The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic Download PDFInfo
- Publication number
- CN107191195A CN107191195A CN201710609421.8A CN201710609421A CN107191195A CN 107191195 A CN107191195 A CN 107191195A CN 201710609421 A CN201710609421 A CN 201710609421A CN 107191195 A CN107191195 A CN 107191195A
- Authority
- CN
- China
- Prior art keywords
- platform
- maintenance
- lifting
- top layer
- vcehicular tunnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012423 maintenance Methods 0.000 title claims abstract description 157
- 230000002787 reinforcement Effects 0.000 title claims abstract description 51
- 229910000831 Steel Inorganic materials 0.000 claims description 13
- 239000010959 steel Substances 0.000 claims description 13
- 238000005096 rolling process Methods 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 abstract description 3
- 230000007423 decrease Effects 0.000 description 9
- 230000000694 effects Effects 0.000 description 6
- 230000008439 repair process Effects 0.000 description 6
- 230000033001 locomotion Effects 0.000 description 5
- 238000004140 cleaning Methods 0.000 description 3
- 230000005611 electricity Effects 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/12—Devices for removing or hauling away excavated material or spoil; Working or loading platforms
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The invention provides the vcehicular tunnel maintenance and reinforcement platform and device of a kind of uninterrupted traffic, it is related to tunnel and builds field.The vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic includes detachable support frame, top layer operating desk, top layer lifts maintenance platform, first lifting column and support base, top layer operating desk is installed on the top of detachable support frame, top layer lifting maintenance platform is located at the top of top layer operating desk, one end of first lifting column is slidably connected with top layer operating desk, the bottom surface that the other end of first lifting column lifts maintenance platform with top layer is fixedly connected, the first control unit is embedded with first lifting column, first control unit includes the first signal receiving module, first processing module and the first lifting drive module, detachable support frame is installed on the top of the support base, support base is formed with automobile passage.The position of the replaceable maintenance of operating personnel and the work posture of maintenance, more easily can be repaired to tunnel, and automobile can pass through from the automobile passage of support base formation, and traffic normal pass is not influenceed.
Description
Technical field
Field is built the present invention relates to tunnel, in particular to a kind of vcehicular tunnel maintenance and reinforcement of uninterrupted traffic
Platform and device.
Background technology
Tunnel (tunnel), that is, build and supply the passage of running car in underground, typically also double as the passages such as pipeline and pedestrian.
The main building thing in tunnel is typically made up of barrel, lining cutting and portal, the location easily caved at hole, is also added and is built open cut tunnel.Tunnel
The auxiliary construction in road has waterproof and pumping equipment, ventilation and lighting installation, traffic signals facility and emergency service etc..
Tunnel is during long-term operation, situations such as Lining cracks, percolating water easily occur, it is therefore desirable to attendant couple
Tunnel progress is irregular to be checked and carries out maintenance and reinforcement, in the prior art, when Lining cracks or percolating water etc. occurs in tunnel
, it is necessary to which attendant station is repaired on scaffold to tunnel during situation, during maintenance, maintenance personal wants adjustment
Operating position is very inconvenient with operation posture, and carry or take operation apparatus and equipment it is also very inconvenient.
The content of the invention
It is an object of the invention to provide one kind influence traffic tunnel maintenance platform and device, it is intended to improve above-mentioned ask
Topic.
The present invention provides a kind of technical scheme:
In a first aspect, the embodiments of the invention provide a kind of vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic, including
Detachable support frame, top layer operating desk, top layer lifting maintenance platform, the first lifting column and support base, the top layer behaviour
The top of the detachable support frame is installed on as platform, the top layer lifting maintenance platform is located at the top layer operating desk
Top, one end of first lifting column is slidably connected with the top layer operating desk, the other end of first lifting column and institute
The bottom surface for stating top layer lifting maintenance platform is fixedly connected, and the first control unit, described first are embedded with first lifting column
Control unit includes the first signal receiving module, first processing module and the first lifting drive module, first processing
Module is electrically connected with first signal receiving module, the first lifting drive module respectively, and the first processing module is used
Instruct, and driven according to the lifting instruction control first lifting in receiving lifting by first signal receiving module
Whole first lifting column of module drive performs rise or the operation declined, and the detachable support frame is installed on described
The top of support base, the support base is formed with automobile passage.
Further, the top layer lifting maintenance platform is provided with mechanical arm, and the mechanical arm is lifted with the top layer and tieed up
Equating platform is rotated by Universal connector and connected, and one end of the remote top layer lifting maintenance platform of the mechanical arm is provided with fluting
Machine.
Further, the top layer lifting maintenance platform is also equipped with three hydraulic top pushing devices, two of which hydraulic top
Pushing device is located at the both sides that the top layer lifts maintenance platform, and another hydraulic top pushing device is located at the two of which hydraulic top
Between pushing device.
Further, the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic also includes middle level operating desk, the second people
Row movable type step, the middle level operating desk is installed on the detachable support frame, and the middle level operating desk is located at institute
State the lower section that top layer lifts maintenance platform, the two ends of the portable step of the second people row take respectively in the middle level operating desk,
The top layer operating desk.
