***的拔除柱施工方法
CN108915725A (zh) 一种双侧壁导坑隧道小模板衬砌施工方法
CN103603359A (zh) 一种深基坑斜撑支护结构拆除方法
CN104863063A (zh) 基于pvc复合模板的桥梁水下结构免围堰快速加固方法
CN104060760B (zh) 高层建筑结构转换层混凝土超大梁分层施工方法
CN110939051A (zh) 一种地铁隐盖梁施工方法
CN107268634A (zh) 深基坑腰梁施工定型模板体系
CN108330902B (zh) 高桩码头现浇下横梁施工方法
CN111074950B (zh) 地下室外墙预封闭超前止水后浇带及施工方法
CN110106889A (zh) 一种深基坑灌注护坡桩加锚索支护施工工法
CN205976167U (zh) 基于可拆卸式定位控制件现浇楼板结构
CN205348761U (zh) 地下室无梁顶板上安装无基础升降机的加固结构
CN103938871A (zh) 一种采用钢筋混凝土环梁节点的钢管混凝土柱有粘结预应力框架梁结构的施工方法
CN105625199B (zh) 一种变截面连续箱梁底板崩裂区处理方法及修补结构
CN209837009U (zh) 一种用于架空输电线路灌注桩的钢筋笼支撑构件
CN105370027B (zh) 高层悬空结构中整体提升支撑钢平台结构的施工方法
CN209244242U (zh) 一种型钢悬挑脚手架半工具式u型螺栓固定装置
CN206769199U (zh) 后穿式后张法竖向预应力现浇混凝土柱结构
CN108755701A (zh) 深基坑的支撑结构的施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210107

Address after: 251800 Liangwang village, Yanghu Township, Yangxin County, Binzhou City, Shandong Province

Patentee after: Yangxin Longfeng metal products Co.,Ltd.

Address before: Room 302, building 11, Jingshan group, Wenzhou City, Zhejiang Province 325000

Patentee before: Ye Xiangzhu

TR01 Transfer of patent right

Effective date of registration: 20210602

Address after: No. 58, Yingbin Avenue, Xiadu community, Pingnan County, Guigang City, Guangxi Zhuang Autonomous Region, 537300

Patentee after: Li Weizhi

Address before: 251800 Liangwang village, Yanghu Township, Yangxin County, Binzhou City, Shandong Province

Patentee before: Yangxin Longfeng metal products Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221019

Address after: 353500 No. 275, Gongnong East Road, Songyuan street, Songxi County, Nanping City, Fujian Province

Patentee after: Fujian Zhonglin Engineering Construction Co.,Ltd.

Patentee after: Qiaozhi Construction Co.,Ltd.

Patentee after: FUZHOU University

Address before: No. 58, Yingbin Avenue, Xiadu community, Pingnan County, Guigang City, Guangxi Zhuang Autonomous Region, 537300

Patentee before: Li Weizhi

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190830

CF01 Termination of patent right due to non-payment of annual fee