Further, the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic also includes the second lifting column and main dimension
Side scaling platform is repaiied, the main maintenance side scaling platform is located at the top of the placement platform, and the main maintenance side scaling platform
Positioned at the side of the detachable support frame, one end of second lifting column is slided with the main maintenance side scaling platform
Connection, the other end of second lifting column is fixedly connected with the bottom surface of the main maintenance side scaling platform, second lifting
Be embedded with the second control unit in post, second control unit include secondary signal receiving module, Second processing module with
And second lifting drive module, the Second processing module respectively with the secondary signal receiving module, it is described second lifting drive
Dynamic model block is electrically connected, and the Second processing module is used to receive lifting instruction, and foundation by the secondary signal receiving module
Whole second lifting column of lifting instruction control the second lifting drive module driving performs rise or the behaviour declined
Make.
Further, the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic also includes main maintenance hoistable platform and electricity
Dynamic lifting device, the main maintenance hoistable platform is located at the side of the detachable support frame, the electric lifting device
Including the first spool, steel cable, four rolling and motor, what the detachable support frame was oppositely arranged including two
First column and the second column, first column, second column are provided with guide rail, roller described in two of which point
The bottom of a guide rail is not embedded at, and two other roller is embedded at the top of a guide rail respectively, is located at
Two rollers of the same guide rail are connected by the steel rope gearing, and the motor is used to drive first spool
Rotation, the main maintenance hoistable platform is connected to by the steel cable of the first spool folding and unfolding.
Further, the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic also includes multiple expansion links, Mei Gesuo
The one end for stating expansion link is connected with the top layer operating desk, and the other end of each expansion link and top layer lifting maintenance are flat
Platform is connected.
Further, the top layer operating desk, the edge of top layer lifting maintenance platform are provided with guardrail.
Further, top layer operation edge of table is provided with the second spool, the second motor and by described the
The lifting rope of two spool folding and unfoldings, one end of the remote top layer operating desk of the lifting rope is provided with hook, the second driving electricity
Machine is used to drive second spool to operate.
Second aspect, the embodiment of the present invention additionally provides a kind of vcehicular tunnel maintenance and reinforcement device of uninterrupted traffic, bag
Include the vcehicular tunnel maintenance and reinforcement platform of driving equipment and above-mentioned uninterrupted traffic, the driving equipment with it is described detachable
The side of support frame is detachably connected, and the driving equipment is not on the bearing of trend of the automobile passage, the support
The bottom of seat sets at least three wheels, and the driving equipment is used for the vcehicular tunnel maintenance and reinforcement for driving the uninterrupted traffic
Platform moves ahead or stopped.
The vcehicular tunnel maintenance and reinforcement platform for the uninterrupted traffic that the present invention is provided and the beneficial effect of device are:Operator
Member can stand and the top in tunnel is repaired in top layer lifting maintenance platform in operation, when needing to move the position of maintenance activity
When putting, because one end and the top layer operating desk of the first lifting column are slidably connected, therefore top layer lifting maintenance platform can be grasped in top layer
Make to move on platform, furthermore, when needing to adjust the height of maintenance activity, operating personnel, which only need to input to the first lifting column, to be risen
Instruction declines instruction, so as to control the first lifting column to rise or fall, and rises so as to drive top layer to lift maintenance platform
Or decline, by movement or rising and decline that maintenance platform is lifted to top layer.Operating personnel can repair and replacement position
And the work posture of maintenance, so as to more easily be repaired to tunnel, the operating experience sense of operating personnel is improved, and
When operating personnel is carrying out maintenance activity to tunnel, automobile can pass through from the automobile passage of support base formation, from without shadow
Ring traffic normal pass.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be attached to what is used required in embodiment
Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, therefore is not construed as pair
The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this
A little accompanying drawings obtain other related accompanying drawings.
The vcehicular tunnel dimension for the uninterrupted traffic that Fig. 1 provides for the first embodiment of first embodiment of the embodiment of the present invention
Repair the structural representation for reinforcing platform;
Fig. 2 connects for the circuit of the control unit of first embodiment first of first embodiment provided in an embodiment of the present invention
Block diagram;
Fig. 3 connects for the circuit of the control unit of first embodiment second of first embodiment provided in an embodiment of the present invention
Block diagram;
The vcehicular tunnel dimension for the uninterrupted traffic that Fig. 4 provides for the second embodiment of first embodiment of the embodiment of the present invention
Repair the structural representation for reinforcing platform;
Fig. 5 is the second embodiment of the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic provided in an embodiment of the present invention
Structural representation when in tunnel.
Icon:The detachable support frames of 101-;102- top layer operating desks;103- top layers lift maintenance platform;104-
One lifting column;The signal receiving modules of 105- first;106- first processing modules;107- first lifts drive module;108- middle levels
Operating desk;The second people of 110- row movable type step;The lifting columns of 111- second;The main maintenance side scaling platforms of 112-;113- second believes
Number receiving module;114- Second processing modules;115- second lifts drive module;The main maintenance hoistable platforms of 116-;117- first
Spool;118- steel cables;119- rollers;The columns of 120- first;The columns of 121- second;122- wheels;123- expansion links;124- is protected
Column;The spools of 125- second;126- lifting ropes;127- is linked up with;128- security protection waistbands;129- support bases;130- mechanical arms;131-
Hydraulic top pushing device;132- groovers;133- automobile passages.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention
In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is
A part of embodiment of the present invention, rather than whole embodiments.The present invention implementation being generally described and illustrated herein in the accompanying drawings
The component of example can be arranged and designed with a variety of configurations.
Therefore, the detailed description of embodiments of the invention below to providing in the accompanying drawings is not intended to limit claimed
The scope of the present invention, but be merely representative of the present invention selected embodiment.Based on the embodiment in the present invention, this area is common
The every other embodiment that technical staff is obtained under the premise of creative work is not made, belongs to the model that the present invention is protected
Enclose.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi
It is defined in individual accompanying drawing, then it further need not be defined and explained in subsequent accompanying drawing.
In the description of the invention, it is to be understood that term " " center ", " on ", " under ", "left", "right", " vertical ",
The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, or should
Orientation or position relationship that invention product is usually put when using, or the orientation or position that those skilled in the art usually understand
Relation is put, the description present invention is for only for ease of and simplifies description, rather than indicate or imply that the equipment or element of meaning are necessary
With specific orientation, with specific azimuth configuration and operation, therefore it is not considered as limiting the invention.
In addition, term " first ", " second ", " the 3rd " etc. are only used for distinguishing description, and it is not intended that indicating or implying
Relative importance.
In the description of the invention, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, term " setting ",
" installation ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or one
Connect body;Can be mechanical connection or electrical connection;Can be joined directly together, can also be indirect by intermediary
It is connected, can is the connection of two element internals.For the ordinary skill in the art, on being understood with concrete condition
State the concrete meaning of term in the present invention.
First embodiment
Referring to Fig. 1, the embodiments of the invention provide a kind of vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic, including
Detachable support frame 101, top layer operating desk 102, the top layer lifting lifting column 104 of maintenance platform 103 and first.This implementation
In example, " the long wide * of * are high " size of detachable support frame 101 is respectively " 5m*3.3m*4.8m, detachable support frame
101 include the first column 120, the second column 121, the 3rd column, the 4th column and many crossbeams, the bottom of support base 129
Set and hydraulic lifting adjusting means is provided with four wheels 122, and each wheel 122, hydraulic lifting adjusting means is used to adjust
The height of each adjustable apparatus is saved, the vcehicular tunnel maintenance and reinforcement platform of whole uninterrupted traffic horizontality can be in,
It is achieved thereby that at the vcehicular tunnel maintenance and reinforcement platform of whole uninterrupted traffic side will not be produced because of road the right and left gradient
Turn over danger.Adjustable apparatus is set in traveling wheel position base, promotes job platform working face to remain horizontality, first
Column 120, the second column 121, the 3rd column, the line of the end points of the same side of the 4th column constitute rectangle, every crossbeam
Two ends are connected to constitute detachable support frame 101 with per two adjacent columns.
The geometry of top layer operating desk 102 is rectangle, and top layer operating desk 102 is installed on detachable support frame 101
Top, for for top layer lifting maintenance platform 103 provide support force, certain operating personnel can also stand top layer lift repair
Platform 103 is repaired to tunnel.Top layer lifting maintenance platform 103 is located at the top of top layer operating desk 102, top layer lifting maintenance
The geometry of platform 103 is also rectangle, and the area of top layer lifting maintenance platform 103 is less than the area of top layer operating desk 102.Can
Detachable support frame 101 is installed on the top of support base 129, and support base 129 is formed with automobile passage 133.This not in break off a friendship
Logical vcehicular tunnel maintenance and reinforcement platform also includes bottom operation platform, and bottom operation stage+module is in the detachable support
The bottom of skeleton 101.
In order to meet the demand of tunnel-liner fluting, mechanical arm 130, mechanical arm are installed in top layer lifting maintenance platform
130 lift maintenance platform with top layer is connected by Universal connector rotation, and the remote top layer of mechanical arm 130 lifts one end of maintenance platform
It is provided with groover 132.Operating personnel is by rotating mechanical arm 130 i.e. using groover 132 in all directions to tunnel
Side wall carry out lining cutting fluting, it is easy to operate.
In order to meet the job requirements in the whole inwall sticking steel plate band in tunnel, top layer lifting maintenance platform is also equipped with three
Individual hydraulic top pushing device 131, two of which hydraulic top pushing device 131 is located at the both sides that the top layer lifts maintenance platform, another
Individual hydraulic top pushing device 131 is located between the two of which hydraulic top pushing device 131.
One end of first lifting column 104 is slidably connected with top layer operating desk 102, specifically, in the present embodiment, top layer operation
Platform 102, which is provided with chute, chute, is embedded with sliding block, and one end of the first lifting column 104 is connected with sliding block, the first lifting column 104
The other end and top layer lift the bottom surface of maintenance platform 103 and be fixedly connected so that can band while mobile first lifting column 104
Dynamic top layer lifting maintenance platform 103 is moved.The first control unit is embedded with first lifting column 104, as shown in Fig. 2 the first control
Unit processed includes at the first signal receiving module 105, the lifting drive module 107 of first processing module 106 and first, first
Reason module 106 is electrically connected with the first signal receiving module 105, first lifting drive module 107 respectively, first processing module 106
For receiving lifting instruction by the first signal receiving module 105, and drive module 107 is lifted according to lifting instruction control first
Whole first lifting column 104 is driven to perform rise or the operation declined.In the present embodiment, the first signal receiving module 105 can be with
For remote control signal receiving module, staff can be sent climb command using remote control in operation or decline instruction to remote control letter
Number receiving module, first processing module 106 after receiving the climb command of remote control signal receiving module transmission or declining instruction,
Lift drive module 107 according to climb command or decline instruction control first and drive whole first lifting column 104 to perform rise
Or the operation declined.Of course, the edge that maintenance platform 103 can also be lifted in top layer sets lifting button to lift dimension to top layer
The height of equating platform 103 is adjusted, and is not limited herein.
The vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic also includes the portable platform of middle level operating desk 108, second people's row
Rank 110, middle level operating desk 108 is installed on detachable support frame 101, and middle level operating desk 108 is located at top layer and lifts maintenance
The lower section of platform 103, middle level operating desk 108 can be used for the operation apparatus and implement for stacking operating personnel.Second people
Take respectively in middle level operating desk 108, top layer operating desk 102 at the two ends of row movable type step 110.Operating personnel can pass through second
Therefrom layer operation platform 108, to top layer operating desk 102, then directly climbs up top to people's row movable type step 110 from top layer operating desk 102
Layer lifting maintenance platform 103 carries out construction operation.And middle level operating desk 108 is also equipped with tunnel cleaning maintenance of equipment, tunnel is clear
Clean maintenance of equipment includes cleaning device, concrete sander, concrete cutting type groove cutting machine.
The vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic also includes the second lifting column 111 and main maintenance side is flexible flat
Platform 112, main maintenance side scaling platform 112 be located at middle level operating desk 108 top, and main maintenance side scaling platform 112 be located at can
The side of detachable support frame 101, as shown in figure 5, i.e. main maintenance side lift telescopic platform 112 is located at detachable support rib
Frame 101 presses close to tunnel-liner side.Operating personnel can stand and the side wall in tunnel is tieed up on main maintenance side scaling platform 112
Repair.One end of second lifting column 111 is slidably connected with main maintenance side scaling platform 112, the other end of the second lifting column 111 and master
The bottom surface of maintenance side scaling platform 112 is fixedly connected, so as to can drive top layer lifting dimension while mobile first lifting column 104
Equating platform 103 is moved.
The second control unit is embedded with second lifting column 111, as shown in figure 3, the second control unit includes the second letter
Number receiving module 113, the lifting drive module 115 of Second processing module 114 and second, Second processing module 114 is respectively with the
The lifting of binary signal receiving module 113, second drive module 115 is electrically connected, and Second processing module 114 is used to connect by secondary signal
Receive module 113 and receive lifting instruction, and drive module 115 is lifted according to lifting instruction control second and drive whole second lifting column
111 perform rise or the operation declined.In the present embodiment, secondary signal receiving module 113 can also be remote control signal receiving
Block, staff can be sent climb command using remote control in operation or decline instruction to remote control signal receiving module, second
Processing module 114 is after receiving the climb command of remote control signal receiving module transmission or declining instruction, i.e., according to climb command
Or decline the operation for instructing the lifting drive module 115 of control second to drive whole second lifting column 111 to perform rise or decline.When
So, the height that the edge that maintenance platform 103 can also be lifted in top layer sets lifting button to lift maintenance platform 103 to top layer
It is adjusted, is not limited herein.
The vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic also includes main maintenance hoistable platform 116 and filled with electronic lifting
Put, the main maintenance hoistable platform 116 operation apparatus required during operation for putting and equipment.Electric lifting device includes the first spool
117th, steel cable 118, the motor of four rolling 119 and first, as described above, detachable support frame 101 includes two
The first column 120 and the second column 121 being oppositely arranged, and the first column 120, the second column 121 are provided with guide rail,
Two of which roller 119 is embedded at the bottom of a guide rail respectively, and two other roller 119 is embedded at the top of a guide rail respectively
Portion, two rollers 119 positioned at same guide rail are connected by steel cable 118, and the first motor is used to drive the first volume
The rotation of axle 117, main maintenance hoistable platform 116 is connected to by the steel cable 118 of the folding and unfolding of the first spool 117.Pass through the first driving electricity
Machine drives the motion of the first spool 117 that steel cable 118 can be driven to realize the lifting to main maintenance hoistable platform 116.
The vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic also includes multiple expansion links 123, the one of each expansion link 123
End is connected with top layer operating desk 102, and the other end of each expansion link 123 is connected with top layer lifting maintenance platform 103, expansion link
123 are used to provide support for top layer lifting maintenance platform 103, so that operator station lifts maintenance platform 103 in top layer
The stable safety of Shi Gengjia.Expansion link 123 is driven to stretch when the first lifting column 104 rises, the band when the second lifting column 111 declines
Dynamic expansion link 123 compresses.
Top layer operating desk 102, top layer lifting maintenance platform 103, main maintenance side scaling platform 112 and main maintenance lifting are flat
The edge of platform 116 is provided with guardrail 124, and guardrail 124 can prevent operating personnel from, when repairing tunnel, preventing operating personnel from falling
Fall, so as to ensure that the safety of operating personnel.It should be noted that in the present embodiment, top layer operating desk 102, top layer lifting dimension
Equating platform 103, main maintenance side scaling platform 112, middle level operating desk 108 and main maintenance hoistable platform 116 anti-skidding decorative pattern
Steel plate, with prevent operating personnel top layer operating desk 102, top layer lifting maintenance platform 103, main maintenance side scaling platform 112, in
Layer operation platform 108 and main maintenance hoistable platform 116 skid when walking about.
The edge of top layer operating desk 102 is provided with the second spool 125, the second motor and received by the second spool 125
The lifting rope 126 put, one end of the remote top layer operating desk 102 of lifting rope 126 is provided with hook 127, and the second motor is used to drive
Dynamic second spool 125 is operated.Drive the motion of the second spool 125 to drive the lifting of lifting rope 126 by the second motor, hang
The hook 127 of rope 126 can hang the equipment or material needed for operating personnel.
The edge of top layer operating desk 102 is additionally provided with security protection waistband 128, and operating personnel can prevent safety in operation
Back belt 128 is bound to waist, so that safety when further ensuring operation.
It should be noted that, alternatively embodiment, as shown in figure 4, highway generally includes reversed carriage, direct motion car
In road, therefore the present embodiment, the vcehicular tunnel maintenance and reinforcement platform splicing for two uninterrupted traffics that above-described embodiment is provided
Together, the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic in two tracks is constituted.
Second embodiment
The embodiment of the present invention additionally provides a kind of vcehicular tunnel maintenance and reinforcement device of uninterrupted traffic, including pulling equipment
With the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic described in first embodiment, including described in driving equipment and embodiment one
Uninterrupted traffic vcehicular tunnel maintenance and reinforcement platform, driving equipment and the side of detachable support frame detachably connect
Connect, and driving equipment is not on the bearing of trend of automobile passage, driving equipment is used for the highway tunnel for driving the uninterrupted traffic
Road maintenance and reinforcement platform moves ahead or stopped.
In summary, the vcehicular tunnel maintenance and reinforcement platform and device for the uninterrupted traffic that the present invention is provided, operating personnel
In operation, it can stand and the top in tunnel is repaired in top layer lifting maintenance platform 103, when needing to move the position of maintenance activity
When putting, because one end and the top layer operating desk 102 of the first lifting column 104 are slidably connected, therefore top layer lifting maintenance platform 103 can
Moved on top layer operating desk 102, furthermore, when needing to adjust the height of maintenance activity, operating personnel are only needed to first liter
Drop the input climb command of post 104 or decline instruction, so as to control the first lifting column 104 to rise or fall, so as to drive top
Layer lifting maintenance platform 103 rises or falls, by movement or rising and decline that maintenance platform 103 is lifted to top layer.Behaviour
Make personnel can repair and replacement position and the work posture of maintenance, so as to more easily be repaired to tunnel, improve
The operating experience sense of operating personnel, and when operating personnel is carrying out maintenance activity to tunnel, automobile can be from support base 129
The automobile passage 133 of formation passes through, from without influenceing traffic normal pass.
In addition, preventing take up track during the vcehicular tunnel maintenance and reinforcement platform operations of the uninterrupted traffic, it can ensure to put down simultaneously
Platform and the safety in track, the profile of the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic are adapted to vcehicular tunnel Internal periphery, utilize
Main maintenance side lift telescopic platform and top layer hoistable platform, can press close to maintenance work, this is not interrupted in the expansion of multiple elevations simultaneously
The vcehicular tunnel maintenance and reinforcement platform of traffic is quick detachable to be easily assembled, and has both been facilitated the cleaning maintenance and reinforcement to tunnel-liner, has been carried again
The high efficiency of operating personnel.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area
For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies
Change, equivalent substitution, improvement etc., should be included in the scope of the protection.
Claims (10)
1. the vcehicular tunnel maintenance and reinforcement platform of a kind of uninterrupted traffic, it is characterised in that including detachable support frame, top
Layer operation platform, top layer lifting maintenance platform, the first lifting column and support base, the top layer operating desk is installed on described detachable
The top of formula support frame, the top layer lifting maintenance platform is located at the top of the top layer operating desk, first lifting column
One end be slidably connected with the top layer operating desk, the other end of first lifting column lifts maintenance platform with the top layer
Bottom surface is fixedly connected, and the first control unit is embedded with first lifting column, and first control unit includes the first letter
Number receiving module, first processing module and the first lifting drive module, the first processing module respectively with the described first letter
Number receiving module, the first lifting drive module electrical connection, the first processing module are used to connect by first signal
Receive module and receive lifting instruction, and according to the lifting instruction control the first lifting drive module driving whole described first
Lifting column performs rise or the operation declined, and the detachable support frame is installed on the top of the support base, the branch
Support seat is formed with automobile passage.
2. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that the top layer
Lifting maintenance platform is provided with mechanical arm, and the mechanical arm lifts maintenance platform with the top layer and is connected by Universal connector rotation,
One end of the remote top layer lifting maintenance platform of the mechanical arm is provided with groover.
3. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that the top layer
Lifting maintenance platform is also equipped with three hydraulic top pushing devices, and two of which hydraulic top pushing device is located at the top layer and lifts maintenance
The both sides of platform, another hydraulic top pushing device is located between the two of which hydraulic top pushing device.
4. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that it is described not in
The vcehicular tunnel maintenance and reinforcement platform for breaking off a friendship logical also includes the portable step of middle level operating desk, second people's row, the middle layer operation
Platform is installed on the detachable support frame, and the middle level operating desk is located at the lower section that the top layer lifts maintenance platform,
Take respectively in the middle level operating desk, the top layer operating desk at the two ends of the portable step of the second people row.
5. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 4, it is characterised in that it is described not in
The vcehicular tunnel maintenance and reinforcement platform for breaking off a friendship logical also includes the second lifting column and main maintenance side scaling platform, the main maintenance side
Scaling platform is located at the top of the placement platform, and the main maintenance side scaling platform is located at the detachable support frame
Side, one end of second lifting column is slidably connected with the main maintenance side scaling platform, second lifting column it is another
End is fixedly connected with the bottom surface of the main maintenance side scaling platform, and the second control unit, institute are embedded with second lifting column
State the second control unit and include secondary signal receiving module, Second processing module and the second lifting drive module, described the
Two processing modules are electrically connected with the secondary signal receiving module, the second lifting drive module respectively, the second processing
Module is used to receive lifting instruction by the secondary signal receiving module, and according to described second liter of the lifting instruction control
Drop whole second lifting column of drive module driving and perform rise or the operation declined.
6. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that it is described not in
The vcehicular tunnel maintenance and reinforcement platform for breaking off a friendship logical also includes main maintenance hoistable platform and electric lifting device, the main maintenance lifting
Platform be located at the detachable support frame side, electric lifting device include the first spool, steel cable, four rolling and
Motor, the detachable support frame includes two the first columns and the second column being oppositely arranged, described first
Column, second column are provided with guide rail, and roller is embedded at the bottom of a guide rail respectively described in two of which, separately
Outer two rollers are embedded at the top of a guide rail respectively, and two rollers positioned at the same guide rail pass through institute
Steel rope gearing connection is stated, the motor is used for the rotation for driving first spool, by the steel of the first spool folding and unfolding
Rope is connected to the main maintenance hoistable platform.
7. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that it is described not in
The vcehicular tunnel maintenance and reinforcement platform for breaking off a friendship logical also includes multiple expansion links, and one end and the top layer of each expansion link are grasped
Make platform connection, the other end of each expansion link is connected with top layer lifting maintenance platform.
8. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that the top layer
Operating desk, the edge of top layer lifting maintenance platform are provided with guardrail.
9. the vcehicular tunnel maintenance and reinforcement platform of uninterrupted traffic according to claim 1, it is characterised in that the top layer
Operation edge of table is provided with the second spool, the second motor and the lifting rope by the second spool folding and unfolding, the lifting rope
One end of the remote top layer operating desk be provided with hook, second motor is used to drive second spool to transport
Turn.
10. the vcehicular tunnel maintenance and reinforcement device of a kind of uninterrupted traffic, it is characterised in that including driving equipment and claim
The vcehicular tunnel maintenance and reinforcement platform of 1~9 any uninterrupted traffic, the driving equipment and the detachable support rib
The side of frame is detachably connected, and the driving equipment is not on the bearing of trend of the automobile passage, the bottom of the support base
Portion sets at least three wheels, and the driving equipment is used to drive before the vcehicular tunnel maintenance and reinforcement platform of the uninterrupted traffic
Row stops.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710609421.8A CN107191195A (en) | 2017-07-25 | 2017-07-25 | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710609421.8A CN107191195A (en) | 2017-07-25 | 2017-07-25 | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107191195A true CN107191195A (en) | 2017-09-22 |
Family
ID=59884616
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710609421.8A Pending CN107191195A (en) | 2017-07-25 | 2017-07-25 | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107191195A (en) |
Citations (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB700333A (en) * | 1950-09-20 | 1953-11-25 | Atlas Diesel Ab | Improvements in drill wagons for use in tunnelling |
CN2242927Y (en) * | 1995-03-28 | 1996-12-18 | 中国地质大学(武汉) | Scarfold-type digging construction platform |
CN202441387U (en) * | 2012-02-06 | 2012-09-19 | 中铁十六局集团有限公司 | Multifunctional tunnel working rack |
CN102996062A (en) * | 2012-11-30 | 2013-03-27 | 衡水供电公司 | Maintenance lifting platform and application method thereof |
CN103277112A (en) * | 2013-06-22 | 2013-09-04 | 中铁十八局集团第二工程有限公司 | Tunnel engineering train type rapid lifting and folding working platform |
CN103670435A (en) * | 2013-12-24 | 2014-03-26 | 中铁西南科学研究院有限公司 | Existing line railway tunnel defect comprehensive improvement operation trolley |
CN103835727A (en) * | 2014-03-31 | 2014-06-04 | 中铁西南科学研究院有限公司 | Extended type multi-platform railway tunnel operation trolley |
CN203769796U (en) * | 2014-04-09 | 2014-08-13 | 中国十九冶集团有限公司 | Multifunctional operation platform for tunnel |
CN203961989U (en) * | 2014-07-05 | 2014-11-26 | 中铁三局集团有限公司 | A kind of full section rock drilling stand for the short benching tunnelling method construction in tunnel |
CN204344143U (en) * | 2014-12-23 | 2015-05-20 | 中铁岩锋成都科技有限公司 | Tunnel defect Fast-Maintenance car |
CN104653194A (en) * | 2015-02-28 | 2015-05-27 | 中铁十九局集团第七工程有限公司 | Multi-platform railway tunnel operation trolley |
CN204476438U (en) * | 2014-12-25 | 2015-07-15 | 浙江金筑交通建设有限公司 | For the ascending/decending chassis of tunnel roof-bolter construction |
CN104790966A (en) * | 2015-04-23 | 2015-07-22 | 北京建工土木工程有限公司 | Multi-functional starting and receiving construction operation frame of earth pressure balance shield machine |
CN205000974U (en) * | 2015-07-24 | 2016-01-27 | 中国铁建大桥工程局集团有限公司 | A tire formula automatic rising equipment rack for tunnel excavation construction |
CN205558915U (en) * | 2016-03-08 | 2016-09-07 | 中国葛洲坝集团第五工程有限公司 | Portable operation device |
CN205811387U (en) * | 2016-07-27 | 2016-12-14 | 国网山东省电力公司惠民县供电公司 | A kind of multi-functional power transformation equipment overhauling stand |
CN205977243U (en) * | 2016-08-01 | 2017-02-22 | 湖南五新隧道智能装备股份有限公司 | A platform truck for tunnel water proofing board is laid and reinforcement |
CN106437795A (en) * | 2016-11-25 | 2017-02-22 | 中铁隧道集团第五建筑有限公司 | Tunnel vehicle-mounted folding type multifunctional work rack |
CN106522997A (en) * | 2016-11-24 | 2017-03-22 | 中铁十四局集团第五工程有限公司 | Construction trolley for lagging jack in tunnel and underground construction and construction method |
CN106593480A (en) * | 2017-01-13 | 2017-04-26 | 中交公局第六工程有限公司 | Comprehensive tunnel maintenance trolley |
CN106703689A (en) * | 2016-12-10 | 2017-05-24 | 中国铁建电气化局集团北方工程有限公司 | Automatic punching device and method for high-speed railway tunnel anchor implantation |
CN106869981A (en) * | 2017-02-17 | 2017-06-20 | 中铁二十局集团第三工程有限公司 | The constructing tunnel cantilever chassis of automatically retractable platform |
CN206280086U (en) * | 2016-12-09 | 2017-06-27 | 中铁建大桥工程局集团第二工程有限公司 | A kind of adjustable height tunnel reinforcement trolley |
CN207377567U (en) * | 2017-07-25 | 2018-05-18 | 重庆交通大学 | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic |
-
2017
- 2017-07-25 CN CN201710609421.8A patent/CN107191195A/en active Pending
Patent Citations (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB700333A (en) * | 1950-09-20 | 1953-11-25 | Atlas Diesel Ab | Improvements in drill wagons for use in tunnelling |
CN2242927Y (en) * | 1995-03-28 | 1996-12-18 | 中国地质大学(武汉) | Scarfold-type digging construction platform |
CN202441387U (en) * | 2012-02-06 | 2012-09-19 | 中铁十六局集团有限公司 | Multifunctional tunnel working rack |
CN102996062A (en) * | 2012-11-30 | 2013-03-27 | 衡水供电公司 | Maintenance lifting platform and application method thereof |
CN103277112A (en) * | 2013-06-22 | 2013-09-04 | 中铁十八局集团第二工程有限公司 | Tunnel engineering train type rapid lifting and folding working platform |
CN103670435A (en) * | 2013-12-24 | 2014-03-26 | 中铁西南科学研究院有限公司 | Existing line railway tunnel defect comprehensive improvement operation trolley |
CN103835727A (en) * | 2014-03-31 | 2014-06-04 | 中铁西南科学研究院有限公司 | Extended type multi-platform railway tunnel operation trolley |
CN203769796U (en) * | 2014-04-09 | 2014-08-13 | 中国十九冶集团有限公司 | Multifunctional operation platform for tunnel |
CN203961989U (en) * | 2014-07-05 | 2014-11-26 | 中铁三局集团有限公司 | A kind of full section rock drilling stand for the short benching tunnelling method construction in tunnel |
CN204344143U (en) * | 2014-12-23 | 2015-05-20 | 中铁岩锋成都科技有限公司 | Tunnel defect Fast-Maintenance car |
CN204476438U (en) * | 2014-12-25 | 2015-07-15 | 浙江金筑交通建设有限公司 | For the ascending/decending chassis of tunnel roof-bolter construction |
CN104653194A (en) * | 2015-02-28 | 2015-05-27 | 中铁十九局集团第七工程有限公司 | Multi-platform railway tunnel operation trolley |
CN104790966A (en) * | 2015-04-23 | 2015-07-22 | 北京建工土木工程有限公司 | Multi-functional starting and receiving construction operation frame of earth pressure balance shield machine |
CN205000974U (en) * | 2015-07-24 | 2016-01-27 | 中国铁建大桥工程局集团有限公司 | A tire formula automatic rising equipment rack for tunnel excavation construction |
CN205558915U (en) * | 2016-03-08 | 2016-09-07 | 中国葛洲坝集团第五工程有限公司 | Portable operation device |
CN205811387U (en) * | 2016-07-27 | 2016-12-14 | 国网山东省电力公司惠民县供电公司 | A kind of multi-functional power transformation equipment overhauling stand |
CN205977243U (en) * | 2016-08-01 | 2017-02-22 | 湖南五新隧道智能装备股份有限公司 | A platform truck for tunnel water proofing board is laid and reinforcement |
CN106522997A (en) * | 2016-11-24 | 2017-03-22 | 中铁十四局集团第五工程有限公司 | Construction trolley for lagging jack in tunnel and underground construction and construction method |
CN106437795A (en) * | 2016-11-25 | 2017-02-22 | 中铁隧道集团第五建筑有限公司 | Tunnel vehicle-mounted folding type multifunctional work rack |
CN206280086U (en) * | 2016-12-09 | 2017-06-27 | 中铁建大桥工程局集团第二工程有限公司 | A kind of adjustable height tunnel reinforcement trolley |
CN106703689A (en) * | 2016-12-10 | 2017-05-24 | 中国铁建电气化局集团北方工程有限公司 | Automatic punching device and method for high-speed railway tunnel anchor implantation |
CN106593480A (en) * | 2017-01-13 | 2017-04-26 | 中交公局第六工程有限公司 | Comprehensive tunnel maintenance trolley |
CN106869981A (en) * | 2017-02-17 | 2017-06-20 | 中铁二十局集团第三工程有限公司 | The constructing tunnel cantilever chassis of automatically retractable platform |
CN207377567U (en) * | 2017-07-25 | 2018-05-18 | 重庆交通大学 | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic |
Non-Patent Citations (1)
Title |
---|
薛永庆;: "全断面隧道掘进机同步清理台车研究" * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206427933U (en) | A kind of bridge crane | |
CN106348188B (en) | The manufacture method of planer-type building-construction lifting device | |
CN103183297B (en) | Mobile rescue elevator and rescue vehicle | |
CN103726421B (en) | Height and span adjustable track paver for metro construction | |
CN110655015A (en) | Trackless self-propelled platform car for subway tunnel maintenance | |
CN206562264U (en) | A kind of hanging device for transport outside high-rise building | |
CN103821084B (en) | Operational method at the bottom of implement at the bottom of beam and beam | |
CN205973684U (en) | Portable insulating operation device of ascending a height of distribution lines | |
CN103274315A (en) | Installing and hoisting device for side plate and upright of gas chamber | |
CN107263695A (en) | The walking blank truck device of high-pressure forming machine | |
CN207377567U (en) | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic | |
CN206144559U (en) | Portable mining lifting support that fixes | |
CN211256692U (en) | Transport beam structure of newly-built upper bridge on current bridge | |
CN207377568U (en) | The low vcehicular tunnel maintenance and reinforcement platform and device for influencing traffic | |
CN107191195A (en) | The vcehicular tunnel maintenance and reinforcement platform and device of uninterrupted traffic | |
CN107089602A (en) | The double gantries for setting loop wheel machine running of twin beams | |
CN215633039U (en) | Tunnel waterproof board installation trolley structure | |
CN206607860U (en) | A kind of hydraulic self-creeping formwork with turnover panel | |
CN207061690U (en) | Bridge crane with suspender maintenance rig | |
CN217642393U (en) | Mechanical lifting crossing frame | |
CN113446035B (en) | Tunnel waterproof board mounting trolley structure and construction method thereof | |
CN107152289A (en) | The vcehicular tunnel maintenance and reinforcement platform and device of low influence traffic | |
CN205556016U (en) | Three -dimensional scissors formula workstation | |
CN108706471A (en) | A kind of large-sized gantry hangs the method for dismounting of rigid leg | |
CN201512364U (en) | Telescopic hoisting gantry crane used for paving unballasted tracks |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170922 |